CN206816274U - A kind of repairing and reinforcement structure of shield duct piece - Google Patents

A kind of repairing and reinforcement structure of shield duct piece Download PDF

Info

Publication number
CN206816274U
CN206816274U CN201720739245.5U CN201720739245U CN206816274U CN 206816274 U CN206816274 U CN 206816274U CN 201720739245 U CN201720739245 U CN 201720739245U CN 206816274 U CN206816274 U CN 206816274U
Authority
CN
China
Prior art keywords
groove
duct piece
shield duct
baffle plate
shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720739245.5U
Other languages
Chinese (zh)
Inventor
李宏飞
王少甲
邢鲁明
李绍辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201720739245.5U priority Critical patent/CN206816274U/en
Application granted granted Critical
Publication of CN206816274U publication Critical patent/CN206816274U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model belongs to shield duct piece technical field,A kind of more particularly to repairing and reinforcement structure of shield duct piece,After solving shield duct piece generation breakage,Change the problem of difficulty is big and cost is high,Including shield duct piece,The reinforcing position to be repaired of shield duct piece is provided with groove,Groove includes transverse concave groove and the vertical groove that square crossing is set,Bottom portion of groove is provided with waterproof matrix,It is provided with groove and its structure identical reinforced mesh,Reinforced mesh is included by tying up fixed silk and orthogonal transverse steel and longitudinal reinforcement,Transverse steel is arranged in transverse concave groove,Longitudinal reinforcement is arranged in vertical groove,Mounting hole is symmetrically provided with shield duct piece on the outside of groove,Concrete has been poured in groove,Baffle plate is provided with the outside of groove,Baffle plate radian and shield duct piece radian identical,Baffle plate is fixed on shield duct piece by screw and mounting hole.The utility model greatly enhance repair structure stability, while avoid reinforcing after the completion of impression quality difference the defects of.

Description

A kind of repairing and reinforcement structure of shield duct piece
Technical field
The utility model belongs to shield duct piece technical field, more particularly to a kind of repairing and reinforcement structure of shield duct piece.
Background technology
At present, method for tunnel construction has cut and cover method, subsurface excavation method etc., wherein, the shield method in subsurface excavation method is a kind of full machinery Change construction method, because shield method has the advantages that to excavate facility that is safe, not influenceing ground, be widely used in tunnel and build If such as:Railway tunnel, vcehicular tunnel, subaqueous tunnel, underground railway etc., following is a brief introduction of the structure of shield machine and The process of shield-tunneling construction:Shield machine includes main frame and rear three supporting vehicle frames, and the front end of main frame is cutterhead, is installed on cutterhead There is different cutters, motor drives the rotation of cutterhead, and some groups of hydraulic jacks promote cutterhead to advance, so as to realize to soil layer Chip, by pipeline by the dregs transportation after chip to tunnel outer, after cutterhead pushes ahead a certain distance, hydraulic jack Top bounces back to the direction of cutterhead temporarily, and duct piece assembling machine slings shield segment assembling to the hydraulic jack to have bounced back with having installed Between good shield duct piece, then the rear end of hydraulic jack and the front end of shield duct piece compress, and last several pipe sheet assemblings are Annulus, assembled rear jack top elongation is completed, continues to push ahead cutterhead.
Shield duct piece is typically manufactured using armored concrete, and intensity is higher, but toughness is poor, by some vibrations or punching When hitting, buffer capacity is limited, if regular is given a shock, is such as arranged in subway tunnel, it will cause shield duct piece The appearance for the problems such as sealing or bulk strength progressively decline, or even the blocking breakage in section of jurisdiction can be caused.When shield duct piece occurs After breakage, if changed to section of jurisdiction, difficulty it is larger, it is necessary to equipment it is more, if directly repaired to section of jurisdiction, mesh It is preceding also to be realized without preferable technological means.
Therefore, the repairing and reinforcement structure for inventing a kind of shield duct piece seems very necessary.
The content of the invention
The utility model in order to solve shield duct piece occur it is damaged after, to section of jurisdiction change that difficulty is big, cost is high asks A kind of topic, there is provided the repairing and reinforcement structure of shield duct piece.
The utility model is achieved by the following technical solution:A kind of repairing and reinforcement structure of shield duct piece, including shield Structure section of jurisdiction, the reinforcing position to be repaired of shield duct piece are provided with groove, and groove includes the transverse concave groove that square crossing sets and vertical Groove, bottom portion of groove are provided with waterproof matrix, be provided with groove with its structure identical reinforced mesh, reinforced mesh include by Tie up fixed silk and orthogonal transverse steel and longitudinal reinforcement, transverse steel are arranged in transverse concave groove, longitudinal reinforcement is set In vertical groove, mounting hole is symmetrically provided with the shield duct piece on the outside of groove, concrete has been poured in groove, has been set on the outside of groove Baffle plate is equipped with, baffle plate radian and shield duct piece radian identical, baffle plate are fixed on shield duct piece by screw and mounting hole.Gear Plate be provided with section of jurisdiction identical radian, be advantageous to baffle plate and be preferably bonded with section of jurisdiction, avoid the concrete in groove come off and The loosening of reinforced mesh, it ensure that the consolidation effect of shield duct piece.
The groove domestic demand casting concrete of repairing and reinforcement structure, the depth of groove determine the thickness of concrete, newly poured Concrete is excessively thin easily to come off, blocked up waste of materials, increases cost.To ensure that groove inner concrete and being bonded for shield duct piece are steady Gu preferably, the depth bounds of groove is 6-8 centimetres, and the concrete grade poured in groove is than shield duct piece concrete The high grade of label.
Bed course is provided between baffle plate and shield duct piece, bed course is located at the external margin of groove, and is set around groove, bed course Using paper -based asphalt felt.Paper -based asphalt felt can effectively prevent the stream of its internal moisture after concreting Lose, ensure the pouring quality of concrete, improve the durability of shield duct piece repairing and reinforcement structure.
Waterproof matrix is to smear to form using cement-base infiltration crystallization.Cementitious capillary waterproofing material is that one kind contains The powdery water-repellent paint of active compound, under the conditions of having existing for water, reactive compound permeates to inside concrete, in hole A large amount of long chain crystallizations not soluble in water, plug capillary channel of filling in a form are formed in gap and crack, so that concrete is fine and close, waterproof, It is applicable to the surfaces externally and internally of various concrete structures or the waterproof of body and the repairerment of permanent waterproof.
The utility model has the advantage that compared with prior art is with caused effect:
It is simple in construction, reasonable in design, by laying equal stress on needing the shield duct piece of repairing and reinforcement progress cover type to open up groove Transverse concave groove and vertical groove combining structure new to apply reinforced concrete structure, that groove is set using square crossing, greatly The stability for repairing structure is enhanced, cement-base infiltration crystallization is scribbled in groove, can fast and effectively play waterproof action, is repaired The baffle plate being fixed with shield piece identical radian measure itself is reinforced on the outside of position, avoids lacking for impression quality difference after the completion of reinforcing Fall into.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the structural representation of the utility model groove;
Fig. 3 is the structural representation of the utility model reinforced mesh.
In figure:1- shield duct pieces, 2- waterproof matrixs, 3- grooves, 31- transverse concave grooves, 32- vertical grooves, 4- reinforced mesh, 41- transverse steels, 42- longitudinal reinforcements, 43- tie up silk, 5- bed courses, 6- mounting holes, 7- baffle plates, 8- screws.
Embodiment
The utility model is described further with reference to Fig. 1-Fig. 3, a kind of repairing and reinforcement structure of shield duct piece, including Shield duct piece 1, waterproof matrix 2, groove 3, reinforced mesh 4, bed course 5, mounting hole 6, baffle plate 7 and screw 8, the two of shield duct piece 1 End is provided with connecting portion, and some shield duct pieces 1 are connected as into sealing endless belt by connecting portion;The damaged part of shield duct piece 1 Fluted 3 are cut, the groove 3 need to integrally cover damaged part, and groove 3 includes transverse concave groove 31 and vertical groove 32, and horizontal It is distributed to groove 31 and the square crossing of vertical groove 32;Reinforced mesh 4 is placed in groove 3, and reinforced mesh 4 includes transverse steel 41, longitudinal reinforcement 42 and tie up silk 43, transverse steel 41 and the square crossing of longitudinal reinforcement 42 are placed, and are bundled by tying up silk 43 Fixed, bed course 5 is located at the external margin of groove 3, and is set around groove 3;The outside of groove 3 is provided with mounting hole 6, and mounting hole 6 quantity uses 4 or 6, and baffle plate 7 is fixed on shield duct piece 1 by screw 8, and the screw 8 is connected with mounting hole 6.
Connecting portion uses dovetail configuration, is advantageous to bonding strength between raising shield duct piece 1, when shield duct piece 1 is damaged It can avoid influenceing the reliability being connected to each other.
One layer of cement-base infiltration crystallization is scribbled inside groove 3, reinforced mesh 4 is bundled according to the layout of groove 3, reinforcing bar Mesh sheet 4 is caught in the bottom of groove 3 by the end of transverse steel 41 and longitudinal reinforcement 42, then uses than shield duct piece 1 high one The concrete of grade fills and leads up groove 3.Wherein, the arrangement reinforced mesh 4 in the groove 3, be advantageous to improve the rigidity of section of jurisdiction 1 and strong Degree, plays preferable repairing and reinforcement effect, the cement-base infiltration crystallization scribbled, can effectively prevent groove 3 from seeping water, and has preferable Waterproof effect.
Bed course 5 uses paper -based asphalt felt, is advantageous to prevent the damaged part of section of jurisdiction 1 from internally seeping water, and improves anti- Water effect, while itself water conservation of concrete material after concreting is also beneficial to, so as to ensure that the reparation of shield duct piece adds Stereoplasm amount.
Baffle plate 7 uses stainless steel plate, and folding have with the identical radian of shield duct piece 1, be advantageous to baffle plate 7 preferably and shield Section of jurisdiction 1 is bonded, and avoids the concrete in groove 3 from coming off, and screw 8 uses swell fixture, is advantageous to baffle plate 7 is more firm solid It is scheduled on section of jurisdiction 1.After concrete strength reaches the 75% of design strength, baffle plate 7 is removed, baffle plate 7 can be by removing spiral shell After nail 8, baffle plate 7 is removed standby.
Embodiment:
The Beijing Metro project that my company undertakes the construction of, is constructed using shield method, is found in work progress, due to shield During transporting to underground some damaged in collision easily occur for section of jurisdiction 1, if to directly its change, construction cost compared with Greatly.By the research of technical staff, shield duct piece repairing and reinforcement structure described in the utility model is drawn.
This ruggedized construction uses mainly for 300-800mm of damaged face regional diameter scope, first passes through cutting machine by shield The damaged area of structure section of jurisdiction 1 is cut off, and to ensure the overall appearance after reinforcing, cutting will carry out along straight line, damaged area is cut The structure of groove 3 of transverse concave groove 31 and the square crossing of vertical groove 32 composition is cut into, carries out the cleaning of the bottom surface of groove 3.
Further, one layer of cement-base infiltration crystallization is smeared into as waterproof matrix 2 in the bottom of groove 3, treats that waterproof matrix 2 is dry After thoroughly, according to the structure setting transverse steel 41 of groove 3 and longitudinal reinforcement 42, wherein transverse steel 41 and longitudinal reinforcement 42 is utilized and tied up Silk 43 is fixed.
Further, groove 3 is poured using concrete of 1 grade higher than shield duct piece itself concrete grade, and Apply baffle plate 7 be fixed, baffle plate 7 be stainless steel plate, and roll over have with the identical radian of shield duct piece 1, it is more preferable to be advantageous to baffle plate 7 Be bonded with section of jurisdiction 1, avoid the concrete in groove 3 from coming off, screw 8 uses swell fixture, and baffle plate 7 is fixed on into shield duct piece On 1.

Claims (4)

1. a kind of repairing and reinforcement structure of shield duct piece, including shield duct piece(1), it is characterised in that:Shield duct piece(1)It is to be repaired It is added with maintenance and puts and is provided with groove(3), groove(3)The transverse concave groove set including square crossing(31)And vertical groove(32), it is recessed Groove(3)Bottom is provided with waterproof matrix(2), groove(3)Inside it is provided with and its structure identical reinforced mesh(4), reinforced mesh (4)Including by tying up silk(43)Fixed and orthogonal transverse steel(41)And longitudinal reinforcement(42), transverse steel(41)Set In transverse concave groove(31)It is interior, longitudinal reinforcement(42)It is arranged on vertical groove(32)It is interior, groove(3)The shield duct piece in outside(1)On Symmetrically it is provided with mounting hole(6), groove(3)Concrete, groove are inside poured(3)Outside is provided with baffle plate(7), baffle plate(7)Radian With shield duct piece(1)Radian is identical, baffle plate(7)Pass through screw(8)And mounting hole(6)It is fixed on shield duct piece(1)On.
A kind of 2. repairing and reinforcement structure of shield duct piece according to claim 1, it is characterised in that:Groove(3)Depth Scope is 6-8 centimetres, and groove(3)The concrete grade inside poured compares shield duct piece(1)The high grade of concrete grade.
A kind of 3. repairing and reinforcement structure of shield duct piece according to claim 1, it is characterised in that:Baffle plate(7)And shield Section of jurisdiction(1)Between be provided with bed course(5), bed course(5)Positioned at groove(3)External margin, and around groove(3)Set, bed course(5) Using paper -based asphalt felt.
A kind of 4. repairing and reinforcement structure of shield duct piece according to claim 1, it is characterised in that:Waterproof matrix(2)It is Smeared and formed using cement-base infiltration crystallization.
CN201720739245.5U 2017-06-23 2017-06-23 A kind of repairing and reinforcement structure of shield duct piece Expired - Fee Related CN206816274U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720739245.5U CN206816274U (en) 2017-06-23 2017-06-23 A kind of repairing and reinforcement structure of shield duct piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720739245.5U CN206816274U (en) 2017-06-23 2017-06-23 A kind of repairing and reinforcement structure of shield duct piece

Publications (1)

Publication Number Publication Date
CN206816274U true CN206816274U (en) 2017-12-29

Family

ID=60761618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720739245.5U Expired - Fee Related CN206816274U (en) 2017-06-23 2017-06-23 A kind of repairing and reinforcement structure of shield duct piece

Country Status (1)

Country Link
CN (1) CN206816274U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080796A (en) * 2019-04-22 2019-08-02 杨帆 Tunnel segment repair technique
CN111927502A (en) * 2020-06-02 2020-11-13 神华包神铁路集团有限责任公司 Method for treating tunnel water leakage and tunnel water leakage prevention structure
CN113622949A (en) * 2021-08-02 2021-11-09 中铁十六局集团有限公司 Shield segment repairing and reinforcing method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080796A (en) * 2019-04-22 2019-08-02 杨帆 Tunnel segment repair technique
CN111927502A (en) * 2020-06-02 2020-11-13 神华包神铁路集团有限责任公司 Method for treating tunnel water leakage and tunnel water leakage prevention structure
CN113622949A (en) * 2021-08-02 2021-11-09 中铁十六局集团有限公司 Shield segment repairing and reinforcing method
CN113622949B (en) * 2021-08-02 2024-03-22 中铁十六局集团有限公司 Shield segment repairing and reinforcing method

Similar Documents

Publication Publication Date Title
CN204401432U (en) A kind of measures of cracks on concrete pavement repairs structure
CN101906768B (en) Panel construction method of concrete faced rock-fill dam
CN105839850B (en) Precompressed construction method is poured into a mould after basement top-down method shaft
CN206816274U (en) A kind of repairing and reinforcement structure of shield duct piece
CN101818645B (en) Construction method for newly increasing arched open cut tunnel at railway operating line tunnel portal
CN103276639A (en) Roadbed structure for deep soft soil region
CN101298781B (en) Basement bottom plate rear pouring tape construction method
CN106677787A (en) Vertical shaft restoration and reinforcement structure and restoration and reinforcement construction method
CN105714635B (en) A kind of concrete drainage pavement and its construction, method for repairing and mending
CN207616844U (en) Foundation platform precast concrete side form and molding machine
CN203488189U (en) Tunnel structure for emptying renovation
CN106930777A (en) The construction method of the lining of Bored Section of Metro main track assembled two
CN110158389A (en) A kind of light soil road structure and its construction method
CN106149554A (en) A kind of prefabricated bridge expansion joint connecting elements, preparation method and construction method thereof
CN109236322A (en) It a kind of artificial bottom plate preventing soft-rock tunnel pucking and its constructs and method for maintaining
CN110344844A (en) A kind of track engineering section of track well construction method
CN202925561U (en) Bearing platform template structure
CN204782044U (en) Reinforced structure of existing structure roof beam
CN105822068B (en) Ultralong thin walled concrete walls under hot environment pour and maintenance process
CN204097889U (en) A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement
CN209066480U (en) A kind of precast hollow module block type concrete retaining wall
CN207265621U (en) A kind of power cable pipe trench structure
CN106939586B (en) A kind of panel construction of concrete face rockfill dam
CN109667434A (en) A kind of construction method of strap and straw board reinforcing raw-soil wall
CN113235646B (en) Construction method for crossing subway station on comprehensive pipe rack

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171229

CF01 Termination of patent right due to non-payment of annual fee