CN206706637U - A kind of mine road surface barrier clearing device - Google Patents
A kind of mine road surface barrier clearing device Download PDFInfo
- Publication number
- CN206706637U CN206706637U CN201720212680.2U CN201720212680U CN206706637U CN 206706637 U CN206706637 U CN 206706637U CN 201720212680 U CN201720212680 U CN 201720212680U CN 206706637 U CN206706637 U CN 206706637U
- Authority
- CN
- China
- Prior art keywords
- bottom plate
- forklift
- bolted connection
- slide rail
- motor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000004347 surface barrier Methods 0.000 title claims abstract description 19
- 229910000831 Steel Inorganic materials 0.000 claims description 14
- 239000010959 steel Substances 0.000 claims description 14
- 239000000463 material Substances 0.000 claims description 10
- 230000008878 coupling Effects 0.000 claims description 7
- 238000010168 coupling process Methods 0.000 claims description 7
- 238000005859 coupling reaction Methods 0.000 claims description 7
- 239000004575 stone Substances 0.000 abstract description 39
- 238000010586 diagram Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 238000010009 beating Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 229910052500 inorganic mineral Inorganic materials 0.000 description 2
- 239000011707 mineral Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 238000012827 research and development Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Landscapes
- Road Paving Machines (AREA)
Abstract
It the utility model is related to a kind of mine device, more particularly to a kind of mine road surface barrier clearing device.The technical problems to be solved in the utility model is to provide a kind of labor intensity that can be reduced and patrol recluse person, it is possible to increase handling efficiency, can keep mine road unimpeded mine road surface barrier clearing device.In order to solve the above-mentioned technical problem, the utility model provides such a mine road surface barrier clearing device, includes bottom plate etc.;The bottom of bottom plate is provided with the first roller, the left surface top of bottom plate is hingedly connected with swash plate by hinge member, the top right side of bottom plate is connected with support by bolted connection, the front side of support left surface is provided with hoist engine by bolted connection, drawstring is wound with hoist engine, the end of drawstring is connected with forklift.More stone disposably can be carried to roadside by the utility model by forklift, it is not necessary to patrolled a pair of the stones of recluse person 1 and carried, the labor intensity for patrolling recluse person can be reduced so as to reach.
Description
Technical field
It the utility model is related to a kind of mine device, more particularly to a kind of mine road surface barrier clearing device.
Background technology
Mineral resources be the earth's crust its it is long-term formed, development and the product in evolution process, be nature mineral matter one
Under fixed geological conditions, assemble formation through certain geologic process.Different geologic processes can form different types of ore deposit
Production.
Miner needs to be transported away ore deposit with transport vehicle after the ore deposit in mine is dug out, due to digging ore deposit, the geology knot in mine
Structure is destroyed, therefore stone can be usually tumbled on the road in mine, and in order to keep the unimpeded of road, patrolling recluse person needs road
Upper stone is removed to roadside, and recluse person is patrolled when road has more stone to be needed one by one to move stone, so patrols recluse person's
Labor intensity is big, and handling efficiency is low, and when stone is larger, patrolling recluse person is difficult to carry stone, so as to influence
Road it is unimpeded, therefore need research and development badly and a kind of can reduce the labor intensity for patrolling recluse person, it is possible to increase handling efficiency, can keep
Mine road unimpeded mine road surface barrier clearing device.
Utility model content
(1)Technical problems to be solved
The utility model in order to overcome patrol recluse person stone is moved one by one patrol recluse person labor intensity it is big, and carry effect
Rate is low, and when stone is larger, and patrolling recluse person is difficult to carry stone, so as to can influence road it is unimpeded the shortcomings that, this reality
It is to provide a kind of can reduce with new technical problems to be solved and patrols the labor intensity of recluse person, it is possible to increase handling efficiency,
Mine road unimpeded mine road surface barrier clearing device can be kept.
(2)Technical scheme
In order to solve the above-mentioned technical problem, the utility model provides such a mine road surface barrier clearing device, including
There are bottom plate, the first roller, swash plate, support, hoist engine, drawstring, forklift and the second roller, the bottom of bottom plate is provided with the first roller,
The left surface top of bottom plate is hingedly connected with swash plate by hinge member, and the top right side of bottom plate connects by bolted connection
Support is connected to, the front side of support left surface is provided with hoist engine, drawstring, drawstring are wound with hoist engine by bolted connection
End be connected with forklift, the bottom of forklift is provided with the second roller, be provided with the top of bottom plate with the second roller coordinate race.
Preferably, also include and move up and down device, move up and down device and include slide rail, sliding block, bearing block, the first electricity
Machine, screw mandrel, nut and push pedal, the top left side of bottom plate are provided with groove, at the top of the bottom plate in groove by bolted connection
Vertical to be connected with slide rail, slide rail is provided with the sliding block being slidably matched with it, and the right flank upper and lower part of slide rail passes through bolt
The mode of connection is provided with bearing block, and the right flank of slide rail is provided with the first motor, and the output shaft of the first motor is connected by shaft coupling
Screw mandrel is connected to, screw mandrel is connected by way of interference connection with the bearing of bearing block, and screw mandrel is provided with nut, the left side of nut
Face is connected with the right flank of sliding block by bolted connection, and the right flank of nut is connected with by bolted connection
Push pedal.
Preferably, fixing device is also included, the right flank of bottom plate is provided with fixing device, and fixing device includes fixed block
And inserted link, the left surface of fixed block are connected with bottom plate by bolted connection, guide hole is provided with fixed block, is set in guide hole
There is inserted link.
Preferably, the first motor is by bolted connection on the right flank of slide rail, and the first motor is positioned at upper
The top of side shaft holder, the first motor are servomotor.
Preferably, by bolted connection with being connected at the top of bottom plate, support is connected to bottom plate for the bottom of support
Top right side, the making material of support is Q235 steel.
Preferably, the front/rear end of forklift is triangle, and forklift making material is Q235 steel.
Operation principle:When initial, forklift is located on bottom plate.When the stone on road is carried into roadside, by swash plate
Laying makes swash plate be contacted with ground, then manually starts hoist engine and release drawstring, and forklift is moved to the left side of stone, and forklift moves
Move to during the left side of stone and close hoist engine, then restart hoist engine by drawstring withdraw forklift is moved right, forklift to
Moving right and stone is scooped up and stone is entered in forklift, drawstring pulls forklift to move right and is moved to through swash plate on bottom plate, when
Second roller closes hoist engine after entering race.Subsequently moving up swash plate resets swash plate, then moves the utility model
To roadside, then manually the stone in forklift is removed again.More stone can disposably be carried by repeating aforesaid operations
Head, it is not necessary to patrol recluse person and one by one carried stone, and can also carry larger stone.Therefore the utility model can
Reduce the labor intensity for patrolling recluse person, it is possible to increase handling efficiency, mine road can be kept unimpeded.
Because also including and moving up and down device, move up and down device include slide rail, sliding block, bearing block, the first motor,
Screw mandrel, nut and push pedal, the top left side of bottom plate are provided with groove, and the top of the bottom plate in groove is erected by bolted connection
Direct-connected to be connected to slide rail, slide rail is provided with the sliding block being slidably matched with it, and the right flank upper and lower part of slide rail is connected by bolt
The mode connect is provided with bearing block, and the right flank of slide rail is provided with the first motor, and the output shaft of the first motor is connected by shaft coupling
There is screw mandrel, screw mandrel is connected by way of interference connection with the bearing of bearing block, and screw mandrel is provided with nut, the left surface of nut
It is connected by bolted connection with the right flank of sliding block, the right flank of nut is connected with by bolted connection to be pushed away
Plate.Manually starting the first motor rotates clockwise screw mandrel, and screw mandrel, which rotates clockwise, to move up nut, and nut is upward
Mobile push pedal is moved up therewith, and push pedal is moved up to promote and moved up on the left of forklift, when being moved up on the left of forklift,
Manually the utility model is fixed.Forklift can so tilted to pour out the stone in forklift, it is not necessary to which patrolling recluse person will
Stone is removed, and so as to further reduce the labor intensity for patrolling recluse person, can further improve handling efficiency.Stone
After pouring out by the first motor close, then restarting the first motor rotates counterclockwise screw mandrel, moves down push pedal, push pedal to
The left side of lower mobile forklift moves down reset therewith, and forklift closes the first motor after resetting.
Because also including fixing device, the right flank of bottom plate is provided with fixing device, fixing device include fixed block and
Inserted link, the left surface of fixed block are connected with bottom plate by bolted connection, and guide hole is provided with fixed block, is provided with guide hole
Inserted link.Beating inserted link with hammer makes inserted link insert ground, can fix the utility model, improves stability, so need not
Patrol recluse person to fix the utility model, so can further reduce the labor intensity for patrolling recluse person.
Because for the first motor by bolted connection on the right flank of slide rail, the first motor is located at upper shaft
The top of bearing, the first motor are servomotor, and servomotor can more accurately control its rotating speed, make operation more steady.
Because by bolted connection with being connected at the top of bottom plate, support is connected to the top of bottom plate for the bottom of support
On the right side of portion, the making material of support is Q235 steel, and the ability to bear of Q235 steel is big, is capable of the service life of extending bracket.
Because the front/rear end of forklift is triangle, forklift making material is Q235 steel, and the front/rear end of forklift is triangle
Shape quickly can scoop up stone, and the ability to bear of Q235 steel is big, can extend the service life of forklift.
(3)Beneficial effect
More stone disposably can be carried to roadside by the utility model by forklift, it is not necessary to patrol recluse person one by one
Stone is carried, the labor intensity for patrolling recluse person can be reduced so as to reach, it is possible to increase handling efficiency, can keep
The unimpeded effect of mine road.
Brief description of the drawings
Fig. 1 is the first main structure diagram of the present utility model.
Fig. 2 is second of main structure diagram of the present utility model.
Fig. 3 is the third main structure diagram of the present utility model.
Mark in accompanying drawing for:1- bottom plates, the rollers of 2- first, 3- swash plates, 4- supports, 5- hoist engines, 6- drawstrings, 7- shovels
Car, the rollers of 8- second, 9- races, 10- move up and down device, 101- grooves, 102- slide rails, 103- sliding blocks, 104- bearing blocks,
The motors of 105- first, 106- screw mandrels, 107- nuts, 108- push pedals, 11- fixing devices, 111- fixed blocks, 112- guide holes, 113-
Inserted link.
Embodiment
The utility model is further described with reference to the accompanying drawings and examples.
Embodiment 1
A kind of mine road surface barrier clearing device, as Figure 1-3, include bottom plate 1, the first roller 2, swash plate 3, support 4,
Hoist engine 5, drawstring 6, the roller 8 of forklift 7 and second, the bottom of bottom plate 1 are provided with the first roller 2, and the left surface top of bottom plate 1 passes through
Hinge member is hingedly connected with swash plate 3, and the top right side of bottom plate 1 is connected with support 4 by bolted connection, and support 4 is left
The front side of side is provided with hoist engine 5 by bolted connection, and drawstring 6, the end connection of drawstring 6 are wound with hoist engine 5
There is forklift 7, the bottom of forklift 7 is provided with the second roller 8, and the top of bottom plate 1 is provided with the race 9 coordinated with the second roller 8.
Embodiment 2
A kind of mine road surface barrier clearing device, as Figure 1-3, include bottom plate 1, the first roller 2, swash plate 3, support 4,
Hoist engine 5, drawstring 6, the roller 8 of forklift 7 and second, the bottom of bottom plate 1 are provided with the first roller 2, and the left surface top of bottom plate 1 passes through
Hinge member is hingedly connected with swash plate 3, and the top right side of bottom plate 1 is connected with support 4 by bolted connection, and support 4 is left
The front side of side is provided with hoist engine 5 by bolted connection, and drawstring 6, the end connection of drawstring 6 are wound with hoist engine 5
There is forklift 7, the bottom of forklift 7 is provided with the second roller 8, and the top of bottom plate 1 is provided with the race 9 coordinated with the second roller 8.
Also include and move up and down device 10, move up and down device 10 include slide rail 102, sliding block 103, bearing block 104,
First motor 105, screw mandrel 106, nut 107 and push pedal 108, the top left side of bottom plate 1 are provided with groove 101, the bottom in groove 101
The top of plate 1 is connected with slide rail 102 vertically by bolted connection, and slide rail 102 is provided with the sliding block being slidably matched with it
103, the right flank upper and lower part of slide rail 102 is provided with bearing block 104, the right side of slide rail 102 by bolted connection
Side is provided with the first motor 105, and the output shaft of the first motor 105 is connected with screw mandrel 106 by shaft coupling, and screw mandrel 106 passed through
The mode of connection of being full of is connected with the bearing of bearing block 104, and screw mandrel 106 is provided with nut 107, and the left surface of nut 107 passes through
Bolted mode is connected with the right flank of sliding block 103, and the right flank of nut 107 is connected with by bolted connection
Push pedal 108.
Embodiment 3
A kind of mine road surface barrier clearing device, as Figure 1-3, include bottom plate 1, the first roller 2, swash plate 3, support 4,
Hoist engine 5, drawstring 6, the roller 8 of forklift 7 and second, the bottom of bottom plate 1 are provided with the first roller 2, and the left surface top of bottom plate 1 passes through
Hinge member is hingedly connected with swash plate 3, and the top right side of bottom plate 1 is connected with support 4 by bolted connection, and support 4 is left
The front side of side is provided with hoist engine 5 by bolted connection, and drawstring 6, the end connection of drawstring 6 are wound with hoist engine 5
There is forklift 7, the bottom of forklift 7 is provided with the second roller 8, and the top of bottom plate 1 is provided with the race 9 coordinated with the second roller 8.
Also include and move up and down device 10, move up and down device 10 include slide rail 102, sliding block 103, bearing block 104,
First motor 105, screw mandrel 106, nut 107 and push pedal 108, the top left side of bottom plate 1 are provided with groove 101, the bottom in groove 101
The top of plate 1 is connected with slide rail 102 vertically by bolted connection, and slide rail 102 is provided with the sliding block being slidably matched with it
103, the right flank upper and lower part of slide rail 102 is provided with bearing block 104, the right side of slide rail 102 by bolted connection
Side is provided with the first motor 105, and the output shaft of the first motor 105 is connected with screw mandrel 106 by shaft coupling, and screw mandrel 106 passed through
The mode of connection of being full of is connected with the bearing of bearing block 104, and screw mandrel 106 is provided with nut 107, and the left surface of nut 107 passes through
Bolted mode is connected with the right flank of sliding block 103, and the right flank of nut 107 is connected with by bolted connection
Push pedal 108.
Also include fixing device 11, the right flank of bottom plate 1 is provided with fixing device 11, and fixing device 11 includes fixed block
111 and inserted link 113, the left surface of fixed block 111 be connected by bolted connection with bottom plate 1, be provided with fixed block 111
Guide hole 112, guide hole 112 is interior to be provided with inserted link 113.
Embodiment 4
A kind of mine road surface barrier clearing device, as Figure 1-3, include bottom plate 1, the first roller 2, swash plate 3, support 4,
Hoist engine 5, drawstring 6, the roller 8 of forklift 7 and second, the bottom of bottom plate 1 are provided with the first roller 2, and the left surface top of bottom plate 1 passes through
Hinge member is hingedly connected with swash plate 3, and the top right side of bottom plate 1 is connected with support 4 by bolted connection, and support 4 is left
The front side of side is provided with hoist engine 5 by bolted connection, and drawstring 6, the end connection of drawstring 6 are wound with hoist engine 5
There is forklift 7, the bottom of forklift 7 is provided with the second roller 8, and the top of bottom plate 1 is provided with the race 9 coordinated with the second roller 8.
Also include and move up and down device 10, move up and down device 10 include slide rail 102, sliding block 103, bearing block 104,
First motor 105, screw mandrel 106, nut 107 and push pedal 108, the top left side of bottom plate 1 are provided with groove 101, the bottom in groove 101
The top of plate 1 is connected with slide rail 102 vertically by bolted connection, and slide rail 102 is provided with the sliding block being slidably matched with it
103, the right flank upper and lower part of slide rail 102 is provided with bearing block 104, the right side of slide rail 102 by bolted connection
Side is provided with the first motor 105, and the output shaft of the first motor 105 is connected with screw mandrel 106 by shaft coupling, and screw mandrel 106 passed through
The mode of connection of being full of is connected with the bearing of bearing block 104, and screw mandrel 106 is provided with nut 107, and the left surface of nut 107 passes through
Bolted mode is connected with the right flank of sliding block 103, and the right flank of nut 107 is connected with by bolted connection
Push pedal 108.
Also include fixing device 11, the right flank of bottom plate 1 is provided with fixing device 11, and fixing device 11 includes fixed block
111 and inserted link 113, the left surface of fixed block 111 be connected by bolted connection with bottom plate 1, be provided with fixed block 111
Guide hole 112, guide hole 112 is interior to be provided with inserted link 113.
By bolted connection on the right flank of slide rail 102, the first motor 105 is located at first motor 105
The top of upper shaft bearing 104, the first motor 105 are servomotor.
Top of the bottom of support 4 by bolted connection with bottom plate 1 is connected, and support 4 is connected to the top of bottom plate 1
On the right side of portion, the making material of support 4 is Q235 steel.
The front/rear end of forklift 7 is triangle, and the making material of forklift 7 is Q235 steel.
Operation principle:When initial, forklift 7 is located on bottom plate 1., will be oblique when the stone on road is carried into roadside
Plate 3, which is laid, makes swash plate 3 be contacted with ground, then manually starts hoist engine 5 and release drawstring 6, and forklift 7 is moved to a left side for stone
Side, closes hoist engine 5 when forklift 7 is moved to the left side of stone, then restart hoist engine 5 by drawstring 6 withdraw make forklift 7 to
Move right, forklift 7, which moves right, to be scooped up stone and stone is entered in forklift 7, and drawstring 6 pulls forklift 7 to move right through oblique
Plate 3 is moved on bottom plate 1, is closed hoist engine 5 after the second roller 8 enters race 9.Subsequently moving up swash plate 3 makes swash plate 3
Reset, the utility model is then moved into roadside, then again manually removed the stone in forklift 7.Repeat aforesaid operations
More stone can disposably be carried, it is not necessary to patrol recluse person and one by one carried stone, and can also carry larger
Stone.Therefore the utility model can reduce the labor intensity for patrolling recluse person, it is possible to increase handling efficiency, can keep mine
The coast is clear.
Device 10 is moved up and down because also including, device 10 is moved up and down and includes slide rail 102, sliding block 103, bearing block
104th, the first motor 105, screw mandrel 106, nut 107 and push pedal 108, the top left side of bottom plate 1 are provided with groove 101, in groove 101
The top of bottom plate 1 be connected with slide rail 102 vertically by bolted connection, slide rail 102 is provided with to be slidably matched with it
Sliding block 103, the right flank upper and lower part of slide rail 102 are provided with bearing block 104, slide rail 102 by bolted connection
Right flank be provided with the first motor 105, the output shaft of the first motor 105 is connected with screw mandrel 106 by shaft coupling, and screw mandrel 106 is logical
The mode of interference connection is connected with the bearing of bearing block 104, and screw mandrel 106 is provided with nut 107, the left surface of nut 107
The right flank with sliding block 103 is connected by bolted connection, and the right flank of nut 107 connects by bolted connection
It is connected to push pedal 108.Manually starting the first motor 105 rotates clockwise screw mandrel 106, and screw mandrel 106, which rotates clockwise, can make spiral shell
Mother 107 moves up, and nut 107 moves up push pedal 108 and moved up therewith, and push pedal 108 moves up the left side for promoting forklift 7
It is laterally moved, when the left side of forklift 7 moves up, manually the utility model is fixed.Forklift 7 can so tilted will
Stone in forklift 7 is poured out, it is not necessary to is patrolled recluse person and is removed stone, so as to further reduce the work for patrolling recluse person
Intensity, it can further improve handling efficiency.Stone closes the first motor 105 after pouring out, and then restarts the first motor
105 rotate counterclockwise screw mandrel 106, move down push pedal 108, and push pedal 108 moves down the left side of forklift 7 therewith to moving down
Dynamic to reset, forklift 7 closes the first motor 105 after resetting.
Because also including fixing device 11, the right flank of bottom plate 1 is provided with fixing device 11, and fixing device 11 includes solid
Determine block 111 and inserted link 113, the left surface of fixed block 111 is connected with bottom plate 1 by bolted connection, on fixed block 111
Guide hole 112 is provided with, inserted link 113 is provided with guide hole 112.Beating inserted link 113 with hammer makes inserted link 113 insert ground, can be by this
Utility model is fixed, and is improved stability, need not so be patrolled recluse person and fix the utility model, so can be further
Reduce the labor intensity for patrolling recluse person.
Because the first motor 105 is arranged on the right flank of slide rail 102 by bolted connection, the first motor 105
Positioned at the top of upper shaft bearing 104, the first motor 105 is servomotor, and servomotor can more accurately control its rotating speed,
Make operation more steady.
Because top of the bottom of support 4 by bolted connection with bottom plate 1 is connected, support 4 is connected to bottom plate 1
Top right side, the making material of support 4 is Q235 steel, and the ability to bear of Q235 steel is big, be capable of extending bracket 4 use year
Limit.
Because the front/rear end of forklift 7 is triangle, the making material of forklift 7 is Q235 steel, and the front/rear end of forklift 7 is three
Angular quickly to scoop up stone, the ability to bear of Q235 steel is big, can extend the service life of forklift 7.
Embodiment described above only expresses preferred embodiment of the present utility model, and its description is more specific and detailed,
But therefore it can not be interpreted as the limitation to the utility model patent scope.It should be pointed out that for the common of this area
For technical staff, without departing from the inventive concept of the premise, some deformations can also be made, improves and substitutes, these are all
Belong to the scope of protection of the utility model.Therefore, the protection domain of the utility model patent should be determined by the appended claims.
Claims (6)
1. a kind of mine road surface barrier clearing device, it is characterised in that include bottom plate(1), the first roller(2), swash plate(3), branch
Frame(4), hoist engine(5), drawstring(6), forklift(7)With the second roller(8), bottom plate(1)Bottom be provided with the first roller(2), bottom
Plate(1)Left surface top swash plate is hingedly connected with by hinge member(3), bottom plate(1)Top right side be bolted
Mode be connected with support(4), support(4)The front side of left surface is provided with hoist engine by bolted connection(5), elevator
Machine(5)On be wound with drawstring(6), drawstring(6)End be connected with forklift(7), forklift(7)Bottom be provided with the second roller(8), bottom
Plate(1)Top be provided with and the second roller(8)The race of cooperation(9).
2. a kind of mine road surface barrier clearing device according to claim 1, it is characterised in that also include and move up and down dress
Put(10), move up and down device(10)Include slide rail(102), sliding block(103), bearing block(104), the first motor(105), silk
Bar(106), nut(107)And push pedal(108), bottom plate(1)Top left side be provided with groove(101), groove(101)Interior bottom plate
(1)Top is connected with slide rail vertically by bolted connection(102), slide rail(102)It is provided with the cunning being slidably matched with it
Block(103), slide rail(102)Right flank upper and lower part bearing block is installed by bolted connection(104), slide rail
(102)Right flank be provided with the first motor(105), the first motor(105)Output shaft screw mandrel is connected with by shaft coupling
(106), screw mandrel(106)Interference connection by way of and bearing block(104)Bearing be connected, screw mandrel(106)It is provided with spiral shell
It is female(107), nut(107)Left surface by bolted connection with sliding block(103)Right flank be connected, nut
(107)Right flank be connected with push pedal by bolted connection(108).
3. a kind of mine road surface barrier clearing device according to claim 2, it is characterised in that also include fixing device
(11), bottom plate(1)Right flank be provided with fixing device(11), fixing device(11)Include fixed block(111)And inserted link
(113), fixed block(111)Left surface by bolted connection with bottom plate(1)It is connected, fixed block(111)On be provided with
Guide hole(112), guide hole(112)It is interior to be provided with inserted link(113).
A kind of 4. mine road surface barrier clearing device according to claim 3, it is characterised in that the first motor(105)Pass through
Bolted mode is arranged on slide rail(102)Right flank on, the first motor(105)Positioned at upper shaft bearing(104)It is upper
Side, the first motor(105)For servomotor.
A kind of 5. mine road surface barrier clearing device according to claim 4, it is characterised in that support(4)Bottom pass through
Bolted mode and bottom plate(1)Top be connected, support(4)It is connected to bottom plate(1)Top right side, support(4)'s
Making material is Q235 steel.
A kind of 6. mine road surface barrier clearing device according to claim 5, it is characterised in that forklift(7)Front/rear end
For triangle, forklift(7)Making material is Q235 steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720212680.2U CN206706637U (en) | 2017-03-07 | 2017-03-07 | A kind of mine road surface barrier clearing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720212680.2U CN206706637U (en) | 2017-03-07 | 2017-03-07 | A kind of mine road surface barrier clearing device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206706637U true CN206706637U (en) | 2017-12-05 |
Family
ID=60470329
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720212680.2U Active CN206706637U (en) | 2017-03-07 | 2017-03-07 | A kind of mine road surface barrier clearing device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206706637U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108560458A (en) * | 2018-01-06 | 2018-09-21 | 南昌首诺科技有限公司 | A kind of geological disaster mud-rock flow soil cleaning plant |
CN108867297A (en) * | 2018-07-12 | 2018-11-23 | 姚焕根 | A kind of construction is banketed equipment |
-
2017
- 2017-03-07 CN CN201720212680.2U patent/CN206706637U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108560458A (en) * | 2018-01-06 | 2018-09-21 | 南昌首诺科技有限公司 | A kind of geological disaster mud-rock flow soil cleaning plant |
CN108867297A (en) * | 2018-07-12 | 2018-11-23 | 姚焕根 | A kind of construction is banketed equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102996131A (en) | Solid-filling coal mining method with two pre-excavating tunnels for advancing | |
CN102535559A (en) | Chain cutter type mixing pile wall forming equipment | |
CN206706637U (en) | A kind of mine road surface barrier clearing device | |
CN103032071A (en) | Shield receiving forward-shift construction method of boulder group open excavation and embedment mutation space | |
CN102587933A (en) | Gob-side entry retaining method using prefabricated walls | |
CN202391424U (en) | Supporting type comprehensive bolter miner | |
CN106761758A (en) | Artificial concrete guard wall reconstruct studding waste fill mining methods | |
CN202595730U (en) | Chain cutter type mixing pile wall forming equipment | |
CN104533408A (en) | Large-width comprehensive coal road driving anchor machine with simultaneous drifting function | |
CN203530886U (en) | Multifunctional full-hydraulic self-propelled piling pile-pulling drilling all-in-one machine for road anti-collision guardrail | |
CN203499559U (en) | Conveniently moved hydraulic anchoring drill for roadway | |
CN204386597U (en) | The coal road comprehensive dig-anchor machine of large width simultaneous drifting | |
CN103981856A (en) | Construction method and excavating-cutting machine for seamlessly connecting underground diaphragm walls | |
CN103862257B (en) | A kind of reamer disassembly robot device and its function mode | |
WO2019109535A1 (en) | Clean and efficient coal mining method | |
CN210194392U (en) | Road leveling device is used in municipal works construction | |
CN209162801U (en) | Continuously hang down film wall building machine for a kind of underground | |
CN107338802A (en) | A kind of beach cofferdam construction device and construction method | |
CN101509265B (en) | Pull-type soil shifter smoothing technique for soft foundation field and pull-type soil shifter | |
Song et al. | Adaptability study of EPB shield machine in clay stratum in Xuzhou | |
CN206486780U (en) | Electromagnetic type steel plate lays car | |
CN209040780U (en) | A kind of environmental-friendly circulation device of hardened place prospecting | |
CN203214072U (en) | Extruded concrete lining device for construction of full face tunnel boring machine | |
CN202990854U (en) | Oil hydraulic system for crawler-type full-hydraulic underground drill rig | |
CN206121822U (en) | Pressure -resisting pipe stake waste material processor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180928 Address after: 836703 Sarkozy, Habahe, Aletai, the Xinjiang Uygur Autonomous Region Patentee after: Xinjiang Xin Wang mining Limited by Share Ltd Address before: 362000 No. 100 Piedmont, new residence community, Quangang District, Quanzhou, Fujian Patentee before: Zeng Chengzhu |