CN206887895U - A kind of overflow-type mud-rock flow blocking dam group - Google Patents

A kind of overflow-type mud-rock flow blocking dam group Download PDF

Info

Publication number
CN206887895U
CN206887895U CN201720562724.4U CN201720562724U CN206887895U CN 206887895 U CN206887895 U CN 206887895U CN 201720562724 U CN201720562724 U CN 201720562724U CN 206887895 U CN206887895 U CN 206887895U
Authority
CN
China
Prior art keywords
aerial drainage
rock flow
dam
overflow
drainage hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720562724.4U
Other languages
Chinese (zh)
Inventor
叶伟林
魏万鸿
孟兴民
宿星
杨涛
刘兴荣
冯乐涛
王得楷
吴玮江
周自强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Geological Natural Disaster Prevention Research Institute Gansu Academy Of Sciences
Lanzhou University
Original Assignee
Geological Natural Disaster Prevention Research Institute Gansu Academy Of Sciences
Lanzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Geological Natural Disaster Prevention Research Institute Gansu Academy Of Sciences, Lanzhou University filed Critical Geological Natural Disaster Prevention Research Institute Gansu Academy Of Sciences
Priority to CN201720562724.4U priority Critical patent/CN206887895U/en
Application granted granted Critical
Publication of CN206887895U publication Critical patent/CN206887895U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a kind of overflow-type mud-rock flow blocking dam group, including overflow-type mud-rock flow blocking dam and the dam group that is made up of some overflow-type mud-rock flow blocking dams;The overflow-type mud-rock flow blocking dam is made up of key dam body, downflow weir, aerial drainage hole, and downflow weir is located above key dam body, and aerial drainage hole is several, is arranged on key dam body bottom, and key dam body is provided with spilled water hole, and spilled water hole is located above aerial drainage hole.The beneficial effects of the utility model are structure safety, desilting convenience, and retaining storage capacity can be used repeatedly, positive effect of preventing and reducing natural disasters.

Description

A kind of overflow-type mud-rock flow blocking dam group
Technical field
The utility model belongs to hazards control technical field, is related to a kind of overflow-type mud-rock flow blocking dam and dam group.
Background technology
At present, the effect of mud-rock flow blocking dam is typically based on blocking, and its purpose predominantly blocks that to carry water husky, changes water delivery, defeated Husky condition, adjust amount of water to be discharged and sedimentary loading, stabling slope and cheuch.When effective storage is become silted up by silt particle full in blocking dam, will lose Go to retain, regulatory function, function of preventing and reducing natural disasters weakens significantly.
After effective storage is become silted up completely by silt particle in blocking dam, a large amount of solid bulk materials are stored in raceway groove, blocking dam is held The Accumulation In Debris-flow pressure received is big, and blocking dam once bursts, and solid bulk materials are concentrated, fully supply, are formed bigger Mud-rock flow, once causing downstream stages blocking dam enlarge-effect step by step, cause calamity ability to greatly reinforce, it is new hidden so as to be formed Suffer from.
Utility model content
The purpose of this utility model is to provide a kind of overflow-type mud-rock flow blocking dam and dam group, and solving in blocking dam has After effect storage capacity is silted completely, retain, the mudstone that effective storage is born after being become silted up completely by silt particle in regulatory function Problem of Failure and blocking dam Flow the problem of deposit pressure is big, and blocking dam easily bursts.
Technical scheme is to include overflow-type mud-rock flow blocking dam and by some overflow-type mudstones used by the utility model Flow the dam group of blocking dam composition;The overflow-type mud-rock flow blocking dam is made up of key dam body, downflow weir, aerial drainage hole, downflow weir position Above key dam body, aerial drainage hole is several, is arranged on key dam body bottom, and key dam body is provided with spilled water hole, and spilled water hole, which is located at, to be let out Flow above hole.
Further, downflow weir and aerial drainage hole conveyance capacity meet the mud-rock flow maximum stream flow for ensureing blocking dam safety.
Further, aerial drainage hole letdown flow, which is less than under the maximum for ensureing downstream guard plot safety, lets out safe traffic.
Further, aerial drainage hole minimum widith can guarantee that maximum stone particle diameter and desilting vehicle and equipment are led in excessively stream in raceway groove Cross.
Further, dam group is made up of multiple overflow-type mud-rock flow blocking dams, and blocking dam and dam group's aggregate storage capacity can effectively block The mud-rock flow maximum once total amount of going out under norm for civil defense.
Further, the ratio of aerial drainage hole minimum widith and maximum stone particle diameter in excessively stream is 1.5-2.0.
The beneficial effects of the utility model are structure safety, desilting convenience, and retaining storage capacity can be used repeatedly.
Brief description of the drawings
Fig. 1 is blocking dam structural representation of the present utility model;
Fig. 2 is blocking dam group horizontal layout schematic diagram of the present utility model.
In figure, 1. key dam bodies, 2. downflow weirs, 3. aerial drainage holes, 4. above-ground routes, 5. spilled water holes, 6.1# reservoir areas storage capacity, 7.2# Reservoir area storage capacity.
Embodiment
The utility model is described in detail with reference to embodiment.
As shown in figure 1, overflow-type mud-rock flow blocking dam is made up of key dam body 1, downflow weir 2, aerial drainage hole 3, key dam body 1 is according to ground Upper thread 4 is built, and downflow weir 2 is located at the top of key dam body 1, and aerial drainage hole 3 is several, is arranged on the bottom of key dam body 1, and downflow weir 2 flows Amount, the flow of aerial drainage hole 3 should meet following condition:
1. downflow weir 2 and the conveyance capacity of aerial drainage hole 3 meet the mud-rock flow maximum stream flow for ensureing blocking dam safety;
QOverflow+∑QLet out≥Qmax
2. the letdown flow of aerial drainage hole 3 should be less than letting out safe traffic under the maximum of guarantee downstream guard plot safety;
∑QLet out≤QS
The minimum widith of aerial drainage hole 3 can guarantee that maximum stone particle diameter and desilting vehicle and equipment pass through in excessively stream in raceway groove;It is excellent Choosing
3. being also provided with spilled water hole 5 on key dam body 1, spilled water hole 5 is located at the top of aerial drainage hole 3.Further strengthen sluicing energy Power.
Q overflow-weir discharge;Q lets out-aerial drainage hole flow;Qmax-mud-rock flow is set up defences flow;Qs-under let out secure flows Amount;D-aerial drainage hole minimum widith;Dmax is maximum stone particle diameter in excessively stream.
Overflow-type mud-rock flow blocking dam group, dam group is formed by multiple overflow-type mud-rock flow blocking dams, dam group's aggregate storage capacity should expire Foot row condition:
Blocking dam and dam group's aggregate storage capacity can effectively block under norm for civil defense the mud-rock flow maximum once total amount of going out;
∑Vi≥Vmax
I is natural number in formula, and Vmax is the debris flow gully maximum once total amount of going out under design frequency.
As shown in Fig. 2 the dam group of two overflow-type mud-rock flow blocking dam compositions, 1# reservoir areas storage capacity 6;2# reservoir areas storage capacity 7.
Blocking dam and dam group arrangement, the parameter such as spacing and dam body length, height of dam can be selected according to raceway groove actual conditions.
When mud-rock flow occurs, mud-rock flow safety upstream blocking dam downflow weir and aerial drainage hole under design frequency, mud-rock flow Total make of ditch maximum, which is all temporarily blocked, is stranded in two blocking dam reservoir areas, and is downstream drained by aerial drainage hole, most Next stage blocking dam reservoir area mud-rock flow under aerial drainage hole only by letting out, and letdown flow is less than downstream guard plot safe traffic, under guarantee Guard plot safety is swum, so as to realize purpose of preventing and reducing natural disasters.
After mud-rock flow terminates, the mud-rock flow overwhelming majority that blocking dam group is temporarily deposited each reservoir area passes through under the aerial drainage hole of bottom Let out, reservoir area siltation solid bulk materials are less.These drifts can lead in the case where later stage flood or small-scale mud-rock flow wash away carrying Cross aerial drainage hole to clear up naturally, so as to empty storage capacity, guarantee blocks that to carry water husky, changes water delivery, Sediment Transport Condition, adjusts amount of water to be discharged and defeated The realization of sand amount function, reaches the long-acting purpose prevented and reduced natural disasters., can be by letting out to part oversize block and trees, high-stem plant Flow the transport of hole manual cleaning.
It should be noted that only when debris flow and landslips are more than downstream guard plot safe traffic, just there is mud in blocking dam Rock glacier is temporarily retained, and when debris flow and landslips are less than downstream guard plot flow, debris flow and landslips all pass through overflow-type blocking dam Let out under the whole safety of bottom aerial drainage hole.
Because aerial drainage hole size is big, handling capacity is strong, and reservoir area is forever deposited, and solid matter is few, and solid bulk materials are to blocking Dam pressure is substantially not present, so as to ensure blocking dam safe operation.
The quantity of blocking dam can be according to the occurrence frequency and uninterrupted reasonable selection of this area's mud-rock flow;Blocking dam dam type Reasonable selection under the conditions of aforementioned dimensions and conveyance capacity, storage capacity etc. can be referred to before stabilization is met.
To sum up, the beneficial effects of the utility model are:Mud-rock flow blocking dam structure of dam type is simple, and it is strong to retain ability, under Vent flow is safe and reliable, and drift is cleared up naturally in storehouse, retains the repeatable utilization of storage capacity, and temporary traffic is unimpeded in raceway groove, is not required to Another to set around dam road, later stage desilting is convenient, the Accumulation In Debris-flow pressure that blocking dam is not subject to substantially, to mud-rock flow raceway groove from Right evolutionary process influences smaller, positive effect of preventing and reducing natural disasters.Overflow-type mud-rock flow flood detention blocking dam provided by the utility model and Dam, which is mined massively, takes the mode that is combined with aerial drainage of remaining in a standstill, and dam body is blocked, downflow weir and the flood discharge of aerial drainage hole while is carried out.Blocking dams at different levels Formation effectively retains storage capacity, blocks and carries water sand, changes water delivery, Sediment Transport Condition, extends under mud-rock flow and lets out the time, ensures that amount of water to be discharged is expired Foot trip guard plot safety;A small amount of bulk solid mass that mud-rock flow deposits later is more compared with small flood or mud-rock flow by the later stage Secondary wash away under carrying is let out, and reservoir area siltation thing is voluntarily cleared up, and ensures that effective storage can block mud-rock flow maximum one under stagnant norm for civil defense Mud-rock flow is retained in the secondary amount of going out, realization, adjusts letdown flow function, and retaining storage capacity can be used repeatedly, increase blocking dam and The ability of preventing and reducing natural disasters of dam group.Aerial drainage hole size facilitate later stage vehicle and equipment by and dredging operation.For reservoir area siltation Part super large particle diameter and trees, high-stem plant etc. influence the material of aerial drainage hole conveyance capacity, can by aerial drainage hole passage manually according to Secondary cleaning and transport, accomplish " retain, remain in a standstill, aerial drainage, desilting " multidigit in same mud-rock flow blocking dam and dam group's countermeasure system One, realizes the purpose prevented and reduced natural disasters.
Described above is only to better embodiment of the present utility model, not makees any form to the utility model On limitation, every any simple modification made according to the technical essence of the utility model to embodiment of above is equivalent to become Change and modify, belong in the range of technical solutions of the utility model.

Claims (1)

  1. A kind of 1. overflow-type mud-rock flow blocking dam group, it is characterised in that:It is made up of multiple overflow-type mud-rock flow blocking dams, overflow-type Mud-rock flow blocking dam is made up of key dam body, downflow weir, aerial drainage hole, and downflow weir is located above key dam body, and aerial drainage hole is several, if Put in key dam body bottom, key dam body is provided with spilled water hole, and spilled water hole is located above aerial drainage hole;
    Downflow weir and aerial drainage the hole conveyance capacity meets the mud-rock flow maximum stream flow for ensureing blocking dam safety;
    Aerial drainage hole letdown flow, which is less than under the maximum for ensureing downstream guard plot safety, lets out safe traffic;
    Aerial drainage hole minimum widith can guarantee that maximum stone particle diameter and desilting vehicle and equipment pass through in excessively stream in raceway groove;
    The ratio of aerial drainage hole minimum widith and maximum stone particle diameter in excessively stream is 1.5-2.0.
CN201720562724.4U 2017-05-19 2017-05-19 A kind of overflow-type mud-rock flow blocking dam group Expired - Fee Related CN206887895U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720562724.4U CN206887895U (en) 2017-05-19 2017-05-19 A kind of overflow-type mud-rock flow blocking dam group

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720562724.4U CN206887895U (en) 2017-05-19 2017-05-19 A kind of overflow-type mud-rock flow blocking dam group

Publications (1)

Publication Number Publication Date
CN206887895U true CN206887895U (en) 2018-01-16

Family

ID=61342532

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720562724.4U Expired - Fee Related CN206887895U (en) 2017-05-19 2017-05-19 A kind of overflow-type mud-rock flow blocking dam group

Country Status (1)

Country Link
CN (1) CN206887895U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505489A (en) * 2018-04-19 2018-09-07 齐绍诚 A kind of novel protective dike and its means of defence
CN108867569A (en) * 2018-07-12 2018-11-23 中国地质科学院探矿工艺研究所 Natural dredging debris flow sand dam and application thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505489A (en) * 2018-04-19 2018-09-07 齐绍诚 A kind of novel protective dike and its means of defence
CN108867569A (en) * 2018-07-12 2018-11-23 中国地质科学院探矿工艺研究所 Natural dredging debris flow sand dam and application thereof

Similar Documents

Publication Publication Date Title
CN104912087B (en) Center line type tailing damming method applying mold bags
CN103397645B (en) A kind of dry heap arranges with wet the tailings pile discharge method combined
CN107034853A (en) A kind of overflow-type mud-rock flow blocking dam and dam group
CN106801403B (en) A method of preventing mud-stone flow disaster and mudstone apoblema recycles
CN108374384B (en) Zero-emission tailing pond system and implementation method
CN103821218A (en) Initial rainwater and mixed rain-sewage overflow water impounding sewage facility
CN207512028U (en) A kind of water quality of river in-situ purification system
CN206887895U (en) A kind of overflow-type mud-rock flow blocking dam group
CN103061327B (en) Comprehensive water control technique for dump
CN108797652B (en) Water return regulating method for phosphogypsum reservoir
CN102162229A (en) Sediment storage dam for protecting against large-scale low-frequency debris flow
CN112709233A (en) Mine waste rock and concentrated tailing cooperative disposal system and construction method
CN205954559U (en) A ditch water treatment structure that is used for large -scale sediment field of blocking
CN105064291A (en) Step sand-blocking dam ecosystem for reservoir desilting and sand prevention
CN110468792B (en) Non-clogging ecological permeable dam and construction method thereof
CN104963379B (en) For the water intaking structure on mountain channel
KR20140108476A (en) Debris barrier
CN106013007B (en) Suitable for the husky separation building of water of linear pattern chute spillway
CN103233440B (en) Slag type debris flow formation mechanism based prevention method
JPH10252042A (en) Mechanism and method for discharging sand from dam reservoir
CN104831689A (en) Siltation-preventing water intake facility achieving automatic flood prevention and pollution discharge
KR101170789B1 (en) Complex debris barrier of eco-friendly
CN205530160U (en) Drop energy absorber
CN112982611A (en) Dry red mud yard and arrangement method thereof
CN109577268A (en) Do not deposit reservoir

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180116

Termination date: 20180519