CN208328902U CN201820946000.4U CN201820946000U CN208328902U CN 208328902 U CN208328902 U CN 208328902U CN 201820946000 U CN201820946000 U CN 201820946000U CN 208328902 U CN208328902 U CN 208328902U
Authority
CN
China
Prior art keywords
steel reinforcement
reinforcement cage
positioning plate
connecting rod
positioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820946000.4U
Other languages
Chinese (zh)
Inventor
隆元刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Longsheng International Construction Group Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820946000.4U priority Critical patent/CN208328902U/en
Application granted granted Critical
Publication of CN208328902U publication Critical patent/CN208328902U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a kind of steel reinforcement cage positioning devices of bored concrete pile, belong to building foundation built-in fitting field of locating technology, and it is fixed difficult to solve the problems, such as to position when steel reinforcement cage enters stake holes.It includes the locating piece that steel reinforcement cage two sides are arranged in, and locating piece includes two pieces of positioning plates and is arranged in parallel along steel reinforcement cage two sides.Two pieces of positioning plates are connected by connecting rod, and steel reinforcement cage and two poles for steel reinforcement cage positioning are provided through on positioning plate.After steel reinforcement cage transfers to stake holes, locating piece is installed to the two sides of steel reinforcement cage, the muscle hole on steel reinforcement cage is passed through by a pole, righting steel reinforcement cage, it is passed through again by another pole and is in conplane muscle hole with the muscle hole that a upper pole passes through, the plane that steel reinforcement cage is formed at the pole place of passing through at this time is substantially parallel to the ground, prevents steel reinforcement cage from deviation occurs in stake holes slip casting, while being also prevented from steel reinforcement cage and floating cage phenomenon occurs.

Description

A kind of steel reinforcement cage positioning device of bored concrete pile
Technical field
The utility model relates to building foundation built-in fitting field of locating technology more particularly to a kind of steel reinforcement cage of bored concrete pile are fixed Position device.
Background technique
With flourishing for China's construction of road and bridge cause, constantly built across rivers, the bridge in straits and grand bridge, bridge Execution conditions, the geological conditions of beam also become increasingly complex, and wherein underwater cast-in-place pile is mostly large aperture, big depth filling concrete Stake guarantees that position precision of steel reinforcement cage during filling concrete is extremely important, otherwise steel reinforcement cage position during piling It is more to set offset, steel bar cage protecting layer thickness low LCL will be caused, so as to cause engineering construction quality.
However when steel reinforcement cage enters pile hole construction, steel reinforcement cage tends not to effectively be corrected in fender pile deviation problem, So that pier stud construction when it is difficult, quality also it is difficult to ensure that.To solve the problems, such as steel reinforcement cage deviation, need in steel reinforcement cage When entering hole, needs to put into a large amount of man power and material until filling concrete is complete requires to adjust repeatedly, during this, increase The operation difficulty and labor intensity of people are processed, while increasing construction cost.
Utility model content
The purpose of this utility model is to provide a kind of steel reinforcement cage positioning devices of bored concrete pile, have and enter stake for steel reinforcement cage Fixed advantage is positioned when hole.
The above-mentioned purpose of the utility model has the technical scheme that
A kind of steel reinforcement cage positioning device of bored concrete pile, the locating piece including steel reinforcement cage two sides are arranged in, the locating piece packet It includes two pieces of positioning plates and is arranged in parallel along the steel reinforcement cage two sides, two pieces of positioning plates are connected by connecting rod, the positioning plate On be provided through the steel reinforcement cage and for the steel reinforcement cage positioning two poles.
Implement above-mentioned technical proposal locating piece is installed to the two sides of steel reinforcement cage, is passed through after steel reinforcement cage transfers to stake holes Piece pole passes through the muscle hole on steel reinforcement cage, righting steel reinforcement cage, then by another pole across passing through with a upper pole Muscle hole is in conplane muscle hole, and the plane that steel reinforcement cage is formed at the pole place of passing through at this time is substantially parallel to the ground, prevents steel In stake holes slip casting deviation occurs for muscle cage, while being also prevented from steel reinforcement cage and floating cage phenomenon occurs.
Further, the fixing glue connecting with ground is provided on the positioning plate.
Implement above-mentioned technical proposal, fixed on the ground positioning plate by fixing glue, it is fixed when steel reinforcement cage positions to prevent Position plate, which generates displacement, causes steel reinforcement cage to shift.
Further, the positioning plate along its length on be provided with first sliding groove, be provided with cunning in the first sliding groove Block is provided with the sleeve with pole cooperation on the sliding block.
Implement above-mentioned technical proposal, pole is fixed on positioning plate by the sleeve being arranged on sliding block, pole is passed through Grafting is carried out by the position of slidable adjustment sleeve of the sliding block in sliding slot behind muscle hole and with pole.
Further, it is provided with screw rod on the sliding block, is threaded on the screw rod and is supported with the first sliding groove outer wall Tight wing nut.
Implement above-mentioned technical proposal, after facilitating sleeve and pole grafting, sliding block is adjusted to suitable position and passes through butterfly Nut is fixed.
Further, the positioning plate includes the first positioning plate and the second positioning plate, is provided with cunning on second positioning plate Bar, the second sliding slot with sliding bar cooperation is provided in first positioning plate, and the slide bar is fixed far from described second One end of position plate is provided with the block for preventing the slide bar from skidding off.
Implement above-mentioned technical proposal, positioning plate length can be adjusted according to the size of steel reinforcement cage, while positioning plate It is convenient for collecting after being shunk after use, save the space that positioning plate is placed.
Further, first positioning plate is connected by a snap with second positioning plate.
Implement above-mentioned technical proposal, can be fixed by buckle after positioning plate use is finished and stored.
Further, the connecting rod is threaded on the side wall of the positioning plate.
Implement above-mentioned technical proposal, facilitates and locating piece is stored after dismantling connecting rod.
Further, the connecting rod includes first connecting rod and is arranged in described first with second connecting rod, the second connecting rod and connects It is slidably connected in bar and with the first connecting rod.
Implement above-mentioned technical proposal, length of connecting rod can be adjusted according to the size of steel reinforcement cage.
Further, the second connecting rod is provided with far from one end of the positioning plate for the tight of first connecting rod described in clamping Gu screw.
Implement above-mentioned technical proposal, after length adjustment is suitable, prevents first connecting rod and second after fixing by fastening screw Opposite sliding occurs for connecting rod.
In conclusion the utility model has the following beneficial effects:
One, it prevents steel reinforcement cage from deviation occurs in stake holes slip casting, while being also prevented from steel reinforcement cage and floating cage phenomenon occurs;
Two, positioning plate length can be adjusted according to the size of steel reinforcement cage, is shunk after positioning plate use It is convenient for collecting afterwards, save the space that positioning plate is placed.
Detailed description of the invention
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor Under, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the scheme of installation of the steel reinforcement cage positioning device of the utility model embodiment bored concrete pile;
Fig. 2 is the explosive view of the steel reinforcement cage positioning device of the utility model embodiment bored concrete pile;
Fig. 3 is the explosive view of the utility model embodiment connecting rod.
Appended drawing reference: 1, steel reinforcement cage;2, locating piece;3, positioning plate;301, the first positioning plate;302, the second positioning plate;4, Connecting rod;401, first connecting rod;402, second connecting rod;5, pole;6, fixing glue;7, first sliding groove;8, sliding block;9, sleeve;10, spiral shell Bar;11, wing nut;12, slide bar;13, second sliding slot;14, block;15, it buckles;16, fastening screw.
Specific embodiment
Below in conjunction with attached drawing, the technical solution of the utility model embodiment is described.
As shown in Figure 1, a kind of steel reinforcement cage positioning device of bored concrete pile, pass through fixation including be arranged in 1 two sides of steel reinforcement cage The locating piece 2 fixed with ground of nail 6.Locating piece 2 includes two pieces of positioning plates 3 and is arranged in parallel along 1 two sides of steel reinforcement cage, two pieces of positioning Plate 3 is connected by connecting rod 4, and connecting rod 4 is threaded on the side wall of positioning plate 3.
As shown in Fig. 2, positioning plate 3 includes the first positioning plate 301 and the second positioning plate 302.It is arranged on second positioning plate 302 There is slide bar 12, the second sliding slot 13 being slidably matched with slide bar 12 is provided in the first positioning plate 301, slide bar 12 is far from the second positioning One end of plate 302 is provided with the block 14 for preventing slide bar 12 from skidding off.Construction personnel can be according to the size of steel reinforcement cage 1 to positioning plate 3 length are adjusted, while convenient for collecting after being shunk after 3 use of positioning plate, save the space that positioning plate 3 is placed. First positioning plate 301 is connect with the second positioning plate 302 by buckle 16, can be led to after 3 use of positioning plate is finished and stored Buckle 16 is crossed to be fixed.
As shown in Fig. 2, positioning plate 3 along its length on be provided with first sliding groove 7, be provided with sliding block in first sliding groove 7 8, it is provided with the sleeve 9 cooperated with pole 5 on sliding block 8, pole 5 passes through after steel reinforcement cage 1 and carries out grafting with sleeve 9.On sliding block 8 It is provided with screw rod 10, the wing nut 11 pushed against with 7 outer wall of first sliding groove is threaded on screw rod 10, facilitates sleeve 9 and circle After 5 grafting of rod, sliding block 8 is adjusted to suitable position and is fixed by wing nut 11.
As shown in figure 3, connecting rod 4 includes first connecting rod 401 and is arranged in first connecting rod 401 and slides with first connecting rod 401 The second connecting rod 402 of dynamic connection, one end of the remotely located plate 3 of second connecting rod 402 is provided with for the tight of clamping first connecting rod 401 Gu screw 15.By passing through fastening screw 15 after opposite sliding adjustment 4 length of connecting rod of first connecting rod 401 and second connecting rod 402 Prevent first connecting rod 401 and second connecting rod 402 from opposite slide occurs after fixation.
Specific work process: after steel reinforcement cage 1 transfers to stake holes, two pieces of positioning plates 3 are installed at 1 two sides of steel reinforcement cage.Root The length for passing through the first positioning plate 301 and the opposite sliding adjustment positioning plate 3 of the second positioning plate 302 according to the size of steel reinforcement cage 1.It adjusts After integration is suitable, positioning plate 3 is fixed on the ground by fixing glue 6.Then connecting rod 4 is threaded in the side wall of locating piece On, the length of first connecting rod 401 and the opposite sliding adjustment positioning plate 3 of second connecting rod 402 is passed through according to the size of steel reinforcement cage 1. After adjustment is suitable, it is fixed by fastening screw 15.
The muscle hole on steel reinforcement cage 1 is passed through by a pole 5, is passing through sliding adjusting sleeve of the sliding block 8 in first sliding groove 7 9 position on positioning plate 3 of cylinder simultaneously carries out grafting with pole 5, and then sliding block 8 is fixed by wing nut 11 again.Such as Deviation, righting steel reinforcement cage 1 occur in stake holes for fruit steel reinforcement cage 1, then are passed through by another pole 5 and passed through with a upper pole 5 Muscle hole be in conplane muscle hole, then pole 5 and another pair sleeve 9 are subjected to grafting, and pass through 11 pairs of cunnings of wing nut Block 8 is fixed.At this point, steel reinforcement cage 1 is substantially parallel to the ground in the plane that the place of passing through of pole 5 is formed, prevent steel reinforcement cage 1 in stake Deviation occurs when the slip casting of hole, while being also prevented from steel reinforcement cage 1 and floating cage phenomenon occurs.

Claims (9)

1. a kind of steel reinforcement cage positioning device of bored concrete pile, including the locating piece (2) in steel reinforcement cage (1) two sides is arranged, feature exists In the locating piece (2) includes two pieces of positioning plates (3) and is arranged in parallel along the steel reinforcement cage (1) two sides, two pieces of positioning plates (3) it is connected by connecting rod (4), the steel reinforcement cage (1) is provided through on the positioning plate (3) and for the steel reinforcement cage (1) Two poles (5) of positioning.
2. a kind of steel reinforcement cage positioning device of bored concrete pile according to claim 1, which is characterized in that the positioning plate (3) On be provided with the fixing glue (6) connecting with ground.
3. a kind of steel reinforcement cage positioning device of bored concrete pile according to claim 2, which is characterized in that the positioning plate (3) It is provided with first sliding groove (7), is provided with sliding block (8) in the first sliding groove (7), on the sliding block (8) on along its length It is provided with the sleeve (9) with pole cooperation.
4. a kind of steel reinforcement cage positioning device of bored concrete pile according to claim 3, which is characterized in that on the sliding block (8) It is provided with screw rod (10), the wing nut pushed against with the first sliding groove (7) outer wall is threaded on the screw rod (10) (11)。
5. a kind of steel reinforcement cage positioning device of bored concrete pile according to claim 4, which is characterized in that the positioning plate (3) Including the first positioning plate (301) and the second positioning plate (302), it is provided with slide bar (12) on second positioning plate (302), it is described It is provided with the second sliding slot (13) being slidably matched with the slide bar (12) in first positioning plate (301), the slide bar (12) is separate One end of second positioning plate (302) is provided with the block (14) for preventing the slide bar (12) from skidding off.
6. a kind of steel reinforcement cage positioning device of bored concrete pile according to claim 5, which is characterized in that first positioning plate (301) it is connect with second positioning plate (302) by buckling (15).
7. a kind of steel reinforcement cage positioning device of bored concrete pile according to claim 5, which is characterized in that connecting rod (4) spiral shell Line is connected on the side wall of the positioning plate (3).
8. a kind of steel reinforcement cage positioning device of bored concrete pile according to claim 7, which is characterized in that connecting rod (4) packet Include first connecting rod (401) and with second connecting rod (402), the second connecting rod (402) is arranged in the first connecting rod (401) simultaneously It is slidably connected with the first connecting rod (401).
9. a kind of steel reinforcement cage positioning device of bored concrete pile according to claim 8, which is characterized in that the second connecting rod (402) one end far from the positioning plate (3) is provided with the fastening screw (16) for first connecting rod described in clamping (401).
CN201820946000.4U 2018-06-19 2018-06-19 A kind of steel reinforcement cage positioning device of bored concrete pile Active CN208328902U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820946000.4U CN208328902U (en) 2018-06-19 2018-06-19 A kind of steel reinforcement cage positioning device of bored concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820946000.4U CN208328902U (en) 2018-06-19 2018-06-19 A kind of steel reinforcement cage positioning device of bored concrete pile

Publications (1)

Publication Number Publication Date
CN208328902U true CN208328902U (en) 2019-01-04

Family

ID=64771622

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820946000.4U Active CN208328902U (en) 2018-06-19 2018-06-19 A kind of steel reinforcement cage positioning device of bored concrete pile

Country Status (1)

Country Link
CN (1) CN208328902U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185027A (en) * 2019-06-24 2019-08-30 福建磐基岩土工程有限公司 A kind of guiding device in fashioned iron insertion casing
CN110485412A (en) * 2019-09-20 2019-11-22 五冶集团上海有限公司 The bracket system and its application method of pile foundation more piece steel reinforcement cage connection construction
CN110670585A (en) * 2019-10-23 2020-01-10 中建七局安装工程有限公司 Pile extension construction method
CN111395344A (en) * 2020-03-25 2020-07-10 中国一冶集团有限公司 Reusable secant pile positioning device and construction method
CN112523092A (en) * 2020-11-17 2021-03-19 成都交投建筑工业化有限公司 Use method of connecting base capable of being adapted to pier columns of different sizes
CN115652976A (en) * 2022-11-03 2023-01-31 中建八局第二建设有限公司 Modular frame post dowel bar fixing device
CN115652976B (en) * 2022-11-03 2024-07-09 中建八局第二建设有限公司 Combined frame column dowel bar fixing device

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185027A (en) * 2019-06-24 2019-08-30 福建磐基岩土工程有限公司 A kind of guiding device in fashioned iron insertion casing
CN110485412A (en) * 2019-09-20 2019-11-22 五冶集团上海有限公司 The bracket system and its application method of pile foundation more piece steel reinforcement cage connection construction
CN110485412B (en) * 2019-09-20 2022-09-02 五冶集团上海有限公司 Bracket device for pile foundation multi-section reinforcement cage connection construction and use method thereof
CN110670585A (en) * 2019-10-23 2020-01-10 中建七局安装工程有限公司 Pile extension construction method
CN110670585B (en) * 2019-10-23 2021-03-26 中建七局安装工程有限公司 Pile extension construction method
CN111395344A (en) * 2020-03-25 2020-07-10 中国一冶集团有限公司 Reusable secant pile positioning device and construction method
CN112523092A (en) * 2020-11-17 2021-03-19 成都交投建筑工业化有限公司 Use method of connecting base capable of being adapted to pier columns of different sizes
CN115652976A (en) * 2022-11-03 2023-01-31 中建八局第二建设有限公司 Modular frame post dowel bar fixing device
CN115652976B (en) * 2022-11-03 2024-07-09 中建八局第二建设有限公司 Combined frame column dowel bar fixing device

Similar Documents

Publication Publication Date Title
CN208328902U (en) A kind of steel reinforcement cage positioning device of bored concrete pile
CN110359636A (en) A kind of novel fabricated building fixing steel plate and its construction method
CN207749517U (en) A kind of pile extension device for concrete pipe pile
CN202164825U (en) Fastener for adjusting positions
US3861046A (en) Batter board construction
CN109083331B (en) Fast-assembling prestressed anchorage for concrete building
CN109056756B (en) A kind of suspension device and its construction method of High water cut side slope
CN209941667U (en) Positioning and marking device for drilled pile
CN207420036U (en) Steel bar template positions constructing structure in reinforced concrete member
CN203579870U (en) Prestress combined support pile steel mold structure
CN208733665U (en) A kind of fixed structure of concrete side built-in fitting
CN108149926B (en) Split bolt assembly and application thereof in water conservancy pouring template system
CN206971773U (en) Precast beam lifts positioner
CN205875202U (en) Cast -in -place frame tunnel formwork system of high water content ultra -soft soil box multi -chambered
CN215594765U (en) Auxiliary tool for forming setting slurry between component and ground
CN205242684U (en) Wall body erection joint spare
CN211312542U (en) Steel sheet pile foundation pit supporting structure
KR101495318B1 (en) Civil and building structures for mounting support
CN207934462U (en) Super plane earth post-cast strip flatness accurately controls tooling
CN203238674U (en) Fixing device of steel plate waterstop belt
CN208844597U (en) A kind of single-ended fixed water-stopping pull rod
DE102012214338B4 (en) Method for producing an injection pile below a water surface
CN207878663U (en) Pre-embedded bolt
CN209873571U (en) Plate girder template fastening device
CN217811096U (en) Fertilizer groove backfill unilateral formwork structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200805

Address after: No.2, floor 2, building 8, No.139, South jiaodu Road, Wuhou District, Chengdu City, Sichuan Province 610000

Patentee after: LONGSHENG INTERNATIONAL CONSTRUCTION GROUP Co.,Ltd.

Address before: 641220 Xielong Village Group 3, Songjiazhen, Zizhong County, Neijiang City, Sichuan Province

Patentee before: Long Yuangang

TR01 Transfer of patent right