CN207063267U - For making the connection component of superimposed sheet - Google Patents

For making the connection component of superimposed sheet Download PDF

Info

Publication number
CN207063267U
CN207063267U CN201720903573.4U CN201720903573U CN207063267U CN 207063267 U CN207063267 U CN 207063267U CN 201720903573 U CN201720903573 U CN 201720903573U CN 207063267 U CN207063267 U CN 207063267U
Authority
CN
China
Prior art keywords
screw rod
supporting plate
connection component
sleeve
locking member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720903573.4U
Other languages
Chinese (zh)
Inventor
李荣鹏
王征
韩阳
沃海燕
樊亮
窦学峰
刘红科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban Construction Engineering Tenth Co Ltd
Original Assignee
Beijing Urban Construction Engineering Tenth Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban Construction Engineering Tenth Co Ltd filed Critical Beijing Urban Construction Engineering Tenth Co Ltd
Priority to CN201720903573.4U priority Critical patent/CN207063267U/en
Application granted granted Critical
Publication of CN207063267U publication Critical patent/CN207063267U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

Be used to making the connection component of superimposed sheet the utility model discloses a kind of, connection component include supporting plate and it is multiple hang mould, supporting plate is used to block strip neutral gear, and hanging mould includes:Part is born, it is used to abut with two prefabricated boards;Screw rod, its upper end, which is fixed on, to be born on part, and its lower end wears supporting plate;Locking member, it is set in the lower end of screw rod, and locking member is connected with screw flight;First sleeve, it is set on screw rod and positioned at the top of supporting plate, and when concreting is in strip neutral gear, first sleeve is embedded in poured concrete.Because screw rod is arranged in first sleeve and freely can be extracted from first sleeve, therefore, the concrete of solidification is extracted without limitation on screw rod, so as to when dismantling connection component, screw rod can be extracted from first sleeve, first sleeve is only stayed in concrete, avoid because screw rod can not be extracted from concrete and caused by material waste.

Description

For making the connection component of superimposed sheet
Technical field
Technical field of building construction is the utility model is related to, more particularly to a kind of connection component for being used to make superimposed sheet.
Background technology
Concrete folding plate is to use prefabricated prestressed concrete bottom plate (or for prefabricated board) and cast-in-place concrete layer The assembled integral structure of (Bars In Poured Concrete Slab) composition, it has good globality and shock resistance.Concrete folding plate, which saves, to be applied Template in work, accelerates construction speed, so as to reduce engineering cost.
At present, the technical process of job site making concrete folding plate is:Prefabricated board is laid at the construction field (site), prefabricated Cast-in-place concrete on plate, Bars In Poured Concrete Slab is formed after the cast-in-place concrete setting.
During prefabricated board is laid, by job site size and the size of prefabricated board mismatch can cause to be laid Last two pieces of prefabricated boards between neutral gear it is larger, it is necessary in cast-in-place concrete, utilize Concrete Filled neutral gear.
For the Concrete Filled neutral gear can be made, bottom is hung using reinforcing bar on prefabricated board using reinforcing bar cross-arm in the prior art Mould, and after casting concrete, reinforcing bar can not be removed out, compare waste.
Utility model content
For defect present in prior art, the utility model embodiment provides a kind of connection for being used to make superimposed sheet Component.
In order to solve the above technical problems, the technical scheme that embodiment of the present utility model uses is:
A kind of connection component for being used to make superimposed sheet, for being installed in two prefabricated boards formed with strip neutral gear, The connection component includes supporting plate and hangs mould along the multiple of strip neutral gear bearing of trend arrangement, and the supporting plate is used for and two The bottom of the individual prefabricated board abuts, each described to hang mould and include to block the strip neutral gear:
Part is born, it is used to abut with the top of two prefabricated boards;
Screw rod, its upper end be fixed on it is described bear on part, its lower end is used to wear the supporting plate;
Locking member, it is set in the lower end of the screw rod and positioned at the lower section of the supporting plate, the locking member and the spiral shell Bar is threadedly coupled, and the locking member is by screwing so that the supporting plate is tight against on the prefabricated board;
First sleeve, it is set on the screw rod and positioned at the top of the supporting plate, when concreting is in the bar When in shape neutral gear, the first sleeve is embedded in poured concrete.
Preferably, it is described to bear on part formed with two push rods, it is described to bear part by two push rods respectively with two The top of the individual prefabricated board abuts, and the second sleeve pipe is arranged with two push rods, with when the concreting is in described When on prefabricated board to form Bars In Poured Concrete Slab, two second sleeve pipes are embedded in the Bars In Poured Concrete Slab.
Preferably, the part that bears is in shaft-like, and two push rods, which are arranged at, described to be born the both ends of part and held with described Draw piece is vertical.
Preferably, the connection component also includes two filler strips, and two filler strips are set in parallel under the supporting plate Side, and it is relative with two prefabricated boards respectively;Hanging mould described in each also includes bridge piece;The bridge piece is used to be overlapped on two On the individual filler strip and positioned at the lower section of the filler strip, the screw rod wears the bridge piece, and the locking member is taken positioned at described The lower section of fitting, the locking member are screwed to push against the supporting plate tight against the prefabricated board by the bridge piece.
Preferably, the bridge piece is folded to form by a reinforcing bar, after the lower end of the screw rod wears the reinforcing bar doubling The gap between two sections formed.
Preferably, the locking member include offer screwed hole main part and be arranged at the main part it is relative two The stopper section of side.
Preferably, the push rod is fixedly connected by welding manner with the part that bears, and the screw rod passes through welding manner It is fixedly connected with the part that bears.
The invention also discloses a kind of preparation method of superimposed sheet, comprise the following steps:
S10:Prefabricated board is laid on building;
S20:The above-mentioned connection component for being used to make superimposed sheet is installed in two prefabricated boards formed with strip neutral gear Place, wherein, S20 steps include:
S21:Supporting plate is arranged at the bottoms of two prefabricated boards to block strip neutral gear;
S22:The part that bears for making to be fixedly connected with screw rod and push rod is arranged along strip neutral gear bearing of trend;
S23:First sleeve is arranged on screw rod, and the lower end of screw rod is worn supporting plate, locking member is set in screw rod Lower end, the second sleeve pipe is arranged respectively on two push rods;
S24:Locking member is screwed, makes supporting plate tight against two prefabricated boards;
S30:Casting concrete in strip neutral gear and on prefabricated board, and the concrete to being poured is conserved with shape Into Bars In Poured Concrete Slab;
S40:Locking member is screwed out from the lower end of screw rod, and above carry and bear part, screw rod is deviate from from first sleeve, push rod Deviate from from the second sleeve pipe.
Preferably, after step S40, in addition to step S50:
Utilize upper face of the label higher than the floating Bars In Poured Concrete Slab of concrete of Bars In Poured Concrete Slab.
Preferably, also comprise the following steps between step 40 and step 50:If first sleeve protrudes from the upper of Bars In Poured Concrete Slab Plate face, by the Partial Resection of protrusion;If the second sleeve pipe protrudes from the upper face of Bars In Poured Concrete Slab, by the Partial Resection of protrusion.
Compared with prior art, the connection component for being used to make superimposed sheet of embodiment offer of the present utility model is beneficial Effect is:After concrete setting, first sleeve is just embedded in concrete, because screw rod is arranged in first sleeve and can be certainly By extracted from first sleeve, therefore, the concrete of solidification is extracted without limitation on screw rod, so as to when dismantling connection component, Screw rod can be extracted from first sleeve, only stay first sleeve in concrete, avoid because screw rod can not pull out from concrete Go out and cause the waste of material.
Brief description of the drawings
Fig. 1 is that the connection component for being used to make superimposed sheet that embodiment of the present utility model provides is installed on prefabricated board Structural representation, wherein, not yet casting concrete on prefabricated board.
Fig. 2 is Fig. 1 A direction views.
Fig. 3 is Fig. 1 B direction views.
Fig. 4 is that the structure of locking member in the connection component for being used to make superimposed sheet that embodiment of the present utility model provides is shown It is intended to.
Fig. 5 is that the connection component for being used to make superimposed sheet that embodiment of the present utility model provides is installed on prefabricated board Structural representation, wherein, concrete has been poured on prefabricated board.
In figure:
10- bears part;20- screw rods;30- supporting plates;40- locking members;41- main parts;42- stopper sections;50- filler strips;60- takes Fitting;70- push rods;80- first sleeves;The sleeve pipes of 90- second;100- prefabricated boards;200- strip neutral gears;300- Bars In Poured Concrete Slabs.
Embodiment
It is below in conjunction with the accompanying drawings and specific real to make those skilled in the art be better understood from the technical solution of the utility model Mode is applied to elaborate to the utility model.
As shown in Figure 1 to Figure 3, one embodiment of the present utility model discloses a kind of connection component, and the connection component is used In being installed on two formed with strip neutral gear 200 prefabricated boards 100.The connection component specifically includes supporting plate 30 and multiple hung Mould.Supporting plate 30 is strip, and its width is more than the width of strip neutral gear 200, and supporting plate 30 can be made up of plank, composite plate, iron plate, Supporting plate 30 is arranged on the lower section of two prefabricated boards 100 and with strip neutral gear 200 relatively to block strip neutral gear 200, supporting plate 30 Both sides on width are connected on two prefabricated boards 100 respectively.Multiple direction cloth for hanging mould and extending along strip neutral gear 200 Put, each hanging mould includes bearing part 10, screw rod 20, locking member 40 and first sleeve 80;Bear part 10 be arranged at two it is prefabricated The top of plate 100, this bears part 10 and is used to directly or indirectly abut with two prefabricated boards 100;The upper end of screw rod 20 is fixed On part 10 is born, the lower end of screw rod 20 wears supporting plate 30;Locking member 40 is set in the lower end of screw rod 20 and positioned at supporting plate 30 Lower section, locking member 40 are threadedly coupled with screw rod 20, locking member 40 is pushed up to supporting plate 30 by rotary fastenings 40, with regulation Supporting plate 30 is with bearing the distance between part 10, so that bearing part 10 and supporting plate 30 respectively tight against prefabricated board 100;First sleeve 80 are set on screw rod 20 and positioned at the top of supporting plate 30, formed with larger between the inner hole wall and screw rod 20 of the first sleeve 80 Gap, so that screw rod 20 can freely wear first sleeve 80 or freely extract from first sleeve 80, and make The length of first sleeve 80 should meet that after strip 200 casting concrete of neutral gear, the upper end of first sleeve 80 is higher by what is poured The upper surface of concrete, so that after the completion of concreting, concrete will not enter the inner hole wall and screw rod 20 of first sleeve 80 In the gap formed, so that screw rod 20 still is able to freely extract from first sleeve 80.
Being sentenced when the connection component of said structure installed in the strip neutral gear 200 of two prefabricated boards 100 blocks supporting plate 30 After strip neutral gear 200, by concreting in strip neutral gear 200, two prefabricated boards 100 are just realized after concrete setting Connection.
The utility model has the advantage of:After concrete setting, first sleeve 80 is just embedded in concrete, due to spiral shell Bar 20 is arranged in first sleeve 80 and freely can extracted from first sleeve 80, therefore, the concrete of solidification without limitation on Screw rod 20 is extracted, so as to which when dismantling connection component, screw rod 20 can be extracted from first sleeve 80, only stay first sleeve 80 to exist In concrete, avoid because screw rod 20 can not be extracted from concrete and caused by material waste.
The making of superimposed sheet just can be completed to make above-mentioned connection component once be assembled and disassembled, i.e. pass through connection component Once assembling and disassembling just can complete pouring for strip neutral gear 200 and pouring for Bars In Poured Concrete Slab 300 on prefabricated board 100, make to bear part 10 Distance to prefabricated board 100 is more than the thickness for the Bars In Poured Concrete Slab 300 to be poured.Specifically, as shown in figure 1, on part 10 is born Two push rods 70 are set, the lower end of two push rods 70 is connected on two prefabricated boards 100 of the both sides of strip neutral gear 200 respectively, And the height of push rod 70 need to cause the minimum position for bearing part 10 to be more than Bars In Poured Concrete Slab 300 to the distance of the upper face of prefabricated board 100 Thickness, and be arranged the second sleeve pipe 90 respectively on two push rods 70, now, first sleeve 80, the length of the second sleeve pipe 90 should For the satisfaction after the completion of Bars In Poured Concrete Slab 300 pours, the upper end of the sleeve pipe 90 of first sleeve 80 and second should be higher than that the upper table of Bars In Poured Concrete Slab 300 Face.In this way, being set in as shown in figure 5, working as the sleeve pipe 90 of first sleeve 80 and second and corresponding to respectively on screw rod 20 and push rod 70, and hold in the palm After plate 30 blocks strip neutral gear 200, to the casting concrete of strip neutral gear 200, after concrete pours strip neutral gear 200 completely, after Continue to casting concrete on all prefabricated boards 100, until the thickness of the concrete poured meets the thickness requirement of Bars In Poured Concrete Slab 300 Untill, after concrete setting, the concrete of the top of prefabricated board 100 just forms the Bars In Poured Concrete Slab 300 of superimposed sheet.In this way, when mixed After solidifying soil solidification, the sleeve pipe 90 of first sleeve 80 and second is just embedded in concrete, and screw rod 20 and push rod 70 due to wearing respectively In the sleeve pipe 90 of first sleeve 80 and second, and the sleeve pipe 90 of first sleeve 80 and second is higher by poured concrete, because This, screw rod 20 and push rod 70 are not limited by the concrete solidified, can be extracted from the sleeve pipe 90 of first sleeve 80 and second. In the present embodiment, because there is provided push rod 70 so that the thickness that part 10 is at least above 100 1 Bars In Poured Concrete Slabs 300 of prefabricated board is born, So as to just complete the filling of strip neutral gear 200 and the shaping of Bars In Poured Concrete Slab 300 by one-time-concreting.To reduce cost, first The sleeve pipe 90 of sleeve pipe 80 and second selects plastic bushing.
Various structures can be had by bearing part 10, for example, it is platy structure to bear part 10.Part is born to save material and making 10 process, as depicted in figs. 1 and 2, it is rod-like structure to bear part 10, bears part 10 for example, being used as from a reinforcing bar, and select By the use of another two isometric reinforcing bars as push rod 70, two push rods 70 are fixed by welding in the both ends for bearing part 10, and screw rod 20 is logical The middle part for being weldingly fixed on and bearing part 10 is crossed, in this way, the part 10 that bears for being welded with two push rods 70 and a screw rod 20 is in one " mountain " type.
To prevent the locking member 40 in tightening state directly acts on supporting plate 30 from causing supporting plate 30 to deform, in this practicality In a new preferred embodiment, as shown in figure 1, the both sides of supporting plate 30 with being all provided with below two prefabricated component abutment portions It is equipped with filler strip 50;Screw rod 20 wears a bridge piece 60 again after wearing supporting plate 30, and locking member 40 is located at the lower section of bridge piece 60, taken The both ends of fitting 60 are connected on two filler strips 50 respectively.In this way, when screwing locking member 40, the power that locking member 40 is applied passes through Bridge piece 60 passes to filler strip 50, then passes to prefabricated board 100 by filler strip 50, is applied so as to preventing locking member 40 Power, which is directly passed to supporting plate 30, deforms supporting plate 30.The structure of locking member 40 and bridge piece 60 can have it is a variety of, in this implementation In example, as shown in figure 4, locking member 40 is by offering the main part 41 of screwed hole and being shaped in relative two of main part 41 The stopper section 42 of side is formed;As shown in figure 3, bridge piece 60 is folded to form by a reinforcing bar, the lower end of screw rod 20 wears reinforcing bar pair The gap between two sections formed after folding.Stopper section 42 on locking member 40 can prevent locking member 40 is overall to stretch into screw rod 20 The hole that is worn and lead to not completion and screw.Bridge piece 60 in the present embodiment makes simply, easy to use.
It is first prefabricated above-mentioned before stating method on the implementation the invention also discloses a kind of preparation method of superimposed sheet Connection component, specifically, from an a diameter of 20mm, the one-level reinforcing bar that length is 500mm is as part 10 is born, from one A diameter of 20mm, length are 330mm screw rod 20;From two a diameter of 20mm, length is 170mm one-level reinforcing bar as two Individual push rod 70, the upper end of screw rod 20 is welded on the middle part for bearing part 10, and the upper end of two push rods 70 is welded on and bears part 10 Two sections, make the outer formation for bearing part 10 after welding fall " mountain " font;Cut out one block of supporting plate 30;Produce locking member 40; From a plastic bushing as first sleeve 80, from two plastic bushings as the second sleeve pipe 90;Prepare two filler strips 50; Prepare bridge piece 60 corresponding with bearing 10 numbers of part.
The preparation method of superimposed sheet of the present utility model specifically includes following steps:
S10:Tile prefabricated board 100 successively on building;If forming strip neutral gear between two neighboring prefabricated board 100, Just following step is implemented;If two neighboring prefabricated board does not form strip neutral gear, just directly poured on the prefabricated board 100 laid Concrete is built, Bars In Poured Concrete Slab 300 is just formed after the concrete setting poured.
It should be noted that:Due to the size of job site size and prefabricated board 100 be in most cases it is unmatched, because This, after the completion of prefabricated board 100 is laid, often can at least form strip neutral gear 300 between two prefabricated boards 100, and bar Shape neutral gear 300 would generally be formed between two prefabricated boards 100 finally laid.
S20:Above-mentioned connection component is installed on two prefabricated boards 100 formed with strip neutral gear 200, wherein, S20 Step specifically includes:
S21:Supporting plate 30 is arranged at the bottoms of two prefabricated boards 100 to block strip neutral gear 200;(
S22:The part 10 that bears for making to be welded with screw rod 20 and push rod 70 is arranged along the bearing of trend of strip neutral gear 200;
S23:First sleeve 80 is arranged on screw rod 20, is arranged the second sleeve pipe 90 respectively on two push rods 70, and make spiral shell The lower end of bar 20 wears supporting plate 30 and bridge piece 60, the lower end of two push rods 70 is born against the upper of two prefabricated boards 100 Plate face, locking member 40 is set to be set in the lower end of screw rod 20;
S24:Filler strip 50 is placed respectively in the position that supporting plate 30 abuts with two prefabricated boards 100, makes the both ends of bridge piece 60 Abutted respectively with two filler strips 50, screw locking member 40, bridge piece 60 is compressed supporting plate 30 by filler strip 50, so that supporting plate 30 Both sides tight against two prefabricated boards 100.Make supporting plate 30 tight against two prefabricated boards 100 tight against in prefabricated board 100.
S30:As shown in figure 5, casting concrete in strip neutral gear 200 and on prefabricated board 100, and it is mixed to what is poured Solidifying soil is conserved, and the concrete of the solidification above prefabricated board 100 forms the Bars In Poured Concrete Slab 300 of superimposed sheet.
S40:Locking member 40 is screwed out from the lower end of screw rod 20, and above carry and bear part 10, make screw rod 20 and two push rods 70 Extracted respectively from the sleeve pipe 90 of first sleeve 80 and second, first sleeve 80, the second sleeve pipe 90 are then protruded from into Bars In Poured Concrete Slab 300 Upper face Partial Resection.
S50:Utilize upper face of the label higher than the floating Bars In Poured Concrete Slab 300 of concrete of Bars In Poured Concrete Slab 300.
Above example is only exemplary embodiment of the present utility model, is not used in limitation the utility model, and this practicality is new The protection domain of type is defined by the claims.Those skilled in the art can be in essence of the present utility model and protection domain It is interior, various modifications or equivalent substitution are made to the utility model, this modification or equivalent substitution also should be regarded as new in this practicality In the protection domain of type.

Claims (7)

1. a kind of connection component for being used to make superimposed sheet, for being installed in two prefabricated boards formed with strip neutral gear, its It is characterised by, the connection component includes supporting plate and hangs mould, the support along the multiple of strip neutral gear bearing of trend arrangement Plate is used to abut with the bottom of two prefabricated boards, to block the strip neutral gear, it is each described in hang mould and include:
Part is born, it is used to abut with the top of two prefabricated boards;
Screw rod, its upper end be fixed on it is described bear on part, its lower end wears the supporting plate;
Locking member, it is set in the lower end of the screw rod and positioned at the lower section of the supporting plate, the locking member and the screw rod spiral shell Line connects, and the locking member is by screwing so that the supporting plate is tight against on the prefabricated board;
First sleeve, it is set on the screw rod and positioned at the top of the supporting plate, when concreting is empty in the strip When in shelves, the first sleeve is embedded in poured concrete.
2. the connection component according to claim 1 for being used to make superimposed sheet, it is characterised in that described bear is formed on part There are two push rods, the part that bears is abutted by top of two push rods respectively with two prefabricated boards, described in two The second sleeve pipe is arranged with push rod, with when the concreting is when on the prefabricated board to form Bars In Poured Concrete Slab, described in two Second sleeve pipe is embedded in the Bars In Poured Concrete Slab.
3. the connection component according to claim 2 for being used to make superimposed sheet, it is characterised in that the part that bears is in bar Shape, two push rods be arranged at the both ends for bearing part and with described to bear part vertical.
4. the connection component according to claim 1 for being used to make superimposed sheet, in addition to two filler strips, two filler strips The lower section of the supporting plate is set in parallel in, and it is relative with two prefabricated boards respectively;Hanging mould described in each also includes bridge piece, The bridge piece is used to be overlapped on two filler strips and wears the overlap joint positioned at the lower section of the filler strip, the screw rod Part, the locking member are located at the lower section of the bridge piece, and the locking member is screwed to push against the supporting plate by the bridge piece Tight against the prefabricated board.
5. the connection component according to claim 4 for being used to make superimposed sheet, the bridge piece is by a reinforcing bar doubling shape The gap between two sections formed after wearing the reinforcing bar doubling into the lower end of, the screw rod.
6. the connection component according to claim 1 for being used to make superimposed sheet, the locking member include offering screwed hole Main part and be arranged at the stopper sections of the relative both sides of the main part.
Be used to making the connection component of superimposed sheet 7. according to claim 3, the push rod by welding manner with it is described Bear part to be fixedly connected, the screw rod is fixedly connected by welding manner with the part that bears.
CN201720903573.4U 2017-07-24 2017-07-24 For making the connection component of superimposed sheet Active CN207063267U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720903573.4U CN207063267U (en) 2017-07-24 2017-07-24 For making the connection component of superimposed sheet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720903573.4U CN207063267U (en) 2017-07-24 2017-07-24 For making the connection component of superimposed sheet

Publications (1)

Publication Number Publication Date
CN207063267U true CN207063267U (en) 2018-03-02

Family

ID=61517431

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720903573.4U Active CN207063267U (en) 2017-07-24 2017-07-24 For making the connection component of superimposed sheet

Country Status (1)

Country Link
CN (1) CN207063267U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107687219A (en) * 2017-07-24 2018-02-13 北京城建十建设工程有限公司 For the preparation method of the connection component and superimposed sheet that make superimposed sheet
CN110241959A (en) * 2019-06-06 2019-09-17 中南林业科技大学 A kind of superimposed sheet and its construction method
CN111996921A (en) * 2020-09-07 2020-11-27 中冶建工集团有限公司 Construction method for hanging formwork at building joint
CN113293982A (en) * 2021-05-23 2021-08-24 晟通科技集团有限公司 Template combination

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107687219A (en) * 2017-07-24 2018-02-13 北京城建十建设工程有限公司 For the preparation method of the connection component and superimposed sheet that make superimposed sheet
CN110241959A (en) * 2019-06-06 2019-09-17 中南林业科技大学 A kind of superimposed sheet and its construction method
CN111996921A (en) * 2020-09-07 2020-11-27 中冶建工集团有限公司 Construction method for hanging formwork at building joint
CN113293982A (en) * 2021-05-23 2021-08-24 晟通科技集团有限公司 Template combination

Similar Documents

Publication Publication Date Title
CN207063267U (en) For making the connection component of superimposed sheet
CN107687219A (en) For the preparation method of the connection component and superimposed sheet that make superimposed sheet
CN107254884A (en) A kind of detachable prefabricated assembled concrete-filled steel square tubular column pin node
CN202706536U (en) Lateral support formwork applied to post-cast strip or construction joint
CN107476470A (en) Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method
CN204703498U (en) Wall of High-building deformation joint template construction structure
CN101864836B (en) Construction method for supporting template at construction joint of frame structure
CN206784158U (en) A kind of prefabricated bent cap constructs with Precast Pier Columns connecting node
CN102995572A (en) Connecting method and device for bridge-lifted thin-wall hollow pier and original pier column
CN106677520A (en) Beam, floor and corner uptight column composite structure of building aluminium alloy templates
CN104805960B (en) One kind exempts from form removal beams of concrete and its construction method
CN106087739A (en) A kind of combination U rib shaped steel floorings and preparation method thereof
CN107514083A (en) Side hangs reinforcing bar band shear key reinforced concrete slab structure and connection method
CN204781960U (en) High -rise building shear force wall movement joint department template is propped up and is established and reinforcement system
CN209924484U (en) Device with sleeve prefabricated part for reinforcing damaged reinforced concrete column
CN204112712U (en) A kind of side root haunch cast-in-place wall model sheetinstallat device
CN206329032U (en) Template suitable for pouring section after assembled beam-column
CN212271326U (en) Cast-in-place concrete wall body of combined truss reinforcing steel bars and steel plates
CN106499176A (en) Template and its installation method of section is poured after being applied to assembled beam-column
CN109537775A (en) The method for preparing assembly concrete shear wall using local corrugated thin-wall steel pipe
CN112627034A (en) Synchronous construction method for turning over mold of high pier of bridge
CN204112200U (en) Edge of a wing enhanced waveform steel web plate composite box girder
CN103216085B (en) A kind of removable lining self-bearing type reinforcement bar truss mould plate
CN206957198U (en) Cast-in-situ template structure at a kind of sandwich exterior wall J-shaped wall of prefabricated concrete structure
CN106759857B (en) Steel tube regeneration monolith assembling structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant