- CN207249468U CN207249468U CN201720956124.6U CN201720956124U CN207249468U CN 207249468 U CN207249468 U CN 207249468U CN 201720956124 U CN201720956124 U CN 201720956124U CN 207249468 U CN207249468 U CN 207249468U
- Authority
- CN
- China
- Prior art keywords
- storage
- lift
- mould
- master control
- piler
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Landscapes
- Warehouses Or Storage Devices (AREA)
Abstract
The utility model is related to a kind of tire-mold be put in storage, store automatically, the Information Management System of outbound.The mold storage system of full-automatic mould vertical library, including storage system, transportation system and master control system;The mould may be contained within pallet, and pallet is equipped with RFID chip;The storage system includes cavity warehouse compartment and die sleeve warehouse compartment;Lift-on/Lift-off System that the transport system includes setting gradually, travelling bogie and go out to be put in storage stacking system;Be additionally provided with master control system, the master control system respectively with Lift-on/Lift-off System, travelling bogie, go out to be put in storage stacking system and storage system is electrically connected and carries out data transmission;The master control system is APS systems and MES system;Wherein, Lift-on/Lift-off System is driving, and travelling bogie is RGV trolleies, and it is piler to go out to be put in storage stacking system.The utility model realizes intelligent, information-based, automation the management mode of mould.
Description
Technical field
The utility model is related to a kind of tire-mold be put in storage, store automatically, the Information Management System of outbound, it is especially logical
Cross APS and produce production planning and sequencing automatically, construction job sheet and instruction, mould vertical library WMS systems are automatically generated according to die information by MES
System precisely realizes that mould goes out the intelligent management of storage.
Background technology
The various complexity of tire-mold specification, model, quantity, at present tyre production enterprise mold storage use Ping Ku and storage
Frame is stored.More relatively advanced also to carry out storage information management simply by bar code system, the position of mold storage completely can only
Logical people identifies to search, time-consuming longer.The another whole artificial or fork truck coordinating operations of mold storing, personnel's setting is more, and safety is hidden
Suffer from also larger.Another mould construction job sheet complete people is to be compiled according to the production schedule, mould machine account and tyre series parameter list
System is assigned, error-prone.
The content of the invention
In order to solve to take up a large area present in conventional tire mold storage, search inconvenience, high labor cost, construction times
It is engaged in error-prone.The utility model provides the storage of mould vertical library and way to manage, and production planning and sequencing is produced automatically by APS to realize,
Construction job sheet and instruction are automatically generated according to die information by MES, mould vertical library precisely realizes that mould goes out the intelligence of storage
Management.Error rate, raising production efficiency are reduced so as to reach.
The technical solution of the utility model is:
The mold storage system of full-automatic mould vertical library, including storage system, transportation system and master control system;Described
Mould may be contained within pallet, and pallet is equipped with RFID chip;The storage system includes cavity warehouse compartment and die sleeve warehouse compartment;
Lift-on/Lift-off System that the transportation system includes setting gradually, travelling bogie and go out to be put in storage stacking system;It is additionally provided with master control system
System, the master control system respectively with Lift-on/Lift-off System, travelling bogie, go out to be put in storage stacking system and storage system be electrically connected into
Row data transfer;The master control system is APS systems and MES system;Wherein, Lift-on/Lift-off System is driving, and travelling bogie is
RGV trolleies, it is piler to go out to be put in storage stacking system.
The piler includes cavity carrier-and-stacker and die sleeve carrier-and-stacker;The cavity warehouse compartment is equipped with corresponding cavity
Vomitory, die sleeve warehouse compartment are equipped with corresponding die sleeve Vomitory.
Piler transverse direction transplanter is additionally provided with the piler.
A kind of mold storage method of full-automatic mould vertical library, is deposited using the mould of full-automatic mould vertical library as described above
Storage system, includes the following steps:
(1)Generation mold changing work order:APS systems assign mould plan of needs, after being confirmed by technical staff, MES system root
According to mould machine account and tire specification parameters in series table generation mold changing construction job sheet and print, and confirmed by technical staff;
(2)Mould goes out storage:Mold changing construction job sheet after being determined by technical staff, MES system automatically generate out storage
Information;And after being confirmed by technical staff perform following operation:
During outbound, corresponding die sleeve or cavity outbound, while MES system renewal material are automatically found according to instruction by piler
Information;Die sleeve is come in and gone out by die sleeve Vomitory, and cavity is come in and gone out by cavity Vomitory;Corresponding die sleeve or cavity outbound are turned
It is transported on RGV trolleies, then is adjusted to assembly platform via driving and is assembled;
During storage, by broken up, clean, repair, maintain after die sleeve or cavity according to storage information, be hung to by driving
On pallet on RGV trolleies, RGV trolleies send die sleeve or cavity to piler, and piler pitches die sleeve or cavity according to finger
Automatic transport is made to be stored to corresponding warehouse compartment, while MES system renewal material information.
Before and after the mould or mold repair purchased back, be put in storage by scanning the two-dimensional code binding information, MES system renewal thing
Expect information.
The utility model has technical effect that:
1st, intelligent mould, informationization, automatic management pattern are realized, APS systems, which precisely assign mould, to be needed to plan,
MES system automatically generates mould construction job sheet, reduces die parameters and goes out rate;
2nd, mould goes out storage, storage automation improves labor productivity, (is changed by original traditional 2,000,000 tires yield
6/day of modulus) need 45 people of die operation personnel only to need 25 people after reducing the utility model till now, it can save every year manually
Cost about 1,200,000;
3rd, improve work efficiency, tradition looks for a secondary mould used time then 30 minutes short, it is long then when 2 is small, present one pair of mould goes out
Storehouse 10-20 minutes, and realize whole unmanned searching, personnel only need to hang mould to assembly platform from outlet.
Brief description of the drawings
Fig. 1 is relation schematic diagram of the mold storage system tray with RGV trolleies of the full-automatic mould vertical library of the utility model.
Fig. 2 is the mold storage system structure diagram of the full-automatic mould vertical library of the utility model.
Fig. 3 increases flow chart newly for the utility model mould.
Fig. 4 is put in storage flow chart for the utility model mould.
Fig. 5 assigns flow chart for the utility model work order.
Fig. 6 is the utility model mould outbound flow chart.
Reference numeral:1st, pallet, 2, RGV trolleies, 3, mould, 4, cavity carrier-and-stacker, 5, piler transverse direction transplanter, 6,
Die sleeve carrier-and-stacker, 7, die sleeve Vomitory, 8, cavity Vomitory, 9, assembly platform.
Embodiment
The mold storage system of full-automatic mould vertical library, including storage system, transportation system and master control system;Described
Mould 3 may be contained within pallet 1, and pallet 1 is equipped with RFID chip;The storage system includes cavity warehouse compartment and die sleeve storehouse
Position;Lift-on/Lift-off System that the transportation system includes setting gradually, travelling bogie and go out to be put in storage stacking system;It is additionally provided with master control
System, the master control system respectively with Lift-on/Lift-off System, travelling bogie, go out to be put in storage stacking system and storage system is electrically connected
Carry out data transmission;The master control system is APS systems and MES system;Wherein, Lift-on/Lift-off System is drives a vehicle, travelling bogie
For RGV trolleies 2, it is piler to go out to be put in storage stacking system.The piler includes cavity carrier-and-stacker 4 and die sleeve carrier-and-stacker 6;
The cavity warehouse compartment is equipped with corresponding cavity Vomitory 8, and die sleeve warehouse compartment is equipped with corresponding die sleeve Vomitory 7.Described
Piler transverse direction transplanter 5 is additionally provided with piler.
A kind of mold storage method of full-automatic mould vertical library, is deposited using the mould of full-automatic mould vertical library as described above
Storage system, includes the following steps:
(1)Generation mold changing work order:APS systems assign 3 plan of needs of mould, after being confirmed by technical staff, MES system root
According to 3 machine account of mould and tire specification parameters in series table generation mold changing construction job sheet and print, and confirmed by technical staff;
(2)Mould 3 goes out storage:Mold changing construction job sheet after being determined by technical staff, MES system automatically generate out storage
Information;And after being confirmed by technical staff perform following operation:
During outbound, corresponding die sleeve or cavity outbound, while MES system renewal material are automatically found according to instruction by piler
Information;Die sleeve is come in and gone out by die sleeve Vomitory 7, and cavity is come in and gone out by cavity Vomitory 8;By corresponding die sleeve or cavity outbound
It is transported on RGV trolleies 2, then is adjusted to assembly platform 9 via driving and is assembled;
During storage, by broken up, clean, repair, maintain after die sleeve or cavity or according to storage information, by driving a vehicle
It is hung on the pallet 1 on RGV trolleies 2, RGV trolleies 2 send die sleeve or cavity to piler, and piler pitches die sleeve or cavity
Stored according in instruction automatic transport to corresponding warehouse compartment, while MES system renewal material information.The mould 3 purchased back
Or before and after mould 3-dimensional is repaiied, be put in storage by scanning the two-dimensional code binding information, MES system renewal material information.
The utility model realizes intelligent mould, informationization, automatic management pattern, and APS systems are precisely assigned mould and needed
Plan, MES system automatically generates mould construction job sheet, reduces die parameters and goes out rate;Mould goes out storage, storage automation
Labor productivity is improved, 45 people of die operation personnel is needed by original traditional 2,000,000 tires yield (6/day of mold changing amount)
25 people are only needed after reducing the utility model till now, cost of labor about 1,200,000 can be saved every year;Present one pair of mould outbound 10-
20 minutes, and realize whole unmanned searching, personnel only need to hang mould to assembly platform 9 from outlet.
Claims (3)
1. the mold storage system of full-automatic mould vertical library, it is characterised in that:Including storage system, transportation system and master control system
System;The mould(3)It may be contained within pallet(1)On, pallet(1)It is equipped with RFID chip;The storage system includes type
Chamber warehouse compartment and die sleeve warehouse compartment;Lift-on/Lift-off System that the transportation system includes setting gradually, travelling bogie and go out to be put in storage heap
Pile system;Be additionally provided with master control system, the master control system respectively with Lift-on/Lift-off System, travelling bogie, go out to be put in storage stacking system and
Storage system, which is electrically connected, to be carried out data transmission;The master control system is APS systems and MES system;Wherein, lifting system
Unite to drive a vehicle, travelling bogie is RGV trolleies(2), it is piler to go out to be put in storage stacking system.
2. the mold storage system of full-automatic mould vertical library according to claim 1, it is characterised in that:The piler
Including cavity carrier-and-stacker(4)And die sleeve carrier-and-stacker(6);The cavity warehouse compartment is equipped with corresponding cavity Vomitory(8), mould
Set warehouse compartment is equipped with corresponding die sleeve Vomitory(7).
3. the mold storage system of full-automatic mould vertical library according to claim 2, it is characterised in that:The piler
On be additionally provided with piler transverse direction transplanter(5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720956124.6U CN207249468U (en) | 2017-08-02 | 2017-08-02 | The mold storage system of full-automatic mould vertical library |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720956124.6U CN207249468U (en) | 2017-08-02 | 2017-08-02 | The mold storage system of full-automatic mould vertical library |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207249468U true CN207249468U (en) | 2018-04-17 |
Family
ID=61880363
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720956124.6U Active CN207249468U (en) | 2017-08-02 | 2017-08-02 | The mold storage system of full-automatic mould vertical library |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207249468U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107203195A (en) * | 2017-08-02 | 2017-09-26 | 合肥万力轮胎有限公司 | The mold storage system and method for full-automatic mould vertical library |
CN109624208A (en) * | 2019-01-10 | 2019-04-16 | 泰瑞机器股份有限公司 | An a kind of injection molding machine production group of planes for intelligent control |
-
2017
- 2017-08-02 CN CN201720956124.6U patent/CN207249468U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107203195A (en) * | 2017-08-02 | 2017-09-26 | 合肥万力轮胎有限公司 | The mold storage system and method for full-automatic mould vertical library |
CN109624208A (en) * | 2019-01-10 | 2019-04-16 | 泰瑞机器股份有限公司 | An a kind of injection molding machine production group of planes for intelligent control |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107256469A (en) | Optimization in-out-storehouse management system and method based on fork-lift type AGV dollies | |
CN207249468U (en) | The mold storage system of full-automatic mould vertical library | |
CN109814505A (en) | A kind of SMART MATERIALS movement system based on AGV trolley | |
CN108382779A (en) | A kind of intelligent storage sorting system and shelf, AGV | |
CN109353732A (en) | A kind of large size material automated warehousing system and method | |
US4993906A (en) | Green tire feed system between forming and vulcanizing processes | |
CN107203195A (en) | The mold storage system and method for full-automatic mould vertical library | |
CN106773686B (en) | Path model method for building up is dispatched with piler under the double vehicle operational modes of rail | |
CN208499394U (en) | A kind of intelligent storage sorting system and shelf, AGV | |
CN206766889U (en) | A kind of automated three-dimensional Yi nationality medicine warehouse | |
CN110202214A (en) | A kind of steel plate diced system | |
CN106363416A (en) | Intelligent production line for small component cutting | |
CN112678543B (en) | Self-adaptive feeding system and method | |
CN105527947A (en) | Slab-yard tracking and management system | |
CN107491048B (en) | AGV-based workshop production waste automatic recycling system and method | |
WO2024021941A1 (en) | Unmanned forklift-based stamping plant scheduling system and method | |
CN110963219B (en) | Intelligent production line for disassembling and assembling container freight yard station | |
CN109472514A (en) | A kind of oral preparation intelligence production link system and method | |
CN116477257A (en) | Full-automatic die changing system and method, equipment and medium for heavy-duty die of stamping processing line | |
CN202625140U (en) | Intelligentized warehousing system for cast sand cores | |
CN104691813A (en) | Full-automatic destacking, stacking and packaging system | |
CN212502242U (en) | Intelligent three-dimensional storehouse | |
CN113743861A (en) | Intelligent replenishment system for supply chain of automobile accessory industry and warehouse thereof | |
CN106364832B (en) | A kind of full-automatic warehouse logistics management and control system and method | |
CN211135769U (en) | Steel plate cutting system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |