CN113775087A - Zipper argil plate curtain wall and construction method thereof - Google Patents

Zipper argil plate curtain wall and construction method thereof Download PDF

Info

Publication number
CN113775087A
CN113775087A CN202111041689.9A CN202111041689A CN113775087A CN 113775087 A CN113775087 A CN 113775087A CN 202111041689 A CN202111041689 A CN 202111041689A CN 113775087 A CN113775087 A CN 113775087A
Authority
CN
China
Prior art keywords
mounting
mounting sleeve
holes
curtain wall
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111041689.9A
Other languages
Chinese (zh)
Other versions
CN113775087B (en
Inventor
刘振华
曹鑫鑫
吴浩
钱新宇
姜新为
包兴华
李楠
周刚
李旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Gold Mantis Curtain Wall Co Ltd
Original Assignee
Suzhou Gold Mantis Curtain Wall Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Gold Mantis Curtain Wall Co Ltd filed Critical Suzhou Gold Mantis Curtain Wall Co Ltd
Priority to CN202111041689.9A priority Critical patent/CN113775087B/en
Publication of CN113775087A publication Critical patent/CN113775087A/en
Application granted granted Critical
Publication of CN113775087B publication Critical patent/CN113775087B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/90Passive houses; Double facade technology

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The invention discloses a zipper argil plate curtain wall which comprises a first installation sleeve and a second installation sleeve, wherein installation cavities are respectively formed in the first installation sleeve and the second installation sleeve, one side of each of the first installation sleeve and the second installation sleeve is respectively provided with a connecting cross rod, the outer side of each connecting cross rod is provided with a transverse loop rod, an adjusting structure is arranged in each transverse loop rod, the outer side walls of the first installation sleeve and the second installation sleeve are provided with a plurality of groups of through holes, the through holes are connected with a reinforcing structure, the invention also discloses a construction method of the zipper argil plate curtain wall, and S1, two groups of first installation sleeves, two groups of second installation sleeves and transverse loop rods, four groups of connecting cross rods, a plurality of groups of connecting angle seats, vertical supporting rods and transverse supporting rods are prefabricated, and the parts are transported to a site to be constructed and assembled. Has the advantages that: the function of better realization prefab automatic adjustment is convenient to the processing under the different conditions to have the simple installation, resources are saved's function.

Description

Zipper argil plate curtain wall and construction method thereof
Technical Field
The invention relates to the technical field of architectural decoration engineering, in particular to a zipper pottery clay plate curtain wall and a construction method thereof.
Background
As a new building exterior curtain wall, the ceramic plate curtain wall has the advantages of acid and alkali resistance, frost resistance, fire resistance, flame retardance, simple and convenient maintenance, energy conservation, environmental protection and the like, and is applied to a plurality of building projects, particularly high-grade office buildings, large museums, exhibition halls, subway station waiting halls and the like.
Through retrieval, the Chinese authorization number CN107386505B discloses a construction method of a frame-shaped pottery clay plate curtain wall, which mainly comprises the following steps: the construction method comprises the following steps of construction preparation, arrangement of built-in bolts and built-in base plates, installation and construction of stand columns, installation and construction of cross beams, installation of prefabricated hanging seats, installation of prefabricated hanging pieces and clay plates, seam treatment of the clay plates and construction of heat insulation layers, wherein in the prior art, although the joint connection strength and the positioning accuracy of clay plate curtain walls can be improved, the following problems can occur in prefabricated parts:
1. the actual field is not matched with the prefabricated part, and the theoretical design height cannot be adjusted according to the actual field;
2. the processing steps are more, and are comparatively loaded down with trivial details when the actual installation to can't adjust the intensity of curtain to different design environment.
Based on the utilization, the invention designs the zipper argil plate curtain wall and the construction method thereof.
Disclosure of Invention
The invention aims to solve the problems in the prior art and provides a zipper pottery clay plate curtain wall and a construction method thereof.
The utility model provides a zip argil board curtain, includes first installation cover and second installation cover, set up an installation cavity in first installation cover and the second installation cover respectively, the second installation cover is close to the junction with first installation cover and cooperatees with the installation cavity in the first installation cover, one side of first installation cover and second installation cover is provided with a connection horizontal pole respectively, every run through in the connection horizontal pole 4 and seted up the passageway, every the outside of connecting the horizontal pole all is provided with a horizontal loop bar, be provided with the adjustment structure in the horizontal loop bar, the lateral wall of first installation cover and second installation cover is provided with the multiunit through-hole, the through-hole is connected with reinforced structure.
In foretell an argil board curtain of zip lock, the adjustment structure is located relative one side including setting up the locating hole in horizontal loop bar both sides the common fixedly connected with of locating hole erects branch, the one end fixedly connected with locating piece that the connecting cross rod is located horizontal loop bar, the size of a dimension of locating piece cooperatees with the internal diameter of horizontal loop bar, seted up in the locating piece with locating hole complex screw hole, the sealed inner wall that runs through corresponding installation cover of one end of connecting the cross rod and keeping away from the locating piece, the one end fixedly connected with fixed plate of connecting the cross rod in corresponding the installation cover, first installation cover and second installation cover are close to the part that corresponds the fixed plate and are provided with the mounting hole jointly.
In foretell an argil board curtain of zip, reinforced structure includes a plurality of connection angle seats of being connected the setting with the through-hole, first installation cover and second installation cover all set up to type of calligraphy structure, the multiunit the through-hole divide into two sets ofly and two sets of through-hole settings are at the upside and the symmetry setting of type of calligraphy part, lie in with one side the through-hole equidistance sets up, lies in one side through-hole in the outside second installation cover of first installation cover is provided with the sealing plug jointly, the sealing plug sets up in the one side of keeping away from the connection horizontal pole, and is a plurality of the connection angle seat sets up the one side of keeping away from the sealing plug at the through-hole, every two adjacent through-holes are connected to the connection angle seat, the opposite side fixedly connected with cross-strut pole of connection angle seat, and is a plurality of the other end of cross-strut and the connection angle seat fixed connection that the opposite side set up.
In the zipper argil plate curtain wall, a communication port is formed in the bottom of the concave shape of the first installation sleeve, the communication port is communicated with the installation cavity, a first installation plug is arranged on the part, located at the communication port, of the installation cavity in the first installation sleeve in a sliding mode, a second installation plug is arranged in the same position of the installation cavity in the second installation sleeve in a sliding mode, compression springs are fixedly connected to the first installation plug and the second installation plug, fixed ends of the compression springs are fixedly connected with the side wall of the installation cavity, and the outside injects reinforcing liquid into the installation cavity through the communication port.
In the zipper clay plate curtain wall, the through holes of the first mounting sleeve and the second mounting sleeve which are positioned on the same side are connected with the reinforcing bolts in a matching mode, the positioning block is internally provided with the communicating channel in a penetrating mode, and the communicating port is hermetically provided with the horizontal pipe which is horizontally arranged.
A construction method of a zipper argil plate curtain wall comprises the following steps:
s1, prefabricating two groups of first installation sleeves, second installation sleeves and transverse sleeve rods, four groups of connecting transverse rods, and a plurality of groups of connecting angle seats, vertical supporting rods and transverse supporting rods, and transporting the parts to a site to be constructed for assembly;
and S2, performing secondary detection and design on the spot, checking the length and height of the curtain wall, after obtaining a result, stretching the first mounting sleeve and the second mounting sleeve to the height to be processed, fixing a sealing plug and a reinforcing bolt by a plurality of through holes on the sides of the two groups of mounting sleeves far away from each other, moving the two connecting cross rods and the transverse sleeve rods to the length to be processed, and fixing the two groups of positioning holes far away from one side of the connecting cross rods through threaded holes on the positioning blocks.
In the construction method of the zipper argil plate curtain wall, the plurality of transverse supporting rods and the plurality of vertical supporting rods are respectively fixed with one connecting angle seat, the connecting angle seats are respectively connected and fixed with the through holes and the positioning holes on the opposite side, and the fixing plate is connected and fixed with the mounting sleeve through the mounting holes.
In the construction method of the zipper argil plate curtain wall, the reinforcement liquid is injected through the communication port on one side to improve the stability of the prefabricated part, then the plurality of argil plates are fixed on the prefabricated support, and the heat insulation layer is filled between the prefabricated support and the argil plates, so that the integral structure of the curtain wall is realized, the reinforcement liquid is extracted from the communication port on the other side through the transverse pipe, and the curtain wall can be repeatedly used in different use environments, so that resources are saved.
Compared with the prior art, the invention has the advantages that:
1: through the first installation cover of the multiunit of design and second installation cover as main cradling piece, realize the adjustment to the prefab height, through the adjustment of connecting the slip realization between horizontal pole and the horizontal loop bar to prefab length, conveniently finely tune the design at the scene like this, better realization is to the processing of argil board curtain.
2: the first installation cover of multiunit, second installation cover, connection horizontal pole and horizontal loop bar of design all can conveniently be dismantled to convenient transportation has reduced transportation and processing cost like this, simultaneously because above-mentioned component is hollow state under the transport condition, has consequently also reduced the degree of difficulty and the load of manual installation.
3: through the control to the kind and the volume of consolidating liquid for both can realize processing the effect that detects, can adjust the intensity of prefab according to the actual atress of curtain and heat preservation state again, and after using, can take out some consolidation liquid in right amount and reduce the weight of curtain, realize resources are saved's function.
Drawings
FIG. 1 is a schematic view of a zipper clay panel curtain wall according to the present invention;
FIG. 2 is a schematic view of the exterior of a zipper clay plate curtain wall according to the present invention;
FIG. 3 is an enlarged schematic view of portion A of a zipper clay plate curtain wall in accordance with the present invention;
FIG. 4 is an enlarged schematic view of section B of a zipper clay plate curtain wall in accordance with the present invention;
fig. 5 is a schematic structural view of a connecting angle seat and a transverse strut in a zipper clay plate curtain wall provided by the invention.
In the figure: the mounting structure comprises a first mounting sleeve 1, a second mounting sleeve 2, a mounting cavity 3, a connecting cross rod 4, a transverse sleeve rod 5, a through hole 6, a positioning hole 7, a vertical supporting rod 8, a positioning block 9, a threaded hole 10, a fixing plate 11, a mounting hole 12, a sealing plug 13, a connecting angle seat 14, a transverse supporting rod 15, a communication port 16, a first mounting plug 171, a second mounting plug 172, a compression spring 18, a reinforcing bolt 19, a communication channel 20 and a transverse pipe 21.
Detailed Description
Referring to fig. 1-3, a zipper clay plate curtain wall comprises a first installation sleeve 1 and a second installation sleeve 2, wherein an installation cavity 3 is respectively formed in the first installation sleeve 1 and the second installation sleeve 2, the second installation sleeve 2 is close to a joint with the first installation sleeve 1 and is matched with the installation cavity 3 in the first installation sleeve 1, one side of each of the first installation sleeve 1 and the second installation sleeve 2 is respectively provided with a connecting cross rod 4, a channel is formed in each connecting cross rod 4 in a penetrating mode, the outer side of each connecting cross rod 4 is provided with a transverse loop bar 5, an adjusting structure is arranged in each transverse loop bar 5, the outer side walls of the first installation sleeve 1 and the second installation sleeve 2 are provided with a plurality of groups of through holes 6, and the through holes 6 are connected with a reinforcing structure.
Referring to fig. 2-5, the adjusting structure includes positioning holes 7 disposed on two sides of a transverse loop bar 5, vertical support bars 8 fixedly connected to the positioning holes 7 on opposite sides, a positioning block 9 fixedly connected to one end of a connecting cross bar 4 disposed in the transverse loop bar 5, the size of the positioning block 9 matching with the inner diameter of the transverse loop bar 5, a threaded hole 10 formed in the positioning block 9 and matching with the positioning hole 7, the transverse loop bar 5 and the connecting cross bar 4 are fixed to each other through the threaded hole 10 and the positioning hole 7, the fixing portion is disposed on the side of the two transverse loop bars 5 away from each other, the side close to each other increases the connection strength of the prefabricated member through a plurality of vertical support bars 8, thus achieving the positioning effect and increasing the strength of the prefabricated member, the end of the connecting cross bar 4 away from the positioning block 9 hermetically penetrates through the inner wall of the corresponding mounting sleeve, and the end of the connecting cross bar 4 in the corresponding mounting sleeve is fixedly connected with a fixing plate 11, the parts of the first mounting sleeve 1 and the second mounting sleeve 2 close to the corresponding fixing plate 11 are provided with mounting holes 12 together, the fixing plate 11 and the mounting sleeves are fixed through the mounting holes 12, so that the length of the prefabricated member can be adjusted and increased only by moving the transverse loop bar 5, and during transportation, the connecting transverse bar 4 is positioned inside the transverse loop bar 5 and the mounting sleeves, thereby reducing the length of the outside, facilitating transportation and saving transportation space, the reinforcing structure comprises a plurality of connecting angle seats 14 connected with the through holes 6, the first mounting sleeve 1 and the second mounting sleeve 2 are both arranged into a concave structure, a plurality of groups of through holes 6 are divided into two groups, two groups of through holes 6 are arranged at the upper side of the concave part and are symmetrically arranged, the through holes 6 at the same side are arranged at equal intervals, the through hole 6 at one side in the second mounting sleeve 2 positioned outside the first mounting sleeve 1 is provided with a sealing plug 13 together, the sealing plug 13 is arranged at one side far away from the connecting transverse bar 4, sealing plug 13 plays the effect of sealed second installation cover 2, a plurality of connection angle seat 14 set up the one side of keeping away from sealing plug 13 at through-hole 6, two adjacent through-holes 6 are connected to every connection angle seat 14, the opposite side fixedly connected with horizontal pole branch 15 of connection angle seat 14, the other end of a plurality of horizontal pole branches 15 and the connection angle seat 14 fixed connection of opposite side setting, the joint strength of prefab is further strengthened through a plurality of horizontal pole branches 15, wherein be provided with the axle sleeve in the connection angle seat 14, when actual installation, also can directly insert horizontal pole branch 15 or perpendicular pole 8 and establish the requirement that satisfies joint strength to the axle sleeve in, such benefit lies in, need not to customize horizontal pole branch 15 and perpendicular pole 8, because the axle sleeve can make horizontal pole branch 15 and perpendicular pole 8 take place the small-amplitude and move.
The bottom of the first mounting sleeve 1 in the shape of the Chinese character 'ao' is provided with a communication port 16, the communication port 16 is communicated with the mounting cavity 3, the communication port 16 is used for inputting reinforcing liquid, when the reinforcing liquid is cement or non-Newtonian liquid with high viscosity, the first mounting sleeve 1 and the second mounting sleeve 2 are integrally fixed after solidification, the reinforcing liquid filled with the reinforcing liquid stabilizes the components, so that the prefabricated member has great strength, the mounting and connection of the ceramic plate are convenient, when the reinforcing liquid is inert liquid with only small viscosity, the reinforcing liquid only provides the strength function of gravity, the prefabricated member after mounting only provides small strength, but the reinforcing liquid has recoverability after use, and partial or all reinforcing liquid can be extracted according to the mounting occasion of the curtain wall for multiple use;
the part of the mounting cavity 3 in the first mounting sleeve 1, which is positioned at the communication port 16, is provided with a first mounting plug 171 in a sliding manner, the same position of the mounting cavity 3 in the second mounting sleeve 2 is provided with a second mounting plug 172 in a sliding manner, the first mounting plug 171 and the second mounting plug 172 are both fixedly connected with a compression spring 18, and the fixed end of the compression spring 18 is fixedly connected with the side wall of the mounting cavity 3, wherein the first mounting plug 171 and the second mounting plug 172 both seal the channel in the connecting cross rod 4 in an initial state, so that the phenomenon that the internal corrosion of the connecting cross rod 4 is caused by the external air before mounting and the strength of the connecting cross rod is influenced is avoided, when the connecting cross rod 4 is pulled to the fixed plate 11 to be attached to the inner wall of the mounting cavity 3 in use, the mounting plug opens the channel in the connecting cross rod, so that the reinforcing liquid can flow in, the use is satisfied during transportation and processing, the external liquid is injected into the mounting cavity 3 through the communication port 16, the through-hole cooperation that lies in first installation cover 1 and second installation cover 2 with one side is connected with reinforcing bolt 19, runs through in the locating piece 9 and has seted up intercommunication passageway 20, and the sealed violently pipe 21 that is provided with the level setting of intercommunication mouth 16 will consolidate the liquid input or take out through violently pipe 21, and after the curtain formed, the outer tip part of violently pipe 21 will be in the lateral wall of curtain, will violently take out in the pipe 21 part liquid this moment after will violently pipe 21 seals and can realize consolidating the work of accomplishing.
A construction method of a zipper clay plate curtain wall comprises the following steps of S1, prefabricating two groups of first installation sleeves 1, second installation sleeves 2 and transverse sleeve rods 5, four groups of connecting transverse rods 4, a plurality of groups of connecting angle seats 14, vertical supporting rods 8 and transverse supporting rods 15, and transporting the parts to a site to be constructed for assembly; and S2, performing secondary detection and design on the spot, checking the length and height of the curtain wall, after obtaining results, stretching the first mounting sleeve 1 and the second mounting sleeve 2 to the height to be processed, fixing the sealing plugs 13 and the reinforcing bolts 19 by the through holes 6 on the sides of the two groups of mounting sleeves far away from each other, moving the two connecting cross rods 4 and the transverse sleeve rods 5 to the length to be processed, and fixing the two groups of positioning holes 9 on the sides far away from the connecting cross rods 4 through the threaded holes 10 on the positioning blocks 7.
A plurality of transverse supporting rods 15 and a plurality of vertical supporting rods 8 are respectively fixed with a connecting angle seat 14, the connecting angle seat 14 is respectively connected and fixed with a through hole 6 and a positioning hole 9 on the opposite side, a fixing plate 11 is connected and fixed with a mounting sleeve through a mounting hole 12, reinforcing liquid is injected through a communication port 16 on one side to increase the stability of the prefabricated part, then a plurality of argil plates are fixed on a prefabricated support, and a heat insulation layer is filled between the prefabricated support and the argil plates, so that the integral structure of the curtain wall is realized, the reinforcing liquid is extracted from the communication port 16 on the other side through a transverse pipe 21, the curtain wall is repeatedly used in different use environments, and resources are saved.

Claims (8)

1. A zipper argil plate curtain wall comprises a first mounting sleeve (1) and a second mounting sleeve (2), it is characterized in that the first mounting sleeve (1) and the second mounting sleeve (2) are respectively provided with a mounting cavity (3), the second mounting sleeve (2) is matched with the mounting cavity (3) in the first mounting sleeve (1) near the joint with the first mounting sleeve (1), one side of each of the first mounting sleeve (1) and the second mounting sleeve (2) is provided with a connecting cross rod (4), a channel is arranged in each connecting cross rod (4) in a penetrating way, the outer side of each connecting cross rod (4) is provided with a transverse loop bar (5), be provided with the adjustment structure in horizontal loop bar (5), the lateral wall of first installation cover (1) and second installation cover (2) is provided with multiunit through-hole (6), through-hole (6) are connected with reinforced structure.
2. A zipper clay plate curtain wall as claimed in claim 1, characterized in that the adjustment structure comprises positioning holes (7) arranged on both sides of the transverse loop bar (5), the positioning holes (7) on opposite sides being jointly and fixedly connected with vertical support bars (8), one end of the connecting cross rod (4) positioned in the cross loop bar (5) is fixedly connected with a positioning block (9), the size of the positioning block (9) is matched with the inner diameter of the transverse loop bar (5), a threaded hole (10) matched with the positioning hole (7) is arranged in the positioning block (9), one end of the connecting cross rod (4) far away from the positioning block (9) penetrates through the inner wall of the corresponding mounting sleeve in a sealing way, one end of the connecting cross rod (4) in the corresponding mounting sleeve is fixedly connected with a fixing plate (11), the parts of the first mounting sleeve (1) and the second mounting sleeve (2) close to the corresponding fixing plates (11) are provided with mounting holes (12) together.
3. A zipper clay plate curtain wall as claimed in claim 2, wherein the reinforcing structure comprises a plurality of connecting angle seats (14) connected with the through holes (6), the first mounting sleeve (1) and the second mounting sleeve (2) are arranged in a concave structure, the plurality of groups of through holes (6) are divided into two groups, two groups of through holes (6) are arranged on the upper side of the concave part and symmetrically arranged, the through holes (6) on the same side are arranged at equal intervals, one side through hole (6) in the second mounting sleeve (2) outside the first mounting sleeve (1) is provided with a sealing plug (13) together, the sealing plug (13) is arranged on the side far away from the connecting cross bar (4), the plurality of connecting angle seats (14) are arranged on the side far away from the sealing plug (13) of the through hole (6), each connecting angle seat (14) connects two adjacent through holes (6), the other side of connecting angle seat (14) fixedly connected with cross struts (15), a plurality of the other end and the connecting angle seat (14) fixed connection that the opposite side set up of cross struts (15).
4. The zipper clay plate curtain wall as claimed in claim 3, wherein a communication port (16) is formed in the bottom of the first mounting sleeve (1) in the shape of a Chinese character 'ao', the communication port (16) is communicated with a mounting cavity (3), a first mounting plug (171) is slidably arranged on a portion, located at the communication port (16), of the mounting cavity (3) in the first mounting sleeve (1), a second mounting plug (172) is slidably arranged at the same position of the mounting cavity (3) in the second mounting sleeve (2), the first mounting plug (171) and the second mounting plug (172) are both fixedly connected with a compression spring (18), the fixed end of the compression spring (18) is both fixedly connected with the side wall of the mounting cavity (3), and a reinforcing liquid is injected into the mounting cavity (3) through the communication port (16) from the outside.
5. The zipper clay plate curtain wall as claimed in claim 4, wherein the through holes of the first mounting sleeve (1) and the second mounting sleeve (2) on the same side are connected with reinforcing bolts (19) in a matching manner, a communicating channel (20) penetrates through the positioning block (9), and the communicating port (16) is hermetically provided with a horizontal pipe (21) which is horizontally arranged.
6. A construction method of a zipper argil plate curtain wall comprises the following steps,
s1, prefabricating two groups of first installation sleeves (1), second installation sleeves (2) and transverse sleeve rods (5), four groups of connecting transverse rods (4), a plurality of groups of connecting angle seats (14), vertical supporting rods (8) and transverse supporting rods (15), and transporting the parts to a site to be constructed for assembly;
and S2, performing secondary detection and design on the spot, checking the length and height of the curtain wall, stretching the first mounting sleeve (1) and the second mounting sleeve (2) to the height to be processed after obtaining results, fixing a sealing plug (13) and a reinforcing bolt (19) by a plurality of through holes (6) on one side, far away from each other, of the two groups of mounting sleeves respectively, moving the two connecting cross rods (4) and the cross sleeve rod (5) to the length to be processed, and fixing the two groups of positioning holes (9) on one side, far away from the connecting cross rod (4), through threaded holes (10) in a positioning block (7).
7. A construction method of a zipper clay plate curtain wall as claimed in claim 6, wherein a plurality of horizontal supporting rods (15) and a plurality of vertical supporting rods (8) are respectively fixed with a connecting angle seat (14), the connecting angle seats (14) are respectively fixed with the through holes (6) and the positioning holes (9) at the opposite side, and the fixing plate (11) is connected and fixed with the mounting sleeve through the mounting holes (12).
8. The construction method of the zipper clay plate curtain wall as claimed in claim 7, wherein the reinforcement liquid is injected through the communication port (16) at one side to increase the stability of the prefabricated member, then a plurality of clay plates are fixed on the prefabricated bracket, and the heat insulation layer is filled between the prefabricated bracket and the clay plates, thereby realizing the integral structure of the curtain wall, and the reinforcement liquid is extracted from the communication port (16) at the other side through the transverse pipe (21) to be reused under different use environments, thereby saving resources.
CN202111041689.9A 2021-09-07 2021-09-07 Zipper argil plate curtain wall and construction method thereof Active CN113775087B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111041689.9A CN113775087B (en) 2021-09-07 2021-09-07 Zipper argil plate curtain wall and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111041689.9A CN113775087B (en) 2021-09-07 2021-09-07 Zipper argil plate curtain wall and construction method thereof

Publications (2)

Publication Number Publication Date
CN113775087A true CN113775087A (en) 2021-12-10
CN113775087B CN113775087B (en) 2022-07-08

Family

ID=78841453

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111041689.9A Active CN113775087B (en) 2021-09-07 2021-09-07 Zipper argil plate curtain wall and construction method thereof

Country Status (1)

Country Link
CN (1) CN113775087B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001311252A (en) * 2000-04-28 2001-11-09 Sankyo Alum Ind Co Ltd Column apparatus equipped with panel
CN206903018U (en) * 2017-06-30 2018-01-19 宿迁市明远建筑安装工程有限公司 A kind of curtain wall construction device for building
CN213774028U (en) * 2020-09-24 2021-07-23 深圳市瑞玮工程有限公司 Outdoor curtain wall keel mounting structure
CN113152749A (en) * 2021-04-22 2021-07-23 山西建筑工程集团有限公司 Hang argil board curtain wall construction futilely
CN214062056U (en) * 2020-10-29 2021-08-27 中建不二幕墙装饰有限公司 Keel component for aluminum plate curtain wall plate during installation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001311252A (en) * 2000-04-28 2001-11-09 Sankyo Alum Ind Co Ltd Column apparatus equipped with panel
CN206903018U (en) * 2017-06-30 2018-01-19 宿迁市明远建筑安装工程有限公司 A kind of curtain wall construction device for building
CN213774028U (en) * 2020-09-24 2021-07-23 深圳市瑞玮工程有限公司 Outdoor curtain wall keel mounting structure
CN214062056U (en) * 2020-10-29 2021-08-27 中建不二幕墙装饰有限公司 Keel component for aluminum plate curtain wall plate during installation
CN113152749A (en) * 2021-04-22 2021-07-23 山西建筑工程集团有限公司 Hang argil board curtain wall construction futilely

Also Published As

Publication number Publication date
CN113775087B (en) 2022-07-08

Similar Documents

Publication Publication Date Title
CN104563384B (en) A kind of decoration integrated large scale prefabricated out-hung panel of structural thermal insulation and preparation method thereof
US20100024323A1 (en) Energy Saving House
US20140338283A1 (en) House constructed from finished product components and constructing method thereof
WO2020034173A1 (en) Building structure module and preparation method thereof
CN107989238A (en) A kind of cast-in-place sandwiched heat-preservation shear wall structure, assembled architecture and engineering method
CN113775087B (en) Zipper argil plate curtain wall and construction method thereof
CN107119826B (en) Autoclaved aerated concrete plate filling wall and column connecting node structure and construction method thereof
CN103031892B (en) Steel truss brace and manufacturing method for steel truss platform
CN204781575U (en) Structure keeps warm and decorates outer wall hanging plate of large -scale prefabrication of integration
CN205742601U (en) Foam concrete wallboard
CN212450188U (en) Fast-assembling well frame construction
CN211286151U (en) Peripheral revetment body of assembled building
CN105804273A (en) Foam concrete wall plate
CN207597652U (en) A kind of cast-in-place sandwiched heat-preservation shear wall structure and assembled architecture
CN110847435A (en) Peripheral revetment body of assembled building
CN216108953U (en) Integrated assembled steel construction building
CN220184735U (en) Supporting structure based on assembled floor
CN111827612A (en) Energy-saving building insulation wallboard's fixed fossil fragments
CN205857581U (en) A kind of self-heat conserving decoration integrated Multi-function light concrete composite plates and curtain wall
CN213626285U (en) Assembled building component
CN219118544U (en) Light dense rib sandwich groove type wallboard
CN205047100U (en) Slope honeycomb bearing exit
CN107611909A (en) A kind of pre-buried well with cable guide structure
CN115110676B (en) Hanging frame supporting glass curtain wall system uniformly stressed and construction method thereof
CN211622191U (en) Wind-proof curtain wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant