CN206903018U - A kind of curtain wall construction device for building - Google Patents
A kind of curtain wall construction device for building Download PDFInfo
- Publication number
- CN206903018U CN206903018U CN201720780592.2U CN201720780592U CN206903018U CN 206903018 U CN206903018 U CN 206903018U CN 201720780592 U CN201720780592 U CN 201720780592U CN 206903018 U CN206903018 U CN 206903018U
- Authority
- CN
- China
- Prior art keywords
- curtain wall
- fixed
- fix bar
- keel
- wall unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
The utility model discloses a kind of curtain wall construction device for building, including keel and fixation kit, the bottom of the keel is weldingly fixed on the middle part of fixed plate in advance, the both sides of the fixed plate are fixed on the surface of wall by expansion bolt, the top of the keel is fixedly connected with installing plate by hexagon socket head cap screw, the installing plate is provided with mounting hole, and fixation kit is fixed with the mounting hole, curtain wall unit is fixedly connected with the fixation kit.The utility model leads to simple to operate, by the position for adjusting fix bar top nut, the extension elongation of another fix bar one end can be adjusted, curtain wall unit is arranged on to the fix bar other end for being cased with sleeve pipe again, and is fixed by flat head bolt, curtain wall unit can be caused to be located in unified plane, installation effectiveness is high, by rubber washer, effectively curtain wall unit can be fixed, prevent that curtain wall unit is caused to damage.
Description
Technical field
The utility model belongs to construction engineering technical field, and in particular to a kind of curtain wall construction device for building.
Background technology
Curtain wall is the exterior wall enclosure of building, not load-bearing, is hung up as curtain, therefore also known as " curtain wall ", it is modern
The Light Wall with decorative effect that large-scale and skyscraper is commonly used.It is made up of panel and support system, can be relative
Agent structure has certain displacement ability or itself has certain deformability, do not undertake the building external shield of agent structure effect used
Structure or decorative structure.Curtain wall unit is typically directly fixed on keel, caused in raw work progress by existing curtain wall
When curtain wall is installed, plane difference be present between curtain wall unit, influence attractive in appearance and construction effect.
Utility model content
The purpose of this utility model is to provide a kind of curtain wall construction device for building, to solve to carry in above-mentioned background technology
The problem of going out.
To achieve the above object, the utility model provides following technical scheme:A kind of curtain wall construction device for building, including
Keel and fixation kit, the bottom of the keel are weldingly fixed on the middle part of fixed plate in advance, and the both sides of the fixed plate pass through
Expansion bolt is fixed on the surface of wall, and the top of the keel is fixedly connected with installing plate, the peace by hexagon socket head cap screw
Loading board is provided with mounting hole, and fixation kit is fixed with the mounting hole, curtain wall unit is fixedly connected with the fixation kit.
Preferably, the mounting hole is symmetrical along the both sides of installing plate, the top of the hexagon socket head cap screw and installing plate
Surface flush.
Preferably, the lower surface of the installing plate is provided with groove, and groove is connected to the top of keel.
Preferably, the fixation kit includes fix bar, and the medial extremity of the fix bar passes through mounting hole, the fix bar
Outboard end inside be threadedly coupled with flat head bolt.
Preferably, nut has been connected through a screw thread in the fix bar, the nut offsets with the both sides of installing plate respectively
Tightly.
Preferably, the outboard end of the fix bar passes through curtain wall unit, and the fix bar is socketed with curtain wall unit joint
There is sleeve pipe, rubber washer is also socketed with the fix bar, the rubber washer pushes against with the both sides of curtain wall unit respectively.
Technique effect of the present utility model and advantage:The curtain wall construction device for building, by using expansion bolt in advance
The fixed plate for being fixed with keel is fixed on to the surface of wall, afterwards, installing plate is fixed on keel by hexagon socket head cap screw,
The fix bar on fixation kit is fixed in mounting hole by nut afterwards, the position of the nut by adjusting through hole both sides,
The extension elongation of the other end can be adjusted, then curtain wall unit is arranged on to the fix bar other end for being cased with sleeve pipe, and passes through tack
Bolt is fixed, and by rubber washer, effectively curtain wall unit can be fixed, and prevents that curtain wall unit is caused to damage
It is bad.
Brief description of the drawings
Fig. 1 is positive structure schematic of the present utility model;
Fig. 2 is side structure schematic diagram of the present utility model;
Fig. 3 is overlooking the structure diagram of the present utility model;
Fig. 4 is fixation kit structural representation of the present utility model.
In figure:1 hexagon socket head cap screw, 2 keel, 3 fixed plates, 4 expansion bolts, 5 mounting holes, 6 installing plates, 7 walls, 8 are fixed
Component, 801 fix bars, 802 nuts, 803 rubber washers, 804 flat head bolts, 805 sleeve pipes, 9 curtain wall units.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out
Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment obtained, belong to the scope of the utility model protection.
The utility model provides a kind of curtain wall construction device for building as Figure 1-4, including keel 2 and fixed group
Part 8, the bottom of the keel 2 are weldingly fixed on the middle part of fixed plate 3 in advance, and the both sides of the fixed plate 3 pass through expansion bolt 4
The surface of wall 7 is fixed on, the top of the keel 2 is fixedly connected with installing plate 6, the installing plate 6 by hexagon socket head cap screw 1
Mounting hole 5 is provided with, fixation kit 8 is fixed with the mounting hole 5, curtain wall unit is fixedly connected with the fixation kit 8
9。
Further, both sides of the mounting hole 5 along installing plate 6 are symmetrical, the top of the hexagon socket head cap screw 1 and peace
The surface of loading board 6 flushes, and prevents hexagon socket head cap screw 1 from causing to damage to curtain wall unit 9.
Further, the lower surface of the installing plate 6 is provided with groove, and groove is connected to the top of keel 2, improves installation
When positioning precision, improve installation effectiveness.
Further, the fixation kit 8 includes fix bar 801, and the medial extremity of the fix bar 801 passes through mounting hole 5,
It is threadedly coupled inside the outboard end of the fix bar 801 with flat head bolt 804.
Further, be connected through a screw thread nut 802 in the fix bar 801, the nut 802 respectively with installing plate
6 both sides offset, and can determine the distance between curtain wall unit 9 and keel 2 by the position of adjusting nut 802, be advantageous to
Curtain wall unit 9 keeps smooth when installing, and improves installation quality.
Further, the outboard end of the fix bar 801 passes through curtain wall unit 9, the fix bar 801 and curtain wall unit 9
Joint is socketed with sleeve pipe 805, is also socketed with rubber washer 803 in the fix bar 801, the rubber washer 803 respectively with
The both sides of curtain wall unit 9 push against, and by rubber washer 803, effectively curtain wall unit 9 can be fixed, prevented to curtain wall
Unit 9 causes to damage.
Specifically, in use, the fixed plate 3 for being fixed with keel is fixed on to the table of wall 7 using expansion bolt 4 in advance
Face, afterwards, installing plate 6 is fixed on keel by hexagon socket head cap screw 1, afterwards passed through the fix bar 801 on fixation kit 8
Nut 802 is fixed in mounting hole 6, the position of the nut 802 by adjusting the both sides of through hole 6, can adjust the stretching of the other end
Length, then curtain wall unit 9 is arranged on to the other end of fix bar 801 for being cased with sleeve pipe 805, and consolidated by flat head bolt 804
It is fixed, by rubber washer 803, effectively curtain wall unit 9 can be fixed, prevent that curtain wall unit 9 is caused to damage.
Finally it should be noted that:Preferred embodiment of the present utility model is the foregoing is only, is not limited to this
Utility model, although the utility model is described in detail with reference to the foregoing embodiments, for those skilled in the art
For, it can still modify to the technical scheme described in foregoing embodiments, or to which part technical characteristic
Progress equivalent substitution, all within the spirit and principles of the utility model, any modification, equivalent substitution and improvements made etc.,
It should be included within the scope of protection of the utility model.
Claims (6)
1. a kind of curtain wall construction device for building, including keel(2)And fixation kit(8), it is characterised in that:The keel(2)
Bottom be weldingly fixed on fixed plate in advance(3)Middle part, the fixed plate(3)Both sides pass through expansion bolt(4)It is fixed on
Wall(7)Surface, the keel(2)Top pass through hexagon socket head cap screw(1)It is fixedly connected with installing plate(6), the installation
Plate(6)It is provided with mounting hole(5), the mounting hole(5)Inside it is fixed with fixation kit(8), the fixation kit(8)Upper fixation is even
It is connected to curtain wall unit(9).
A kind of 2. curtain wall construction device for building according to claim 1, it is characterised in that:The mounting hole(5)Along peace
Loading board(6)Both sides it is symmetrical, the hexagon socket head cap screw(1)Top and installing plate(6)Surface flush.
A kind of 3. curtain wall construction device for building according to claim 1, it is characterised in that:The installing plate(6)Under
Surface is provided with groove, and groove is connected to keel(2)Top.
A kind of 4. curtain wall construction device for building according to claim 1, it is characterised in that:The fixation kit(8)Bag
Include fix bar(801), the fix bar(801)Medial extremity pass through mounting hole(5), the fix bar(801)Outboard end in
Portion and flat head bolt(804)Threaded connection.
A kind of 5. curtain wall construction device for building according to claim 4, it is characterised in that:The fix bar(801)On
It has been connected through a screw thread nut(802), the nut(802)Respectively with installing plate(6)Both sides offset.
A kind of 6. curtain wall construction device for building according to claim 4, it is characterised in that:The fix bar(801)'s
Outboard end passes through curtain wall unit(9), the fix bar(801)With curtain wall unit(9)Joint is socketed with sleeve pipe(805), it is described
Fix bar(801)On be also socketed with rubber washer(803), the rubber washer(803)Respectively with curtain wall unit(9)Both sides support
Tightly.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720780592.2U CN206903018U (en) | 2017-06-30 | 2017-06-30 | A kind of curtain wall construction device for building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720780592.2U CN206903018U (en) | 2017-06-30 | 2017-06-30 | A kind of curtain wall construction device for building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206903018U true CN206903018U (en) | 2018-01-19 |
Family
ID=61292427
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720780592.2U Expired - Fee Related CN206903018U (en) | 2017-06-30 | 2017-06-30 | A kind of curtain wall construction device for building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206903018U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113775087A (en) * | 2021-09-07 | 2021-12-10 | 苏州金螳螂幕墙有限公司 | Zipper argil plate curtain wall and construction method thereof |
CN114396130A (en) * | 2021-12-22 | 2022-04-26 | 晨达建设集团有限公司 | Curtain wall for building engineering design and construction method |
CN114704010A (en) * | 2022-05-13 | 2022-07-05 | 山东盛邦实业集团有限公司 | Building curtain wall mounting structure and building curtain wall mounting method |
-
2017
- 2017-06-30 CN CN201720780592.2U patent/CN206903018U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113775087A (en) * | 2021-09-07 | 2021-12-10 | 苏州金螳螂幕墙有限公司 | Zipper argil plate curtain wall and construction method thereof |
CN114396130A (en) * | 2021-12-22 | 2022-04-26 | 晨达建设集团有限公司 | Curtain wall for building engineering design and construction method |
CN114704010A (en) * | 2022-05-13 | 2022-07-05 | 山东盛邦实业集团有限公司 | Building curtain wall mounting structure and building curtain wall mounting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206903018U (en) | A kind of curtain wall construction device for building | |
CN208870242U (en) | A kind of aluminum facade mounting structure | |
CN209509277U (en) | A kind of adjustable curtain-wall adapter | |
CN204691158U (en) | Decorative panel Components installation syndeton | |
CN104018605A (en) | Argil curtain wall and construction method thereof | |
CN206956989U (en) | A kind of building curtain wall of installation easy to disassemble | |
CN108643420A (en) | A kind of aluminum facade mounting structure | |
CN204781688U (en) | Convenient abluent balcony building balustrade | |
CN210369480U (en) | Balcony curtain wall | |
CN211007615U (en) | Scaffold groove type shape fixing device | |
CN203729587U (en) | Horizontal tie fixing device of high-low spanned side die of building structure | |
CN203769327U (en) | Tower concrete pump pipe fixing device | |
CN209637050U (en) | A kind of building curtain wall mounting and fixing bracket | |
CN207568015U (en) | A kind of high intensity curtain wall support structure for building | |
CN207086976U (en) | A kind of architectural engineering drilling bracket | |
CN218580958U (en) | Building wall curtain wall mounting structure | |
CN209535822U (en) | Suspension device is used in a kind of transhipment of cement backplate | |
CN209145111U (en) | A kind of curtain wall construction device for building with fixed effect | |
CN214590292U (en) | Angle steel stand bracket sectional fixture | |
CN209945329U (en) | Special quick mounting base of observation device on tower | |
CN211850772U (en) | Building engineering external scaffolding is wall spare even | |
CN210067160U (en) | Connection supporting device for foundation building curtain wall | |
CN205077662U (en) | But adjusting device below stone material and porcelain plate curtain plate | |
CN201459970U (en) | Bracing cable clamp | |
CN205172036U (en) | Formwork support equipment for building engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: No. 188, Jinji Lake Road, Suqian economic and Technological Development Zone, Jiangsu Province, Jiangsu Patentee after: Suqian Mingyuan Construction Co., Ltd. Address before: No. 188, Jinji Lake Road, Suqian economic and Technological Development Zone, Jiangsu Province, Jiangsu Patentee before: Suqian Mingyuan construction and Installation Engineering Co., Ltd. |
|
CP01 | Change in the name or title of a patent holder | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180119 Termination date: 20190630 |
|
CF01 | Termination of patent right due to non-payment of annual fee |