CN207194224U - One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction - Google Patents

One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction Download PDF

Info

Publication number
CN207194224U
CN207194224U CN201721096326.4U CN201721096326U CN207194224U CN 207194224 U CN207194224 U CN 207194224U CN 201721096326 U CN201721096326 U CN 201721096326U CN 207194224 U CN207194224 U CN 207194224U
Authority
CN
China
Prior art keywords
flat steel
steel pipe
bracing piece
shear wall
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721096326.4U
Other languages
Chinese (zh)
Inventor
何志强
徐前
张祥伟
张世伟
曹菁华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Original Assignee
China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Bureau Installation Engineering Co Ltd filed Critical China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Priority to CN201721096326.4U priority Critical patent/CN207194224U/en
Application granted granted Critical
Publication of CN207194224U publication Critical patent/CN207194224U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model proposes one kind to wear muscle anchoring concrete-filled steel tube shear wall fabricated construction, to solve the problems, such as that shear wall construction complex procedures, anti-deformation are poor in the prior art, adaptability is not wide, including Flat steel pipe, in the side wall of Flat steel pipe bracing piece is provided with quincunx, concrete has been poured in the internal cavities of Flat steel pipe, the bracing piece is peg, and the connected mode of Flat steel pipe and bracing piece is welding;The bracing piece is Ribbed Bar, and the connected mode of Flat steel pipe and bracing piece is welding;The bracing piece is rivet, and the connected mode of Flat steel pipe and bracing piece is staking;The utility model directly carries out the welding of bracing piece and Flat steel pipe in Flat steel pipe processing factory, pouring for concrete is directly carried out after prefabricated Flat steel pipe is installed in building-site, Flat steel pipe can improve its scope of application also to intercept suitable length according to construction requirement.

Description

One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction
Technical field
Technical field of structural engineering is the utility model is related to, one kind is particularly related to and wears muscle anchoring concrete-filled steel tube shear wall dress With formula structure.
Background technology
Under horizontal loads, in ratio increase, this will for the horizontal displacement on structure summit and the biquadratic of structure height Ask skyscraper to need larger lateral rigidity, make the relative storey displacement under horizontal loads within the scope of as defined in specification. To realize this target, Frame-Shear Wall or Frame-Shear wall system have turned into general in high level, high-rise building at present All over the structural system used.To ensure the ductility and deformability of armored concrete and Core Walls Structure, generally use has excellent anti- The steel-concrete compound shear wall of shock stability.
In the recent period, country determines to greatly develop assembled architecture, and assembling type steel structure building has that energy consumption is low, building waste Less, the advantage such as short construction period, it is a kind of green building for meeting sustainable development.And in steel building, shear wall one As need to carry out template to set up colligation with reinforcing bar, on-site construction processes are numerous and diverse, and construction speed is slow.
The content of the invention
The utility model proposes one kind to wear muscle anchoring concrete-filled steel tube shear wall fabricated construction, solves in the prior art The problem of shear wall construction complex procedures, anti-deformation are poor, adaptability is not wide.
What the technical solution of the utility model was realized in:
One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction, including Flat steel pipe, is in plum in the side wall of Flat steel pipe Flower-shape is provided with bracing piece, and concrete has been poured in the internal cavities of Flat steel pipe.
The bracing piece is peg, and the connected mode of Flat steel pipe and bracing piece is welding.
The bracing piece is Ribbed Bar, and the connected mode of Flat steel pipe and bracing piece is welding.
The bracing piece is rivet, and the connected mode of Flat steel pipe and bracing piece is staking.
The shear wall is L-type, and shear wall is welded to form by two Flat steel pipes and L parts.
The shear wall is T-shaped, and shear wall is welded to form by three Flat steel pipes and steel plate.
The shear wall is cross, and shear wall is welded to form by four Flat steel pipes.
Bracing piece of the present utility model can strengthen the connection of concrete and Flat steel pipe, Flat steel pipe and concrete is fully sent out Wave the advantages of respective, and then improve bearing capacity, ductility and the deformability of shear wall;The utility model is processed at the construction field (site) When do not need supporting module and assembling reinforcement, only need to carry out pouring for concrete in the cavity of Flat steel pipe, so as to simplify construct Process, accelerating construction progress;The utility model on-site construction processes are simple, easy for installation, and section form is various, built in steel construction It is applied widely in building.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art Or the required accompanying drawing used is briefly described in description of the prior art, it should be apparent that, drawings in the following description are only It is some embodiments of the utility model, for those of ordinary skill in the art, is not paying the premise of creative work Under, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is a kind of schematic diagram worn when muscle anchoring concrete-filled steel tube shear wall fabricated construction is L-type;
Fig. 2 is a kind of schematic diagram worn when muscle anchoring concrete-filled steel tube shear wall fabricated construction is T-shaped;
Fig. 3 is a kind of schematic diagram worn when muscle anchoring concrete-filled steel tube shear wall fabricated construction is cross;
Fig. 4 is the front view of Flat steel pipe;
Fig. 5 is A-A sectional views of Fig. 4 when bracing piece is peg;
Fig. 6 is A-A sectional views of Fig. 4 when bracing piece is Ribbed Bar;
Fig. 7 is A-A sectional views of Fig. 4 when bracing piece is rivet.
In figure:1st, Flat steel pipe 2, bracing piece 3, concrete 4, L parts 5, steel plate.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is paid The every other embodiment obtained, belong to the scope of the utility model protection.
Embodiment 1
As shown in Fig. 1,4,5, the utility model embodiment provides one kind and wears muscle anchoring concrete-filled steel tube shear wall assembling Formula structure, including Flat steel pipe 1, bracing piece 2 is provided with quincunx in the side wall of Flat steel pipe 1, is poured in the internal cavities of Flat steel pipe 1 Concrete 3 is built.
The bracing piece 2 is peg, and the connected mode of Flat steel pipe 1 and bracing piece 2 is welding.
The shear wall is L-type, and shear wall is welded to form by two Flat steel pipes 1 and L parts 4.
The utility model directly carries out the welding of bracing piece 2 and Flat steel pipe 1 in Flat steel pipe processing factory, pacifies in building-site Pouring for concrete is directly carried out after filling prefabricated Flat steel pipe, two Flat steel pipes 1 of L-type shear wall can be according to construction requirement Suitable length is intercepted, improves its scope of application.
Embodiment 2
As shown in Fig. 2,4,6, the utility model embodiment provides one kind and wears muscle anchoring concrete-filled steel tube shear wall assembling Formula structure, including Flat steel pipe 1, bracing piece 2 is provided with quincunx in the side wall of Flat steel pipe 1, is poured in the internal cavities of Flat steel pipe 1 Concrete 3 is built.
The bracing piece 2 is Ribbed Bar, and the connected mode of Flat steel pipe 1 and bracing piece 2 is welding.
The shear wall is T-shaped, and shear wall is welded to form by three Flat steel pipes 1 and steel plate 5.
The utility model directly carries out the welding of bracing piece 2 and Flat steel pipe 1 in Flat steel pipe processing factory, pacifies in building-site Pouring for concrete is directly carried out after filling prefabricated Flat steel pipe, three Flat steel pipes 1 of T-shaped shear wall can be according to construction requirement Suitable length is intercepted, improves its scope of application.
Embodiment 3
As shown in Fig. 3,4,7, the utility model embodiment provides one kind and wears muscle anchoring concrete-filled steel tube shear wall assembling Formula structure, including Flat steel pipe 1, bracing piece 2 is provided with quincunx in the side wall of Flat steel pipe 1, is poured in the internal cavities of Flat steel pipe 1 Concrete 3 is built.
The bracing piece 2 is rivet, and the connected mode of Flat steel pipe 1 and bracing piece 2 is staking.
The shear wall is cross, and shear wall is welded to form by four Flat steel pipes 1.
The staking assembling that the utility model directly carries out bracing piece 2 and Flat steel pipe 1 in Flat steel pipe processing factory, shows in building site Field directly carries out pouring for concrete after installing prefabricated Flat steel pipe, and four Flat steel pipes 1 of cross shear wall can basis Construction requirement intercepts suitable length, improves its scope of application.
Embodiment 4
As shown in Fig. 3-7, the utility model embodiment provides one kind and wears muscle anchoring concrete-filled steel tube shear wall assembled Structure, including Flat steel pipe 1, bracing piece 2 is provided with quincunx in the side wall of Flat steel pipe 1, is poured in the internal cavities of Flat steel pipe 1 There is concrete 3.
The bracing piece 2 is peg, and the connected mode of Flat steel pipe 1 and bracing piece 2 is welding.
The bracing piece 2 is Ribbed Bar, and the connected mode of Flat steel pipe 1 and bracing piece 2 is welding.
The bracing piece 2 is rivet, and the connected mode of Flat steel pipe 1 and bracing piece 2 is staking.
The shear wall is cross, and shear wall is welded to form by four Flat steel pipes 1.
The staking assembling that the utility model directly carries out bracing piece 2 and Flat steel pipe 1 in Flat steel pipe processing factory, shows in building site Field directly carries out pouring for concrete after installing prefabricated Flat steel pipe, the interior setting of four Flat steel pipes 1 of cross shear wall Bracing piece 2 in any combination, for example can set peg in the Flat steel pipe of horizontal edge, Ribbed Bar is set in the Flat steel pipe of vertical edge;Ten Four Flat steel pipes 1 of I-shaped shear wall can intercept suitable length according to construction requirement, improve its scope of application.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc., the utility model should be included in Protection domain within.

Claims (7)

1. one kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction, it is characterised in that:Including Flat steel pipe(1), Flat steel pipe (1)Side wall on be provided with bracing piece in quincunx(2), Flat steel pipe(1)Internal cavities in poured concrete(3).
2. one kind according to claim 1 wears muscle anchoring concrete-filled steel tube shear wall fabricated construction, it is characterised in that:Institute State bracing piece(2)For peg, Flat steel pipe(1)And bracing piece(2)Connected mode for welding.
3. one kind according to claim 1 wears muscle anchoring concrete-filled steel tube shear wall fabricated construction, it is characterised in that:Institute State bracing piece(2)For Ribbed Bar, Flat steel pipe(1)And bracing piece(2)Connected mode for welding.
4. one kind according to claim 1 wears muscle anchoring concrete-filled steel tube shear wall fabricated construction, it is characterised in that:Institute State bracing piece(2)For rivet, Flat steel pipe(1)And bracing piece(2)Connected mode be staking.
5. one kind according to any one of claim 1-4 wears muscle anchoring concrete-filled steel tube shear wall fabricated construction, it is special Sign is:The shear wall is L-type, and shear wall is by two Flat steel pipes(1)With L parts(4)It is welded to form.
6. one kind according to any one of claim 1-4 wears muscle anchoring concrete-filled steel tube shear wall fabricated construction, it is special Sign is:The shear wall is T-shaped, and shear wall is by three Flat steel pipes(1)And steel plate(5)It is welded to form.
7. one kind according to any one of claim 1-4 wears muscle anchoring concrete-filled steel tube shear wall fabricated construction, it is special Sign is:The shear wall is cross, and shear wall is by four Flat steel pipes(1)It is welded to form.
CN201721096326.4U 2017-08-30 2017-08-30 One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction Expired - Fee Related CN207194224U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721096326.4U CN207194224U (en) 2017-08-30 2017-08-30 One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721096326.4U CN207194224U (en) 2017-08-30 2017-08-30 One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction

Publications (1)

Publication Number Publication Date
CN207194224U true CN207194224U (en) 2018-04-06

Family

ID=61795650

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721096326.4U Expired - Fee Related CN207194224U (en) 2017-08-30 2017-08-30 One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction

Country Status (1)

Country Link
CN (1) CN207194224U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107558631A (en) * 2017-08-30 2018-01-09 中建七局安装工程有限公司 One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction
CN109944362A (en) * 2019-04-09 2019-06-28 河南绿建建筑科技有限公司 T-steel and threaded sleeve assembly and connection formula steel concrete compound tube T-type node

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107558631A (en) * 2017-08-30 2018-01-09 中建七局安装工程有限公司 One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction
CN109944362A (en) * 2019-04-09 2019-06-28 河南绿建建筑科技有限公司 T-steel and threaded sleeve assembly and connection formula steel concrete compound tube T-type node

Similar Documents

Publication Publication Date Title
CN203961054U (en) A kind of combined connecting structure of fabricated shear wall plate
CN103122665A (en) Combined-type steel-box-shaped steel plate shear wall
CN203174771U (en) Annular plate node of steel pipe concrete column and bonded prestress steel bar concrete beam
CN201901879U (en) Nonstandard foundation used for fixing tower crane
CN205046677U (en) Assembled concrete frame nodal connection structure
CN207194224U (en) One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction
CN107558631A (en) One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction
CN106760073A (en) Assembly concrete lining structural assembly
CN106245769B (en) A kind of structure of profile steel concrete column beam column universal nodes
CN108487504A (en) A kind of prefabricated assembled double steel plate shear wall combined structure of easy-to-mount unit
CN114541621A (en) Modularization shear force wall convenient to connect and level and vertical connection structure thereof
CN203742077U (en) Concrete-filled thin-wall steel tube column with built-in steel bar trusses
CN212104574U (en) Floor board and shear wall corner steel construction for assembly type building
CN106639151B (en) Built-in X-type is to drawing steel plate type welding rectangular steel-tube concrete column and construction method
CN102003030A (en) Prefabricated coal gangue concrete hollow shear wallboard
CN110792166B (en) Reinforced assembled beam column joint
CN107816126A (en) A kind of embedded prefabricated post of assembly concrete and prefabricated balcony
CN205024719U (en) Pile foundation and integrated reverse construction vertical braces system of underground continuous wall
CN111749328A (en) Novel assembly type beam joint and construction form thereof
CN104762961B (en) A kind of ultra-high performance concrete and ordinary concrete compound pile and construction method thereof
CN207003719U (en) A kind of prefabricated steel faced wall with steel bar girder
CN207392509U (en) Assembled soft steel energy dissipation wall
CN102561555A (en) Method for connecting wallboard components of precast concrete shear wall structure
CN102051929A (en) Block masonry wall configured with steel ribs and manufacture method thereof
CN205530324U (en) Cold-formed thin-wall section steel micro pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180406