CN206368308U - Pre-stress type levelling prefabrication and assembly construction concrete - Google Patents

Pre-stress type levelling prefabrication and assembly construction concrete Download PDF

Info

Publication number
CN206368308U
CN206368308U CN201720009418.8U CN201720009418U CN206368308U CN 206368308 U CN206368308 U CN 206368308U CN 201720009418 U CN201720009418 U CN 201720009418U CN 206368308 U CN206368308 U CN 206368308U
Authority
CN
China
Prior art keywords
tensioning
precast slab
reserving hole
hole channel
prefabrication
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720009418.8U
Other languages
Chinese (zh)
Inventor
罗海君
张立兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Broad Highway Transportation Technology Co Ltd
Original Assignee
Beijing Broad Highway Transportation Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Broad Highway Transportation Technology Co Ltd filed Critical Beijing Broad Highway Transportation Technology Co Ltd
Priority to CN201720009418.8U priority Critical patent/CN206368308U/en
Application granted granted Critical
Publication of CN206368308U publication Critical patent/CN206368308U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model provides a kind of pre-stress type levelling prefabrication and assembly construction concrete, the square precast slab of the polylith that is fixed together including level connection joint, four corners of the precast slab are respectively fixed with installation suspension ring, four corners of the precast slab further respectively have vertical grouting duct, the bottom in the grouting duct is provided with leveling knob, two horizontal tensioning reserving hole channels are provided with the precast slab, the grouting duct and tensioning reserving hole channel run through precast slab, presstressed reinforcing steel is installed with the tensioning reserving hole channel, the middle part of the precast slab is provided with working space of two square grooves as two presstressed reinforcing steels of connection, the tensioning reserving hole channel is each passed through square groove.The pre-stress type levelling prefabrication and assembly construction concrete that the utility model is provided is rational in infrastructure, it is easy to ensures structure flatness, improve structural integrity.

Description

Pre-stress type levelling prefabrication and assembly construction concrete
Technical field
The present invention relates to highway engineering technology and airport pavement engineering technology, and in particular to a kind of pre-stress type levelling is pre- System assembling concrete.
Background technology
If at present the country cement concrete road base based on cast in situs, site operation can produce substantial amounts of waste water, Waste gas, waste residue, the construction operation time are long, and construction machinery volume of traffic is big, and personnel specialty degree is low, when needing long after cast in situs Between the unfavorable factor such as maintenance.Due to economic fast development, it is necessary to expressway construction faster, it is firmer, more environmentally friendly.
In recent years, prefabricated construction is widely used in building industry, promotes the more green ring of development of building trade Protect, construction quality is got better protection, and substantially reduce the construction period.In transportation industry, prefabricated assembled road Face is, in precasting yard concentration pre-casting concrete flag, intensity then to be reached into the concrete prefabricated board of design requirement is transported and applied Work scene, the cement concrete pavement being assembled to form.
But, common prefabricated assembled road surface has that surface evenness is poor, road deck function of surface hole is more, influence The defects such as road surface globality.
The content of the invention
For the drawbacks described above and problem of prior art, the present invention provides one kind and is easy to ensure structure flatness, improves knot The pre-stress type levelling prefabrication and assembly construction concrete of structure globality.
In order to achieve the above object, the present invention provides following technical scheme:
Pre-stress type levelling prefabrication and assembly construction concrete, including the polylith that level connection joint is fixed together are square Precast slab, four corners of the precast slab are respectively fixed with installation suspension ring, the precast slab Four corners further respectively have vertical grouting duct, and the bottom in the grouting duct is provided with leveling knob, the concrete Two horizontal tensioning reserving hole channels are provided with native plate, the grouting duct and tensioning reserving hole channel run through precast slab, Presstressed reinforcing steel is installed with the tensioning reserving hole channel, the middle part of the precast slab is used as connection provided with two square grooves The working space of two presstressed reinforcing steels, the tensioning reserving hole channel is each passed through square groove.
In above-mentioned technical proposal, the precast slab be cuboid, the tensioning reserving hole channel it is parallel to each other and Consistent with the length direction of precast slab, the grouting duct is located at the outside of tensioning reserving hole channel and the two hangs down mutually Directly.
In above-mentioned technical proposal, the leveling knob is cylindrical shape, includes what is be welded and fixed together successively from top to bottom Top steel pipe, middle part steel pipe and bottom steel pipe, the top steel pipe and grouting hole link, the central spiral shell dress of the bottom steel pipe There is vertical leveling bolt, the bottom of the leveling bolt is fixed with the circular gasket of a level, a left side for the bottom steel pipe Right two ends are also provided with grouting material tap hole.
In above-mentioned technical proposal, the depth of the square groove is more than the half of precast concrete plate thickness, the tensioning The distance of reserving hole channel to top surface is the half of precast concrete plate thickness, and the tensioning reserving hole channel to the distance of side is pre- / 3rd of concrete slab width processed.
The pre-stress type levelling prefabrication and assembly construction concrete that the present invention is provided is easy to ensure structure flatness, improved Structural integrity.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, without having to pay creative labor, may be used also To obtain other accompanying drawings according to these accompanying drawings.
Fig. 1 is structural representation of the invention;
Fig. 2 is the structural representation of leveling knob.
Wherein:1st, precast slab;2nd, square groove;3rd, tensioning reserving hole channel;4th, grouting duct;21st, top steel pipe; 22nd, middle part steel pipe;23rd, leveling bolt;24th, bottom steel pipe;25th, grouting material tap hole;26th, circular gasket.
Embodiment
Below in conjunction with the accompanying drawing of the present invention, technical scheme is clearly and completely described, it is clear that institute The embodiment of description is only a part of embodiment of the invention, rather than whole embodiments.Based on the embodiment in the present invention, The every other embodiment that those of ordinary skill in the art are obtained under the premise of creative work is not made, belongs to this hair The scope of bright protection.
According to Fig. 1, the pre-stress type levelling prefabrication and assembly construction concrete shown in embodiment, including water are used as The square precast slab of polylith that flushconnection is fixed together, four corners of precast slab are respectively fixed with installation Suspension ring, four corners of precast slab further respectively have vertical grouting duct, and the bottom in duct of being in the milk is revolved provided with leveling Two horizontal tensioning reserving hole channels are provided with button, precast slab, grouting duct and tensioning reserving hole channel are through prefabricated mixed Presstressed reinforcing steel is installed with concrete board, tensioning reserving hole channel, the middle part of precast slab is used as connection provided with two square grooves The working space of two presstressed reinforcing steels, tensioning reserving hole channel is each passed through square groove.The depth of square groove is more than prefabricated mixed The half of concrete board thickness, size meets prestressed stretch-draw anchorage operation, can realize that a upper tensioned unit is pre- by the space The presstressed reinforcing steel insertion of the unilateral stretch-draw anchor and next precast slab of stress rib.Distance of the tensioning reserving hole channel to top surface For the half of precast concrete plate thickness, the distance of tensioning reserving hole channel to side for precast slab width three/ One.
In present embodiment, precast slab is cuboid, and tensioning reserving hole channel is parallel to each other and and concrete The length direction of native plate is consistent, and grouting duct is located at the outside of tensioning reserving hole channel and the two is orthogonal.
As shown in Fig. 2 in present embodiment, leveling knob is cylindrical shape, include being weldingly fixed on one from top to bottom successively Top steel pipe, middle part steel pipe and the bottom steel pipe risen, top steel pipe is screwed with perpendicular with grouting hole link, the center of bottom steel pipe Straight leveling bolt, the bottom of leveling bolt is fixed with the circular gasket of a level, and the left and right ends of bottom steel pipe are also provided with Grouting material tap hole.
Construction procedure:
101:Described concrete prefabricated board lifting is placed to the specified stowed location of job site, it is ensured that change the road of position Face is smooth, solid.
102:Described concrete prefabricated board is lifted in construction area, is molded by Pavement Design position is once assembled, Keep plate body contact consolidation.
103:By 4 leveling knobs in Fig. 1, leveling bolt therein is rotated, makes entire plate holding level, and it is all Plate body keeps level.
104:Ready presstressed reinforcing steel is imported by reserved duct, each block of precast assembly plate is passed sequentially through, Tensioning and anchoring are completed in reserved tensioning working space.Then the presstressed reinforcing steel used in next tensioned unit is imported, repeated This process, until all plate bodys complete tensioning operation.
105:Slip casting is carried out by leveling knob integration component and prestressed stretch-draw duct, it is ensured that slip casting is abundant.Treat slurry Reach the assembled work that whole road surface is completed after prescribed strength.
The present invention provides a kind of pre-stress type levelling prefabrication and assembly construction concrete, and multiple precast slabs pass through The working space of prestressed stretch-draw duct and square groove formed after tensioning the overall structure layer of bearing load.By pre- Leveling knob is set in concrete slab processed, in assembling, leveling can be carried out to precast slab using the device, so as to protect The structure sheaf of barrier assembling has good flatness.
The foregoing is only a specific embodiment of the invention, but protection scope of the present invention is not limited thereto, any Those familiar with the art the invention discloses technical scope in, change or replacement can be readily occurred in, should all be contained Cover within protection scope of the present invention.Therefore, protection scope of the present invention described should be defined by scope of the claims.

Claims (4)

1. pre-stress type levelling prefabrication and assembly construction concrete, it is characterised in that:It is fixed together including level connection joint The square precast slab of polylith, four corners of the precast slab are respectively fixed with installation suspension ring, described prefabricated Four corners of concrete slab further respectively have vertical grouting duct, and the bottom in the grouting duct is provided with leveling knob, institute State and two horizontal tensioning reserving hole channels are provided with precast slab, the grouting duct and tensioning reserving hole channel are through prefabricated Presstressed reinforcing steel is installed with concrete slab, the tensioning reserving hole channel, the middle part of the precast slab is square recessed provided with two Groove is each passed through square groove as the working space for connecting two presstressed reinforcing steels, the tensioning reserving hole channel.
2. pre-stress type levelling prefabrication and assembly construction concrete according to claim 1, it is characterised in that:It is described pre- Concrete slab processed is cuboid, and the tensioning reserving hole channel is parallel to each other and length direction of with precast slab is consistent, The grouting duct is located at the outside of tensioning reserving hole channel and the two is orthogonal.
3. pre-stress type levelling prefabrication and assembly construction concrete according to claim 1, it is characterised in that:It is described to adjust Flat knob is cylindrical shape, includes top steel pipe, middle part steel pipe and the bottom steel pipe being welded and fixed together, institute successively from top to bottom Top steel pipe and grouting hole link are stated, the center of the bottom steel pipe is screwed with vertical leveling bolt, the leveling bolt Bottom be fixed with the circular gasket of a level, the left and right ends of the bottom steel pipe are also provided with grouting material tap hole.
4. pre-stress type levelling prefabrication and assembly construction concrete according to claim 1, it is characterised in that:The side The depth of connected in star is more than the half of precast concrete plate thickness, and the distance of the tensioning reserving hole channel to top surface is concrete The half of native plate thickness, the distance of the tensioning reserving hole channel to side is 1/3rd of precast slab width.
CN201720009418.8U 2017-01-05 2017-01-05 Pre-stress type levelling prefabrication and assembly construction concrete Active CN206368308U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720009418.8U CN206368308U (en) 2017-01-05 2017-01-05 Pre-stress type levelling prefabrication and assembly construction concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720009418.8U CN206368308U (en) 2017-01-05 2017-01-05 Pre-stress type levelling prefabrication and assembly construction concrete

Publications (1)

Publication Number Publication Date
CN206368308U true CN206368308U (en) 2017-08-01

Family

ID=59390940

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720009418.8U Active CN206368308U (en) 2017-01-05 2017-01-05 Pre-stress type levelling prefabrication and assembly construction concrete

Country Status (1)

Country Link
CN (1) CN206368308U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108547197A (en) * 2018-04-08 2018-09-18 浙江中用市政园林设计股份有限公司 A kind of prepackage type cement road structure facilitating draining
CN110004791A (en) * 2019-04-19 2019-07-12 河北建设集团股份有限公司 A kind of prestressing without bondn assembled road and its construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108547197A (en) * 2018-04-08 2018-09-18 浙江中用市政园林设计股份有限公司 A kind of prepackage type cement road structure facilitating draining
CN110004791A (en) * 2019-04-19 2019-07-12 河北建设集团股份有限公司 A kind of prestressing without bondn assembled road and its construction method

Similar Documents

Publication Publication Date Title
CN102383418B (en) Anti-seismic prefabricated concrete solid square pile and production method thereof
US20210348354A1 (en) Method for sealing post-cast strip in foundation with no gap
CN206667459U (en) A kind of pre-splicing Standard formula building of prefabrication type reinforced concrete shear wall
CN108360712A (en) A kind of assembled steel reinforced concrete shear force wall and its construction method
CN213205219U (en) Full prefabricated wall
CN107090908B (en) A kind of vertical prefabricated components joint connecting method
CN106545030B (en) Small-sized buried reservoir of one kind and preparation method thereof
CN201567584U (en) Prefabricated construction reinforced concrete cushion cap foundation
CN206368308U (en) Pre-stress type levelling prefabrication and assembly construction concrete
CN108277714A (en) Pre-stress type levelling prefabrication and assembly construction concrete
CN205529742U (en) Prefabricated assembly concrete structure inter -layer
CN110552706A (en) Permanent-temporary combined shield hoisting hole sealing structure and method
CN208168479U (en) A kind of prefabricated rod structure in inspection hole
CN206368306U (en) A kind of dismountable composite structure layer
CN202401667U (en) Prefabricated column with reserved embedded column porous channel and embedded column type full-assembly anti-seismic building
CN211900603U (en) Face combination shield structure hole of hoist enclosed construction forever
CN205529743U (en) Prefabricated assembly concrete structure inter -layer of sleeper beam formula
CN110306398B (en) Sectional beam-setting pretensioning staggered symmetrical tensioning prestressed tendon superposed assembly road and construction method thereof
CN114622482A (en) Layered corrugated pipe connection prefabricated assembly bent cap structure, construction method and design method
CN209759116U (en) Filter plate for denitrification filter tank
CN205663095U (en) Precast concrete composite floor
CN105755920A (en) Prefabricated concrete structure layer and assembling method thereof
CN111705987A (en) Large-span prefabricated ribbed prestressed hollow bidirectional laminated slab
CN206359993U (en) Stud structure for main transformer fire wall
CN204000958U (en) A kind of novel ater-casting place braced structures

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant