CN208167666U - A kind of high narrow big aperture inlet gate drainage arrangement - Google Patents
A kind of high narrow big aperture inlet gate drainage arrangement Download PDFInfo
- Publication number
- CN208167666U CN208167666U CN201820519907.2U CN201820519907U CN208167666U CN 208167666 U CN208167666 U CN 208167666U CN 201820519907 U CN201820519907 U CN 201820519907U CN 208167666 U CN208167666 U CN 208167666U
- Authority
- CN
- China
- Prior art keywords
- gate
- inlet gate
- inlet
- bulkhead
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Barrages (AREA)
Abstract
The utility model discloses a kind of high narrow big aperture inlet gate drainage arrangements, including inlet gate(1)Be located at inlet gate(1)The bulkhead gate of upstream(5);Inlet gate(1)Top is equipped with inlet gate filling valve(7), bulkhead gate(5)Top is equipped with bulkhead gate filling valve(8);In inlet gate(1)With bulkhead gate(5)Between ground sill(10)It is equipped with interim immersible pump(9), interim immersible pump(9)Outlet and inlet gate filling valve(7)Water inlet connection.The water pressure that the utility model reduces inlet gate receiving then reduces Qi Menli, the headstock gear capacity for meeting normal operation opens inlet gate requirement, and without increasing inlet gate headstock gear capacity, so that it may meet the needs used, to reduce the cost of investment of inlet gate.
Description
Technical field
The utility model relates to a kind of high narrow big aperture inlet gate drainage arrangements, belong to hydraulic and hydroelectric engineering metal structure
Technical field.
Background technique
For water inlet stop gate or axis stream unit water inlet emergency gate(Hereinafter referred to as inlet gate), generally use
One machine arrangement considers that inlet gate maintenance needs, bulkhead gate generally is arranged in the front.In construction time or maintenance
Phase considers that water blocking installation or maintenance unit need, and inlet gate, which is in, closes water blocking state, terminates in construction or turn(a)round, needs
When opening inlet gate progress unit has water debugging, unit guide vane, which cannot be in close state inlet gate sometimes and can not achieve, to be filled
Level pressure.The prior art generally closes water blocking using decentralization bulkhead gate, excludes water-filling using the filling valve at the top of inlet gate
Dynamic water unlatching inlet gate after water body more than valve water inlet, the prior art inlet gate little for conventional aperture height,
Because the water pressure that 2~4m differential water pressures that the water pressure that dynamic water opens door is operated normally with inlet gate generate is not much different, therefore intake
What gate operated normally open, and Men Li is able to satisfy moves water under the filling valve water inlet to gate ground sill head and open inlet gate and want
It asks.But for high narrow big aperture inlet gate, filling valve water inlet is higher to inlet gate ground sill head, some engineerings reach
20m, the Qi Menli operated normally well beyond inlet gate, need to increase headstock gear capacity can just open door, this will increase engineering
Investment, particularly with the more aobvious protrusion of hydroelectric project of porous mouth, and the probability very little that this kind of operating condition occurs when operating normally, it is
One unconventional operating condition, which increases opening and closing capacity, then seems very uneconomical, therefore the prior art is there is also deficiency, up for into one
It walks perfect.
Utility model content
The purpose of this utility model is that:A kind of high narrow big aperture inlet gate drainage arrangement is provided, by temporarily diving under water
Pump can exclude the water body between inlet gate and bulkhead gate substantially, open power to reduce inlet gate, meet and operate normally
Headstock gear capacity open inlet gate requirement, no replacement is required biggish inlet gate headstock gear capacity reduces cost of investment, from
And overcome the deficiencies in the prior art.
What the technical solution of the utility model was realized in:
A kind of high narrow big aperture inlet gate drainage arrangement of the utility model, including inlet gate and be located at inlet gate
The bulkhead gate of upstream;It is equipped with inlet gate filling valve at the top of inlet gate, is equipped with bulkhead gate filling valve at the top of bulkhead gate;
Interim immersible pump, the outlet of interim immersible pump and inlet gate water-filling are equipped on ground sill between inlet gate and bulkhead gate
The water inlet of valve connects.
In aforementioned device, the gate pier at the top of the inlet gate is equipped with inspection platform;Inspection platform is close to bulkhead gate
Side is equipped with rectangular recess, and the inspection platform of rectangular recess bottom is equipped with round hole, round hole and bulkhead gate and intake gate
It is communicated at the top of runner between door;Hook is equipped on the gate pier at the top of round hole, hook is connect through iron chains with interim immersible pump.
In aforementioned device, the inspection platform is equipped with service aisle.
By adopting the above-described technical solution, the utility model is compared with prior art, the utility model is in inlet gate
Inspection platform upstream side in the middle part of open a rectangular recess, rectangular recess lower part be arranged a round hole pass to lower part bulkhead gate with
At the top of runner between inlet gate.In inlet gate and bulkhead gate water filling process, it can be placed by round hole interim latent
Water pump is by water outlet.This method can substantially reduce inlet gate and open power, and the headstock gear capacity for meeting normal operation opens water inlet
Gate requirement, without increasing inlet gate headstock gear capacity, effectively saves investment;It is equipped with hook at the top of rectangular recess, is used for
The iron chains of interim immersible pump is hung, the interim immersible pump of execute-in-place is convenient for;It is logical that rectangular recess is located at the work of inspection platform upstream side
Road top, do not influence the walking of operations staff, the effective guarantee safety of operations staff;Round hole pass to lower part bulkhead gate with
At the top of runner between inlet gate, exhaust velocity when bulkhead gate water-filling concora crush can be increased.
Detailed description of the invention
Fig. 1 is that the utility model is drained using inlet gate filling valve to its filling valve import schematic diagram;
Fig. 2 is the A-A cross-sectional view of Fig. 1;
Fig. 3 is that the utility model utilizes the interim immersible pump exclusion following water body schematic diagram of inlet gate filling valve import;
Fig. 4 is the B-B cross-sectional view of Fig. 3.
In figure:1- inlet gate, 2- inspection platform, 3- rectangular recess, 4- round hole, 5- bulkhead gate, at the top of 6- runner,
7- inlet gate filling valve, 8- bulkhead gate filling valve, the interim immersible pump of 9-, 10- ground sill, 11- iron chains, 12- service aisle,
13- hook.
Specific embodiment
The utility model is described in further detail below, but not as any restrictions to the utility model.
The utility model is constituted according to a kind of following high narrow big aperture inlet gate water discharge methods, and this method is such as
Shown in Fig. 1~4, this method is the setting rectangular recess 3 in the middle part of 2 upstream side of inspection platform of inlet gate 1, in rectangular recess 3
Bottom round hole 4 is set, 6 communicate at the top of runner between round hole 4 and bulkhead gate 5 and inlet gate 1;In inlet gate
When its top draining of filling valve 7 to 7 water inlet of filling valve of 1 utilization, interim immersible pump 9 is placed on by maintenance lock by round hole 4
On ground sill 10 between door 5 and inlet gate 1, by interim immersible pump 9 by water remaining between bulkhead gate 5 and inlet gate 1
Body is evacuated to 1 filling valve of inlet gate, 7 water inlet, and water is drained into dam body downstream by 7 water outlet of the filling valve of inlet gate 1;
To reduce the Qi Menli of inlet gate 1, the headstock gear capacity for meeting normal operation opens the requirement of inlet gate 1, without increasing
1 headstock gear capacity of inlet gate, to reduce the cost of investment of inlet gate 1.
In the aforementioned narrow big aperture inlet gate water discharge method of height, the bore of the round hole 4 is greater than interim immersible pump 9 most
Large scale;The gate pier at 4 top of round hole is equipped with hook 13, and interim immersible pump 9 is transferred through iron chains 11 to bulkhead gate 5 and water inlet
Ground sill 10 between gate 1, and iron chains 11 is hung on hook 13, interim immersible pump 9 is received from ground sill 10 when not need
It returns.
According to a kind of high narrow big aperture inlet gate drainage arrangement of the utility model that the above method is constituted, including water inlet
Gate 1 and bulkhead gate 5 positioned at 1 upstream of inlet gate;Inlet gate filling valve 7, bulkhead gate are equipped at the top of inlet gate 1
5 tops are equipped with bulkhead gate filling valve 8;Interim immersible pump 9 is equipped on ground sill 10 between inlet gate 1 and bulkhead gate 5,
The outlet of interim immersible pump 9 is connect with the water inlet of inlet gate filling valve 7.
In aforementioned device, the gate pier at 1 top of inlet gate is equipped with inspection platform 2;Inspection platform 2 is close to maintenance lock
5 sides of door are equipped with rectangular recess 3, and the inspection platform 2 of 3 bottom of rectangular recess is equipped with round hole 4, round hole 4 and bulkhead gate 5
6 communicate at the top of runner between inlet gate 1;Hook 13 is equipped on the gate pier at 4 top of round hole, hook 13 is through iron chains 11
It is connect with interim immersible pump 9.
In aforementioned device, the inspection platform 2 is equipped with service aisle 12.
Embodiment
The embodiments of the present invention as shown in figures 1-4, open a square in the middle part of 2 upstream side of inspection platform of inlet gate 1
Connected in star 3 is arranged a round hole 4 in 3 lower part of rectangular recess and passes to the runner top between lower part bulkhead gate 5 and inlet gate 1
Portion 6.When inlet gate 1 is using the draining of filling valve 7 to 7 water inlet of filling valve at the top of it, by round hole 4 by interim immersible pump
9 are placed on the ground sill 10 between bulkhead gate 5 and inlet gate 1, by interim immersible pump 9 by bulkhead gate 5 and intake gate
Remaining water body is evacuated to 1 filling valve of inlet gate, 7 water inlet between door 1, and by 7 water outlet of filling valve of inlet gate 1 by water
Drain into dam body downstream;Rectangular recess 3 is set to the top in 2 upstream side aisle 12 of inspection platform;3 top of rectangular recess setting hook
13;Hook 13 is for hanging the iron chains 14 of interim immersible pump 9.
This example can exclude substantially the water body between bulkhead gate 5 and inlet gate 1, greatly reduce inlet gate 1 and open
Men Li, what inlet gate 1 operated normally opens a power satisfaction unlatching requirement, effective to save without increasing inlet gate headstock gear capacity
Investment is saved.
Claims (3)
1. a kind of high narrow big aperture inlet gate drainage arrangement, including inlet gate(1)Be located at inlet gate(1)The inspection of upstream
Repair gate(5);Inlet gate(1)Top is equipped with inlet gate filling valve(7), bulkhead gate(5)Top is filled equipped with bulkhead gate
Water valve(8);It is characterized in that:In inlet gate(1)With bulkhead gate(5)Between ground sill(10)It is equipped with interim immersible pump
(9), interim immersible pump(9)Outlet and inlet gate filling valve(7)Water inlet connection.
2. high narrow big aperture inlet gate drainage arrangement according to claim 1, it is characterised in that:The inlet gate(1)
The gate pier at top is equipped with inspection platform(2);Inspection platform(2)Close to bulkhead gate(5)Side is equipped with rectangular recess(3), square
Connected in star(3)The inspection platform of bottom(2)It is equipped with round hole(4), round hole(4)With bulkhead gate(5)And inlet gate(1)
Between runner at the top of(6)It communicates;In round hole(4)The gate pier at top is equipped with hook(13), hook(13)Through iron chains(11)
With interim immersible pump(9)Connection.
3. high narrow big aperture inlet gate drainage arrangement according to claim 2, it is characterised in that:The inspection platform(2)
It is equipped with service aisle(12).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820519907.2U CN208167666U (en) | 2018-04-12 | 2018-04-12 | A kind of high narrow big aperture inlet gate drainage arrangement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820519907.2U CN208167666U (en) | 2018-04-12 | 2018-04-12 | A kind of high narrow big aperture inlet gate drainage arrangement |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208167666U true CN208167666U (en) | 2018-11-30 |
Family
ID=64370360
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820519907.2U Active CN208167666U (en) | 2018-04-12 | 2018-04-12 | A kind of high narrow big aperture inlet gate drainage arrangement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208167666U (en) |
-
2018
- 2018-04-12 CN CN201820519907.2U patent/CN208167666U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201473933U (en) | Combination layout structure of tail water emergency gate and tail water surge shaft in pumped storage power station | |
CN106284240A (en) | A kind of power station is in construction time downstream interim water-supply structure and method | |
CN108330921A (en) | A kind of high narrow big aperture inlet gate water discharge method and device | |
CN101302763B (en) | Self-elevating drilling platform pile punching apparatus | |
CN208167666U (en) | A kind of high narrow big aperture inlet gate drainage arrangement | |
CN207092033U (en) | A kind of flood discharging tunnel | |
CN204626349U (en) | Gate of hydropower station top Accrete clearing device | |
CN105040648A (en) | Reservoir emptying tunnel for over 200-meter ultrahigh dam and arrangement method and application thereof | |
CN209891288U (en) | Drainage pump station | |
CN208088251U (en) | Ecological flow discharge structure during lower lock water storage | |
CN204982820U (en) | A lock chamber arrangement structure that is used for high arch dam water conservancy diversion bottom outlet | |
CN103114838B (en) | High-pressure automatic sand discharge device | |
CN207314279U (en) | It is a kind of to take into account small river flood control water drainage pump brake system integrated with moisturizing demand in city | |
CN209620172U (en) | A kind of novel aqueduct of falling rainbow spoil disposal emptying structure | |
CN212336278U (en) | Large-scale underground type hydropower station factory building leakage drainage system combined with slope shaft | |
CN211057931U (en) | Tunnel fire control water supply double-supply system | |
CN205314233U (en) | Multi -functional sump pit structure in power station | |
CN105268574B (en) | One kind spraying main frame and its method of work | |
CN200946262Y (en) | High-water head ship lock | |
CN203412625U (en) | Underground coal mine drainage facility | |
CN209603077U (en) | Two dam structures of runtime not pump drainage turn(a)round interim pump drainage | |
CN103741703B (en) | A kind of radial pumped well formula siphon drainage device | |
CN207376762U (en) | A kind of flood control electricity row station | |
CN207701337U (en) | Deep well pump sand control check three-port structure | |
CN207297109U (en) | Steam turbine jetting case overflow recovery control system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |