CN108446867A - A kind of assembled architecture prefabricated components and its management method based on BIM5D - Google Patents

A kind of assembled architecture prefabricated components and its management method based on BIM5D Download PDF

Info

Publication number
CN108446867A
CN108446867A CN201810480206.7A CN201810480206A CN108446867A CN 108446867 A CN108446867 A CN 108446867A CN 201810480206 A CN201810480206 A CN 201810480206A CN 108446867 A CN108446867 A CN 108446867A
Authority
CN
China
Prior art keywords
prefabricated components
bim5d
assembled architecture
dimension code
code label
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810480206.7A
Other languages
Chinese (zh)
Inventor
李政道
王家远
彭明
朱俊乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen University
Shenzhen Genew Technologies Co Ltd
Original Assignee
Shenzhen University
Shenzhen Genew Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen University, Shenzhen Genew Technologies Co Ltd filed Critical Shenzhen University
Priority to CN201810480206.7A priority Critical patent/CN108446867A/en
Publication of CN108446867A publication Critical patent/CN108446867A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K17/00Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to assembled architecture technical fields, disclose a kind of assembled architecture prefabricated components and its management method based on BIM5D, which includes:Member body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed in the member body, and the member body includes the concrete structure and/or wood moulding structure of default specification and size;Design, production, the whole-process management of construction information that prefabricated components are realized by BIM5D technologies, improve construction precision, reduce waste of material.

Description

A kind of assembled architecture prefabricated components and its management method based on BIM5D
Technical field
The present invention relates to assembled architecture technical field more particularly to a kind of prefabricated structures of assembled architecture based on BIM5D Part and its management method.
Background technology
Traditional interior wall partition wall or exterior wall are built by laying bricks or stones for one piece one piece with brick mostly, the weight that assembled architecture rises Point is prefabrication, and largely building work by laying bricks or stones by site operation is changed into machinery production, is quickly assembled after transport, and reaches Construction vision to the purpose quickly produced, the industry emerging as one, prefabricated panel is, from plant produced, to arrive building site group Dress, just like the progress as assembly line without any confusion, the importance of people reduces, and the advantage of machinery and means of transport is played.But It is in fact whether genuine suchThe investigation of the sides of taking part in building of building trade is shown more according to us, it is really not so.Its existing rank The development of section still has construction problem to fail to solve.
Problem 1 uses concrete prefabricated wallboard or the cored slab of new material.It is not aware that on building site when plant produced The length of each piece of wall needed, factory produce some fixed sizes in advance, and general wall uses these different in width Board group closes out, and remainder is reused by cutting.Its length is about 300CM, substantially disclosure satisfy that the height of first floor Degree, by the way that in this harden structure bulk transport to construction site, further working cut, is applied on wall, construction site Small-sized processing of cutting factory there are one needing.
Problem 2, it is prefabricated by the whole wall of factory.Prefabricated several specifications can be generally used, first pass through BIM modelings in this case With calculation amount, compares and be adapted to standard house type.The garden and house type of some great developments quotient is reproducible.The specification of wall is substantially solid Fixed such as width is 3 meters, 2 meters, 1 meter, the pre-cast concrete walling with door, concrete prefabricated wall with window etc..This prefabricated update It is advanced, directly reach the assembled a set of set house type room of effect for spelling building blocks.Larger problem is still big in production difficulty, transport at This is higher.Assembled blanking management slightly has difficulty.
Problem 3, transport.Factory is more distant at a distance from building site, estimates the inaccuracy of dosage, can usually cause to transport The increase of defeated cost.
Problem 4, field management.It is cut in construction site, then transports and installed on corresponding partition wall upstairs.At this time It is not general to have some plates, which is transported and puts work flowing water section, consigns to which teams and groups uses, and can only lean on a hand It copies and is singly allocated.Inevitably there is the material transportation in the areas A to the areas B for example, usually having, leads to various in-fightings.
Problem 5, installation.By a series of transport in front, many batches of wallboards has transported under wall, actually which block First installWhich installed after blockThis needs very careful planning, otherwise can encounter and accidentally fill, the wallboard of not at all easy completion Also to unload to get off to readjust again.
Invention content
It is a primary object of the present invention to propose a kind of assembled architecture prefabricated components based on BIM5D and its manager Method is realized design, production, the whole-process management of construction information of prefabricated components by BIM5D technologies, improves construction precision, Reduce waste of material.
To achieve the above object, a kind of assembled architecture prefabricated components based on BIM5D provided by the invention, including:Structure Part main body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed in the member body, described Member body includes the concrete structure and/or wood moulding structure of default specification and size.
Optionally, the positioning label is that ultra wide band UWB positions label.
Optionally, further include protective shell, form a paper chamber for housing the two-dimension code label, the guarantor in the protective shell The edge of protective case is provided with mounting hole, and the protective shell is fixed by the muscle structure of the mounting hole and the prefabricated components to be connected It connects.
Optionally, the protective shell is plastic protection casing or metal coating shell.
Optionally, the protective shell is rectangle protective shell, and there are four mounting holes for setting on four angles of the rectangle.
Optionally, it is stored on the two-dimension code label:Project name, floor information, location information, is born building information Blame teams and groups' information, plan set-up time information, date of manufacture and component ID.
As another aspect of the present invention, a kind of manager of the assembled architecture prefabricated components based on BIM5D provided Method, including:
Construction plan is formulated by BIM5D application programs, the construction plan includes the specification, size and original of prefabricated components Material;
The prefabricated components are produced according to the construction plan;
The prefabricated components are packaged, corresponding two-dimension code label and positioning device are fixed on the prefabricated components On;
Distribute the prefabricated components by preset flowing water section;
Assembling is carried out according to the information on the two-dimension code label.
Optionally, further include after the prefabricated components by the distribution of preset flowing water section:
The prefabricated components are tracked according to the positioning device.
Optionally, further include after the information progress Assembling according on the two-dimension code label:
According on the two-dimension code label information and the construction plan confirm installation it is whether errorless.
Optionally, the BIM5D application programs are installed on mobile terminals.
A kind of assembled architecture prefabricated components and its management method based on BIM5D proposed by the present invention, the prefabricated components Including:Member body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed on the member body On, the member body includes the concrete structure and/or wood moulding structure of default specification and size;It is realized by BIM5D technologies Design, production, the whole-process management of construction information of prefabricated components, improve construction precision, reduce waste of material.
Description of the drawings
Fig. 1 is a kind of assembled architecture prefabricated components structural schematic diagram based on BIM5D that the embodiment of the present invention one provides;
Fig. 2 is the two-dimension code label fixed structure chart that the embodiment of the present invention one provides;
Fig. 3 is a kind of management method of the assembled architecture prefabricated components based on BIM5D provided by Embodiment 2 of the present invention Flow chart;
Fig. 4 is the manager of another assembled architecture prefabricated components based on BIM5D provided by Embodiment 2 of the present invention Method flow chart;
Fig. 5 is the manager of another assembled architecture prefabricated component based on BIM5D provided by Embodiment 2 of the present invention Method flow chart.
Wherein, the reference numeral of Fig. 2 is:1- two-dimension code labels, 2- protective shells, 3- mounting holes, 4- muscle structures.
The embodiments will be further described with reference to the accompanying drawings for the realization, the function and the advantages of the object of the present invention.
Specific implementation mode
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
In subsequent description, using for indicating that the suffix of such as " module ", " component " or " unit " of element is only Be conducive to the explanation of the present invention, itself there is no specific meanings.Therefore, " module " can mixedly make with " component " With.
Embodiment one
As shown in Figure 1, in the present embodiment, a kind of assembled architecture prefabricated components based on BIM5D, including:Component master Body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed in the member body, the component Main body includes the concrete structure and/or wood moulding structure of default specification and size.
In the present embodiment, by BIM5D technologies realize the designs of prefabricated components, production, construction information whole process pipe Reason, improves construction precision, reduces waste of material.
In the present embodiment, BIM5D, as the term suggests being there are five dimension, 3D known to us on the basis of, is connected to 4D times and 5D costs.In this case, BIM (Building Information Modeling, Building Information Model) No longer it is a simple Building Information Model, and is through whole building life cycle, extends BIM data and building Full-range application.So BIM5D is the management carried out on the basis of BIM to entire work progress, it is a kind of tool.It is common BIM5D softwares may be mounted on the mobile terminals such as mobile phone, tablet, it is user-friendly.
In the present embodiment, the positioning label is that ultra wide band UWB positions label.
As shown in Fig. 2, in the present embodiment, prefabricated components further include protective shell 2, it is accommodating to form one in the protective shell 2 The edge of the paper chamber of the two-dimension code label 1, the protective shell is provided with mounting hole 3, and the protective shell 2 passes through the fixation Hole 3 is fixedly connected with the muscle structure 4 of the member body.
The muscle structure is concrete structure, wood moulding structure or other support constructions.
In the present embodiment, the protective shell is plastic protection casing or metal coating shell.
In the present embodiment, the protective shell is rectangle protective shell, and there are four solid for setting on four angles of the rectangle Determine hole.
In the present embodiment, it is stored on the two-dimension code label:Project name, building information, floor information, positioning letter Breath is responsible for teams and groups' information, plan set-up time information, date of manufacture and component ID.
In the present embodiment, the following table 1 is the information table of two-dimension code label:
Field attribute Attribute value
Project The squares the XX second phase
Lou Dong A
Floor F3
Positioning A5-A6
It is responsible for teams and groups XX mono- is built
Plan the set-up time On April 10th, 2018
Date of manufacture On March 1st, 2018
Plate ID B654888
Table 1
In the present embodiment, it can be managed using BIM5D systems in each production link, in design link, answer Three-dimensional modeling is carried out with BIM5D systems, and virtual reality scenario, everybody is readable for design effect;In quantities calculation link, answer Accurate Model is carried out with BIM5D systems, quantities and actual error are minimum, can be to prefabricated by the calculation volume production product of Si Weier Material carries out classification statistics, can submit prefabrication, not waste material and transportation cost;At the construction field (site), using BIM5D systems By model interaction to flowing water section.Automatically the material requested amount of each flowing water section is calculated;Link, construction are positioned in prefabricated components Personnel can select a face wall by mobile devices such as tablets from model, check the essential information of wall, can also be from Quick Response Code Upper barcode scanning understands the house type and position that this plate is applied;In quality safety management link, by mobile devices such as mobile phones, record into Degree, quality, safety problem.All-the-way tracking is rectified and improved, and Cost for Coordination is reduced;Link is inquired in item status, can be united by BIM5D The Construction Condition of meter project.
Embodiment two
As shown in figure 3, in the present embodiment, a kind of management method of the assembled architecture prefabricated components based on BIM5D, packet It includes:
S10, construction plan is formulated by BIM5D application programs, the construction plan includes the specification of prefabricated components, size And raw material;
S20, the prefabricated components are produced according to the construction plan;
S30, the prefabricated components are packaged, corresponding two-dimension code label and positioning device are fixed on described prefabricated On component;
S40, distribute the prefabricated components by preset flowing water section;
S50, Assembling is carried out according to the information on the two-dimension code label.
In the present embodiment, by BIM5D technologies realize the designs of prefabricated components, production, construction information whole process pipe Reason, improves construction precision, reduces waste of material.
In the present embodiment, BIM5D, as the term suggests being there are five dimension, 3D known to us on the basis of, is connected to 4D times and 5D costs.In this case, BIM (Building Information Modeling, Building Information Model) No longer it is a simple Building Information Model, and is through whole building life cycle, extends BIM data and building Full-range application.So BIM5D is the management carried out on the basis of BIM to entire work progress, it is a kind of tool.It is common BIM5D softwares may be mounted on the mobile terminals such as mobile phone, tablet, it is user-friendly.
As shown in figure 4, in the present embodiment, further including after the step S40:
S41, the prefabricated components are tracked according to the positioning device.
In transportational process and live distribution procedure, whole information follows, by BIM5D system tracking modes, until having constructed At by its construction team setting completion label on BIM5D, with special color mark, it is normally applied for meeting on threedimensional model Work is completed.
As shown in figure 5, in the present embodiment, further including after the step S50:
S60, according on the two-dimension code label information and the construction plan confirm installation it is whether errorless.
If installation is errorless, then it represents that the construction of the prefabricated components is completed, and otherwise, BIM5D systems initiate rectification notice, whole After the completion of changing, the rectification problem is closed, completes construction.
In the present embodiment, the BIM5D application programs are installed on mobile terminals.
In the present embodiment, it can be managed using BIM5D systems in each production link, in design link, answer Three-dimensional modeling is carried out with BIM5D systems, and virtual reality scenario, everybody is readable for design effect;In quantities calculation link, answer Accurate Model is carried out with BIM5D systems, quantities and actual error are minimum, can be to prefabricated by the calculation volume production product of Si Weier Material carries out classification statistics, can submit prefabrication, not waste material and transportation cost;At the construction field (site), using BIM5D systems By model interaction to flowing water section.Automatically the material requested amount of each flowing water section is calculated;Link, construction are positioned in prefabricated components Personnel can select a face wall by mobile devices such as tablets from model, check the essential information of wall, can also be from Quick Response Code Upper barcode scanning understands the house type and position that this plate is applied;In quality safety management link, by mobile devices such as mobile phones, record into Degree, quality, safety problem.All-the-way tracking is rectified and improved, and Cost for Coordination is reduced;Link is inquired in item status, can be united by BIM5D The Construction Condition of meter project.
It should be noted that herein, the terms "include", "comprise" or its any other variant are intended to non-row His property includes, so that process, method, article or device including a series of elements include not only those elements, and And further include other elements that are not explicitly listed, or further include for this process, method, article or device institute it is intrinsic Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including this There is also other identical elements in the process of element, method, article or device.
The embodiments of the present invention are for illustration only, can not represent the quality of embodiment.
Through the above description of the embodiments, those skilled in the art can be understood that above-described embodiment side Method can add the mode of required general hardware platform to realize by software, naturally it is also possible to by hardware, but in many cases The former is more preferably embodiment.Based on this understanding, technical scheme of the present invention substantially in other words does the prior art Going out the part of contribution can be expressed in the form of software products, which is stored in a storage medium In (such as ROM/RAM, magnetic disc, CD), including some instructions are used so that a station terminal equipment (can be mobile phone, computer, clothes Be engaged in device, air conditioner or the network equipment etc.) execute method described in each embodiment of the present invention.
It these are only the preferred embodiment of the present invention, be not intended to limit the scope of the invention, it is every to utilize this hair Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills Art field, is included within the scope of the present invention.

Claims (10)

1. a kind of assembled architecture prefabricated components based on BIM5D, which is characterized in that including:Member body, two-dimension code label and Positioning device, the two-dimension code label and positioning device are fixed in the member body, and the member body includes default rule The concrete structure and/or wood moulding structure of lattice and size.
2. a kind of assembled architecture prefabricated components based on BIM5D according to claim 1, which is characterized in that described fixed Position label is that ultra wide band UWB positions label.
3. a kind of assembled architecture prefabricated components based on BIM5D according to claim 1, which is characterized in that further include Protective shell, the protective shell is interior to form a paper chamber for housing the two-dimension code label, and the edge of the protective shell is provided with admittedly Determine hole, the protective shell is fixedly connected by the mounting hole with the muscle structure of the prefabricated components.
4. a kind of assembled architecture prefabricated components based on BIM5D according to claim 3, which is characterized in that the guarantor Protective case is plastic protection casing or metal coating shell.
5. a kind of assembled architecture prefabricated components based on BIM5D according to claim 3, which is characterized in that the guarantor Protective case is rectangle protective shell, and there are four mounting holes for setting on four angles of the rectangle.
6. a kind of assembled architecture prefabricated components based on BIM5D according to claim 1, which is characterized in that described two It is stored on dimension code label:When project name, building information, floor information, location information, responsible teams and groups information, plan installation Between information, date of manufacture and component ID.
7. a kind of management method of the assembled architecture prefabricated components based on BIM5D, which is characterized in that including:
Construction plan is formulated by BIM5D application programs, the construction plan includes the specification, size and former material of prefabricated components Material;
The prefabricated components are produced according to the construction plan;
The prefabricated components are packaged, corresponding two-dimension code label and positioning device are fixed on the prefabricated components;
Distribute the prefabricated components by preset flowing water section;
Assembling is carried out according to the information on the two-dimension code label.
8. a kind of management method of assembled architecture prefabricated components based on BIM5D according to claim 7, feature exist In described to further include later by the preset flowing water section distribution prefabricated components:
The prefabricated components are tracked according to the positioning device.
9. a kind of management method of assembled architecture prefabricated components based on BIM5D according to claim 7, feature exist In the information according on the two-dimension code label carries out Assembling and further includes later:
According on the two-dimension code label information and the construction plan confirm installation it is whether errorless.
10. a kind of management method of assembled architecture prefabricated components based on BIM5D according to claim 7, feature It is, the BIM5D application programs installation is on mobile terminals.
CN201810480206.7A 2018-05-18 2018-05-18 A kind of assembled architecture prefabricated components and its management method based on BIM5D Pending CN108446867A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810480206.7A CN108446867A (en) 2018-05-18 2018-05-18 A kind of assembled architecture prefabricated components and its management method based on BIM5D

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810480206.7A CN108446867A (en) 2018-05-18 2018-05-18 A kind of assembled architecture prefabricated components and its management method based on BIM5D

Publications (1)

Publication Number Publication Date
CN108446867A true CN108446867A (en) 2018-08-24

Family

ID=63204747

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810480206.7A Pending CN108446867A (en) 2018-05-18 2018-05-18 A kind of assembled architecture prefabricated components and its management method based on BIM5D

Country Status (1)

Country Link
CN (1) CN108446867A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110969227A (en) * 2019-11-27 2020-04-07 西南交通大学 Two-dimensional code-based assembled component information management method
JP2020109242A (en) * 2019-01-03 2020-07-16 華北水利水電大学 Assembly type shear wall building structure
CN112936559A (en) * 2021-03-16 2021-06-11 河南省公路工程局集团有限公司 Concrete small-sized prefabricated part quality improvement method based on whole process accompanied
CN113610389A (en) * 2021-08-04 2021-11-05 深圳大学 Prefabricated part production quality management system based on BIM and RFID

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006079290A (en) * 2004-09-08 2006-03-23 Kenchiku Pivot:Kk Information management system and information management method
CN105003028A (en) * 2015-07-23 2015-10-28 深圳海龙建筑制品有限公司 Prefabricated component capable of being monitored, monitoring method of prefabricated component and monitoring system of prefabricated component
CN107146168A (en) * 2017-07-11 2017-09-08 大连锐勃电子科技有限公司 Wisdom building site management system based on universe frequency conversion positioning Yu self-identifying technology
CN107542161A (en) * 2017-08-23 2018-01-05 中建八局第建设有限公司 BIDA engineering of integrating technical systems
CN107958101A (en) * 2017-11-07 2018-04-24 山东住工装配建筑有限公司 A kind of assembled architecture Information Management System and method based on BIM

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006079290A (en) * 2004-09-08 2006-03-23 Kenchiku Pivot:Kk Information management system and information management method
CN105003028A (en) * 2015-07-23 2015-10-28 深圳海龙建筑制品有限公司 Prefabricated component capable of being monitored, monitoring method of prefabricated component and monitoring system of prefabricated component
CN107146168A (en) * 2017-07-11 2017-09-08 大连锐勃电子科技有限公司 Wisdom building site management system based on universe frequency conversion positioning Yu self-identifying technology
CN107542161A (en) * 2017-08-23 2018-01-05 中建八局第建设有限公司 BIDA engineering of integrating technical systems
CN107958101A (en) * 2017-11-07 2018-04-24 山东住工装配建筑有限公司 A kind of assembled architecture Information Management System and method based on BIM

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
白庶;张艳坤;韩凤;张德海;李微;: "BIM技术在装配式建筑中的应用价值分析" *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020109242A (en) * 2019-01-03 2020-07-16 華北水利水電大学 Assembly type shear wall building structure
CN110969227A (en) * 2019-11-27 2020-04-07 西南交通大学 Two-dimensional code-based assembled component information management method
CN112936559A (en) * 2021-03-16 2021-06-11 河南省公路工程局集团有限公司 Concrete small-sized prefabricated part quality improvement method based on whole process accompanied
CN113610389A (en) * 2021-08-04 2021-11-05 深圳大学 Prefabricated part production quality management system based on BIM and RFID
CN113610389B (en) * 2021-08-04 2023-06-20 深圳大学 Prefabricated component production quality management system based on BIM and RFID

Similar Documents

Publication Publication Date Title
CN108446867A (en) A kind of assembled architecture prefabricated components and its management method based on BIM5D
CN105023201B (en) Assembled architecture Deepen Design and construction method based on BIM and big data
Polat Factors affecting the use of precast concrete systems in the United States
US20070027732A1 (en) Context-sensitive, location-dependent information delivery at a construction site
Liu et al. Real‐Time Optimization of Precast Concrete Component Transportation and Storage
Re Cecconi et al. Leveraging BIM for digital built environment asset management
Ikonen et al. Use of embedded RFID tags in concrete element supply chains.
CN105303308A (en) Management system and method for whole steel bar engineering process based on 3D figure information platform
CN110110442A (en) A kind of parametric modeling design method of assembled architecture
CN111090903B (en) BIM-based component statistical method and related device
Liu et al. Design for Manufacturing and Assembly: A BIM‐Enabled Generative Framework for Building Panelization Design
KR20150121699A (en) Method and system using standardized structural components
Ekanayake et al. Modeling supply chain resilience in industrialized construction: A Hong Kong case
Zhang et al. Fighting Covid-19 through fast delivery of a modular quarantine camp with smart construction
CN109360123B (en) Multi-professional construction management method and system based on room
Sergei et al. An interactive construction project for method of statement based on BIM technologies for high-speed modular building
Lim et al. Evaluation of CO2 emission reduction effect using in-situ production of precast concrete components
Wang et al. Causes and penalties of variation: Case study of a precast concrete slab production facility
Mésároš et al. Adaptive design of formworks for building renovation considering the sustainability of construction in BIM environment—Case study
CN208689614U (en) A kind of assembled architecture prefabricated components based on BIM5D
Bhattacharjee et al. Adoption of pre-fabrication in construction to achieve sustainability goals: an empirical study
KR20210114621A (en) Design system of building
Inyang et al. A VR model of ergonomics and productivity assessment in panelized construction production line
Okodi-Iyah A comparative evaluation of the environmental impact of prefabrication versus conventional construction in UAE’s construction industry
CN109087076B (en) Production and manufacturing enterprise warehouse architecture autonomous simulator control method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180824

RJ01 Rejection of invention patent application after publication