CN208234420U - Construction site Miniature hanging device - Google Patents
Construction site Miniature hanging device Download PDFInfo
- Publication number
- CN208234420U CN208234420U CN201820534124.1U CN201820534124U CN208234420U CN 208234420 U CN208234420 U CN 208234420U CN 201820534124 U CN201820534124 U CN 201820534124U CN 208234420 U CN208234420 U CN 208234420U
- Authority
- CN
- China
- Prior art keywords
- guide rail
- column
- sliding block
- sprocket
- chain
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Construction site Miniature hanging device, including mobile base and hoisting mechanism, mobile base bottom is set there are four wheel, mobile base upper surface is vertically equipped with column, the upper end of the column is fixed with installation guide rail along left and right horizontal direction, the left bottom of installation guide rail is fixed on the upper end of the column, and hoisting mechanism includes horizontal shifting component and vertical pull element.The utility model has many advantages, such as that simple structure, easily operated, reduction labor intensity of workers, raising working efficiency, security reliability are strong.
Description
Technical field
The utility model relates to lifting machinery field, specially a kind of construction site Miniature hanging device.
Background technique
When construction site is constructed, need to use boom hoisting, such as during municipal road construction, construction material
It is transported by haulage vehicle to job location, needs that heavier construction material is unloaded from Construction traffic, when construction finishes
Afterwards, it when construction material needs to be transported through using vehicle, needs to be not run out construction material and reloads on vehicle, however
It when carrying out these operations, mostly uses carry out manual operation using worker greatly, labor intensity is larger;Or want pre-buried each under road
When kind pipeline (drainpipe, steam heating pipe, natural gas tube etc.) and excavation inspection shaft, inspection-pit, need to carry out trench along road
Slot and foundation pit, when worker carries out construction operation in groove and foundation pit, the worker on ground can deliver into groove and foundation pit to be applied
Work tool and construction material, these constructions are general also using manually being operated, not only large labor intensity, and working efficiency is low, and
And since groove, foundation pit and vehicle periphery are not equipped with protective fence, downward or deliver heavier construction appliance and apply upwards
When work material, there is biggish security risk, therefore just need to design a kind of Miniature hanging device for construction site, reduce work
The labor intensity of people.
Utility model content
The utility model in order to solve shortcoming in the prior art, provide a kind of structure it is simple, it is easily operated, reduce
Labor intensity of workers improves the strong construction site Miniature hanging device of working efficiency, security reliability.
In order to solve the above technical problems, the utility model adopts the following technical solution:
Construction site Miniature hanging device, including mobile base and hoisting mechanism, mobile base bottom are set there are four vehicle
Wheel, mobile base upper surface are vertically equipped with column, and the upper end of the column is fixed with installation guide rail along left and right horizontal direction, installs guide rail
Left bottom is fixed on the upper end of the column, and hoisting mechanism includes horizontal shifting component and vertical pull element;
Mobile base upper surface is equipped with the power mechanism for driving column to horizontally rotate, and power mechanism includes rotating electric machine
And mounting cylinder, mounting cylinder are fixedly mounted on mobile base upper surface, the lower end of column is plugged in mounting cylinder and column and peace
Fitted tube is rotatably assorted, and the main shaft of rotating electric machine is equipped with head sprocket, and column lower part is coaxial to be equipped with accessary sprocket wheel, and head sprocket passes through the
One chain and accessary sprocket wheel are sequentially connected;
Installation guide rail is concrete filled rectangular steel tube members, and the vertical pull element of hoisting mechanism includes electric block and sliding block, installation
Top and bottom on the right side of guide rail are respectively set there are two pilot hole, and two pilot holes are correspondingly arranged up and down and two pilot holes
Length is arranged along left and right horizontal direction, and sliding block is assemblied in the pore of installation guide rail and sliding block passes through idler wheel and installs guide rail
Hole wall is slidably matched, and vertically offers perforation on sliding block, the top and bottom of perforation respectively with the pilot hole at top and
The pilot hole of bottom is corresponding to be connected to, and the mounting rack for being upward through top guide hole, electric block assembly are fixed at the top of sliding block
At the top of mounting rack, the movable end of the wirerope on electric block passes through the pilot hole of upside, perforation and downside vertically downward
The suspension hook being connected with after pilot hole immediately below sliding block;
The horizontal shifting component of hoisting mechanism includes traction electric machine, the first sprocket wheel, the second sprocket wheel and the second chain, traction electricity
Machine is fixed on the upper end of the column portion, and the first sprocket wheel is arranged on the main shaft of traction electric machine, and the second sprocket wheel is rotatably connected on installation guide rail
Right end inside, the left bottom for installing guide rail is provided with the first jockey sprocket, installs and is internally provided with second on the left of guide rail
Jockey sprocket, one end of the second chain and the left side of sliding block connect, and the other end of the second chain and the right side of sliding block connect,
Second chain from left to right successively with the second jockey sprocket, the first sprocket wheel, the first jockey sprocket and the second sprocket engagement, the second chain
One section and wirerope vertical interlaced of the item between the second sprocket wheel and the first jockey sprocket;
Left side in mobile base is provided with clump weight;
Wear-resistant plastic barrel is provided in the perforation of sliding block;
Be fixed with the first stiffener plate between the side wall and mobile base upper surface of mounting cylinder, installation guide rail downside with
Two piece of second stiffener plate is equipped between column.
By adopting the above technical scheme, the utility model has the following beneficial effects:
(1) hoisting mechanism of the utility model includes horizontal shifting component and vertical pull element, and vertical pull element is just
In vertically lifting by crane to construction material, pipeline, material needed for being easy to lift gear grips construction etc. has been also convenient for
It hangs construction material and carries out constructing operation, the horizontal shifting component of the utility model moves left and right convenient for drive suspension hook in left-right direction
To drive construction material to move left and right, the range of lifting extensively makes;
(2) the horizontal shifting component of the hoisting mechanism of the hoisting mechanism of the utility model include traction electric machine, the first sprocket wheel,
Second sprocket wheel and the second chain, traction electric machine are fixed on the upper end of the column portion, and the first sprocket wheel is arranged on the main shaft of traction electric machine, the
Two sprocket wheels are rotatably connected on inside the right end of installation guide rail, and the left bottom for installing guide rail is provided with the first jockey sprocket, installation
The second jockey sprocket is internally provided on the left of guide rail, one end of the second chain and the left side of sliding block connect, the second chain
The connection of the right side of the other end and sliding block, the second chain are successively oriented to the second jockey sprocket, the first sprocket wheel, first from left to right
Sprocket wheel and the second sprocket engagement, one section between the second sprocket wheel and the first jockey sprocket of the second chain is vertical with wirerope to be handed over
Mistake, the utility model horizontal shifting component are convenient for driving suspension hook to move left and right along installation guide rail by sliding block, the model that can be lifted by crane
It encloses greatly, suspension hook is convenient for hoisting construction material, and sliding block vertically offers perforation, and the perforation inner wall of sliding block is equipped with wear-resistant plastic
Cylinder, Wear-resistant plastic barrel can prevent steel rope abrasion sliding block, and Wear-resistant plastic barrel is also convenient for being replaced, the level of the utility model
Traversing component and vertical pull element are used in conjunction with each other, and are improved work efficiency, and structure is simple, high reliablity when use, peace
It is complete highly reliable;
(3) the utility model is equipped with power mechanism, and power mechanism includes rotating electric machine and mounting cylinder, and mounting cylinder is fixedly mounted
In mobile base upper surface, the lower end of column is plugged in mounting cylinder and column is rotatably assorted with mounting cylinder, rotating electric machine
Main shaft is equipped with head sprocket, and column lower part is coaxial to be equipped with accessary sprocket wheel, and head sprocket is sequentially connected by the first chain and accessary sprocket wheel,
After the utility model passes through hoisting mechanism lifting construction material, rotating electric machine drives column to rotate by head sprocket, convenient for operating,
Reduce the labor intensity of worker;
(4) it is equipped with clump weight in the mobile base of the utility model, convenient for enhancing the stability of the utility model, prevented
Topple over, is fixed with the first stiffener plate between the side wall and mobile base upper surface of the mounting cylinder of the utility model, installation is led
Two piece of second stiffener plate is equipped between rail downside and column, horizontal shifting component when the second stiffener plate in installation guide rail
It is safer when being used with vertical pull element, it consolidates, keeps the utility model use more reliable;
In conclusion the utility model has, structure is simple, easily operated, reduction labor intensity of workers, improves work effect
The advantages that rate, strong security reliability.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the sectional view of the installation guide rail of Fig. 1 middle punch vertically;
Fig. 3 is the enlarged drawing in Fig. 1 at M.
Specific embodiment
As shown in Figure 1-3, the construction site Miniature hanging device of the utility model includes mobile base 1 and hoisting machine
Structure, 1 bottom of mobile base are set there are four wheel 2, and 1 upper surface of mobile base is vertically equipped with column 11,11 upper end edge of column or so
Horizontal direction is fixed with installation guide rail 18, and the left bottom of installation guide rail 18 is fixed on 11 upper end of column, and hoisting mechanism includes water
Put down traversing component and vertical pull element;
1 upper surface of mobile base is equipped with the power mechanism for driving column 11 to horizontally rotate, and power mechanism includes rotation
Motor 5 and mounting cylinder 9, mounting cylinder 9 are fixedly mounted on 1 upper surface of mobile base, and the lower end of column 11 is plugged in mounting cylinder 9
And column 11 is rotatably assorted with mounting cylinder 9, the main shaft of rotating electric machine 5 is equipped with head sprocket 6,11 lower part of column is coaxial be equipped with from
Sprocket wheel 7, head sprocket 6 are sequentially connected by the first chain 8 with accessary sprocket wheel 7;
Installation guide rail 18 is concrete filled rectangular steel tube members, and the vertical pull element of hoisting mechanism includes electric block 23 and sliding block
19, it installs and is respectively set at the top and bottom of the right side of guide rail 18 there are two pilot hole 27, two about 27 pilot hole correspondences are set
It sets and the length of two pilot holes 27 is arranged along left and right horizontal direction, sliding block 19 is assemblied in the pore of installation guide rail 18 and sliding
Block 19 is slidably matched by idler wheel 24 and the hole wall of installation guide rail 18, and perforation 21 is vertically offered on sliding block 19, is perforated
The connection corresponding with the pilot hole 27 of the pilot hole 27 at top and bottom respectively of 21 top and bottom, the top fixation of sliding block 19 are oriented
On across top guide hole 27 mounting rack 22, electric block 23 is assemblied in the top of mounting rack 22, the steel wire on electric block 23
Rope 4 movable end pass through vertically downward upside pilot hole 27, perforation 21 and downside pilot hole 27 after be connected with positioned at sliding block
Suspension hook 15 immediately below 19;
The horizontal shifting component of hoisting mechanism includes traction electric machine 14, the first sprocket wheel 26, the second sprocket wheel 17 and the second chain
16, traction electric machine 14 is fixed on 11 upper end of column, and the first sprocket wheel 26 is arranged on the main shaft of traction electric machine 14, the second sprocket wheel 17
It is rotatably connected on inside the right end of installation guide rail 18, the left bottom of installation guide rail 18 is provided with the first jockey sprocket 13, installs
The left side of guide rail 18 is internally provided with the second jockey sprocket 25, and one end of the second chain 16 is connect with the left side of sliding block 19, the
The other end of two chains 16 is connect with the right side of sliding block 19, the second chain 16 from left to right successively with the second jockey sprocket 25,
First sprocket wheel 26, the first jockey sprocket 13 and the engagement of the second sprocket wheel 17, the second chain 16 is in the second sprocket wheel 17 and the first drag chain
One section between wheel 13 and 4 vertical interlaced of wirerope;
Left side in mobile base 1 is provided with clump weight 3;
Wear-resistant plastic barrel 20 is provided in the perforation 21 of sliding block 19;
It is fixed with the first stiffener plate 10 between 1 upper surface of side wall and mobile base of mounting cylinder 9, installs under guide rail 18
Two piece of second stiffener plate 12 is equipped between side and column 11.
The specifically used method of the utility model is as follows:
When using the utility model, first passes through vehicle and transport construction material to job location, it is then practical new using this
Type unloads construction material down from vehicle, and the utility model is first moved to job location, adjusts the lifting of the utility model
Direction makes the direction of suspension hook be directed at the direction of construction material, and traction electric machine 14 is actuated for work, and the main shaft of traction electric machine 14 is just
Turn that the second chain 16 is driven to rotate forward along the first sprocket wheel 26, the second jockey sprocket 25, the second sprocket wheel 17 and the first jockey sprocket 13, the
Pore inner wall of the lower half web movable slider 19 of two chains 16 by idler wheel 24 along installation guide rail 18 slides to the right, and sliding block 19 passes through
Wirerope 4 drives suspension hook 15 to slide to the right, when sliding block 19 slide into the left side of the second sprocket wheel 17 and with the second sprocket wheel 17 close to when, lead
Draw motor 14 to stop working, electric block 23 starts, and electric block 23 drives suspension hook 15 to decline by wirerope 4, and suspension hook 15 exists
Decline under the action of gravity and wirerope 4, when suspension hook 15 touches the construction material on vehicle, electric block 23 stops working;
Then by the direct hook block of construction material on suspension hook 15, electric block 23 starts, and electric block 23 shrinks wirerope
4, wirerope 4, which is shunk, drives suspension hook 15 that construction material is sling certain altitude, and then rotating electric machine 5 starts, the master of rotating electric machine 5
Axis drives column 11 to rotate by head sprocket 6, and the rotation of column 11 drives suspension hook 15 to be directed at job location (in irrigation canals and ditches or foundation pit), connects
Electric block 23 by 4 slow release of wirerope, wirerope 4 slowly extends, and suspension hook 15 drives the construction material of lifting to drop to
In job location (in irrigation canals and ditches or foundation pit), then construction personnel unclamps suspension hook 15, and after unclamping suspension hook 15, electric block 23 shrinks steel
Cord 4, wirerope 4, which is shunk, drives suspension hook 15 to move up, and then construction personnel is constructed using construction material;When construction material
Material is when being not run out, and the utility model can also be used construction material is lifted to again on vehicle and be transported through;
When the utility model use finishes, using the wheel 2 of 1 lower section of the utility model mobile base, by the utility model
New job site is pulled to continue to use.
The present embodiment not makes any form of restriction the shape of the utility model, material, structure etc., all foundations
The technical essence of the utility model any simple modification, equivalent change and modification to the above embodiments, belong to this reality
With the protection scope of new technique scheme.
Claims (7)
1. construction site Miniature hanging device, it is characterised in that: including mobile base and hoisting mechanism, mobile base bottom is set
There are four wheel, mobile base upper surface is vertically equipped with column, and the upper end of the column is fixed with installation guide rail along left and right horizontal direction, peace
The left bottom of dress guide rail is fixed on the upper end of the column, and hoisting mechanism includes horizontal shifting component and vertical pull element.
2. construction site Miniature hanging device according to claim 1, it is characterised in that: mobile base upper surface is equipped with
Power mechanism for driving column to horizontally rotate, power mechanism include rotating electric machine and mounting cylinder, and mounting cylinder is fixedly mounted on
Mobile base upper surface, the lower end of column is plugged in mounting cylinder and column is rotatably assorted with mounting cylinder, the master of rotating electric machine
Axis is equipped with head sprocket, and column lower part is coaxial to be equipped with accessary sprocket wheel, and head sprocket is sequentially connected by the first chain and accessary sprocket wheel.
3. construction site Miniature hanging device according to claim 2, it is characterised in that: installation guide rail is rectangular steel pipe
Structure, the vertical pull element of hoisting mechanism include electric block and sliding block, install the top and bottom on the right side of guide rail and set respectively
Pilot hole there are two setting, two pilot holes are correspondingly arranged up and down and the length of two pilot holes is arranged along left and right horizontal direction,
Sliding block is assemblied in the pore of installation guide rail and sliding block is slidably matched by the hole wall of idler wheel and installation guide rail, along vertical on sliding block
Direction offers perforation, the connection corresponding with the pilot hole of the pilot hole at top and bottom respectively of the top and bottom of perforation, sliding block
Top be fixed with the mounting rack for being upward through top guide hole, electric block is assemblied at the top of mounting rack, on electric block
The movable end of wirerope pass through vertically downward be connected with after the pilot hole of upside, perforation and the pilot hole of downside positioned at sliding block just under
The suspension hook of side.
4. construction site Miniature hanging device according to claim 3, it is characterised in that: the horizontal shifting of hoisting mechanism
Component includes traction electric machine, the first sprocket wheel, the second sprocket wheel and the second chain, and traction electric machine is fixed on the upper end of the column portion, the first chain
Wheel is arranged on the main shaft of traction electric machine, and the second sprocket wheel is rotatably connected on inside the right end of installation guide rail, installs the left side of guide rail
Bottom is provided with the first jockey sprocket, installs and is internally provided with the second jockey sprocket on the left of guide rail, one end of the second chain with
The left side of sliding block connects, and the other end of the second chain and the right side of sliding block connect, and the second chain is from left to right successively with the
Two jockey sprockets, the first sprocket wheel, the first jockey sprocket and the second sprocket engagement, the second chain is in the second sprocket wheel and the first drag chain
One section between wheel and wirerope vertical interlaced.
5. construction site Miniature hanging device according to claim 1, it is characterised in that: the left side in mobile base is set
It is equipped with clump weight.
6. construction site Miniature hanging device according to claim 3, it is characterised in that: be provided in the perforation of sliding block
Wear-resistant plastic barrel.
7. construction site Miniature hanging device according to claim 2, it is characterised in that: the side wall of mounting cylinder and movement
It is fixed with the first stiffener plate between base upper surface, installs and is equipped with two piece of second reinforcing rib between guide rail downside and column
Plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820534124.1U CN208234420U (en) | 2018-04-16 | 2018-04-16 | Construction site Miniature hanging device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820534124.1U CN208234420U (en) | 2018-04-16 | 2018-04-16 | Construction site Miniature hanging device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208234420U true CN208234420U (en) | 2018-12-14 |
Family
ID=64583022
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820534124.1U Expired - Fee Related CN208234420U (en) | 2018-04-16 | 2018-04-16 | Construction site Miniature hanging device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208234420U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109455131A (en) * | 2018-12-20 | 2019-03-12 | 周义浩 | Upper rail can folding-jib moveable vertical hoisting mechanism |
CN109795964A (en) * | 2019-03-27 | 2019-05-24 | 温州宏腾建设有限公司 | A kind of municipal construction culvert pipe hanging device |
-
2018
- 2018-04-16 CN CN201820534124.1U patent/CN208234420U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109455131A (en) * | 2018-12-20 | 2019-03-12 | 周义浩 | Upper rail can folding-jib moveable vertical hoisting mechanism |
CN109455131B (en) * | 2018-12-20 | 2024-04-16 | 周义浩 | Movable vertical hoisting mechanism with upper guide rail capable of being folded into arms |
CN109795964A (en) * | 2019-03-27 | 2019-05-24 | 温州宏腾建设有限公司 | A kind of municipal construction culvert pipe hanging device |
CN109795964B (en) * | 2019-03-27 | 2021-01-12 | 温州宏腾建设有限公司 | Culvert pipe lifting device for municipal construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102530734B (en) | Movable portal crane | |
CN208234420U (en) | Construction site Miniature hanging device | |
CN206255777U (en) | Self-propelled multipurpose is adjustable double lifting point truss straddle truck | |
CN201647906U (en) | Artificial bored well pile earthwork hoister | |
CN102518396A (en) | Automatic drilling machine | |
CN201882805U (en) | Underground self-moving type multifunctional assembling machine | |
CN101949169B (en) | Large pipeline sludge dredging machine | |
CN203684019U (en) | Height and span adjustable track laying machine for subway construction | |
CN204251100U (en) | One fixedly drags for oily device | |
CN110467066B (en) | Quick cable winding and unwinding device for whole dragging and moving drill rig | |
WO2018145327A1 (en) | Vertical lifting equipment and method | |
CN202881952U (en) | Automatic walking type drawbench | |
CN107859084A (en) | Diaphram wall grab type chute forming machine | |
CN104500116B (en) | A kind of machine-carried type auxiliary stand lift transport device | |
JP3372095B2 (en) | Underground sewer maintenance device and workbench used for the underground sewer maintenance device | |
CN206128160U (en) | Operation device that open caisson sinks unearthedly | |
CN205990887U (en) | Light-duty detection drilling machine | |
CN214031291U (en) | Cable conveying system for open caisson construction | |
CN103387114B (en) | A kind of chute installation device of drag conveyer at front part of coalface | |
CN211644368U (en) | Lifting device for bucket of manual hole digging pile | |
CN107761938B (en) | Transverse sewer dredging system and dredging method | |
CN205617379U (en) | A vehicular diesel pile driver for maintenance of oil gas field well head | |
CN215331634U (en) | Device for protecting hole opening of dug pile during lifting | |
CN112878932A (en) | Automatic pulley device for lifting and lowering tubular column in oil well operation | |
CN104860212A (en) | Micro crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181214 Termination date: 20190416 |
|
CF01 | Termination of patent right due to non-payment of annual fee |