CN208183758U - The stake holes lattice column positioning and plumbing system of dry method pore-forming - Google Patents

The stake holes lattice column positioning and plumbing system of dry method pore-forming Download PDF

Info

Publication number
CN208183758U
CN208183758U CN201820475134.2U CN201820475134U CN208183758U CN 208183758 U CN208183758 U CN 208183758U CN 201820475134 U CN201820475134 U CN 201820475134U CN 208183758 U CN208183758 U CN 208183758U
Authority
CN
China
Prior art keywords
lattice column
supporting beam
column
locating rack
stake holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820475134.2U
Other languages
Chinese (zh)
Inventor
陶俊辉
毕德臣
张方敏
辛谦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Original Assignee
Qingdao Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd filed Critical Qingdao Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority to CN201820475134.2U priority Critical patent/CN208183758U/en
Application granted granted Critical
Publication of CN208183758U publication Critical patent/CN208183758U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The stake holes lattice column positioning and plumbing system of dry method pore-forming is symmetrically arranged with two supporting beams the utility model relates to deep foundation pit construction equipment technical field on the ground at the top of stake holes;Supporting beam activity is erected at the top of No.1 locating rack;Fastening crank one end rotates and is plugged in inside pinion steering mechanism after passing through passing through on crank support;The both ends of fastening screw are screwed in the threaded hole of supporting beam by screw thread;Laser plumb instrument is equipped with right above the hole heart of stake holes, the bottom of Laser plumb instrument is fixed on supporting beam top by tripod erection;The top on steel reinforcement cage top and be located at lattice column Basolateral wall on sliding sleeve be equipped with set column holder;Several air bag jacks are fixed on set column holder, lattice column plan-position and verticality can be accurately positioned, it is closely connected to ensure that later period steel linking beam is connect with lattice column, prevent the main stress structure such as lattice column and beam column from clashing, the safety for guaranteeing bracing members installation, answers practicability stronger in urban track traffic deep foundation pit support.

Description

The stake holes lattice column positioning and plumbing system of dry method pore-forming
Technical field
The utility model relates to deep foundation pit construction equipment technical fields, and in particular to the stake holes lattice column of dry method pore-forming positions Verticality-regulating system.
Background technique
Currently, during common deep pit construction, especially in urban track traffic open cut section and open cut In the Deep foundation Pit excavation at station, foundation pit support system in such a way that concrete support and bracing members combine, for greatly across Foundation pit is spent, lattice column is directly rigidly connected with top concrete support, bears most Integral Loading, bottom bracing members Fractional load is acted on lattice column by steel linking beam, the connection of lattice column and concrete support, steel linking beam is reliable Property directly affects the degree of stability of foundation pit support system;Existing lattice column does not have accurate position control device, lattice when installing The installation of column cannot be accurately positioned and adjust verticality, and the lattice column after the completion of constructing can have dislocation, torsion and inclined feelings Condition influences the safety of bracing members installation, it would be highly desirable to improve.
Utility model content
The purpose of this utility model is that in view of the drawbacks of the prior art and insufficient, provide that a kind of structure is simple, and design is closed Reason, the stake holes lattice column positioning and plumbing system of dry method pore-forming easy to use can be accurately positioned lattice column plan-position and hang down Straight degree, so that lattice column plan-position and vertical axis position can meet design requirement, it is ensured that later period steel linking beam and lattice Column connects closely connected, prevents the main stress structure such as lattice column and beam column from clashing, and guarantees the safety of bracing members installation, in city Answer practicability stronger in city's rail traffic deep foundation pit support.
In order to achieve the above purposes, the technical solution adopted by the utility model is:, and it includes supporting beam, No.1 locating rack, two Number locating rack, limit hole, crank support, fastening crank, pinion steering mechanism, limiting device, fastening screw, Laser plumb instrument, Pin hole, cross spacing pin, set column holder, air bag jack, laser reflecting measurement plate;Two are symmetrically arranged on ground at the top of stake holes Root supporting beam, and the middle part of two supporting beams is arranged in stake holes;The both ends bottom of supporting beam is respectively symmetrically vertically fixed equipped with No.1 Position frame, the inside of No.1 locating rack is connected with No. two locating racks by connecting rod, and supporting beam activity is erected at No.1 locating rack Top;It is equipped with symmetrical limit hole in the middle part of the No.1 locating rack and No. two locating racks, two adjacent limit holes Spacing is of same size with supporting beam;The middle part weldering of No.1 locating rack is equipped with crank support;No.1 locating rack and No. two locating racks it Between be equipped with pinion steering mechanism, and pinion steering mechanism bottom is fixed on the ground by limiting device;It wears fastening crank one end It crosses after passing through on crank support to rotate and be plugged in inside pinion steering mechanism, the other end dew for fastening crank is located at No.1 positioning The outside of frame;No.1 locating rack and No. two locating racks both ends bottoms are equipped with sand box support, and sand box support bottom is fixed on On ground;It is threaded through in the middle part of fastening screw on the inside of pinion steering mechanism, and the gear of screw thread and pinion steering mechanism thereon Engagement;The both ends of fastening screw are screwed in the threaded hole of supporting beam by screw thread;Laser lead is equipped with right above the hole heart of stake holes Hammer instrument into shape, the bottom of Laser plumb instrument is fixed on supporting beam top by tripod erection;The side of two supporting beams is equipped with number A pin hole, activity is plugged in two symmetrical pin holes of supporting beam respectively at the both ends of two cross spacing pins;Cross spacing pin with It is inserted with lattice column in the square hole that supporting beam is constituted, the upper end of lattice column is connect with truck crane, and the bottom end of lattice column is plugged in stake In the middle part of steel reinforcement cage in hole;The top on steel reinforcement cage top and be located at lattice column Basolateral wall on sliding sleeve be equipped with set column holder, Sleeve column pedestal upper end is connect by rope with truck crane;Several air bag jacks are fixed with around the set column holder;It is described The interior bottom of lattice column be equipped with laser reflecting measurement plate.
Further, the air bag jack is connected to hemisphere air compressor and intake and exhaust valve group by tracheae On.
After adopting the above structure, the utility model has the beneficial effect that the stake holes lattice of dry method pore-forming described in the utility model Structure column positioning and plumbing system, can be accurately positioned lattice column plan-position and verticality, so that lattice column plan-position and vertical Axial location can meet design requirement, it is ensured that later period steel linking beam connect closely connected with lattice column, prevents lattice column and beam column Equal main stress structure clashes, and guarantees the safety of bracing members installation, answers in urban track traffic deep foundation pit support practical Property it is stronger, the utility model has structure simple, setting rationally, the advantages that low manufacture cost.
Detailed description of the invention
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, before not making the creative labor property It puts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the top view of Fig. 1.
Fig. 3 is the top view of specific embodiment.
Description of symbols:
Supporting beam 1,2, No. two locating racks 3 of No.1 locating rack, limit hole 4, crank support 5, fastening crank 6, gear turn to Mechanism 7, limiting device 8, fastening screw 9, Laser plumb instrument 10, tripod 11, cross spacing pin 12, set column holder 13, air bag Jack 14, laser reflecting measurement plate 15, air compressor and intake and exhaust valve group 16, stake holes 17, lattice column 18, casing 19, Steel reinforcement cage 20, sand box support 21, pin hole 22.
Specific embodiment
The utility model will be further described below with reference to the accompanying drawings.
Referring to as shown in Figure 1-Figure 3, present embodiment the technical solution adopted is that: it includes that supporting beam 1, No.1 are fixed Position 2, No. two locating racks 3 of frame, limit hole 4, crank support 5, fastening crank 6, pinion steering mechanism 7, limiting device 8, fastening spiral shell Bar 9, Laser plumb instrument 10, pin hole 22, cross spacing pin 12, set column holder 13, air bag jack 14, laser reflecting measurement plate 15;Two supporting beams 1 are symmetrically arranged on the ground at 17 top of stake holes, and the middle part of two supporting beams 1 is arranged in stake holes 17;Support The both ends bottom of beam 1 is respectively symmetrically vertically equipped with No.1 locating rack 2, and the inside of No.1 locating rack 2 is connected with two by connecting rod Number locating rack 3, and 1 activity of supporting beam is erected at the top of No.1 locating rack 2;The No.1 locating rack 2 and No. two locating racks 3 Middle part is equipped with symmetrical limit hole 4, and the width and supporting beam 1 of two adjacent limit holes 4 are of same size;No.1 locating rack 2 Middle part weldering be equipped with crank support 5;Pinion steering mechanism 7 is equipped between No.1 locating rack 2 and No. two locating racks 3, and gear turns It is fixed on the ground to 7 bottom of mechanism by limiting device 8;Fastening 6 one end of crank pass through crank support 5 on pass through after rotate It is plugged in inside pinion steering mechanism 7, the other end dew of fastening crank 6 is located at the outside of No.1 locating rack 2;No.1 locating rack 2 It is equipped with sand box support 21 with the both ends bottom of No. two locating racks 3,21 bottom of sand box support fixes on the ground;Fastening screw 9 Middle part be threaded through the inside of pinion steering mechanism 7, and screw thread thereon is engaged with the gear of pinion steering mechanism 7;Fastening screw 9 Both ends be screwed in by screw thread in the threaded hole of supporting beam 1;Laser plumb instrument 10, laser are equipped with right above the hole heart of stake holes 17 The bottom of plummet instrument 10 is fixed on 1 top of supporting beam by the erection of tripod 11;The side of two supporting beams 1 is equipped with several pins Hole 22, activity is plugged in the symmetrical pin hole 22 of two supporting beams 1 respectively at the both ends of two cross spacing pins 12;Cross spacing pin It is inserted with lattice column 18 in 12 square holes constituted with supporting beam 1, the upper end of lattice column 18 is connect with truck crane, the bottom of lattice column 18 Hold 20 middle part of steel reinforcement cage being plugged in stake holes 17;The top on 20 top of steel reinforcement cage and the cunning on 18 Basolateral wall of lattice column Dynamic to be arranged with column holder 13, set 13 upper end of column holder is connect by rope with truck crane;It is solid around the set column holder 13 Surely there are several air bag jacks 14;The middle inside of the lattice column 18 is equipped with laser reflecting measurement plate 15.
Further, four air bag jacks 14 are connected to hemisphere air compressor and intake and exhaust by tracheae In valve group 16.
The working principle of this specific embodiment:: according to measurement and positioning, hand excavation's hole simultaneously embedded casing 19, dry method at After the completion of hole, the dregs on 17 periphery of stake holes is cleaned out, surveyor calculates the azimuth axis in length and breadth of lattice column 18, and on ground On marked with spacer bar;According to orientation axis is by No.1 locating rack 2 and No. two locating racks 3 are hung and orifice position, adjust Whole No.1 locating rack 2 and No. two 3 axis of locating rack are aligned with the axis of stake holes 17, and are placed on the top of sand box support 21;It will It in the decentralization to hole of steel reinforcement cage 20, is fixed after the apertures with cross-arm, slowly protrudes into steel reinforcement cage 20 using truck crane lifting lattice column 18 Interior, lattice column 18 protrudes into 2m in steel reinforcement cage 20,20 center of steel reinforcement cage is located substantially at using crane adjustment 18 position of lattice column, in lattice The horizontal reinforcement that journey groined type welds in 20 main reinforcement of steel reinforcement cage on the every side of structure column 18, and guarantee that lattice column 18 has 30- away from every side The activity of 50mm;Four air bag jacks 14 set column holder 13 is fixed on four faces of lattice column 18, and can more than Lower activity;Air compressor machine and tracheae are connected, and inflation test in advance, is placed on 18 bottom of lattice column;It extracts cross-arm out, transfers lattice column 18 with steel reinforcement cage 20, after steel reinforcement cage 20 all in hole after, pause transfer;Construction personnel shakes fastening crank 6, by I-steel Supporting beam 1 is moved to 18 two sides of lattice column, and every side interspaces 5mm in advance;First cross spacing pin 12 is then penetrated into supporting beam 1 It is interior, continue lower section lattice column 18, and adjust lattice column 18 and be close proximity to first cross spacing pin 12, then laterally limits second Position pin 12 penetrates in supporting beam 1, and so far plane limit is completed, decentralization lattice column 18 to projected depth;Transfer laser reflecting measurement Plate 15, four angles of reflecting plate are respectively and fixedly provided with thin cord, and level stops after transferring to 18 length 1/2 of lattice column;It is pushed up in stake holes 17 Laser plumb instrument 10 is placed in portion, and after adjustment is horizontal, be switched on transmitting laser downwards, and measures the offset of laser reflecting measurement plate 15 Amount;According to the offset of measurement, is inflated using air compressor machine to four air bag jacks 14, filled to the opposite direction jack of offset Gas pressurization, until being overlapped at 15 center of laser reflecting measurement plate with laser using air bag, the adjustment verticality work of lattice column 18 It completes;Then pressurize simultaneously to four air bag jacks 14, fix 18 bottom of lattice column, it is ensured that 18 verticality of lattice column not because Filling concrete process shifts, while preventing steel reinforcement cage 20 from floating;Laser plummet apparatus and laser reflecting measurement plate 15 are packed up, It using crane decentralization conduit to projected depth, transfers in catheter procedure, forbids to collide locating support, forbid quickly to transfer conduit, Filling concrete is freely fallen into stake using hopper;After the completion of pile foundation concreting after 24 hours, can remove locating rack and Vertical adjustment air bag jack 14;After the completion of dismounting, graded broken stone is backfilled into hole, is used for compacted fixed lattice column 18, is prevented from excavating Or concrete stull construction collision lattice column 18, cause its offset.
After adopting the above structure, present embodiment has the beneficial effect that dry method pore-forming described in present embodiment Stake holes lattice column positioning and plumbing system, lattice column plan-position and verticality can be accurately positioned, so that lattice column plane position Design requirement can be met with vertical axis position by setting, it is ensured that later period steel linking beam connect closely connected with lattice column, prevents lattice The main stress structure such as column and beam column clashes, and guarantees the safety of bracing members installation, in urban track traffic deep foundation pit support In answer practicability stronger, the utility model has structure simple, setting rationally, the advantages that low manufacture cost.
The above is merely intended for describing the technical solutions of the present application, but not for limiting the present application, those of ordinary skill in the art couple The other modifications or equivalent replacement that the technical solution of the utility model is made, without departing from technical solutions of the utility model Spirit and scope should all cover in the scope of the claims of the utility model.

Claims (2)

1. the stake holes lattice column positioning and plumbing system of dry method pore-forming, it is characterised in that: it includes supporting beam, No.1 locating rack, two Number locating rack, limit hole, crank support, fastening crank, pinion steering mechanism, limiting device, fastening screw, Laser plumb instrument, Pin hole, cross spacing pin, set column holder, air bag jack, laser reflecting measurement plate;Two are symmetrically arranged on ground at the top of stake holes Root supporting beam, and the middle part of two supporting beams is arranged in stake holes;The both ends bottom of supporting beam is respectively symmetrically vertically fixed equipped with No.1 Position frame, the inside of No.1 locating rack is connected with No. two locating racks by connecting rod, and supporting beam activity is erected at No.1 locating rack Top;It is equipped with symmetrical limit hole in the middle part of the No.1 locating rack and No. two locating racks, two adjacent limit holes Spacing is of same size with supporting beam;The middle part weldering of No.1 locating rack is equipped with crank support;No.1 locating rack and No. two locating racks it Between be equipped with pinion steering mechanism, and pinion steering mechanism bottom is fixed on the ground by limiting device;It wears fastening crank one end It crosses after passing through on crank support to rotate and be plugged in inside pinion steering mechanism, the other end dew for fastening crank is located at No.1 positioning The outside of frame;No.1 locating rack and No. two locating racks both ends bottoms are equipped with sand box support, and sand box support bottom is fixed on On ground;It is threaded through in the middle part of fastening screw on the inside of pinion steering mechanism, and the gear of screw thread and pinion steering mechanism thereon Engagement;The both ends of fastening screw are screwed in the threaded hole of supporting beam by screw thread;Laser lead is equipped with right above the hole heart of stake holes Hammer instrument into shape, the bottom of Laser plumb instrument is fixed on supporting beam top by tripod erection;The side of two supporting beams is equipped with number A pin hole, activity is plugged in two symmetrical pin holes of supporting beam respectively at the both ends of two cross spacing pins;Cross spacing pin with It is inserted with lattice column in the square hole that supporting beam is constituted, the upper end of lattice column is connect with truck crane, and the bottom end of lattice column is plugged in stake In the middle part of steel reinforcement cage in hole;The top on steel reinforcement cage top and be located at lattice column Basolateral wall on sliding sleeve be equipped with set column holder, Sleeve column pedestal upper end is connect by rope with truck crane;Several air bag jacks are fixed with around the set column holder;It is described The interior bottom of lattice column be equipped with laser reflecting measurement plate.
2. the stake holes lattice column positioning and plumbing system of dry method pore-forming according to claim 1, it is characterised in that: the gas Capsule jack is connected on hemisphere air compressor and intake and exhaust valve group by tracheae.
CN201820475134.2U 2018-04-04 2018-04-04 The stake holes lattice column positioning and plumbing system of dry method pore-forming Expired - Fee Related CN208183758U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820475134.2U CN208183758U (en) 2018-04-04 2018-04-04 The stake holes lattice column positioning and plumbing system of dry method pore-forming

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820475134.2U CN208183758U (en) 2018-04-04 2018-04-04 The stake holes lattice column positioning and plumbing system of dry method pore-forming

Publications (1)

Publication Number Publication Date
CN208183758U true CN208183758U (en) 2018-12-04

Family

ID=64436414

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820475134.2U Expired - Fee Related CN208183758U (en) 2018-04-04 2018-04-04 The stake holes lattice column positioning and plumbing system of dry method pore-forming

Country Status (1)

Country Link
CN (1) CN208183758U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610458A (en) * 2019-01-15 2019-04-12 五冶集团上海有限公司 A kind of manually digging hole filling pile steel reinforcement cage deviation preventing mean and its application method
CN113550314A (en) * 2021-07-21 2021-10-26 中交(苏州)城市开发建设有限公司 Deep well soil sampling device in underwater pile and construction method thereof
CN113562629A (en) * 2021-07-15 2021-10-29 海通建设集团有限公司 Lattice column positioning and verticality adjusting system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610458A (en) * 2019-01-15 2019-04-12 五冶集团上海有限公司 A kind of manually digging hole filling pile steel reinforcement cage deviation preventing mean and its application method
CN113562629A (en) * 2021-07-15 2021-10-29 海通建设集团有限公司 Lattice column positioning and verticality adjusting system
CN113562629B (en) * 2021-07-15 2024-03-26 海通建设集团有限公司 Lattice column positioning and verticality adjusting system
CN113550314A (en) * 2021-07-21 2021-10-26 中交(苏州)城市开发建设有限公司 Deep well soil sampling device in underwater pile and construction method thereof

Similar Documents

Publication Publication Date Title
CN208183758U (en) The stake holes lattice column positioning and plumbing system of dry method pore-forming
AU2012201012B2 (en) Device for manufacturing a foundation for a mass located at height, associated method and assembly of the device and a jack-up platform
CN105735145B (en) A kind of Bridge Rotation Construction Technique precise alignment control construction method and its structure
CN108643192A (en) Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method
CN102839812A (en) Intelligent construction platform for construction of super high-rise building
CN110158617A (en) Combined type deep foundation pit support stability maintenance structure and method
CN109706929A (en) Deep water foundation steel sheet pile inserting, driving, guiding and positioning device
CN106013206A (en) Steel pipe column positioning device and steel pipe concrete column and pile foundation connecting structure
CN210918297U (en) Auxiliary device for positioning embedded bolt
CN109252511A (en) A kind of installation of steel reinforcement cage and concrete casting platform
CN109267493A (en) A kind of construction method installed across river steel lid beam
CN114215048A (en) Large-diameter pile foundation reinforcement cage centering device
CN108179749B (en) Lattice column positioner and positioning method thereof
CN110528526B (en) Method and device for positioning and controlling verticality of reinforcement cage of manual hole digging pile
CN111980024A (en) Positioning and guiding equipment for foundation construction of steel trestle
CN208201869U (en) A kind of steady stake platform
CN110777790A (en) High-precision vertical pile positioning and verticality adjusting device
CN214089959U (en) Lattice column positioning device
CN109356021A (en) Temporary rest pier waterborne and its construction method
CN209307839U (en) Temporary rest pier and bridge construction device waterborne
CN210827478U (en) Deep foundation pit underground structure reverse construction method steel pipe column positioning device
CN109201971A (en) For making the positioning device and its construction method of pile foundation steel bar cage
CN213233456U (en) Positioning and guiding equipment for foundation construction of steel trestle
CN106480901A (en) A kind of lattice-type steel column accurate positioning method
CN212612488U (en) Movable underwater concrete pouring guide pipe trolley

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181204

Termination date: 20210404

CF01 Termination of patent right due to non-payment of annual fee