CN208270709U - A kind of intelligent substation integrated power supply Insulation Inspection System - Google Patents

A kind of intelligent substation integrated power supply Insulation Inspection System Download PDF

Info

Publication number
CN208270709U
CN208270709U CN201821044884.0U CN201821044884U CN208270709U CN 208270709 U CN208270709 U CN 208270709U CN 201821044884 U CN201821044884 U CN 201821044884U CN 208270709 U CN208270709 U CN 208270709U
Authority
CN
China
Prior art keywords
unit
relay
power supply
inspection system
integrated power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821044884.0U
Other languages
Chinese (zh)
Inventor
滕松
刘新
许浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Xuzhou Power Supply Co of Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Xuzhou Power Supply Co of Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Xuzhou Power Supply Co of Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201821044884.0U priority Critical patent/CN208270709U/en
Application granted granted Critical
Publication of CN208270709U publication Critical patent/CN208270709U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

The utility model provides a kind of intelligent substation integrated power supply Insulation Inspection System, and the Insulation Inspection System includes signal acquisition unit, signal processing unit, A/D converting unit, central control unit, relay, storage unit, display unit, alarm unit, communication unit and key-press input unit;Signal acquisition unit handles the signal input signal processing unit of acquisition, A/D converting unit is inputted again to carry out A/D conversion and input central control unit, central control unit is compared judgement with preset reference value to the signal of input, detect the integrated power supply insulation status, and storage is carried out by storage unit and display unit and is shown, if there is insulation fault, classification alarm is carried out by alarm unit.The utility model provides a kind of intelligent substation integrated power supply Insulation Inspection System, provides effective guarantee for the normal operation of direct current system safety.

Description

A kind of intelligent substation integrated power supply Insulation Inspection System
Technical field
The utility model belongs to technical field of electric power detection, in particular to a kind of intelligent substation integrated power supply insulation inspection Examining system.
Background technique
With the continuous development of power technology, intelligent substation is commonplace, compared to more traditional direct current supply system System is powered using integrated power source apparatus now: DC power supply, electric power inverter, leads to electric power ac uninterrupted power supply The devices such as credit DC transformating power are combined into one, and share the battery group of DC power supply, and are uniformly monitored complete Equipment.
Insulation monitoring is one of most important guarantee in integrated power supply management, and a perfect power-supply management system is not from Open good Insulation monitoring function.Insulation fault once occurs for integrated power supply, and it is straight that problem often occurs from its main part It flows in power-supply system.When monopole ground connection occurs for direct current system, it cannot be formed into a loop, because without generating short circuit current.But such as Fruit is not handled in time, when two points ground fault or multipoint earthing occurs in system, it is possible to ground short circuit failure is constituted, from And cause protective relaying device, automation equipment and device for signalling that malfunction tripping occurs, DC insurance fusing is even resulted in, Direct current system decompression.Therefore it provides a set of effective integrated power supply Insulation Inspection System is the normal fortune of direct current system safety Row provides effective ensure.
Utility model content
The utility model provides a kind of intelligent substation integrated power supply Insulation Inspection System, is that direct current system is normal safely Operation effective ensure is provided.
The utility model is specially a kind of intelligent substation integrated power supply Insulation Inspection System, the Insulation Inspection System It is single including signal acquisition unit, signal processing unit, A/D converting unit, central control unit, relay, storage unit, display Member, alarm unit, communication unit and key-press input unit, the signal acquisition unit, the signal processing unit, the A/D Converting unit and the central control unit are linked in sequence, the central control unit respectively with the signal acquisition unit, institute State signal processing unit, the relay, the storage unit, the display unit, the alarm unit, the communication unit It is connected with the key-press input unit, the relay is also connected with the signal acquisition unit;The signal acquisition list The signal of acquisition is inputted the signal processing unit and is filtered enhanced processing by member, then is inputted the A/D converting unit and carried out A/D converts and inputs the central control unit, signal and preset reference value of the central control unit to input It is compared judgement, detects the integrated power supply insulation status, and carry out by the storage unit and the display unit Storage display, if there is insulation fault, carries out classification alarm by the alarm unit.
The signal acquisition unit acquisition DC bus positive and negative electrode voltage-to-ground and branch leakage current, the DC bus Positive and negative electrode voltage-to-ground is measured using partial pressure method, and the DC bus positive and negative electrode is directly accessed voltage with conducting wire and accesses circuit Interior, the voltage access circuit is by balance resistance bridge joint ground, and the central control unit is by controlling closing for the relay It closes and disconnects, and then control the state that ground resistance accesses tested branch;The branch leakage current is sensed using DC leakage current Device acquires the out-of-balance current of branch road, and the branch positive and negative electrode cable is all passed through from the DC leakage current center sensor, Electrical link does not occur;The branch number be more than or equal to 1, the DC leakage current number of probes also greater than be equal to 1, and with The branch number is equal.
The signal processing unit includes difference amplifier, low-pass filter, and input signal is amplified and filtered respectively Wave processing.
The display unit uses liquid crystal display, in conjunction with the storage unit, the key-press input unit to the intelligence It can substation's integrated power supply progress parameter setting;The display unit can real-time display DC bus positive and negative electrode it is electric over the ground Pressure value, branch leakage current value and failure report.
The relay includes the first relay and the second relay, and first relay is alternate with DC bus anode It connects, second relay and DC bus cathode are mutually indirect, and the central control unit carries out circulation behaviour to the relay Make, share three steps:
Step 1 is closed first relay, is closed second relay;
Step 2 is closed first relay, disconnects second relay;
Step 3 disconnects first relay, is closed second relay;
It is separated by 10 power frequency periods between each step.
The central control unit controls the signal acquisition unit according to preset relevant parameter, at the signal The acquisition process work for managing unit, relay progress signal, according to the DC bus positive and negative electrode voltage-to-ground of acquisition Value and the branch leakage current value judge whether that ground fault and fault type occurs:
If the branch leakage current value is not zero, the DC bus positive and negative electrode voltage-to-ground value is reduced, then the intelligence Monopolar grounding fault occurs for substation's integrated power supply;
If the branch leakage current value is zero, the DC bus positive and negative electrode voltage-to-ground value is constant, respectively according to It is adopted when first relay closure, second relay disconnect and first relay disconnects, second relay is closed The DC bus positive and negative electrode voltage-to-ground value of collection calculates the two poles of the earth insulation against ground resistance value using Kirchhoff's law, into And judge whether that two pole ground faults occur;
The central control unit carries out Difference Calculation to the DC bus positive and negative electrode voltage-to-ground value of acquisition, sentences Break whether to occur to exchange and scurry into DC Line Fault,The UACHave to scurry into the alternating current of direct current system Valid value, the A are correction coefficient, the u1...unFor collected voltage in each period, the n is adopting in signal period Number of samples.
The communication unit uses MODBUS communications protocol to be communicated with master-slave mode, the Insulation Inspection System conduct The command response that slave is sent according to host computer, and will test data and the analysis result upload host computer.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of intelligent substation integrated power supply Insulation Inspection System of the utility model.
Specific embodiment
With reference to the accompanying drawing to a kind of specific reality of intelligent substation integrated power supply Insulation Inspection System of the utility model The mode of applying elaborates.
As shown in Figure 1, the Insulation Inspection System of the utility model includes signal acquisition unit, signal processing unit, A/D turns Unit, central control unit, relay, storage unit, display unit, alarm unit, communication unit and key-press input unit are changed, The signal acquisition unit, the signal processing unit, the A/D converting unit and the central control unit are linked in sequence, The central control unit is single with the signal acquisition unit, the signal processing unit, the relay, the storage respectively First, the described display unit, the alarm unit, the communication unit are connected with the key-press input unit, the relay Also it is connected with the signal acquisition unit;The signal acquisition unit by the signal of acquisition input the signal processing unit into Row filter amplifying processing, then input the A/D converting unit and carry out A/D conversion and input the central control unit, it is described in Centre control unit is compared judgement with preset reference value to the signal of input, detects the integrated power supply insulation shape Condition, and storage is carried out by the storage unit and the display unit and is shown, it is single by the alarm if there is insulation fault Member carries out classification alarm.
The signal acquisition unit acquisition DC bus positive and negative electrode voltage-to-ground and branch leakage current, the DC bus Positive and negative electrode voltage-to-ground is measured using partial pressure method, and the DC bus positive and negative electrode is directly accessed voltage with conducting wire and accesses circuit Interior, the voltage access circuit is by balance resistance bridge joint ground, and the central control unit is by controlling closing for the relay It closes and disconnects, and then control the state that ground resistance accesses tested branch;The branch leakage current is sensed using DC leakage current Device acquires the out-of-balance current of branch road, and the branch positive and negative electrode cable is all passed through from the DC leakage current center sensor, Electrical link does not occur;The branch number be more than or equal to 1, the DC leakage current number of probes also greater than be equal to 1, and with The branch number is equal.
The signal processing unit includes difference amplifier, low-pass filter, and input signal is amplified and filtered respectively Wave processing.
The display unit uses liquid crystal display, in conjunction with the storage unit, the key-press input unit to the intelligence It can substation's integrated power supply progress parameter setting;The display unit can real-time display DC bus positive and negative electrode it is electric over the ground Pressure value, branch leakage current value and failure report.
The relay includes the first relay and the second relay, and first relay is alternate with DC bus anode It connects, second relay and DC bus cathode are mutually indirect, and the central control unit carries out circulation behaviour to the relay Make, share three steps:
Step 1 is closed first relay, is closed second relay;
Step 2 is closed first relay, disconnects second relay;
Step 3 disconnects first relay, is closed second relay;
It is separated by 10 power frequency periods between each step.
The central control unit controls the signal acquisition unit according to preset relevant parameter, at the signal The acquisition process work for managing unit, relay progress signal, according to the DC bus positive and negative electrode voltage-to-ground of acquisition Value and the branch leakage current value judge whether that ground fault and fault type occurs:
If the branch leakage current value is not zero, the DC bus positive and negative electrode voltage-to-ground value is reduced, then the intelligence Monopolar grounding fault occurs for substation's integrated power supply;
If the branch leakage current value is zero, the DC bus positive and negative electrode voltage-to-ground value is constant, respectively according to It is adopted when first relay closure, second relay disconnect and first relay disconnects, second relay is closed The DC bus positive and negative electrode voltage-to-ground value of collection calculates the two poles of the earth insulation against ground resistance value using Kirchhoff's law, into And judge whether that two pole ground faults occur;
The central control unit carries out Difference Calculation to the DC bus positive and negative electrode voltage-to-ground value of acquisition, sentences Break whether to occur to exchange and scurry into DC Line Fault,The UACHave to scurry into the alternating current of direct current system Valid value, the A are correction coefficient, the u1...unFor collected voltage in each period, the n is adopting in signal period Number of samples.
The communication unit uses MODBUS communications protocol to be communicated with master-slave mode, the Insulation Inspection System conduct The command response that slave is sent according to host computer, and will test data and the analysis result upload host computer.
Finally it should be noted that only illustrating the technical solution of the utility model in conjunction with above-described embodiment rather than limiting it System.Those of ordinary skills in the art should understand that arriving, those skilled in the art can be to the specific implementation of the utility model Mode is modified or replaced equivalently, but these modifications or change are being applied among pending claims.

Claims (6)

1. a kind of intelligent substation integrated power supply Insulation Inspection System, which is characterized in that the Insulation Inspection System includes letter Number acquisition unit, signal processing unit, A/D converting unit, central control unit, relay, storage unit, display unit, report Alert unit, communication unit and key-press input unit, the signal acquisition unit, the signal processing unit, A/D conversion are single First and described central control unit is linked in sequence, the central control unit respectively with the signal acquisition unit, the signal Processing unit, the relay, the storage unit, the display unit, the alarm unit, the communication unit and described Key-press input unit is connected, and the relay is also connected with the signal acquisition unit;The signal acquisition unit will adopt The signal of collection inputs the signal processing unit and is filtered enhanced processing, then inputs the A/D converting unit and carry out A/D conversion And the central control unit is inputted, the central control unit is compared the signal of input with preset reference value Judgement, detects the integrated power supply insulation status, and carry out storage by the storage unit and the display unit and show, If there is insulation fault, classification alarm is carried out by the alarm unit.
2. a kind of intelligent substation integrated power supply Insulation Inspection System according to claim 1, which is characterized in that described Signal acquisition unit acquires DC bus positive and negative electrode voltage-to-ground and branch leakage current, the DC bus positive and negative electrode conducting wire It is directly accessed in voltage access circuit, for the voltage access circuit by balance resistance bridge joint ground, the central control unit is logical The open and close for controlling the relay is crossed, and then controls the state that ground resistance accesses tested branch;The branch electric leakage Stream is using the out-of-balance current of DC leakage flow sensor acquisition branch road, and the branch positive and negative electrode cable is all from the direct current Leakage current sensor center passes through, and electrical link does not occur;The branch number is more than or equal to 1, the DC leakage current sensing Device number is and equal with the branch number also greater than being equal to 1.
3. a kind of intelligent substation integrated power supply Insulation Inspection System according to claim 1, which is characterized in that described Signal processing unit includes difference amplifier, low-pass filter, and input signal is amplified and is filtered respectively.
4. a kind of intelligent substation integrated power supply Insulation Inspection System according to claim 1, which is characterized in that described Display unit uses liquid crystal display, in conjunction with the storage unit, the key-press input unit to the intelligent substation one Change power supply and carries out parameter setting;The display unit being capable of real-time display DC bus positive and negative electrode voltage-to-ground value, branch electric leakage Flow valuve and failure report.
5. a kind of intelligent substation integrated power supply Insulation Inspection System according to claim 1 or 2, which is characterized in that The relay includes the first relay and the second relay, and first relay and DC bus anode are mutually indirect, described Second relay and DC bus cathode are mutually indirect, and the central control unit carries out circulate operation to the relay.
6. a kind of intelligent substation integrated power supply Insulation Inspection System according to claim 1, which is characterized in that described Communication unit uses MODBUS communications protocol to be communicated with master-slave mode, and the Insulation Inspection System is as slave according to upper The command response that machine is sent, and will test data and the analysis result upload host computer.
CN201821044884.0U 2018-07-03 2018-07-03 A kind of intelligent substation integrated power supply Insulation Inspection System Active CN208270709U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821044884.0U CN208270709U (en) 2018-07-03 2018-07-03 A kind of intelligent substation integrated power supply Insulation Inspection System

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821044884.0U CN208270709U (en) 2018-07-03 2018-07-03 A kind of intelligent substation integrated power supply Insulation Inspection System

Publications (1)

Publication Number Publication Date
CN208270709U true CN208270709U (en) 2018-12-21

Family

ID=64690646

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821044884.0U Active CN208270709U (en) 2018-07-03 2018-07-03 A kind of intelligent substation integrated power supply Insulation Inspection System

Country Status (1)

Country Link
CN (1) CN208270709U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109375117A (en) * 2018-07-31 2019-02-22 国网江苏省电力有限公司徐州供电分公司 A kind of intelligent substation integrated power supply Insulation Inspection System based on bridge method and DC leakage current method
CN110596519A (en) * 2019-10-18 2019-12-20 国网江苏省电力有限公司盐城供电分公司 Direct current system ground fault detection system based on Fourier transform and detection method thereof
CN113075457A (en) * 2021-03-26 2021-07-06 阳光电源股份有限公司 Vehicle-mounted charger and alternating current side insulation detection circuit and method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109375117A (en) * 2018-07-31 2019-02-22 国网江苏省电力有限公司徐州供电分公司 A kind of intelligent substation integrated power supply Insulation Inspection System based on bridge method and DC leakage current method
CN110596519A (en) * 2019-10-18 2019-12-20 国网江苏省电力有限公司盐城供电分公司 Direct current system ground fault detection system based on Fourier transform and detection method thereof
CN113075457A (en) * 2021-03-26 2021-07-06 阳光电源股份有限公司 Vehicle-mounted charger and alternating current side insulation detection circuit and method thereof

Similar Documents

Publication Publication Date Title
CN208270709U (en) A kind of intelligent substation integrated power supply Insulation Inspection System
CN109375117A (en) A kind of intelligent substation integrated power supply Insulation Inspection System based on bridge method and DC leakage current method
CN204214977U (en) Neutral line break detection control device
CN205982461U (en) Low -voltage distribution is electric detection means for cabinet
CN108375711A (en) A kind of insulating monitoring method of bipolar earth-free HVDC power-supply systems
CN110112712A (en) Power distribution network earth protective device and its sampling control method with the configuration of double mutual inductors
CN204789852U (en) Detection apparatus for DC power supply system storage battery earth fault
CN206773058U (en) OPGW on-line monitoring systems
CN109142993A (en) A kind of multifunction insulating detector suitable for DC power system
CN203339659U (en) Single-phase electric leakage protection and power supply automation recovery device
CN207410117U (en) A kind of computer room and the online Centralizing inspection device of substation's UPS DC power supplies
CN207516488U (en) A kind of power cable detection device based on polarization depolarization current
CN103812210A (en) Intelligent monitoring system for alternating current-direct current uninterruptible power supply system
CN104035003B (en) Sectionalized single busbar connection PT small current earthing wire-selecting logic decision methods arranged side by side
CN206945939U (en) A kind of detection means of display device for short circuit
CN106908686A (en) Single-phase grounded malfunction in grounded system of low current reliability judgment means based on asymmetric method
CN106546210A (en) A kind of disconnecting switch outer corner measurement system and method for on-line monitoring
CN106066445A (en) Voltage transformer open delta circuit breaking monitoring device and application process
CN203811747U (en) A small current grounding line selection system
CN103595264B (en) There is the high frequency electric source of site manual operation system
CN212808479U (en) Electrified fault diagnosis device of low-voltage transformer area zero line
CN206259694U (en) The protection device of inversion system
CN202522638U (en) Grid failure intelligent identification device
CN205749760U (en) Voltage transformer open delta circuit breaking monitoring device
CN107860968A (en) Power consumption self-diagnostic circuit, power consumption self-diagnosing method and its measuring instrument

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant