CN208235589U - River tunnel is worn under a kind of half adverse construction method of open cut - Google Patents

River tunnel is worn under a kind of half adverse construction method of open cut Download PDF

Info

Publication number
CN208235589U
CN208235589U CN201820636176.XU CN201820636176U CN208235589U CN 208235589 U CN208235589 U CN 208235589U CN 201820636176 U CN201820636176 U CN 201820636176U CN 208235589 U CN208235589 U CN 208235589U
Authority
CN
China
Prior art keywords
tunnel
river
waterproof
protective layer
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820636176.XU
Other languages
Chinese (zh)
Inventor
沈碧辉
彭加强
闫自海
熊松
刘长宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201820636176.XU priority Critical patent/CN208235589U/en
Application granted granted Critical
Publication of CN208235589U publication Critical patent/CN208235589U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

River tunnel is worn under a kind of half adverse construction method of open cut, tunnel includes enclosure wall, tunnel structure top plate, tunnel structure bottom plate and tunnel structure side wall, and tunnel further includes waterproof layer, protective layer and waterproof insulation blanket;It goes along with sb. to guard him coping and is provided with crown beam;Waterproof layer is arranged above tunnel structure top plate, two lateral flanges of waterproof layer to crown beam bottom;The top of waterproof layer is arranged in protective layer;The top of protective layer is arranged in waterproof insulation blanket, and the two sides of waterproof insulation blanket wrap crown beam.It is shorter to solve river dry season, it is desirable that open trench tunnel construct fast quick-recovery river the problem of;Using multiple tracks water proof safeguard procedures, soil excavation and structure below top plate is avoided to pour period river water infiltration;Enclosure wall and internal structure form iterative structure, and whole stress reduces structure uneven subsidence, reduce construction risk.

Description

River tunnel is worn under a kind of half adverse construction method of open cut
Technical field
The utility model relates to wear river tunnel under half adverse construction method of a kind of tunnel more particularly to a kind of open cut.
Background technique
It need to generally guarantee river water flow section when wearing river construction under open trench tunnel, usual way is within river dry season Tunnel is built using Open Cut Method, the wet season restores river water flowing, but when dry season, the time was shorter, applies in dry season tunnel Work does not complete, and there are problems that river can not be restored in time in the wet season.
Utility model content
The purpose of the utility model is to provide wear river tunnel under a kind of half adverse construction method of open cut.Therefore, this is practical new Type uses following technical scheme.
River tunnel is worn under a kind of half adverse construction method of open cut, the tunnel includes enclosure wall, tunnel structure top plate, tunnel Structure base slab and tunnel structure side wall, the tunnel further include waterproof layer, protective layer and waterproof insulation blanket;
The coping of going along with sb. to guard him is provided with crown beam;
The waterproof layer is arranged above the tunnel structure top plate, two lateral flanges of the waterproof layer to the crown beam bottom Portion;
The top of the waterproof layer is arranged in the protective layer;
The top of the protective layer is arranged in the waterproof insulation blanket, and the two sides of the waterproof insulation blanket wrap the hat Beam.
Preferably, the enclosure wall, top plate and bottom plate and side wall are reinforced concrete structure.
Preferably, the tunnel structure top plate, reinforcing bar of the tunnel structure bottom plate with the enclosure wall are plugged by reinforcing bar Device connection, forms one.
Preferably, the protective layer is microlith element concrete structure.
Preferably, the thickness of the protective layer is not less than 0.3 meter.
The beneficial effects of the utility model are: it is shorter to solve river dry season, it is desirable that the fast quick-recovery of open trench tunnel construction The problem of river;Wet season river water is avoided to flood the risk of open-cut foundation ditch;Using multiple tracks water proof safeguard procedures, avoid below top plate River water penetrates into during soil excavation and structure pour;Enclosure wall and internal structure form iterative structure, enclosure wall and internal structure Whole stress can reduce structure uneven subsidence, reduce construction risk.
Detailed description of the invention
Fig. 1 is tunnel structure schematic diagram in the utility model.
Description of symbols: 1, enclosure wall;2, top plate;3, crown beam;4, waterproof layer;5, protective layer;6, waterproof insulation blanket;7, The river bed soil body;8, bottom plate;9, side wall.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Wear river tunnel under a kind of half adverse construction method of open cut, tunnel includes enclosure wall 1, top plate 2, bottom plate 8 and side wall 9, Tunnel further includes waterproof layer 4, protective layer 5 and waterproof insulation blanket 6;The top of enclosure wall 1 is provided with crown beam 3.The setting of waterproof layer 4 exists Above tunnel structure top plate, two lateral flanges of waterproof layer to crown beam bottom.The top of waterproof layer is arranged in protective layer.Anti- water segregation The top of protective layer 5 is arranged in blanket 6, and the two sides of waterproof insulation blanket 6 wrap crown beam 3.Enclosure wall and top plate form iterative structure, And the vertical bearing capacity of enclosure wall is strengthened, the amount of reinforcement of enclosure wall is higher than the amount of reinforcement of common enclosure wall by 5% ~ 10%, reduce construction risk when soil excavation below top plate.Enclosure wall, top plate and bottom plate and side wall are armored concrete knot The reinforcing bar of structure, top plate and bottom plate and side wall connect to form iterative structure by reinforcing bar connector with the reinforcing bar of enclosure wall, enclosure wall Iterative structure is formed with internal structure, i.e. enclosure wall and top plate and bottom plate and side wall is respectively formed iterative structure, forms one, goes along with sb. to guard him Wall and internal structure entirety stress can reduce structure uneven subsidence, reduce construction risk.Half reversed construction method of open cut The tunnel structure applied is as described in Figure 1.
Tunnel open excavation half reversed construction method in river is worn under one kind, comprising the following steps: step 1, in river bed construction foundation pit Enclosure wall 1 is going along with sb. to guard him coping setting crown beam 3, is excavating the river bed soil body 7 to tunnel structure ceiling location.Step 2, in tunnel Structure roof position pours top plate 2, and top plate 2 and enclosure wall 1 form iterative structure.Step 3 applies waterproof layer 4 above top plate, For two lateral flanges of waterproof layer to crown beam bottom, waterproof layer needs to meet level-one waterproofing grade requirement.Step 4, in the upper of waterproof layer Side is laid with protective layer 5, and protective layer can be microlith element concrete structure, and the thickness of protective layer is not less than 0.3 meter, in the top of protective layer Waterproof insulation blanket 6 is set, and the two sides of waterproof insulation blanket wrap crown beam, and setting waterproof insulation blanket uses the protection of multiple tracks water proof and arranges It applies, avoids soil excavation and structure below top plate from pouring period river water infiltration, the two sides of waterproof insulation blanket wrap crown beam and avoid River water is penetrated by gap.Step 5 carries out earthing above waterproof insulation blanket, restores river, excavates under top plate from Adjacent Pit Necromancer body in the case that river restores water flowing or river not water flowing, can carry out applying for the excavation top plate lower section soil body to foundation pit bottom Work.Step 6 pours bottom plate 8 and side wall 9 respectively, and bottom plate and side wall form iterative structure with enclosure wall, and construction is completed.
The above embodiments are only illustrative of the principle and efficacy of the utility model, and not for limitation, this is practical new Type.Any person skilled in the art can all carry out above-described embodiment under the spirit and scope without prejudice to the utility model Modifications and changes.Therefore, such as those of ordinary skill in the art without departing from the revealed essence of the utility model All equivalent modifications or change completed under mind and technical idea, should be covered by the claim of the utility model.

Claims (5)

1. wearing river tunnel under a kind of half adverse construction method of open cut, the tunnel includes enclosure wall, tunnel structure top plate, tunnel knot Structure bottom plate and tunnel structure side wall, which is characterized in that the tunnel further includes waterproof layer, protective layer and waterproof insulation blanket;
The coping of going along with sb. to guard him is provided with crown beam;
The waterproof layer is arranged above the tunnel structure top plate, two lateral flanges of the waterproof layer to the crown beam bottom;
The top of the waterproof layer is arranged in the protective layer;
The top of the protective layer is arranged in the waterproof insulation blanket, and the two sides of the waterproof insulation blanket wrap the crown beam.
2. wearing river tunnel under half adverse construction method of a kind of open cut according to claim 1, which is characterized in that described to go along with sb. to guard him Wall, tunnel structure top plate, tunnel structure bottom plate and tunnel structure side wall are reinforced concrete structure.
3. wearing river tunnel under half adverse construction method of a kind of open cut according to claim 2, which is characterized in that the tunnel Structure roof, tunnel structure bottom plate are connect with the reinforcing bar of the enclosure wall by reinforcing bar connector, and one is formed.
4. wearing river tunnel under half adverse construction method of a kind of open cut according to claim 1, which is characterized in that the protection Layer is microlith element concrete structure.
5. wearing river tunnel under half adverse construction method of a kind of open cut according to claim 1 or 4, which is characterized in that described The thickness of protective layer is not less than 0.3 meter.
CN201820636176.XU 2018-04-28 2018-04-28 River tunnel is worn under a kind of half adverse construction method of open cut Active CN208235589U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820636176.XU CN208235589U (en) 2018-04-28 2018-04-28 River tunnel is worn under a kind of half adverse construction method of open cut

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820636176.XU CN208235589U (en) 2018-04-28 2018-04-28 River tunnel is worn under a kind of half adverse construction method of open cut

Publications (1)

Publication Number Publication Date
CN208235589U true CN208235589U (en) 2018-12-14

Family

ID=64581113

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820636176.XU Active CN208235589U (en) 2018-04-28 2018-04-28 River tunnel is worn under a kind of half adverse construction method of open cut

Country Status (1)

Country Link
CN (1) CN208235589U (en)

Similar Documents

Publication Publication Date Title
CN108589776A (en) Tunnel open excavation half reversed construction method in river is worn under one kind
CN102434175A (en) Tunnel lining self waterproof drainage system
CN202483588U (en) Self water-proof drainage system of tunnel lining
CN205677631U (en) It is combined arch tunnel lining structure at the bottom of the box tunnel with hydrophobic function
CN205134283U (en) Base concrete panel rock -fill dam
CN105297685A (en) Base concrete face rock fill dam and construction method thereof
CN105421497B (en) The waterproof construction method of sole plate and ground wall connecting node in combined fender construction system
CN108316354A (en) With waterproof, the underground pipe gallery structure of drain function and its construction method
CN106884431B (en) A kind of building pit foundation construction safety supporting construction
CN104234081B (en) At cheuch, barrel open cut tunnel directly enters the construction method in hole
CN111472326A (en) Method and structure for building gravity dam on deep covering layer
CN208981282U (en) A kind of high earthquake territory concrete face rockfill dam dam crest structure
CN107338770B (en) Combined dam shape of asphalt concrete core wall dam and concrete gravity dam and construction method thereof
CN214783609U (en) Domatic seepage prevention structure of retaining type road bed that soaks
CN203939036U (en) A kind of steel sheet pile cofferdam structure that is applicable to river course
CN208235589U (en) River tunnel is worn under a kind of half adverse construction method of open cut
CN106567365A (en) Earth and rockfill dam longitudinal reinforcement construction method
CN111424685A (en) Deep water falling hole processing structure and method for backfilling foundation in large karst depression
CN207143965U (en) Steel plate concrete combined type anti-floating water sealing structure
CN105970882A (en) Structure solving reverse osmosis water problem of dam body in construction process of concrete-faced rockfill dam and construction method thereof
CN211200274U (en) Assembled channel shore protection structure
CN212477620U (en) Structure for building gravity dam on deep and thick covering layer
CN204875807U (en) Bridge owner mound cushion cap underground structure on basement rock of river course abrupt slope
CN113846609A (en) A manger plate gravity dam joint design for covering layer connects basement rock foundation
CN207700204U (en) A kind of french drain structure for Slope Prevention

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant