CN207074151U - A kind of hydraulic engineering concrete test device - Google Patents

A kind of hydraulic engineering concrete test device Download PDF

Info

Publication number
CN207074151U
CN207074151U CN201720987749.9U CN201720987749U CN207074151U CN 207074151 U CN207074151 U CN 207074151U CN 201720987749 U CN201720987749 U CN 201720987749U CN 207074151 U CN207074151 U CN 207074151U
Authority
CN
China
Prior art keywords
fixed
block
plate
slide rail
installing frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720987749.9U
Other languages
Chinese (zh)
Inventor
秦庆元
焦树旺
钟尚鹏
高庆国
李兴花
马海苹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720987749.9U priority Critical patent/CN207074151U/en
Application granted granted Critical
Publication of CN207074151U publication Critical patent/CN207074151U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

It the utility model is related to a kind of test device, more particularly to a kind of hydraulic engineering concrete test device.The technical problems to be solved in the utility model is to provide a kind of high efficiency, good test effect, and can be easy to the hydraulic engineering concrete test device carried.In order to solve the above-mentioned technical problem, the utility model provides such a hydraulic engineering concrete test device, includes bottom plate, support base, places plate, side plate, top plate, first elevating mechanism etc.;Top plate is fixed in the top of side plate in the horizontal direction, plate is placed to be fixed at the top of bottom plate by support base, place the standing groove for offering in the middle part of plate and being placed for concrete, first elevating mechanism is fixed in top plate bottom, second elevating mechanism is fixed in top plate bottom, and the first elevating mechanism and the second elevating mechanism are connected.The utility model has reached high efficiency, good test effect, and can be easy to the effect carried.

Description

A kind of hydraulic engineering concrete test device
Technical field
It the utility model is related to a kind of test device, more particularly to a kind of hydraulic engineering concrete test device.
Background technology
Hydraulic engineering is to eliminate the engineering that water damage and utilization water resource are built.It is divided into flood control by its service object Engineering, farmland water conservancy works, hydraulic power project, navigation channel and port engineering, water supply and drainage system, environmental bydraulic engineering engineering, sea Apply project of cultivation etc..It can be the hydraulic engineering of the plurality of target services such as flood control, water supply, irrigation, generating simultaneously, referred to as comprehensively utilize Hydraulic engineering.Hydraulic engineering needs to build dam, dike, spillway, sluice, water inlet, channel, crosses the inhomogeneities such as mortise, log chute, fish pass The hydraulic structure of type, to realize its target.
In hydraulic engineering field, the application of concrete is essential, wherein concrete because of factors such as the ratios of configuration not Together, the concrete strength made has difference, and the concrete required in dam construction needs high intensity, high stress, therefore Need to test made concrete, to improve Quality of Water Conservancy Projects.
The test device of current concrete strength is too heavy, there is be not easy to carry, efficiency is slow, test effect not The shortcomings that good, therefore a kind of high efficiency need to be researched and developed, good test effect, and the hydraulic engineering that can be easy to carry is surveyed with concrete Trial assembly is put.
Utility model content
(1) technical problems to be solved
For the utility model in order to overcome the test device of current concrete strength too heavy, there is be not easy to remove The shortcomings that fortune, efficiency are slow, test is ineffective, the technical problems to be solved in the utility model is to provide a kind of high efficiency, test Effect is good, and can be easy to the hydraulic engineering concrete test device carried.
(2) technical scheme
In order to solve the above-mentioned technical problem, the utility model provides such a hydraulic engineering and filled with concrete test Put, include bottom plate, support base, place plate, side plate, top plate, the first elevating mechanism, the second elevating mechanism and mechanism for testing;Side Plate is vertically fixed in the end of bottom plate, and top plate is fixed in the top of side plate in the horizontal direction, places plate and passes through support base It is fixed at the top of bottom plate, places the standing groove for offering in the middle part of plate and being placed for concrete, the first elevating mechanism is fixed in top plate bottom Portion, the second elevating mechanism are fixed in top plate bottom, and the first elevating mechanism and the second elevating mechanism are connected, and mechanism for testing is affixed In the output end of the second elevating mechanism.
Preferably, the first elevating mechanism includes installing plate, the first sliding block, the first slide rail, rack, head rod, liter Block, the second connecting rod, motor and gear drop;Installing plate is fixed in the bottom of top plate;First slide rail is fixed in the side of installing plate Portion, the second connecting rod are fixed in the other side of installing plate;Rack is slidably connected by the first sliding block and the first slide rail, and first connects Rack bottom is fixed at the top of extension bar, elevator is fixed in head rod bottom, and motor is fixed in the second connecting rod bottom;Tooth The output end of wheel and motor is connected, and wheel and rack engages.
Preferably, the second elevating mechanism includes the first bracing wire, the first elastic component, the second sliding block, the first movable block, second Movable block, the 3rd sliding block, the second elastic component, the second bracing wire, the first electronic reel, first support bar, the second slide rail, first are consolidated Determine block, the first installing frame, the second fixed block, the 3rd slide rail, second support bar, the second electronic reel, the 4th slide rail and the 4th Sliding block;Two the 4th slide rails are fixed in top plate bottom, and are located at installing plate both sides;First installing frame passes through two Four-sliders and the 4th Slide rail is slidably connected, and the first fixed block, the second fixed block are fixed in the first installing frame inner bottom part, and the first electronic reel is fixed in A side wall of first installing frame close to the first fixed block;First support bar is fixed in the first installation frame bottom, and positioned at the first electricity Move between reel and the first fixed block;Second slide rail one end is fixed at the top of first support bar, and the other end is fixed in first On fixed block;First movable block is slidably connected by the second sliding block and the second slide rail;First bracing wire one end is fixed in the second sliding block Sidepiece, the other end are wire-wrapped on the first electronic reel;First movable block is by the first elastic component and the first installing frame close to The side wall of one fixed block is affixed, and the second electronic reel is fixed in a side wall of first installing frame close to the second fixed block;Second Support bar is fixed in the first installation frame bottom, and between the second electronic reel and the second fixed block;3rd slide rail one end Portion is fixed at the top of second support bar, and the other end is fixed on the second fixed block;Second movable block passes through the 3rd sliding block and the 3rd Slide rail is slidably connected;Second bracing wire one end is fixed in the 3rd sliding block sidepiece, and the other end is wire-wrapped on the second electronic reel;Second Movable block is affixed close to the side wall of the second fixed block with the first installing frame by the second elastic component, the second movable block and the first movement Block is engaged.
Preferably, mechanism for testing includes the second installing frame, screw rod, nut, weight block and taps hammer;Second installing frame is consolidated The first installation frame bottom is connected to, more screw rods are fixed in the second installing frame inner bottom part, offer what is passed through for screw rod on weight block Through hole, nut are spirally connected with screw rod, tap hammer and are fixed in the second installation frame bottom.
Operation principle:When that need to detect concrete block, worker is first placed on the concrete block that need to be detected to place and opened on plate If standing groove in, so reach the effect of fixing concrete block, after concrete block places, worker then passes through controller control The operating of the first elevating mechanism is made, so as to drive the second elevating mechanism to rise, when the second elevating mechanism rises to certain position, control The running of the second elevating mechanism is made, now the second elevating mechanism separates with the first elevating mechanism, due to the gravity of mechanism for testing itself Effect, mechanism for testing freely falling body hit concrete block, calculate data when mechanism for testing self gravitation and broken mixed mud block, Therefore the intensity of the concrete block is measured, when a block concrete block, which is tested, to be completed, worker passes through the lifting of controller control first Mechanism is connected with the second elevating mechanism, so as to drive mechanism for testing to return to initial position, by multiple test data, draws The exact value of concrete block.
Because the first elevating mechanism includes installing plate, the first sliding block, the first slide rail, rack, head rod, lifting Block, the second connecting rod, motor and gear;Installing plate is fixed in the bottom of top plate;First slide rail is fixed in a sidepiece of installing plate, Second connecting rod is fixed in the other side of installing plate;Rack is slidably connected by the first sliding block and the first slide rail, the first connection Rack bottom is fixed at the top of bar, elevator is fixed in head rod bottom, and motor is fixed in the second connecting rod bottom;Gear It is connected with the output end of motor, and wheel and rack engages;When the second elevating mechanism needs to rise, worker passes through control Device controlled motor rotates counterclockwise, and so as to be moved downward with carry-over bar along the first slide rail track, and then drives head rod Elevator move downward, elevator is fixed with coordinating to the second elevating mechanism, then controlled motor rotates clockwise, so as to drive Rack moves upwards along the first slide rail track, so drive elevator move upwards, elevator drive the second elevating mechanism to Upper motion so that mechanism for testing being capable of freely falling body progress concrete block strength test.
Because the second elevating mechanism includes the first bracing wire, the first elastic component, the second sliding block, the first movable block, the second shifting Motion block, the 3rd sliding block, the second elastic component, the second bracing wire, the first electronic reel, first support bar, the second slide rail, first are fixed Block, the first installing frame, the second fixed block, the 3rd slide rail, second support bar, the second electronic reel, the 4th slide rail and the 4th are slided Block;Two the 4th slide rails are fixed in top plate bottom, and are located at installing plate both sides;First installing frame is slided by two Four-sliders and the 4th Rail is slidably connected, and the first fixed block, the second fixed block are fixed in the first installing frame inner bottom part, and the first electronic reel is fixed in A side wall of one installing frame close to the first fixed block;First support bar is fixed in the first installation frame bottom, and electronic positioned at first Between reel and the first fixed block;Second slide rail one end is fixed at the top of first support bar, and it is solid that the other end is fixed in first Determine on block;First movable block is slidably connected by the second sliding block and the second slide rail;First bracing wire one end is fixed in the second sliding block side Portion, the other end are wire-wrapped on the first electronic reel;First movable block is by the first elastic component and the first installing frame close to first The side wall of fixed block is affixed, and the second electronic reel is fixed in a side wall of first installing frame close to the second fixed block;Second Strut is fixed in the first installation frame bottom, and between the second electronic reel and the second fixed block;3rd slide rail one end It is fixed at the top of second support bar, the other end is fixed on the second fixed block;Second movable block is slided by the 3rd sliding block and the 3rd Rail is slidably connected;Second bracing wire one end is fixed in the 3rd sliding block sidepiece, and the other end is wire-wrapped on the second electronic reel;Second moves Motion block is affixed close to the side wall of the second fixed block with the first installing frame by the second elastic component, the second movable block and the first movable block It is engaged;When elevator extrudes the first movable block and the second movable block so that the first movable block is with the second movable block mutually from fortune It is dynamic, so that the first elastic component and the second elastic component compress;It is less than the first movable block and the second movable block bottom at the top of elevator During portion, in the presence of the first elastic component and the second elastic component elastic force, so as to drive the first movable block and the second movable block opposite Motion, and then clamp elevator;When elevator drive the first installing frame moved upwards along the 4th slide rail track, until first peace During the arrival specified location that frames up, worker controls the first electronic reel to rotate counterclockwise by controller, the second electronic reel Rotate clockwise so that the first electronic reel winds the first bracing wire, and the second electronic reel winds the second bracing wire, so as to drive First movable block moves right along the second slide rail track to left movement, the second movable block along the 3rd slide rail track so that the One movable block and the second movable block unclamp elevator, while the first elastic component and the second elastic component are compressed, due to test machine The self gravitation effect of structure, so as to mechanism for testing sharp downward movement, complete the test of concrete block.
Because mechanism for testing includes the second installing frame, screw rod, nut, weight block and taps hammer;Second installing frame is affixed Frame bottom is installed in first, more screw rods are fixed in the second installing frame inner bottom part, offer on weight block and lead to for what screw rod passed through Hole, nut are spirally connected with screw rod, tap hammer and are fixed in the second installation frame bottom;When that need to test, worker first passes through weight block logical Hole is positioned on screw rod, and tightening nut, plays a part of fixed weight block, is then hit concrete block by tapping to hammer into shape, is seen The broken situation of concrete block is examined, records test data, the concrete block then cleared up in standing groove, another piece is reentered into and mixes Solidifying soil block, passes through the Action of Gravity Field of different gravity so that the test value of concrete block intensity is more accurate.
Control mode of the present utility model is automatically controlled by controller, and the control circuit of controller passes through this area Technical staff's simple programming i.e. can be achieved, the offer of power supply falls within the common knowledge of this area, and the utility model master To be used for protecting mechanical device, so the utility model is not explained control mode and connected with circuit.
(3) beneficial effect
By controlling the first elevating mechanism to operate, the first elevating mechanism and the second elevating mechanism coordinate the utility model, from And drive the second elevating mechanism to move up and down, and then drive the mechanism for testing movement of falling object to hit concrete block, by multiple Test and record, so as to be detected to concrete block, control the operating of the device by controller in the engineering of detection, make Obtain worker and avoid injury in detection process to a certain extent.
Brief description of the drawings
Fig. 1 is main structure diagram of the present utility model.
Fig. 2 is the main structure diagram of the elevating mechanism of the utility model first.
Fig. 3 is the main structure diagram of the elevating mechanism of the utility model second.
Fig. 4 is the main structure diagram of the utility model mechanism for testing.
Fig. 5 is the main structure diagram of the utility model gravity block.
Mark in accompanying drawing for:1- bottom plates, 2- support bases, 3- place plate, 4- standing grooves, 5- side plates, 6- top plates, 7- first Elevating mechanism, 71- installing plates, the sliding blocks of 72- first, the slide rails of 73- first, 74- racks, 75- head rods, 76- elevators, The connecting rods of 77- second, 78- motors, 79- gears, the elevating mechanisms of 8- second, the bracing wires of 81- first, the elastic components of 82- first, 83- Two sliding blocks, the movable blocks of 84- first, the movable blocks of 85- second, the sliding blocks of 86- the 3rd, the elastic components of 87- second, the bracing wires of 88- second, 89- First electronic reel, 810- first support bars, the slide rails of 811- second, the fixed blocks of 812- first, the installing frames of 813- first, 814- Second fixed block, the slide rails of 815- the 3rd, 816- second support bars, the second electronic reels of 817-, the slide rails of 818- the 4th, 819- Four-slider, 9- mechanism for testing, the installing frames of 91- second, 92- screw rods, 93- nuts, 94- weight blocks, 95- tap hammer, 96- through holes.
Embodiment
The utility model is further described with reference to the accompanying drawings and examples.
Embodiment 1
A kind of hydraulic engineering concrete test device, as Figure 1-5, include bottom plate 1, support base 2, place plate 3, Side plate 5, top plate 6, the first elevating mechanism 7, the second elevating mechanism 8 and mechanism for testing 9;Side plate 5 is vertically fixed in bottom plate 1 End, top plate 6 is fixed in the top of side plate 5, places plate 3 and be fixed in the top of bottom plate 1 by support base 2, put in the horizontal direction Put the middle part of plate 3 and offer the standing groove 4 placed for concrete, the first elevating mechanism 7 is fixed in the bottom of top plate 6, the second lift Structure 8 is fixed in the bottom of top plate 6, and the first elevating mechanism 7 is connected with the second elevating mechanism 8, and mechanism for testing 9 is fixed in second liter The output end of descending mechanism 8.
First elevating mechanism 7 includes installing plate 71, the first sliding block 72, the first slide rail 73, rack 74, head rod 75th, elevator 76, the second connecting rod 77, motor 78 and gear 79;Installing plate 71 is fixed in the bottom of top plate 6;First slide rail 73 A sidepiece of installing plate 71 is fixed in, the second connecting rod 77 is fixed in the other side of installing plate 71;Rack 74 is slided by first Block 72 is slidably connected with the first slide rail 73, and the top of head rod 75 is fixed in the bottom of rack 74, and elevator 76 is fixed in first The bottom of connecting rod 75, motor 78 are fixed in the bottom of the second connecting rod 77;The output end of gear 79 and motor 78 is connected, and tooth Wheel 79 engages with rack 74.
Second elevating mechanism 8 includes the first bracing wire 81, the first elastic component 82, the second sliding block 83, the first movable block 84, Two movable blocks 85, the 3rd sliding block 86, the second elastic component 87, the second bracing wire 88, the first electronic reel 89, first support bar 810, Second slide rail 811, the first fixed block 812, the first installing frame 813, the second fixed block 814, the 3rd slide rail 815, second support bar 816th, the second electronic reel 817, the 4th slide rail 818 and Four-slider 819;Two the 4th slide rails 818 are fixed in the bottom of top plate 6, And it is located at the both sides of installing plate 71;First installing frame 813 is slidably connected by two Four-sliders 819 with the 4th slide rail 818, and first is solid Determine block 812, the second fixed block 814 is fixed in the inner bottom part of the first installing frame 813, the first electronic reel 89 is fixed in the first installation A side wall of the frame 813 close to the first fixed block 812;First support bar 810 is fixed in the bottom of the first installing frame 813, and positioned at the Between the one electronic fixed block 812 of reel 89 and first;The one end of second slide rail 811 is fixed in the top of first support bar 810, separately One end is fixed on the first fixed block 812;First movable block 84 is slidably connected by the second sliding block 83 and the second slide rail 811;The The one end of one bracing wire 81 is fixed in the sidepiece of the second sliding block 83, and the other end is wire-wrapped on the first electronic reel 89;First movable block 84 , the second electronic reel 817 affixed close to the side wall of the first fixed block 812 with the first installing frame 813 by the first elastic component 82 It is fixed in a side wall of first installing frame 813 close to the second fixed block 814;Second support bar 816 is fixed in the first installing frame 813 Bottom, and between the second electronic fixed block 814 of reel 817 and second;The one end of 3rd slide rail 815 is fixed in second The top of strut 816, the other end are fixed on the second fixed block 814;Second movable block 85 passes through the 3rd sliding block 86 and the 3rd slide rail 815 are slidably connected;The one end of second bracing wire 88 is fixed in the sidepiece of the 3rd sliding block 86, and the other end is wire-wrapped in the second electronic reel 817 On;Second movable block 85 is affixed close to the side wall of the second fixed block 814 with the first installing frame 813 by the second elastic component 87, the Two movable blocks 85 are engaged with the first movable block 84.
Mechanism for testing 9 includes the second installing frame 91, screw rod 92, nut 93, weight block 94 and taps hammer 95;Second installation Frame 91 is fixed in the bottom of the first installing frame 813, and more screw rods 92 are fixed in the inner bottom part of the second installing frame 91, opened up on weight block 94 There is the through hole 96 passed through for screw rod 92, nut 93 is spirally connected with screw rod 92, taps hammer 95 and is fixed in the bottom of the second installing frame 91.
Operation principle:When that need to detect concrete block, worker is first placed on the concrete block that need to be detected to place and opened on plate 3 If standing groove 4 in, so reach the effect of fixing concrete block, after concrete block places, worker then passes through controller The first elevating mechanism 7 is controlled to operate, so as to drive the second elevating mechanism 8 to rise, when the second elevating mechanism 8 rises to certain position When, the second elevating mechanism 8 of control operates, and now the second elevating mechanism 8 separates with the first elevating mechanism 7, due to mechanism for testing 9 certainly The Action of Gravity Field of body, the freely falling body of mechanism for testing 9 hit concrete block, calculate the self gravitation of mechanism for testing 9 and mixed mud block is broken Data when broken, therefore the intensity of the concrete block is measured, when a block concrete block, which is tested, to be completed, worker passes through controller control Make the first elevating mechanism 7 to be connected with the second elevating mechanism 8, so as to drive mechanism for testing 9 to return to initial position, by multiple Test data, draw the exact value of concrete block.
Connected because the first elevating mechanism 7 includes installing plate 71, the first sliding block 72, the first slide rail 73, rack 74, first Bar 75, elevator 76, the second connecting rod 77, motor 78 and gear 79;Installing plate 71 is fixed in the bottom of top plate 6;First slide rail 73 are fixed in a sidepiece of installing plate 71, and the second connecting rod 77 is fixed in the other side of installing plate 71;Rack 74 passes through first Sliding block 72 is slidably connected with the first slide rail 73, and the top of head rod 75 is fixed in the bottom of rack 74, and elevator 76 is fixed in the The bottom of one connecting rod 75, motor 78 are fixed in the bottom of the second connecting rod 77;The output end of gear 79 and motor 78 is connected, and Gear 79 engages with rack 74;When the second elevating mechanism 8 needs to rise, worker is turned counterclockwise by controller controlled motor 78 It is dynamic, so as to be moved downward with carry-over bar 74 along the track of the first slide rail 73, and then drive the elevator 76 of head rod 75 to Lower motion, elevator 76 are fixed with coordinating to the second elevating mechanism 8, then controlled motor 78 rotates clockwise, so as to carry-over bar 74 move upwards along the track of the first slide rail 73, and then drive elevator 76 to move upwards, and elevator 76 drives the second lift Structure 8 moves upwards so that mechanism for testing 9 being capable of freely falling body progress concrete block strength test.
Because the second elevating mechanism 8 includes the first bracing wire 81, the first elastic component 82, the second sliding block 83, the first movable block 84th, the second movable block 85, the 3rd sliding block 86, the second elastic component 87, the second bracing wire 88, the first electronic reel 89, first support Bar 810, the second slide rail 811, the first fixed block 812, the first installing frame 813, the second fixed block 814, the 3rd slide rail 815, second Support bar 816, the second electronic reel 817, the 4th slide rail 818 and Four-slider 819;Two the 4th slide rails 818 are fixed in top plate 6 Bottom, and it is located at the both sides of installing plate 71;First installing frame 813 is slidably connected by two Four-sliders 819 with the 4th slide rail 818, First fixed block 812, the second fixed block 814 are fixed in the inner bottom part of the first installing frame 813, and the first electronic reel 89 is fixed in A side wall of one installing frame 813 close to the first fixed block 812;First support bar 810 is fixed in the bottom of the first installing frame 813, and Between the first electronic fixed block 812 of reel 89 and first;The one end of second slide rail 811 is fixed in first support bar 810 Top, the other end are fixed on the first fixed block 812;First movable block 84 is slided by the second sliding block 83 and the second slide rail 811 Connection;The one end of first bracing wire 81 is fixed in the sidepiece of the second sliding block 83, and the other end is wire-wrapped on the first electronic reel 89;First moves Motion block 84 passes through, the second electronic coiling affixed close to the side wall of the first fixed block 812 with the first installing frame 813 of the first elastic component 82 Wheel 817 is fixed in a side wall of first installing frame 813 close to the second fixed block 814;Second support bar 816 is fixed in the first installation The bottom of frame 813, and between the second electronic fixed block 814 of reel 817 and second;The one end of 3rd slide rail 815 is fixed in The top of second support bar 816, the other end are fixed on the second fixed block 814;Second movable block 85 passes through the 3rd sliding block 86 and Three slide rails 815 are slidably connected;The one end of second bracing wire 88 is fixed in the sidepiece of the 3rd sliding block 86, and the other end is wire-wrapped in the second electronic coiling On wheel 817;Second movable block 85 is consolidated by the second elastic component 87 and side wall of first installing frame 813 close to the second fixed block 814 Connect, the second movable block 85 is engaged with the first movable block 84;When elevator 76 extrudes the first movable block 84 and the second movable block 85 so that the first movable block 84 with the phase of the second movable block 85 from motion so that the first elastic component 82 is pressed with the second elastic component 87 Contracting;When the top of elevator 76 is less than the first movable block 84 and the second 85 bottom of movable block, in the first elastic component 82 and the second bullet Property the elastic force of part 87 in the presence of, so as to drive the first movable block 84 and the move toward one another of the second movable block 85, and then clamp elevator 76;When elevator 76 drives the first installing frame 813 to be moved upwards along the track of the 4th slide rail 818, until the first installing frame 813 arrives During up to specified location, worker controls the first electronic reel 89 to rotate counterclockwise by controller, the second electronic reel 817 is suitable Hour hands rotate so that and the first electronic reel 89 winds the first bracing wire 81, and the second electronic reel 817 winds the second bracing wire 88, So as to drive the first movable block 84 along the track of the second slide rail 811 to left movement, the second movable block 85 is along the rail of the 3rd slide rail 815 Mark moves right so that the first movable block 84 and the second movable block 85 unclamp elevator 76, while the first elastic component 82 and second Elastic component 87 is compressed, and due to the self gravitation effect of mechanism for testing 9, so as to the sharp downward movement of mechanism for testing 9, is completed mixed The test of solidifying soil block.
Because mechanism for testing 9 includes the second installing frame 91, screw rod 92, nut 93, weight block 94 and taps hammer 95;Second Installing frame 91 is fixed in the bottom of the first installing frame 813, and more screw rods 92 are fixed in the inner bottom part of the second installing frame 91, on weight block 94 The through hole 96 passed through for screw rod 92 is offered, nut 93 is spirally connected with screw rod 92, taps hammer 95 and is fixed in the bottom of the second installing frame 91; When that need to test, worker is first positioned over weight block 94 on screw rod 92 by through hole 96, and tightening nut 93, plays fixed weight The effect of block 94, concrete block then is hit by tapping hammer 95, observes the broken situation of concrete block, record test data, Then the concrete block cleared up in standing groove 4, is reentered into another block concrete block, by the Action of Gravity Field of different gravity, makes The test value for obtaining concrete block intensity is more accurate.
Control mode of the present utility model is automatically controlled by controller, and the control circuit of controller passes through this area Technical staff's simple programming i.e. can be achieved, the offer of power supply falls within the common knowledge of this area, and the utility model master To be used for protecting mechanical device, so the utility model is not explained control mode and connected with circuit.
Embodiment described above only expresses preferred embodiment of the present utility model, and its description is more specific and detailed, But therefore it can not be interpreted as the limitation to the utility model patent scope.It should be pointed out that for the common of this area For technical staff, without departing from the inventive concept of the premise, some deformations can also be made, improves and substitutes, these are all Belong to the scope of protection of the utility model.Therefore, the protection domain of the utility model patent should be determined by the appended claims.

Claims (4)

1. a kind of hydraulic engineering concrete test device, it is characterised in that include bottom plate (1), support base (2), place plate (3), side plate (5), top plate (6), the first elevating mechanism (7), the second elevating mechanism (8) and mechanism for testing (9);Side plate (5) is along perpendicular For Nogata to the end for being fixed in bottom plate (1), top plate (6) is fixed in the top of side plate (5) in the horizontal direction, places plate (3) and passes through Support base (2) is fixed at the top of bottom plate (1), places the standing groove (4) for offering in the middle part of plate (3) and being placed for concrete, first liter Descending mechanism (7) is fixed in top plate (6) bottom, and the second elevating mechanism (8) is fixed in top plate (6) bottom, the first elevating mechanism (7) with Second elevating mechanism (8) is connected, and mechanism for testing (9) is fixed in the output end of the second elevating mechanism (8).
A kind of 2. hydraulic engineering concrete test device according to claim 1, it is characterised in that the first elevating mechanism (7) installing plate (71), the first sliding block (72), the first slide rail (73), rack (74), head rod (75), elevator are included (76), the second connecting rod (77), motor (78) and gear (79);Installing plate (71) is fixed in the bottom of top plate (6);First slide rail (73) sidepiece of installing plate (71) is fixed in, the second connecting rod (77) is fixed in the other side of installing plate (71);Rack (74) it is slidably connected by the first sliding block (72) and the first slide rail (73), rack (74) bottom is fixed at the top of head rod (75) End, elevator (76) are fixed in head rod (75) bottom, and motor (78) is fixed in the second connecting rod (77) bottom;Gear (79) output end with motor (78) is connected, and gear (79) engages with rack (74).
A kind of 3. hydraulic engineering concrete test device according to claim 2, it is characterised in that the second elevating mechanism (8) the first bracing wire (81), the first elastic component (82), the second sliding block (83), the first movable block (84), the second movable block are included (85), the 3rd sliding block (86), the second elastic component (87), the second bracing wire (88), the first electronic reel (89), first support bar (810), the second slide rail (811), the first fixed block (812), the first installing frame (813), the second fixed block (814), the 3rd slide rail (815), second support bar (816), the second electronic reel (817), the 4th slide rail (818) and Four-slider (819);Two the 4th Slide rail (818) is fixed in top plate (6) bottom, and is located at installing plate (71) both sides;First installing frame (813) passes through two Four-sliders (819) it is slidably connected with the 4th slide rail (818), the first fixed block (812), the second fixed block (814) are fixed in the first installing frame (813) inner bottom part, the first electronic reel (89) are fixed in the first installing frame (813) close to the side of the first fixed block (812) Wall;First support bar (810) is fixed in the first installing frame (813) bottom, and solid with first positioned at the first electronic reel (89) Determine between block (812);Second slide rail (811) one end is fixed at the top of first support bar (810), and it is solid that the other end is fixed in first Determine on block (812);First movable block (84) is slidably connected by the second sliding block (83) and the second slide rail (811);First bracing wire (81) one end is fixed in the second sliding block (83) sidepiece, and the other end is wire-wrapped on the first electronic reel (89);First movable block (84) affixed close to the side wall of the first fixed block (812) with the first installing frame (813) by the first elastic component (82), second is electronic Reel (817) is fixed in a side wall of the first installing frame (813) close to the second fixed block (814);Second support bar (816) is solid The first installing frame (813) bottom is connected to, and between the second electronic reel (817) and the second fixed block (814);3rd slides Rail (815) one end is fixed at the top of second support bar (816), and the other end is fixed on the second fixed block (814);Second movement Block (85) is slidably connected by the 3rd sliding block (86) with the 3rd slide rail (815);Second bracing wire (88) one end is fixed in the 3rd sliding block (86) sidepiece, the other end are wire-wrapped on the second electronic reel (817);Second movable block (85) by the second elastic component (87) with First installing frame (813) is affixed close to the side wall of the second fixed block (814), and the second movable block (85) connects with the first movable block (84) Touch and coordinate.
A kind of 4. hydraulic engineering concrete test device according to claim 3, it is characterised in that mechanism for testing (9) Include the second installing frame (91), screw rod (92), nut (93), weight block (94) and tap hammer (95);Second installing frame (91) It is fixed in the first installing frame (813) bottom, more screw rods (92) are fixed in the second installing frame (91) inner bottom part, on weight block (94) The through hole (96) passed through for screw rod (92) is offered, nut (93) is spirally connected with screw rod (92), taps hammer (95) and is fixed in the second peace Frame up (91) bottom.
CN201720987749.9U 2017-08-09 2017-08-09 A kind of hydraulic engineering concrete test device Expired - Fee Related CN207074151U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720987749.9U CN207074151U (en) 2017-08-09 2017-08-09 A kind of hydraulic engineering concrete test device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720987749.9U CN207074151U (en) 2017-08-09 2017-08-09 A kind of hydraulic engineering concrete test device

Publications (1)

Publication Number Publication Date
CN207074151U true CN207074151U (en) 2018-03-06

Family

ID=61523321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720987749.9U Expired - Fee Related CN207074151U (en) 2017-08-09 2017-08-09 A kind of hydraulic engineering concrete test device

Country Status (1)

Country Link
CN (1) CN207074151U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109060574A (en) * 2018-08-22 2018-12-21 王真 A kind of hydraulic engineering concrete test device and method
CN109269921A (en) * 2018-10-11 2019-01-25 深圳市恩普达工业***有限公司 Battery pole electricity column test macro
CN109612851A (en) * 2018-11-19 2019-04-12 郭才剑 A kind of safety cap detection device
CN111238978A (en) * 2020-01-11 2020-06-05 广东顺水工程建设监理有限公司 Strength detection equipment of hydraulic engineering dam body

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109060574A (en) * 2018-08-22 2018-12-21 王真 A kind of hydraulic engineering concrete test device and method
CN109060574B (en) * 2018-08-22 2020-11-17 天长市水电建筑安装工程公司 Concrete testing device and method for hydraulic engineering
CN109269921A (en) * 2018-10-11 2019-01-25 深圳市恩普达工业***有限公司 Battery pole electricity column test macro
CN109612851A (en) * 2018-11-19 2019-04-12 郭才剑 A kind of safety cap detection device
CN109612851B (en) * 2018-11-19 2021-12-28 西藏瑞华资本管理有限公司 Safety helmet detection equipment
CN111238978A (en) * 2020-01-11 2020-06-05 广东顺水工程建设监理有限公司 Strength detection equipment of hydraulic engineering dam body

Similar Documents

Publication Publication Date Title
CN207074151U (en) A kind of hydraulic engineering concrete test device
CN105780716B (en) A kind of fish pass experimental provision and its operation method
US20190383714A1 (en) Fully automatic true triaxial tunnel and underground project model test system
CN205329624U (en) Fishway experimental apparatus
CN204630746U (en) A kind of top coals' recovery ratio and ore deposit are pressed and are manifested relationship experiments platform
CN104614191A (en) Experiment table of relationship between top coal's recovery ratio and strata behavior, application method thereof
CN104330309A (en) Mechanical load testing machine for photovoltaic module
CN1403685A (en) Pile hole callipers
CN109865974A (en) A kind of steel reinforcement cage shaping equipment
CN104749342B (en) Automatic preloading and unloading centrifuge test robot device
CN103233484B (en) Circulating water supply system for centrifugal model testing and usage method thereof
CN109681268B (en) Indoor experiment method for simulating filling process of metal underground mine stope
CN209432245U (en) A kind of hydraulic engineering water level monitoring device
CN102936868A (en) Precise adjustment auxiliary device for track board of high speed railway and adjusting method thereof
CN207779825U (en) A kind of highway pavement anti-pressure ability detection device
CN207121888U (en) A kind of hydraulic engineering sundries cleaning device
CN216718422U (en) Model test system for testing stability analysis effect of multiple circular arc models
CN215715641U (en) Hydraulic engineering surveys with filling pit equipment
CN213749322U (en) High-speed ring shear test machine capable of simulating environment and measuring shear strength parameters of landslide mass
CN207367471U (en) A kind of native face flattening device suitable for building, water conservancy and ocean engineering indoor model experiments groove
CN108130883A (en) A kind of water-level fluctuation device of tide simulation load
CN205785756U (en) A kind of tracking mode disappears wave overflow means
CN209230857U (en) A kind of lift noise barrier stand column Bolt Torque detection device
CN208568443U (en) A kind of construction material hardness ability to bear detection device
CN102518078A (en) Underwater sand collector for physical river model

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180306