CN108446867A - A kind of assembled architecture prefabricated components and its management method based on BIM5D - Google Patents
A kind of assembled architecture prefabricated components and its management method based on BIM5D Download PDFInfo
- Publication number
- CN108446867A CN108446867A CN201810480206.7A CN201810480206A CN108446867A CN 108446867 A CN108446867 A CN 108446867A CN 201810480206 A CN201810480206 A CN 201810480206A CN 108446867 A CN108446867 A CN 108446867A
- Authority
- CN
- China
- Prior art keywords
- prefabricated components
- bim5d
- assembled architecture
- dimension code
- code label
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000007726 management method Methods 0.000 title claims abstract description 20
- 238000010276 construction Methods 0.000 claims abstract description 37
- 238000004519 manufacturing process Methods 0.000 claims abstract description 15
- 239000000463 material Substances 0.000 claims abstract description 14
- 239000004567 concrete Substances 0.000 claims abstract description 8
- 238000000465 moulding Methods 0.000 claims abstract description 6
- 239000002023 wood Substances 0.000 claims abstract description 6
- 230000001681 protective effect Effects 0.000 claims description 22
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 10
- 238000009434 installation Methods 0.000 claims description 7
- 210000003205 muscle Anatomy 0.000 claims description 5
- 239000011248 coating agent Substances 0.000 claims description 3
- 238000000576 coating method Methods 0.000 claims description 3
- 238000009826 distribution Methods 0.000 claims description 3
- 239000002184 metal Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 19
- 238000013461 design Methods 0.000 abstract description 9
- 239000002699 waste material Substances 0.000 abstract description 7
- 238000005516 engineering process Methods 0.000 abstract description 6
- 230000032258 transport Effects 0.000 description 8
- 230000008569 process Effects 0.000 description 6
- 238000004364 calculation method Methods 0.000 description 5
- 239000011449 brick Substances 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 238000009417 prefabrication Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 238000005520 cutting process Methods 0.000 description 2
- 238000011161 development Methods 0.000 description 2
- 230000018109 developmental process Effects 0.000 description 2
- 230000003993 interaction Effects 0.000 description 2
- 238000005192 partition Methods 0.000 description 2
- 230000004044 response Effects 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 238000011835 investigation Methods 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 239000002994 raw material Substances 0.000 description 1
- 238000003860 storage Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06316—Sequencing of tasks or work
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06K—GRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
- G06K17/00—Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0633—Workflow analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Primary Health Care (AREA)
- General Health & Medical Sciences (AREA)
- Health & Medical Sciences (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention relates to assembled architecture technical fields, disclose a kind of assembled architecture prefabricated components and its management method based on BIM5D, which includes:Member body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed in the member body, and the member body includes the concrete structure and/or wood moulding structure of default specification and size;Design, production, the whole-process management of construction information that prefabricated components are realized by BIM5D technologies, improve construction precision, reduce waste of material.
Description
Technical field
The present invention relates to assembled architecture technical field more particularly to a kind of prefabricated structures of assembled architecture based on BIM5D
Part and its management method.
Background technology
Traditional interior wall partition wall or exterior wall are built by laying bricks or stones for one piece one piece with brick mostly, the weight that assembled architecture rises
Point is prefabrication, and largely building work by laying bricks or stones by site operation is changed into machinery production, is quickly assembled after transport, and reaches
Construction vision to the purpose quickly produced, the industry emerging as one, prefabricated panel is, from plant produced, to arrive building site group
Dress, just like the progress as assembly line without any confusion, the importance of people reduces, and the advantage of machinery and means of transport is played.But
It is in fact whether genuine suchThe investigation of the sides of taking part in building of building trade is shown more according to us, it is really not so.Its existing rank
The development of section still has construction problem to fail to solve.
Problem 1 uses concrete prefabricated wallboard or the cored slab of new material.It is not aware that on building site when plant produced
The length of each piece of wall needed, factory produce some fixed sizes in advance, and general wall uses these different in width
Board group closes out, and remainder is reused by cutting.Its length is about 300CM, substantially disclosure satisfy that the height of first floor
Degree, by the way that in this harden structure bulk transport to construction site, further working cut, is applied on wall, construction site
Small-sized processing of cutting factory there are one needing.
Problem 2, it is prefabricated by the whole wall of factory.Prefabricated several specifications can be generally used, first pass through BIM modelings in this case
With calculation amount, compares and be adapted to standard house type.The garden and house type of some great developments quotient is reproducible.The specification of wall is substantially solid
Fixed such as width is 3 meters, 2 meters, 1 meter, the pre-cast concrete walling with door, concrete prefabricated wall with window etc..This prefabricated update
It is advanced, directly reach the assembled a set of set house type room of effect for spelling building blocks.Larger problem is still big in production difficulty, transport at
This is higher.Assembled blanking management slightly has difficulty.
Problem 3, transport.Factory is more distant at a distance from building site, estimates the inaccuracy of dosage, can usually cause to transport
The increase of defeated cost.
Problem 4, field management.It is cut in construction site, then transports and installed on corresponding partition wall upstairs.At this time
It is not general to have some plates, which is transported and puts work flowing water section, consigns to which teams and groups uses, and can only lean on a hand
It copies and is singly allocated.Inevitably there is the material transportation in the areas A to the areas B for example, usually having, leads to various in-fightings.
Problem 5, installation.By a series of transport in front, many batches of wallboards has transported under wall, actually which block
First installWhich installed after blockThis needs very careful planning, otherwise can encounter and accidentally fill, the wallboard of not at all easy completion
Also to unload to get off to readjust again.
Invention content
It is a primary object of the present invention to propose a kind of assembled architecture prefabricated components based on BIM5D and its manager
Method is realized design, production, the whole-process management of construction information of prefabricated components by BIM5D technologies, improves construction precision,
Reduce waste of material.
To achieve the above object, a kind of assembled architecture prefabricated components based on BIM5D provided by the invention, including:Structure
Part main body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed in the member body, described
Member body includes the concrete structure and/or wood moulding structure of default specification and size.
Optionally, the positioning label is that ultra wide band UWB positions label.
Optionally, further include protective shell, form a paper chamber for housing the two-dimension code label, the guarantor in the protective shell
The edge of protective case is provided with mounting hole, and the protective shell is fixed by the muscle structure of the mounting hole and the prefabricated components to be connected
It connects.
Optionally, the protective shell is plastic protection casing or metal coating shell.
Optionally, the protective shell is rectangle protective shell, and there are four mounting holes for setting on four angles of the rectangle.
Optionally, it is stored on the two-dimension code label:Project name, floor information, location information, is born building information
Blame teams and groups' information, plan set-up time information, date of manufacture and component ID.
As another aspect of the present invention, a kind of manager of the assembled architecture prefabricated components based on BIM5D provided
Method, including:
Construction plan is formulated by BIM5D application programs, the construction plan includes the specification, size and original of prefabricated components
Material;
The prefabricated components are produced according to the construction plan;
The prefabricated components are packaged, corresponding two-dimension code label and positioning device are fixed on the prefabricated components
On;
Distribute the prefabricated components by preset flowing water section;
Assembling is carried out according to the information on the two-dimension code label.
Optionally, further include after the prefabricated components by the distribution of preset flowing water section:
The prefabricated components are tracked according to the positioning device.
Optionally, further include after the information progress Assembling according on the two-dimension code label:
According on the two-dimension code label information and the construction plan confirm installation it is whether errorless.
Optionally, the BIM5D application programs are installed on mobile terminals.
A kind of assembled architecture prefabricated components and its management method based on BIM5D proposed by the present invention, the prefabricated components
Including:Member body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed on the member body
On, the member body includes the concrete structure and/or wood moulding structure of default specification and size;It is realized by BIM5D technologies
Design, production, the whole-process management of construction information of prefabricated components, improve construction precision, reduce waste of material.
Description of the drawings
Fig. 1 is a kind of assembled architecture prefabricated components structural schematic diagram based on BIM5D that the embodiment of the present invention one provides;
Fig. 2 is the two-dimension code label fixed structure chart that the embodiment of the present invention one provides;
Fig. 3 is a kind of management method of the assembled architecture prefabricated components based on BIM5D provided by Embodiment 2 of the present invention
Flow chart;
Fig. 4 is the manager of another assembled architecture prefabricated components based on BIM5D provided by Embodiment 2 of the present invention
Method flow chart;
Fig. 5 is the manager of another assembled architecture prefabricated component based on BIM5D provided by Embodiment 2 of the present invention
Method flow chart.
Wherein, the reference numeral of Fig. 2 is:1- two-dimension code labels, 2- protective shells, 3- mounting holes, 4- muscle structures.
The embodiments will be further described with reference to the accompanying drawings for the realization, the function and the advantages of the object of the present invention.
Specific implementation mode
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
In subsequent description, using for indicating that the suffix of such as " module ", " component " or " unit " of element is only
Be conducive to the explanation of the present invention, itself there is no specific meanings.Therefore, " module " can mixedly make with " component "
With.
Embodiment one
As shown in Figure 1, in the present embodiment, a kind of assembled architecture prefabricated components based on BIM5D, including:Component master
Body, two-dimension code label and positioning device, the two-dimension code label and positioning device are fixed in the member body, the component
Main body includes the concrete structure and/or wood moulding structure of default specification and size.
In the present embodiment, by BIM5D technologies realize the designs of prefabricated components, production, construction information whole process pipe
Reason, improves construction precision, reduces waste of material.
In the present embodiment, BIM5D, as the term suggests being there are five dimension, 3D known to us on the basis of, is connected to
4D times and 5D costs.In this case, BIM (Building Information Modeling, Building Information Model)
No longer it is a simple Building Information Model, and is through whole building life cycle, extends BIM data and building
Full-range application.So BIM5D is the management carried out on the basis of BIM to entire work progress, it is a kind of tool.It is common
BIM5D softwares may be mounted on the mobile terminals such as mobile phone, tablet, it is user-friendly.
In the present embodiment, the positioning label is that ultra wide band UWB positions label.
As shown in Fig. 2, in the present embodiment, prefabricated components further include protective shell 2, it is accommodating to form one in the protective shell 2
The edge of the paper chamber of the two-dimension code label 1, the protective shell is provided with mounting hole 3, and the protective shell 2 passes through the fixation
Hole 3 is fixedly connected with the muscle structure 4 of the member body.
The muscle structure is concrete structure, wood moulding structure or other support constructions.
In the present embodiment, the protective shell is plastic protection casing or metal coating shell.
In the present embodiment, the protective shell is rectangle protective shell, and there are four solid for setting on four angles of the rectangle
Determine hole.
In the present embodiment, it is stored on the two-dimension code label:Project name, building information, floor information, positioning letter
Breath is responsible for teams and groups' information, plan set-up time information, date of manufacture and component ID.
In the present embodiment, the following table 1 is the information table of two-dimension code label:
Field attribute | Attribute value |
Project | The squares the XX second phase |
Lou Dong | A |
Floor | F3 |
Positioning | A5-A6 |
It is responsible for teams and groups | XX mono- is built |
Plan the set-up time | On April 10th, 2018 |
Date of manufacture | On March 1st, 2018 |
Plate ID | B654888 |
Table 1
In the present embodiment, it can be managed using BIM5D systems in each production link, in design link, answer
Three-dimensional modeling is carried out with BIM5D systems, and virtual reality scenario, everybody is readable for design effect;In quantities calculation link, answer
Accurate Model is carried out with BIM5D systems, quantities and actual error are minimum, can be to prefabricated by the calculation volume production product of Si Weier
Material carries out classification statistics, can submit prefabrication, not waste material and transportation cost;At the construction field (site), using BIM5D systems
By model interaction to flowing water section.Automatically the material requested amount of each flowing water section is calculated;Link, construction are positioned in prefabricated components
Personnel can select a face wall by mobile devices such as tablets from model, check the essential information of wall, can also be from Quick Response Code
Upper barcode scanning understands the house type and position that this plate is applied;In quality safety management link, by mobile devices such as mobile phones, record into
Degree, quality, safety problem.All-the-way tracking is rectified and improved, and Cost for Coordination is reduced;Link is inquired in item status, can be united by BIM5D
The Construction Condition of meter project.
Embodiment two
As shown in figure 3, in the present embodiment, a kind of management method of the assembled architecture prefabricated components based on BIM5D, packet
It includes:
S10, construction plan is formulated by BIM5D application programs, the construction plan includes the specification of prefabricated components, size
And raw material;
S20, the prefabricated components are produced according to the construction plan;
S30, the prefabricated components are packaged, corresponding two-dimension code label and positioning device are fixed on described prefabricated
On component;
S40, distribute the prefabricated components by preset flowing water section;
S50, Assembling is carried out according to the information on the two-dimension code label.
In the present embodiment, by BIM5D technologies realize the designs of prefabricated components, production, construction information whole process pipe
Reason, improves construction precision, reduces waste of material.
In the present embodiment, BIM5D, as the term suggests being there are five dimension, 3D known to us on the basis of, is connected to
4D times and 5D costs.In this case, BIM (Building Information Modeling, Building Information Model)
No longer it is a simple Building Information Model, and is through whole building life cycle, extends BIM data and building
Full-range application.So BIM5D is the management carried out on the basis of BIM to entire work progress, it is a kind of tool.It is common
BIM5D softwares may be mounted on the mobile terminals such as mobile phone, tablet, it is user-friendly.
As shown in figure 4, in the present embodiment, further including after the step S40:
S41, the prefabricated components are tracked according to the positioning device.
In transportational process and live distribution procedure, whole information follows, by BIM5D system tracking modes, until having constructed
At by its construction team setting completion label on BIM5D, with special color mark, it is normally applied for meeting on threedimensional model
Work is completed.
As shown in figure 5, in the present embodiment, further including after the step S50:
S60, according on the two-dimension code label information and the construction plan confirm installation it is whether errorless.
If installation is errorless, then it represents that the construction of the prefabricated components is completed, and otherwise, BIM5D systems initiate rectification notice, whole
After the completion of changing, the rectification problem is closed, completes construction.
In the present embodiment, the BIM5D application programs are installed on mobile terminals.
In the present embodiment, it can be managed using BIM5D systems in each production link, in design link, answer
Three-dimensional modeling is carried out with BIM5D systems, and virtual reality scenario, everybody is readable for design effect;In quantities calculation link, answer
Accurate Model is carried out with BIM5D systems, quantities and actual error are minimum, can be to prefabricated by the calculation volume production product of Si Weier
Material carries out classification statistics, can submit prefabrication, not waste material and transportation cost;At the construction field (site), using BIM5D systems
By model interaction to flowing water section.Automatically the material requested amount of each flowing water section is calculated;Link, construction are positioned in prefabricated components
Personnel can select a face wall by mobile devices such as tablets from model, check the essential information of wall, can also be from Quick Response Code
Upper barcode scanning understands the house type and position that this plate is applied;In quality safety management link, by mobile devices such as mobile phones, record into
Degree, quality, safety problem.All-the-way tracking is rectified and improved, and Cost for Coordination is reduced;Link is inquired in item status, can be united by BIM5D
The Construction Condition of meter project.
It should be noted that herein, the terms "include", "comprise" or its any other variant are intended to non-row
His property includes, so that process, method, article or device including a series of elements include not only those elements, and
And further include other elements that are not explicitly listed, or further include for this process, method, article or device institute it is intrinsic
Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including this
There is also other identical elements in the process of element, method, article or device.
The embodiments of the present invention are for illustration only, can not represent the quality of embodiment.
Through the above description of the embodiments, those skilled in the art can be understood that above-described embodiment side
Method can add the mode of required general hardware platform to realize by software, naturally it is also possible to by hardware, but in many cases
The former is more preferably embodiment.Based on this understanding, technical scheme of the present invention substantially in other words does the prior art
Going out the part of contribution can be expressed in the form of software products, which is stored in a storage medium
In (such as ROM/RAM, magnetic disc, CD), including some instructions are used so that a station terminal equipment (can be mobile phone, computer, clothes
Be engaged in device, air conditioner or the network equipment etc.) execute method described in each embodiment of the present invention.
It these are only the preferred embodiment of the present invention, be not intended to limit the scope of the invention, it is every to utilize this hair
Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills
Art field, is included within the scope of the present invention.
Claims (10)
1. a kind of assembled architecture prefabricated components based on BIM5D, which is characterized in that including:Member body, two-dimension code label and
Positioning device, the two-dimension code label and positioning device are fixed in the member body, and the member body includes default rule
The concrete structure and/or wood moulding structure of lattice and size.
2. a kind of assembled architecture prefabricated components based on BIM5D according to claim 1, which is characterized in that described fixed
Position label is that ultra wide band UWB positions label.
3. a kind of assembled architecture prefabricated components based on BIM5D according to claim 1, which is characterized in that further include
Protective shell, the protective shell is interior to form a paper chamber for housing the two-dimension code label, and the edge of the protective shell is provided with admittedly
Determine hole, the protective shell is fixedly connected by the mounting hole with the muscle structure of the prefabricated components.
4. a kind of assembled architecture prefabricated components based on BIM5D according to claim 3, which is characterized in that the guarantor
Protective case is plastic protection casing or metal coating shell.
5. a kind of assembled architecture prefabricated components based on BIM5D according to claim 3, which is characterized in that the guarantor
Protective case is rectangle protective shell, and there are four mounting holes for setting on four angles of the rectangle.
6. a kind of assembled architecture prefabricated components based on BIM5D according to claim 1, which is characterized in that described two
It is stored on dimension code label:When project name, building information, floor information, location information, responsible teams and groups information, plan installation
Between information, date of manufacture and component ID.
7. a kind of management method of the assembled architecture prefabricated components based on BIM5D, which is characterized in that including:
Construction plan is formulated by BIM5D application programs, the construction plan includes the specification, size and former material of prefabricated components
Material;
The prefabricated components are produced according to the construction plan;
The prefabricated components are packaged, corresponding two-dimension code label and positioning device are fixed on the prefabricated components;
Distribute the prefabricated components by preset flowing water section;
Assembling is carried out according to the information on the two-dimension code label.
8. a kind of management method of assembled architecture prefabricated components based on BIM5D according to claim 7, feature exist
In described to further include later by the preset flowing water section distribution prefabricated components:
The prefabricated components are tracked according to the positioning device.
9. a kind of management method of assembled architecture prefabricated components based on BIM5D according to claim 7, feature exist
In the information according on the two-dimension code label carries out Assembling and further includes later:
According on the two-dimension code label information and the construction plan confirm installation it is whether errorless.
10. a kind of management method of assembled architecture prefabricated components based on BIM5D according to claim 7, feature
It is, the BIM5D application programs installation is on mobile terminals.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810480206.7A CN108446867A (en) | 2018-05-18 | 2018-05-18 | A kind of assembled architecture prefabricated components and its management method based on BIM5D |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810480206.7A CN108446867A (en) | 2018-05-18 | 2018-05-18 | A kind of assembled architecture prefabricated components and its management method based on BIM5D |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108446867A true CN108446867A (en) | 2018-08-24 |
Family
ID=63204747
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810480206.7A Pending CN108446867A (en) | 2018-05-18 | 2018-05-18 | A kind of assembled architecture prefabricated components and its management method based on BIM5D |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108446867A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110969227A (en) * | 2019-11-27 | 2020-04-07 | 西南交通大学 | Two-dimensional code-based assembled component information management method |
JP2020109242A (en) * | 2019-01-03 | 2020-07-16 | 華北水利水電大学 | Assembly type shear wall building structure |
CN112936559A (en) * | 2021-03-16 | 2021-06-11 | 河南省公路工程局集团有限公司 | Concrete small-sized prefabricated part quality improvement method based on whole process accompanied |
CN113610389A (en) * | 2021-08-04 | 2021-11-05 | 深圳大学 | Prefabricated part production quality management system based on BIM and RFID |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006079290A (en) * | 2004-09-08 | 2006-03-23 | Kenchiku Pivot:Kk | Information management system and information management method |
CN105003028A (en) * | 2015-07-23 | 2015-10-28 | 深圳海龙建筑制品有限公司 | Prefabricated component capable of being monitored, monitoring method of prefabricated component and monitoring system of prefabricated component |
CN107146168A (en) * | 2017-07-11 | 2017-09-08 | 大连锐勃电子科技有限公司 | Wisdom building site management system based on universe frequency conversion positioning Yu self-identifying technology |
CN107542161A (en) * | 2017-08-23 | 2018-01-05 | 中建八局第建设有限公司 | BIDA engineering of integrating technical systems |
CN107958101A (en) * | 2017-11-07 | 2018-04-24 | 山东住工装配建筑有限公司 | A kind of assembled architecture Information Management System and method based on BIM |
-
2018
- 2018-05-18 CN CN201810480206.7A patent/CN108446867A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006079290A (en) * | 2004-09-08 | 2006-03-23 | Kenchiku Pivot:Kk | Information management system and information management method |
CN105003028A (en) * | 2015-07-23 | 2015-10-28 | 深圳海龙建筑制品有限公司 | Prefabricated component capable of being monitored, monitoring method of prefabricated component and monitoring system of prefabricated component |
CN107146168A (en) * | 2017-07-11 | 2017-09-08 | 大连锐勃电子科技有限公司 | Wisdom building site management system based on universe frequency conversion positioning Yu self-identifying technology |
CN107542161A (en) * | 2017-08-23 | 2018-01-05 | 中建八局第建设有限公司 | BIDA engineering of integrating technical systems |
CN107958101A (en) * | 2017-11-07 | 2018-04-24 | 山东住工装配建筑有限公司 | A kind of assembled architecture Information Management System and method based on BIM |
Non-Patent Citations (1)
Title |
---|
白庶;张艳坤;韩凤;张德海;李微;: "BIM技术在装配式建筑中的应用价值分析" * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2020109242A (en) * | 2019-01-03 | 2020-07-16 | 華北水利水電大学 | Assembly type shear wall building structure |
CN110969227A (en) * | 2019-11-27 | 2020-04-07 | 西南交通大学 | Two-dimensional code-based assembled component information management method |
CN112936559A (en) * | 2021-03-16 | 2021-06-11 | 河南省公路工程局集团有限公司 | Concrete small-sized prefabricated part quality improvement method based on whole process accompanied |
CN113610389A (en) * | 2021-08-04 | 2021-11-05 | 深圳大学 | Prefabricated part production quality management system based on BIM and RFID |
CN113610389B (en) * | 2021-08-04 | 2023-06-20 | 深圳大学 | Prefabricated component production quality management system based on BIM and RFID |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108446867A (en) | A kind of assembled architecture prefabricated components and its management method based on BIM5D | |
CN105023201B (en) | Assembled architecture Deepen Design and construction method based on BIM and big data | |
Polat | Factors affecting the use of precast concrete systems in the United States | |
US20070027732A1 (en) | Context-sensitive, location-dependent information delivery at a construction site | |
Liu et al. | Real‐Time Optimization of Precast Concrete Component Transportation and Storage | |
Re Cecconi et al. | Leveraging BIM for digital built environment asset management | |
Ikonen et al. | Use of embedded RFID tags in concrete element supply chains. | |
CN105303308A (en) | Management system and method for whole steel bar engineering process based on 3D figure information platform | |
CN110110442A (en) | A kind of parametric modeling design method of assembled architecture | |
CN111090903B (en) | BIM-based component statistical method and related device | |
Liu et al. | Design for Manufacturing and Assembly: A BIM‐Enabled Generative Framework for Building Panelization Design | |
KR20150121699A (en) | Method and system using standardized structural components | |
Ekanayake et al. | Modeling supply chain resilience in industrialized construction: A Hong Kong case | |
Zhang et al. | Fighting Covid-19 through fast delivery of a modular quarantine camp with smart construction | |
CN109360123B (en) | Multi-professional construction management method and system based on room | |
Sergei et al. | An interactive construction project for method of statement based on BIM technologies for high-speed modular building | |
Lim et al. | Evaluation of CO2 emission reduction effect using in-situ production of precast concrete components | |
Wang et al. | Causes and penalties of variation: Case study of a precast concrete slab production facility | |
Mésároš et al. | Adaptive design of formworks for building renovation considering the sustainability of construction in BIM environment—Case study | |
CN208689614U (en) | A kind of assembled architecture prefabricated components based on BIM5D | |
Bhattacharjee et al. | Adoption of pre-fabrication in construction to achieve sustainability goals: an empirical study | |
KR20210114621A (en) | Design system of building | |
Inyang et al. | A VR model of ergonomics and productivity assessment in panelized construction production line | |
Okodi-Iyah | A comparative evaluation of the environmental impact of prefabrication versus conventional construction in UAE’s construction industry | |
CN109087076B (en) | Production and manufacturing enterprise warehouse architecture autonomous simulator control method and system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180824 |
|
RJ01 | Rejection of invention patent application after publication |