- CN206831941U CN206831941U CN201720327075.XU CN201720327075U CN206831941U CN 206831941 U CN206831941 U CN 206831941U CN 201720327075 U CN201720327075 U CN 201720327075U CN 206831941 U CN206831941 U CN 206831941U
- Authority
- CN
- China
- Prior art keywords
- casing
- welded
- solid waste
- inlet pipe
- highly effective
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
It the utility model is related to a kind of highly effective drying equipment, more particularly to a kind of solid waste highly effective drying equipment.The technical problems to be solved in the utility model is to provide a kind of consumed energy bottom, and generation is smelly narrow-minded, and added amount of chemical is small, intractability is small, the solid waste highly effective drying equipment that operating cost is low and treatment effect is stable.In order to solve the above-mentioned technical problem, the utility model provides such a solid waste highly effective drying equipment, includes the first casing, mounting seat, neck, mobile device, collection frame, the second casing, the first air inlet pipe, heating wire, air pump, box door device, air cavity etc.;Box door device is installed on the left of first casing, the first casing inner bottom part is welded with mounting seat, neck is welded with mounting seat.Then the utility model controls the electric rotating machine in mobile device to drive nozzle right motion to realize the solid waste of required drying along counterclockwise movement and uniformly air-dried by controlling air pump and heating wire works.
Description
Technical field
It the utility model is related to a kind of highly effective drying equipment, more particularly to a kind of solid waste highly effective drying equipment.
Background technology
After Solid Waste Treatment main flow is desiccation dehydration at present, burned, compost or landfill.And to reach and burn
Burn, the condition of compost or landfill, typically require moisture percentage in sewage sludge control below 60%, burning disposal requires moisture percentage in sewage sludge control
System is below 50%, and moisture percentage in sewage sludge is 75% ~ 85% caused by sewage treatment plant.So we will be carried out to sludge or rubbish
Desiccation dewater treatment.But the principle of current desiccation apparatus mainly directly heats machine after desiccation dehydration or addition medicament
Tool press dewatering, have consumed energy bigger than normal, produce smelly large-minded, added amount of chemical is big, intractability is big, operating cost it is high and
The shortcomings for the treatment of effect is unstable.
Improve solid waste(Sludge or rubbish)Water separation capability can also be reached by changing its physical property.Solid gives up
Thing can change its physical property at a certain temperature and improve its dehydration rate.The current reaction heated existing on the market
Groove, production is widely used in, in order to obtain target product, chuck is designed with reactive tank, can so make vapours
It can not directly be contacted with reactant, reach the uniform purpose of reactant reaction temperature, while this also result in a part of heat
It is lost in.
Therefore a kind of consumed energy bottom of research and development is needed badly, generation is smelly narrow-minded, and added amount of chemical is small, intractability is small, operation
Cost bottom and the solid waste highly effective drying equipment for the treatment of effect stabilization.
Utility model content
(1)Technical problems to be solved
The utility model is in order to overcome consumed energy bigger than normal, and generation is smelly large-minded, and added amount of chemical is big, intractability is big,
Operating cost is high and treatment effect unstable the shortcomings that waiting, and the technical problems to be solved in the utility model is to provide a kind of consumption energy
Bottom is measured, generation is smelly narrow-minded, and added amount of chemical is small, intractability is small, the solid waste of operating cost bottom and treatment effect stabilization
Highly effective drying equipment.
(2)Technical scheme
In order to solve the above-mentioned technical problem, the utility model provides such a solid waste highly effective drying equipment, bag
The first casing, mounting seat, neck, mobile device, collection frame, the second casing, the first air inlet pipe, heating wire, air pump, chamber door are included
Device, air cavity, shower nozzle, support and the 3rd air inlet pipe, the first casing left side are provided with box door device, the welding of the first casing inner bottom part
There is mounting seat, neck is welded with mounting seat, be connected with collection frame in neck by bolted connection, the first casing is outer right
Side roof part is welded with the second casing, is provided with heating wire in the second casing, the first air inlet pipe is welded among the second casing external right side,
Right side is connected with air pump by bolted connection in first casing, and air pump is connected with the 3rd by way of flange connection and entered
Tracheae, mobile device is installed among the first casing inner top, mobile device connects by bolted connection among bottom
There is an air cavity, mobile device bottom right is welded with support, and air cavity bottom is welded with shower nozzle, what the right side of shower nozzle was connected by flange
Mode is connected with the 3rd air inlet pipe left end through support.
Preferably, mobile device also includes mechanical box, bearing block, screw mandrel, nut, electric rotating machine, guide rod, guide pin bushing and peace
Loading board, mechanical box bottom are provided with through hole, and mechanical box inner top is symmetrically welded with two bearing blocks, led in the bearing of two bearing blocks
The mode of interference connection is connected with screw mandrel, and screw mandrel is provided with nut, and screw mandrel cooperates with nut, on the left of mechanical box inner top
Be connected with electric rotating machine by bolted connection, the output shaft of electric rotating machine by way of interference connection with screw mandrel left end
It is connected, two bearing block bottoms are welded with guide rod, and slidingtype is connected with guide pin bushing on guide rod, and the top of guide pin bushing is by way of welding
It is connected with nut bottom, the bottom of guide pin bushing is welded with installing plate, and installing plate is welded with air cavity through through hole.
Preferably, box door device include hinge, the first chamber door, sheet rubber, the first iron block, the first magnet, transparent panel and
Second handle, the first casing left part rear side are provided with hinge, and the first chamber door is connected with hinge, and the first chamber door is equipped with both sides up and down
Sheet rubber, is provided with the first iron block on front side of the first chamber door right part, and the first casing left part front side is embedded with the first magnet, the first magnet and the
One iron block is corresponding, and the first chamber door left part is embedded with transparent panel, and the second handle is provided with front side of the first chamber door.
Preferably, in addition to web plate, the 3rd casing, blast pipe and the second air inlet pipe, the outer right wall downside of the first casing are welded
There is the 3rd casing, be connected with two web plates in the 3rd casing by bolted connection, activated carbon is placed between two web plates, the
Blast pipe is welded with the left of three casing tops, the blast pipe other end connects with the first casing right wall, is welded on the right side of the 3rd casing top
The second air inlet pipe is connected to, the second air inlet pipe other end on the right side of the second bottom half with connecting.
Preferably, screen pack is also included, screen pack is connected with the first air inlet pipe right-hand member by bolted connection.
Preferably, the first tank material is stainless steel.
Preferably, it is Q235 steel to install seat material.
Preferably, electric rotating machine is servomotor.
Operation principle:Move it to the place needed to use first when needing to use this equipment, then manual control case
Door gear is opened, and manually the solid waste by required drying is put into collection frame, and then manual control box door device is closed.So
Manually being powered afterwards to heating wire allows its work, then manual control air pump to start working, and air pump enters the air in the external world by first
Tracheae is sucked in the second casing, and air becomes hot gas by the heating wire of heating and flows into air cavity from the 3rd air inlet pipe by air pump
Interior, the air flowed into air cavity is in the solid waste dried needed for being ejected into by shower nozzle, and at the same time manual control is moved
Dynamic device is started working, and mobile device, which is started working, drives nozzle right motion, and the solid waste of required drying is uniformly added
Heat.The manual control heating wire cut-off when having used this equipment, mobile device and air pump is controlled to be stopped, manual control chamber door
Device is opened, and solid waste dried in collection frame is taken out and closes box door device, then puts this equipment
To suitable position.
Because mobile device also includes mechanical box, bearing block, screw mandrel, nut, electric rotating machine, guide rod, guide pin bushing, installation
Plate, mechanical box bottom are provided with through hole, and mechanical box inner top is symmetrically welded with two bearing blocks, passed through in the bearing of two bearing blocks
The mode of interference connection is connected with screw mandrel, and screw mandrel is provided with nut, and screw mandrel cooperates with nut, logical on the left of mechanical box inner top
Cross bolted mode and be connected with electric rotating machine, the output shaft of electric rotating machine by way of interference connection with screw mandrel left end phase
Even, two bearing block bottoms are welded with guide rod, and slidingtype is connected with guide pin bushing on guide rod, the top of guide pin bushing by way of welding with
Nut bottom is connected, and the bottom of guide pin bushing is welded with installing plate, and installing plate is welded with air cavity through through hole, when it is desired to be used first
Manual control electric rotating machine is started working, and drives screw mandrel to turn clockwise when electric rotating machine works clockwise, screw mandrel is clockwise
Rotation drives nut to drive guide pin bushing to drive installing plate to the left to left movement to left movement, guide pin bushing to left movement to left movement, nut
Motion.Screw mandrel rotate counterclockwise is driven when electric rotating machine works counterclockwise, screw mandrel rotate counterclockwise drives nut to move right,
Nut, which moves right, drives guide pin bushing to move right, and guide pin bushing, which moves right, drives installing plate to move right.So it is achieved that its bottom
The side-to-side movement of part device.
Because box door device includes hinge, the first chamber door, sheet rubber, the first iron block, the first magnet, transparent panel and second
Handle, the first casing left part rear side are provided with hinge, and the first chamber door is connected with hinge, and the first chamber door is equipped with rubber in both sides up and down
Piece, the first chamber door right part front side are provided with the first iron block, the first magnet, the first magnet and the first iron are embedded with front side of the first casing left part
Block is corresponding, and the first chamber door left part is embedded with transparent panel, the second handle is provided with front side of the first chamber door, so when needs place an article within
When in the first casing, staff pulls the second handle to the left so that the first iron block and the separation of the first magnet, while drive first
Chamber door is swung to the left, and so as to open the first chamber door, solid waste is placed in collection frame, is then shut off the first chamber door.
Because also including web plate, the 3rd casing, blast pipe and the second air inlet pipe, the is welded with the downside of the outer right wall of the first casing
Three casings, two web plates are connected with by bolted connection in the 3rd casing, activated carbon, the 3rd case are placed between two web plates
Body top left side is welded with blast pipe, and the blast pipe other end connects with the first casing right wall, is welded with the right side of the 3rd casing top
Second air inlet pipe, the second air inlet pipe other end on the right side of the second bottom half with connecting, when the air pressure in the first casing is too big, the
Hot gas in one casing can be flowed into the 3rd casing from blast pipe, and the hot gas being flowed into the 3rd casing passes through activated carbon
Filtering after from the second air inlet pipe again enter the second casing in gas can so be recycled.
Because also including screen pack, screen pack is connected with the first air inlet pipe right-hand member by bolted connection.Filtering
Net, which can be good at keeping apart the dust in air, does not allow it to be inhaled into air pump.
Because the first tank material is stainless steel, stainless steel corrosion resistance and acid resistance are strong, can extension fixture use the longevity
Life.
Because installation seat material is Q235 steel, Q235 steel hardness is high, it is not easy to deforms, makes the service life of device longer.
Because electric rotating machine is servomotor, anti-overload ability is strong, and high speed performance is good, can be precisely controlled its rotating speed.
(3)Beneficial effect
Then the utility model controls the electric rotating machine in mobile device along the inverse time by controlling air pump and heating wire works
Needle movement drives nozzle right motion to realize the solid waste of required drying and uniformly air-dried, and has reached consumed energy bottom, has produced
Smelly narrow-minded, added amount of chemical is small, intractability is small, the effect of operating cost bottom and treatment effect stabilization.
Brief description of the drawings
Fig. 1 is the first main structure diagram of the present utility model.
Fig. 2 is the main structure diagram of the utility model mobile device.
Fig. 3 is the main structure diagram of the utility model box door device.
Fig. 4 is the main structure diagram of the utility model web plate and the 3rd casing.
Fig. 5 is second of main structure diagram of the present utility model.
Mark in accompanying drawing for:The casings of 1- first, 2- mounting seats, 3- necks, 4- mobile devices, 41- mechanical boxes, 42- lead to
Hole, 43- bearing blocks, 44- screw mandrels, 45- nuts, 46- electric rotating machines, 47- guide rods, 48- guide pin bushings, 49- installing plates, 5- collection frames,
The casings of 6- second, the air inlet pipe of 7- first, 8- heating wire, 9- air pumps, 10- box door devices, 100- hinges, the chamber doors of 101- first,
102- sheet rubbers, the iron blocks of 103- first, the magnet of 104- first, 105- transparent panels, 106- second shake hands, 11- air cavitys, 12- shower nozzles,
13- supports, the air inlet pipe of 14- the 3rd, 15- web plates, the casings of 16- the 3rd, 17- blast pipes, the air inlet pipe of 18- second, 19- screen packs.
Embodiment
The utility model is further described with reference to the accompanying drawings and examples.
Embodiment 1
A kind of solid waste highly effective drying equipment, as Figure 1-5, include the first casing 1, mounting seat 2, neck 3, shifting
Dynamic device 4, collection frame 5, the second casing 6, the first air inlet pipe 7, heating wire 8, air pump 9, box door device 10, air cavity 11, shower nozzle 12,
The air inlet pipe 14 of support 13 and the 3rd, the left side of the first casing 1 are provided with box door device 10, and the inner bottom part of the first casing 1 is welded with installation
Seat 2, neck 3 being welded with mounting seat 2, being connected with collection frame 5 in neck 3 by bolted connection, the first casing 1 is outer right
Side roof part is welded with the second casing 6, is provided with heating wire 8 in the second casing 6, being welded with first among the external right side of the second casing 6 enters
Tracheae 7,1 interior right side of the first casing are connected with air pump 9 by bolted connection, and air pump 9 is connected by way of flange connection
The 3rd air inlet pipe 14 is connected to, mobile device 4 is installed among the inner top of first casing 1, mobile device 4 passes through bolt among bottom
The mode of connection is connected with air cavity 11, and the bottom right of mobile device 4 is welded with support 13, and the bottom of air cavity 11 is welded with shower nozzle 12,
The right side of shower nozzle 12 is connected by way of flange connection with the left end of the 3rd air inlet pipe 14 through support 13.
Embodiment 2
A kind of solid waste highly effective drying equipment, as Figure 1-5, include the first casing 1, mounting seat 2, neck 3, shifting
Dynamic device 4, collection frame 5, the second casing 6, the first air inlet pipe 7, heating wire 8, air pump 9, box door device 10, air cavity 11, shower nozzle 12,
The air inlet pipe 14 of support 13 and the 3rd, the left side of the first casing 1 are provided with box door device 10, and the inner bottom part of the first casing 1 is welded with installation
Seat 2, neck 3 being welded with mounting seat 2, being connected with collection frame 5 in neck 3 by bolted connection, the first casing 1 is outer right
Side roof part is welded with the second casing 6, is provided with heating wire 8 in the second casing 6, being welded with first among the external right side of the second casing 6 enters
Tracheae 7,1 interior right side of the first casing are connected with air pump 9 by bolted connection, and air pump 9 is connected by way of flange connection
The 3rd air inlet pipe 14 is connected to, mobile device 4 is installed among the inner top of first casing 1, mobile device 4 passes through bolt among bottom
The mode of connection is connected with air cavity 11, and the bottom right of mobile device 4 is welded with support 13, and the bottom of air cavity 11 is welded with shower nozzle 12,
The right side of shower nozzle 12 is connected by way of flange connection with the left end of the 3rd air inlet pipe 14 through support 13.
Mobile device 4 also includes mechanical box 41, bearing block 43, screw mandrel 44, nut 45, electric rotating machine 46, guide rod 47, led
Set 48 and installing plate 49, the bottom of mechanical box 41 are provided with through hole 42, and the inner top of mechanical box 41 is symmetrically welded with two bearing blocks 43, and two
Be connected with screw mandrel 44 in the bearing of individual bearing block 43 by way of interference connection, screw mandrel 44 is provided with nut 45, screw mandrel 44 and
Nut 45 cooperates, and the inner top of mechanical box 41 passes on left bolted mode and is connected with electric rotating machine 46, electric rotating machine
46 output shaft is connected by way of interference connection with the left end of screw mandrel 44, and two bottoms of bearing block 43 are welded with guide rod 47, lead
Slidingtype is connected with guide pin bushing 48 on bar 47, and the top of guide pin bushing 48 is connected by way of welding with the bottom of nut 45, guide pin bushing 48
Bottom is welded with installing plate 49, and installing plate 49 is welded with air cavity 11 through through hole 42.
Embodiment 3
A kind of solid waste highly effective drying equipment, as Figure 1-5, include the first casing 1, mounting seat 2, neck 3, shifting
Dynamic device 4, collection frame 5, the second casing 6, the first air inlet pipe 7, heating wire 8, air pump 9, box door device 10, air cavity 11, shower nozzle 12,
The air inlet pipe 14 of support 13 and the 3rd, the left side of the first casing 1 are provided with box door device 10, and the inner bottom part of the first casing 1 is welded with installation
Seat 2, neck 3 being welded with mounting seat 2, being connected with collection frame 5 in neck 3 by bolted connection, the first casing 1 is outer right
Side roof part is welded with the second casing 6, is provided with heating wire 8 in the second casing 6, being welded with first among the external right side of the second casing 6 enters
Tracheae 7,1 interior right side of the first casing are connected with air pump 9 by bolted connection, and air pump 9 is connected by way of flange connection
The 3rd air inlet pipe 14 is connected to, mobile device 4 is installed among the inner top of first casing 1, mobile device 4 passes through bolt among bottom
The mode of connection is connected with air cavity 11, and the bottom right of mobile device 4 is welded with support 13, and the bottom of air cavity 11 is welded with shower nozzle 12,
The right side of shower nozzle 12 is connected by way of flange connection with the left end of the 3rd air inlet pipe 14 through support 13.
Mobile device 4 also includes mechanical box 41, bearing block 43, screw mandrel 44, nut 45, electric rotating machine 46, guide rod 47, led
Set 48 and installing plate 49, the bottom of mechanical box 41 are provided with through hole 42, and the inner top of mechanical box 41 is symmetrically welded with two bearing blocks 43, and two
Be connected with screw mandrel 44 in the bearing of individual bearing block 43 by way of interference connection, screw mandrel 44 is provided with nut 45, screw mandrel 44 and
Nut 45 cooperates, and the inner top of mechanical box 41 passes on left bolted mode and is connected with electric rotating machine 46, electric rotating machine
46 output shaft is connected by way of interference connection with the left end of screw mandrel 44, and two bottoms of bearing block 43 are welded with guide rod 47, lead
Slidingtype is connected with guide pin bushing 48 on bar 47, and the top of guide pin bushing 48 is connected by way of welding with the bottom of nut 45, guide pin bushing 48
Bottom is welded with installing plate 49, and installing plate 49 is welded with air cavity 11 through through hole 42.
Box door device 10 includes hinge 100, the first chamber door 101, sheet rubber 102, the first iron block 103, the first magnet
104th, the handle of transparent panel 105 and second 106, the left part of the first casing 1 rear side are provided with hinge 100, the first case are connected with hinge 100
Door 101, the first chamber door are equipped with sheet rubber 102 in both sides about 101, the first iron block 103 are provided with front side of the right part of the first chamber door 101,
The first magnet 104 is embedded with front side of the left part of first casing 1, the first magnet 104 is corresponding with the first iron block 103, and the first chamber door 101 is left
Portion is embedded with transparent panel 105, and the front side of the first chamber door 101 is provided with the second handle 106.
Embodiment 4
A kind of solid waste highly effective drying equipment, as Figure 1-5, include the first casing 1, mounting seat 2, neck 3, shifting
Dynamic device 4, collection frame 5, the second casing 6, the first air inlet pipe 7, heating wire 8, air pump 9, box door device 10, air cavity 11, shower nozzle 12,
The air inlet pipe 14 of support 13 and the 3rd, the left side of the first casing 1 are provided with box door device 10, and the inner bottom part of the first casing 1 is welded with installation
Seat 2, neck 3 being welded with mounting seat 2, being connected with collection frame 5 in neck 3 by bolted connection, the first casing 1 is outer right
Side roof part is welded with the second casing 6, is provided with heating wire 8 in the second casing 6, being welded with first among the external right side of the second casing 6 enters
Tracheae 7,1 interior right side of the first casing are connected with air pump 9 by bolted connection, and air pump 9 is connected by way of flange connection
The 3rd air inlet pipe 14 is connected to, mobile device 4 is installed among the inner top of first casing 1, mobile device 4 passes through bolt among bottom
The mode of connection is connected with air cavity 11, and the bottom right of mobile device 4 is welded with support 13, and the bottom of air cavity 11 is welded with shower nozzle 12,
The right side of shower nozzle 12 is connected by way of flange connection with the left end of the 3rd air inlet pipe 14 through support 13.
Mobile device 4 also includes mechanical box 41, bearing block 43, screw mandrel 44, nut 45, electric rotating machine 46, guide rod 47, led
Set 48 and installing plate 49, the bottom of mechanical box 41 are provided with through hole 42, and the inner top of mechanical box 41 is symmetrically welded with two bearing blocks 43, and two
Be connected with screw mandrel 44 in the bearing of individual bearing block 43 by way of interference connection, screw mandrel 44 is provided with nut 45, screw mandrel 44 and
Nut 45 cooperates, and the inner top of mechanical box 41 passes on left bolted mode and is connected with electric rotating machine 46, electric rotating machine
46 output shaft is connected by way of interference connection with the left end of screw mandrel 44, and two bottoms of bearing block 43 are welded with guide rod 47, lead
Slidingtype is connected with guide pin bushing 48 on bar 47, and the top of guide pin bushing 48 is connected by way of welding with the bottom of nut 45, guide pin bushing 48
Bottom is welded with installing plate 49, and installing plate 49 is welded with air cavity 11 through through hole 42.
Box door device 10 includes hinge 100, the first chamber door 101, sheet rubber 102, the first iron block 103, the first magnet
104th, the handle of transparent panel 105 and second 106, the left part of the first casing 1 rear side are provided with hinge 100, the first case are connected with hinge 100
Door 101, the first chamber door are equipped with sheet rubber 102 in both sides about 101, the first iron block 103 are provided with front side of the right part of the first chamber door 101,
The first magnet 104 is embedded with front side of the left part of first casing 1, the first magnet 104 is corresponding with the first iron block 103, and the first chamber door 101 is left
Portion is embedded with transparent panel 105, and the front side of the first chamber door 101 is provided with the second handle 106.
Also include web plate 15, the 3rd casing 16, the air inlet pipe 18 of blast pipe 17 and second, welded on the downside of 1 outer right wall of the first casing
The 3rd casing 16 is connected to, two web plates 15 is connected with the 3rd casing 16 by bolted connection, is placed between two web plates 15
Active charcoal, the top left side of the 3rd casing 16 are welded with blast pipe 17, and the other end of blast pipe 17 connects with the right wall of the first casing 1,
The top right side of 3rd casing 16 is welded with the second air inlet pipe 18, and the other end of the second air inlet pipe 18 and the bottom right of the second casing 6 connect
It is logical.
Also include screen pack 19, screen pack 19 is connected with the right-hand member of the first air inlet pipe 7 by bolted connection.
The material of first casing 1 is stainless steel.
The material of mounting seat 2 is Q235 steel.
Electric rotating machine 46 is servomotor.
Operation principle:Move it to the place needed to use first when needing to use this equipment, then manual control case
Door gear 10 is opened, and manually the solid waste of required drying is put into collection frame 5, and then manual control box door device 10 closes
Close.Then being manually powered to heating wire 8 allows its work, then manual control air pump 9 to start working, and air pump 9 leads to the air in the external world
Cross the first air inlet pipe 7 to suck in the second casing 6, air becomes hot gas by the heating wire 8 of heating and by air pump 9 from the 3rd entered
Tracheae 14 is flowed into air cavity 11, and the air flowed into air cavity 11 is being ejected into the required solid waste dried by shower nozzle 12
On, at the same time manual control mobile device 4 is started working, and mobile device 4, which is started working, drives the side-to-side movement of shower nozzle 12, to institute
The solid waste that need to be dried uniformly heats.When having used this equipment, manual control heating wire 8 powers off, and controls mobile device 4
It is stopped with air pump 9, manual control box door device 10 is opened, and solid waste dried in collection frame 5 is taken out and incited somebody to action
Box door device 10 is closed, and this equipment then is put into suitable position.
Because mobile device 4 also includes mechanical box 41, bearing block 43, screw mandrel 44, nut 45, electric rotating machine 46, guide rod
47th, guide pin bushing 48, installing plate 49, the bottom of mechanical box 41 are provided with through hole 42, and the inner top of mechanical box 41 is symmetrically welded with two bearing blocks
43, the bearing of two bearing blocks 43 is interior to be connected with screw mandrel 44 by way of interference connection, and screw mandrel 44 is provided with nut 45, screw mandrel
44 cooperate with nut 45, and the inner top of mechanical box 41 passes on left bolted mode and is connected with electric rotating machine 46, rotation
The output shaft of motor 46 is connected by way of interference connection with the left end of screw mandrel 44, and two bottoms of bearing block 43 are welded with guide rod
47, slidingtype is connected with guide pin bushing 48 on guide rod 47, and the top of guide pin bushing 48 is connected by way of welding with the bottom of nut 45, guide pin bushing
48 bottom is welded with installing plate 49, and installing plate 49 is welded with air cavity 11 through through hole 42, people's industry control first when it is desired to be used
Electric rotating machine 46 processed is started working, and drives screw mandrel 44 to turn clockwise when electric rotating machine 46 works clockwise, the up time of screw mandrel 44
Pin rotation drives nut 45 to drive guide pin bushing 48 to be driven to left movement, guide pin bushing 48 to left movement to left movement to left movement, nut 45
Installing plate 49 is to left movement.The rotate counterclockwise of screw mandrel 44 is driven when electric rotating machine 46 works counterclockwise, screw mandrel 44 revolves counterclockwise
Turn to drive nut 45 to move right, nut 45, which moves right, drives guide pin bushing 48 to move right, and guide pin bushing 48 moves right drive installation
Plate 49 moves right.So it is achieved that the side-to-side movement of its bottom device.
Because box door device 10 includes hinge 100, the first chamber door 101, sheet rubber 102, the first iron block 103, the first magnetic
Iron 104, the handle of transparent panel 105 and second 106, the left part of the first casing 1 rear side are provided with hinge 100, first are connected with hinge 100
Chamber door 101, the first chamber door are equipped with sheet rubber 102 in both sides about 101, the first iron block are provided with front side of the right part of the first chamber door 101
103, the left part of the first casing 1 front side is embedded with the first magnet 104, and the first magnet 104 is corresponding with the first iron block 103, the first chamber door
101 left parts are embedded with transparent panel 105, and the front side of the first chamber door 101 is provided with the second handle 106, so working as needs to place an article within first
When in casing 1, staff pulls the second handle 106 to the left so that the first iron block 103 and the first magnet 104 separate, while band
Dynamic first chamber door 101 is swung to the left, so as to open the first chamber door 101, solid waste is placed in collection frame 5, is then shut off
First chamber door 101.
Because also including web plate 15, the 3rd casing 16, the air inlet pipe 18 of blast pipe 17 and second, under 1 outer right wall of the first casing
Side is welded with the 3rd casing 16, is connected with two web plates 15 in the 3rd casing 16 by bolted connection, between two web plates 15
Activated carbon is placed with, the top left side of the 3rd casing 16 is welded with blast pipe 17, and the other end of blast pipe 17 and the right wall of the first casing 1 connect
Logical, the top right side of the 3rd casing 16 is welded with the second air inlet pipe 18, the other end of the second air inlet pipe 18 and the bottom right of the second casing 6
Connection, when the air pressure in the first casing 1 is too big, the hot gas in the first casing 1 can be flowed into the 3rd casing from blast pipe 17
In 16, it is flowed into the hot gas in the 3rd casing 16 and enters the second casing again from the second air inlet pipe 18 after the filtering of activated carbon
Gas can so be recycled in 6.
Because also including screen pack 19, screen pack 19 is connected with the right-hand member of the first air inlet pipe 7 by bolted connection.
Screen pack 19, which can be good at keeping apart the dust in air, does not allow it to be inhaled into air pump 9.
Because the material of the first casing 1 is stainless steel, stainless steel corrosion resistance and acid resistance are strong, can extension fixture use the longevity
Life.
Because the material of mounting seat 2 is Q235 steel, Q235 steel hardness is high, it is not easy to deforms, makes the service life of device longer.
Because electric rotating machine 46 is servomotor, anti-overload ability is strong, and high speed performance is good, can be precisely controlled its rotating speed.
Embodiment described above only expresses preferred embodiment of the present utility model, and its description is more specific and detailed,
But therefore it can not be interpreted as the limitation to the utility model patent scope.It should be pointed out that for the common of this area
For technical staff, without departing from the inventive concept of the premise, some deformations can also be made, improves and substitutes, these are all
Belong to the scope of protection of the utility model.Therefore, the protection domain of the utility model patent should be determined by the appended claims.
Claims (8)
1. a kind of solid waste highly effective drying equipment, it is characterised in that include the first casing(1), mounting seat(2), neck
(3), mobile device(4), collection frame(5), the second casing(6), the first air inlet pipe(7), heating wire(8), air pump(9), chamber door dress
Put(10), air cavity(11), shower nozzle(12), support(13)With the 3rd air inlet pipe(14), the first casing(1)Left side is provided with chamber door dress
Put(10), the first casing(1)Inner bottom part is welded with mounting seat(2), mounting seat(2)On be welded with neck(3), neck(3)It is interior logical
Cross bolted mode and be connected with collection frame(5), the first casing(1)The second casing is welded with the top of external right side(6), the second case
Body(6)It is interior to be provided with heating wire(8), the second casing(6)The first air inlet pipe is welded among external right side(7), the first casing(1)The interior right side
Side is connected with air pump by bolted connection(9), air pump(9)The 3rd air inlet pipe is connected with by way of flange connection
(14), the first casing(1)Mobile device is installed among inner top(4), mobile device(4)It is bolted among bottom
Mode is connected with air cavity(11), mobile device(4)Bottom right is welded with support(13), air cavity(11)Bottom is welded with shower nozzle
(12), shower nozzle(12)Right side flange connection by way of with pass through support(13)The 3rd air inlet pipe(14)Left end is connected.
A kind of 2. solid waste highly effective drying equipment according to claim 1, it is characterised in that mobile device(4)Also wrap
Mechanical box is included(41), bearing block(43), screw mandrel(44), nut(45), electric rotating machine(46), guide rod(47), guide pin bushing(48)With
Installing plate(49), mechanical box(41)Bottom is provided with through hole(42), mechanical box(41)Inner top is symmetrically welded with two bearing blocks
(43), two bearing blocks(43)Bearing in interference connection by way of be connected with screw mandrel(44), screw mandrel(44)It is provided with spiral shell
It is female(45), screw mandrel(44)With nut(45)Cooperate, mechanical box(41)Inner top passes on left bolted mode and connected
There is electric rotating machine(46), electric rotating machine(46)Output shaft interference connection by way of and screw mandrel(44)Left end is connected, two
Bearing block(43)Bottom is welded with guide rod(47), guide rod(47)Upper slidingtype is connected with guide pin bushing(48), guide pin bushing(48)Top lead to
Cross the mode and nut of welding(45)Bottom is connected, guide pin bushing(48)Bottom be welded with installing plate(49), installing plate(49)Pass through
Through hole(42)It is welded with air cavity(11).
A kind of 3. solid waste highly effective drying equipment according to claim 2, it is characterised in that box door device(10)Including
There is hinge(100), the first chamber door(101), sheet rubber(102), the first iron block(103), the first magnet(104), transparent panel(105)
With the second handle(106), the first casing(1)Hinge is provided with rear side of left part(100), hinge(100)On be connected with the first chamber door
(101), the first chamber door(101)Upper and lower both sides are equipped with sheet rubber(102), the first chamber door(101)The first iron is provided with front side of right part
Block(103), the first casing(1)The first magnet is embedded with front side of left part(104), the first magnet(104)With the first iron block(103)Relatively
Should, the first chamber door(101)Left part is embedded with transparent panel(105), the first chamber door(101)Front side is provided with the second handle(106).
4. a kind of solid waste highly effective drying equipment according to claim 3, it is characterised in that also including web plate(15)、
3rd casing(16), blast pipe(17)With the second air inlet pipe(18), the first casing(1)The 3rd casing is welded with the downside of outer right wall
(16), the 3rd casing(16)Two web plates are inside connected with by bolted connection(15), two web plates(15)Between be placed with work
Property charcoal, the 3rd casing(16)Top left side is welded with blast pipe(17), blast pipe(17)The other end and the first casing(1)Right wall connects
It is logical, the 3rd casing(16)Top right side is welded with the second air inlet pipe(18), the second air inlet pipe(18)The other end and the second casing(6)
Bottom right connects.
5. a kind of solid waste highly effective drying equipment according to claim 4, it is characterised in that also include screen pack
(19), screen pack(19)By bolted connection with the first air inlet pipe(7)Right-hand member is connected.
A kind of 6. solid waste highly effective drying equipment according to claim 5, it is characterised in that the first casing(1)Material
For stainless steel.
A kind of 7. solid waste highly effective drying equipment according to claim 6, it is characterised in that mounting seat(2)Material is
Q235 steel.
A kind of 8. solid waste highly effective drying equipment according to claim 7, it is characterised in that electric rotating machine(46)To watch
Take motor.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720327075.XU CN206831941U (en) | 2017-03-30 | 2017-03-30 | A kind of solid waste highly effective drying equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720327075.XU CN206831941U (en) | 2017-03-30 | 2017-03-30 | A kind of solid waste highly effective drying equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206831941U true CN206831941U (en) | 2018-01-02 |
Family
ID=60766827
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720327075.XU Active CN206831941U (en) | 2017-03-30 | 2017-03-30 | A kind of solid waste highly effective drying equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206831941U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108329966A (en) * | 2018-01-19 | 2018-07-27 | 袁红英 | A kind of efficient making apparatus of honeycomb briquette |
CN108448410A (en) * | 2018-04-12 | 2018-08-24 | 淮阴师范学院 | A kind of easy maintenance electric equipment cabinet with moisture-proof function |
CN108543748A (en) * | 2018-04-18 | 2018-09-18 | 太和县聚蚨发制品有限公司 | A kind of automation wig cleaning, drying system |
CN108609819A (en) * | 2018-07-16 | 2018-10-02 | 杨程飞扬 | A kind of riverway sludge processing unit |
CN109341245A (en) * | 2018-09-29 | 2019-02-15 | 柳州市恒茂木业有限公司 | A kind of plank production drying defatted device |
CN112665333A (en) * | 2020-12-28 | 2021-04-16 | 安徽彩韵服饰有限公司 | Drying equipment for garment materials dyeing and printing |
-
2017
- 2017-03-30 CN CN201720327075.XU patent/CN206831941U/en active Active
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108329966A (en) * | 2018-01-19 | 2018-07-27 | 袁红英 | A kind of efficient making apparatus of honeycomb briquette |
CN108448410A (en) * | 2018-04-12 | 2018-08-24 | 淮阴师范学院 | A kind of easy maintenance electric equipment cabinet with moisture-proof function |
CN108543748A (en) * | 2018-04-18 | 2018-09-18 | 太和县聚蚨发制品有限公司 | A kind of automation wig cleaning, drying system |
CN108609819A (en) * | 2018-07-16 | 2018-10-02 | 杨程飞扬 | A kind of riverway sludge processing unit |
CN109341245A (en) * | 2018-09-29 | 2019-02-15 | 柳州市恒茂木业有限公司 | A kind of plank production drying defatted device |
CN112665333A (en) * | 2020-12-28 | 2021-04-16 | 安徽彩韵服饰有限公司 | Drying equipment for garment materials dyeing and printing |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206831941U (en) | A kind of solid waste highly effective drying equipment | |
CN206113559U (en) | Industrial chemicals crushing and drying equipment | |
CN206996747U (en) | A kind of solid waste treatment device | |
CN207446943U (en) | Anaerobic Digestion of Municipal Solid Waste processing equipment | |
CN204752739U (en) | Agricultural wastes fermenting installation | |
CN106512642A (en) | Activated carbon waste gas treatment device | |
CN108689579A (en) | A kind of continuous compound catenary mud drying device | |
CN202028601U (en) | Restaurant-kitchen garbage processing device with zero discharge | |
CN113979608B (en) | Municipal sludge drying treatment equipment and drying treatment method | |
CN209173943U (en) | A kind of active carbon in-place regeneration device | |
CN209383807U (en) | A kind of corrugated paper waste water collecting methane equipment | |
CN204918338U (en) | Paddle sludge drying machine | |
CN109499557B (en) | Energy-saving environment-friendly active carbon regeneration furnace | |
CN209801961U (en) | novel solid waste screening and drying device | |
CN209077418U (en) | A kind of domestic garbage disposer | |
CN113459566B (en) | Waste paint slag treatment device | |
CN202499815U (en) | Biological dry reactor for domestic garbage | |
CN111392945A (en) | Industrial sewage treatment method and treatment device thereof | |
CN218249733U (en) | Stirring device for producing sewage biological denitrification composite carbon source | |
CN218857288U (en) | Concrete cement electric pole evaporates foster pond | |
CN218910129U (en) | Energy-saving and environment-friendly sludge drying equipment | |
CN110081686A (en) | A kind of garbage dewatering processing unit and its application method | |
CN213746767U (en) | Environment-friendly household garbage incineration device | |
CN215260922U (en) | Water vapor treatment and collection device for coal slime drying | |
CN110152548B (en) | Garbage mixing device for garbage power generation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |