CN206319314U - A kind of additional cuff back-up sand building stones prefabricated pile - Google Patents

A kind of additional cuff back-up sand building stones prefabricated pile Download PDF

Info

Publication number
CN206319314U
CN206319314U CN201621319100.1U CN201621319100U CN206319314U CN 206319314 U CN206319314 U CN 206319314U CN 201621319100 U CN201621319100 U CN 201621319100U CN 206319314 U CN206319314 U CN 206319314U
Authority
CN
China
Prior art keywords
pile
cuff
expanding
prefabricated
pile body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621319100.1U
Other languages
Chinese (zh)
Inventor
王奎华
吴君涛
高柳
肖偲
李振亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University ZJU
Original Assignee
Zhejiang University ZJU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University ZJU filed Critical Zhejiang University ZJU
Priority to CN201621319100.1U priority Critical patent/CN206319314U/en
Application granted granted Critical
Publication of CN206319314U publication Critical patent/CN206319314U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model discloses a kind of additional cuff back-up sand building stones prefabricated pile.After prefabricated pile pile, pile top is expanded by the additional expanding cuff of pile body and stake bottom and is connected with pile body, the expanding pile body in nodular interval is formed.While the prefabricated pile of jacketed hoop is pressed into or squeezes into foundation soil outside, filled out to stake week and send sand material, ultimately formed by additional cuff prefabricated pile, all sandstone fillers of stake, the coefficient composite foundation of foundation soil.Under the method, stake week sandstone filler formation drainage channel, soil solidifying process accelerates, and settlement after construction is controlled after the completion of construction;The bigger soil body internal friction angle of sand material provides the bigger pile side friction of pile foundation, can improve bearing capacity of pile foundation;Additional cuff includes the expanding cuff of pile body and stake end expands pile top making apparatus simply, without independent custom mold, at the same it is adjustable in pile body fixed position, a variety of designs and operating mode are can adapt to, with good engineering adaptability;Being spaced expanding pile body can be provided more than external diameter and the prefabricated pile bearing capacity of extension diameter section identical, while manufacturing cost can be saved, with good economic benefit.

Description

A kind of additional cuff back-up sand building stones prefabricated pile
Technical field
The utility model belongs to construction method field, and in particular to a kind of additional cuff back-up sand building stones prefabricated pile.
Background technology
Pile foundation engineering is as an important step in engineering construction, and quality and economic benefit to whole engineering are suffered from Very important influence.In pile foundation engineering, prefabricated pile has speed of application fast, and single pile bearing capacity is high, and pile quality has guarantor Card, the advantages of economic benefit is excellent obtains relatively broad application in Practical Project.
But there is also some problems in Practical Project work progress for prefabricated pile.For soft soil foundation, particularly satisfy And Soft Clay Foundation, because the drain bar depth for lacking vertical drainage mechanism or setting is long far away from stake, prefabricated pile and stake week Relative settlement is excessive after geotechnique, can cause pile-side negative friction.Pile-side negative friction can cause the change of pile foundation single pile bearing capacity Change and the differential settlement of superstructure, influence can be produced when serious on the resistance to overturning of superstructure.So, prefabricated In the design and work progress of stake need that the settlement after construction of pile foundation is analyzed and controlled.
Utility model content
The purpose of this utility model is to solve in the prior art because foundation soil consolidation slowly causes difference after pile foundation work The problem of sedimentation, and a kind of additional cuff back-up sand building stones prefabricated pile is provided.
In view of having differences sedimentation after soft clay area prefabricated pile and soil around pile work, pile body side friction caused by its result Increase may produce serious consequence, it is necessary to account for the rapidly solidified of soil around pile to reduce after its work to superstructure Sedimentation.And the technical scheme that the utility model solves concrete technical problems use is:
Additional cuff back-up sand building stones prefabricated pile, including prefabricated pile pile body, expanding cuff and stake bottom expand pile top;Described expansion Footpath cuff is in hollow annular, and its external diameter is more than pile body external diameter;Spacer sleeve is provided with several expanding cuff formation nodular stakes on pile body; Described stake bottom expansion pile top is fixed on pile body bottom and maximum outside diameter is not less than the expanding cuff external diameter of pile body;Described prefabricated pile Sand material is filled with the certain limit of pile body periphery, the minimum diameter of the sandstone bed of material is not less than expanding cuff external diameter.
Preferably, the shape of hollow section matches with pile body cross section on the inside of described expanding cuff, make expanding set Hoop laminating is fixed on pile body, is provided with interstitial channels between expanding cuff and prefabricated pile pile body, is used as vertical drainage passage.
Preferably, described expanding cuff is detachably secured on prefabricated pile pile body by fixture.
Preferably, described expanding cuff can be adjusted up and down in the fixed position of pile body.
Preferably, it is in filling type or hoop type that described stake bottom, which expands pile top with the junction of prefabricated pile pile body,.
The beneficial effects of the utility model are as follows:
1. the outside spacers of prefabricated pile pile body secure the expanding cuff of multiple levels, meanwhile, also it is surround on the outside of its pile body One layer of sandstone bed of material with hole with diameter greater than expanding cuff, forms a passage that can be used in draining, drives piles Or the super quiet pore water produced during piling can be able to comparatively fast dissipate by the passage, soil solidifying process accelerates, construction After the completion of settlement after construction be effectively controlled.
2. sand material compares the bigger soil body internal friction angle of foundation soil there is provided the bigger pile side friction of pile foundation, Ke Yiti High bearing capacity of pile foundation;Meanwhile, stake bottom expands pile top and is conducive to being formed one during piling or piling with diameter greater than expanding set The passage of external diameter is bound round, for filling sand material.And pile body enters behind underground layer relevant position, end resistance can also be improved.
3. additional cuff includes the expanding cuff of pile body and stake end expands pile top making apparatus simply, without independent custom mold Tool, while it is adjustable in pile body fixed position, can adapt to a variety of designs and operating mode, with good engineering adaptability;
4. shield bucket and cuff mould can be recycled, with certain economic benefit;
Clearly 5. its bearing capacity of pile body interval hole-enlargement pile of the present utility model is more than external diameter and extension diameter section to result of the test Identical prefabricated pile.It can be seen that it is expanding by pile body interval, manufacture can be reduced on the premise of bearing capacity and security is not lost Cost, with good economic benefit;
Brief description of the drawings
Fig. 1 is a kind of additional cuff prefabricated pile back-up sand stone construction method sectional schematic diagram of the present utility model.
Fig. 2 is that the additional cuff shown in Fig. 1 is connected top view with prefabricated pile pile body.
Fig. 3 is another additional cuff prefabricated pile back-up sand stone construction method sectional schematic diagram of the present utility model.
Fig. 4 is that the additional cuff shown in Fig. 3 is connected top view with prefabricated pile pile body.
In figure:Prefabricated tubular pile pile body 1, precast square pile pile body 2, expanding cuff 3, drainage channel 4, stake bottom expand pile top (plug Enter formula) 5, stake bottom expand pile top (hoop type) 6, shield bucket 7, sandstone filler 8, pending foundation soil 9, bolt connection piece 10.
Embodiment
The utility model is further illustrated with implementation steps below in conjunction with the accompanying drawings.Each specific embodiment in the utility model In technical characteristic in case of no collision, can be mutually combined, be not construed as limiting.
As shown in figure 1, being the jacketed hoop prefabricated pilework vertical section schematic diagram of back-up sand building stones in one embodiment China and foreign countries.This is prefabricated Pilework is embedded in pending foundation soil 9, for supporting top structures or other structures.Prefabricated pilework includes prefabricated pipe Stake pile body 1, expanding cuff 3 and stake bottom expand pile top.The cross section of prefabricated tubular pile pile body 1 is in hollow circular ring shape, can be carried out outside the venue Subsequently assembled at the construction field (site) after prefabricated, can also it is prefabricated directly outside the venue, be completed after be transported to job site.Pile body The upper part for needing to assemble includes expanding cuff 3 and stake bottom expands pile top two parts.Expanding cuff 3 is one in hollow annular Hoop body, for being fastened around on the outside of pile body, therefore its external diameter need to be more than pile body external diameter, and its inner side hollow parts preferably with stake The profile of body matches.In the present embodiment, pile body is in cylinder, and therefore, the inner side of expanding cuff 3 is also slightly larger than pile body for diameter The circle of external diameter.Expanding cuff 3 is preferably detachable to be fixed on pile body.As that in the present embodiment, can be by expanding 3 one points of cuff Two, centre is connected with part 10 and is attached, in order to install, and expanding cuff 3 can go up downward in the fixed position of pile body It is whole.An expanding cuff 3 can be arranged on pile body at a certain distance, prefabricated pile is formed a kind of nodular by several expanding cuffs 3 Stake form.
In addition, the bottom of pile body, which is fixed with a bottom, expands pile top, in order that pile body and expanding cuff 3 smoothly can enter to bury In layer, in order to provide packing space to follow-up sandstone filler, the external diameter that stake bottom expands the cross section maximum of pile top can not be small In the external diameter of expanding cuff 3.
One of the purpose of this utility model is that pile body to be enters the super quiet pore water offer row produced during foundation soil Aquaporin-4, therefore the peripheral certain distance annular of prefabricated pile pile body is filled with sandstone filler 8.The full soil body of the filling of sandstone filler 8 and Annulus between pile body.In order to meet the drainage efficiency of super quiet pore water, the minimum outer diameter of the sandstone bed of material is not less than expanding The external diameter of cuff 3, enables the water below cuff to drain into top quickly through sand material.Certainly, the cross section of 8 layers of sandstone filler is not Must be the annular shape of standard, it is also possible to elliptical ring or other shapes, but its circumferential minimum across footpath need to be more than expanding cuff 3 External diameter, thus has sandstone filler 8 to form drainage channel 4 on the outside of expanding cuff 3.
, can between expanding cuff 3 and prefabricated pile pile body although laminating is fixed on pile body in addition, expanding cuff 3 need to try one's best To be provided with interstitial channels, vertical drainage passage is used as.As shown in Fig. 2 can be in petal form along collarette outside pile body cross section Around multiple semicircular through holes are laid, cuff need not be bypassed by making the water of the expanding lower section of cuff 3, can be discharged directly from through hole. Certainly, the shape of interstitial channels might not use the form in figure, can design according to actual needs.When the expanding outside of cuff 3 Sandstone depth of packing it is inadequate when, can adjust interstitial channels size, to improve drainage efficiency.
Expansion pile top in stake bottom can take various forms with the junction of prefabricated tubular pile pile body 1 is reinforced, in the present embodiment For the design of filling type.Expand such as the stake bottom in figure shown in pile top (filling type) 5, stake bottom, which expands, sets one and stake at the top of pile top The projection that hollow section is matched in body, is then plunged into prefabricated tubular pile pile body 1.
Certainly, there is more deformation in above-described embodiment, such as in another embodiment, as shown in figure 3, its bottom expands Pile top can be using hoop type design, i.e., the stake bottom in figure expands pile top (hoop type) 6.In addition, as shown in figure 4, prefabricated tubular pile stake Body 1 is also replaceable into precast square pile pile body 2.
In addition, the utility model also provides a kind of additional cuff prefabricated pile back-up sand stone construction method for realizing said structure, Comprise the following steps:
Step 1. is spaced (specific interval can be determined according to experiment) on prefabricated pile pile body and fixes several cavity rings The formation nodular stake of expanding cuff 3 of shape, while fixing maximum outside diameter in pile body bottom not less than pile body external diameter (as far as possible more than expanding The external diameter of cuff 3) stake bottom expand pile top;
Step 2. is placed with diameter greater than expanding cuff external diameter in the target construction location of the pending foundation soil 9 of prefabricated pile Bucket 7 is protected, the shield uncovered of bucket 7 is bottomless, only with cylindrical side wall, be easy to fill sandstone material;
The table of pending foundation soil 9 that step 3. will be surrounded by the prefabricated pile one end top assembled in step 1 with shield bucket 7 Face, is then squeezed into or is pressed into soil layer by machinery.In this process, expansion pile top in stake bottom opens up out a post in the soil body Shape passage, for accommodating pile body.Meanwhile, need constantly to fill out into shield bucket 7 in this process and send enough sand materials (at least can Adequately fill up the gap between pile body and the soil body), under the drive of expanding cuff 3, sand material is brought into foundation soil with pile body And be filled in the peripheral certain distance of pile body, form all drainage channels 4 of a stake.
After the completion of step 4. piling, remove shield bucket 7 to recycle.
In order to examine the performance of above-mentioned additional cuff back-up sand building stones prefabricated pile, to the pile body and external diameter and expanding cuff 3 Identical prefabricated pile, identical wall thickness, stake it is long, with stake form and construction method under the conditions of, carried out static load test contrast.Examination Test result to show, the identical of expanding cuff 3 of external diameter and this is compared using its bearing capacity of nodular pilework of the present utility model Prefabricated pile improves 10%-20% or so, and bearing capacity is suitable with the prefabricated pile bearing capacity of larger diameter, is not influenceing bearing capacity Its manufacturing cost has obtained effective reduction simultaneously.Under this structure, the expanding pile top of pile body nodular ledge and stake end is strengthened Pile body supports the contact of soil layer with pile peripheral earth and bottom so that pile side friction and end resistance be obtained for certain journey The raising of degree, the lifting of pile foundation bearing capacity.In addition, when pile body interval hole-enlargement pile is during squeezing into or being pressed into, if in stake Fill out in week and send sand material so that soil around pile internal friction angle increases, then shaft resistance also can accordingly increase, and pile foundation bearing capacity will be obtained To further lifting.In addition, in terms of ground settlement after construction, all drainage channels 4 of stake that all sandstone fillers 8 of stake are formed can be accelerated The diffusion of excess pore water pressure in soil around pile, accelerates ground soil solidifying, greatly reduces ground settlement after construction.
Embodiment described above is a kind of preferably scheme of the present utility model, so itself and be not used to limit this practicality It is new., can be with the case where not departing from spirit and scope of the present utility model about the those of ordinary skill of technical field Make a variety of changes and modification.Therefore the technical scheme that all modes for taking equivalent or equivalent transformation are obtained, all falls within In protection domain of the present utility model.

Claims (5)

1. a kind of additional cuff back-up sand building stones prefabricated pile, it is characterised in that:Expand including prefabricated pile pile body, expanding cuff and stake bottom Pile top;Described expanding cuff is in hollow annular, and its external diameter is more than pile body external diameter;Spacer sleeve is provided with several expanding sets on pile body Hoop into nodular stake;Described stake bottom expansion pile top is fixed on pile body bottom and maximum outside diameter is not less than outside the expanding cuff of pile body Footpath;Sand material is filled with the peripheral certain limit of described prefabricated pile pile body, the minimum diameter of the sandstone bed of material is not less than expanding set Bind round external diameter.
2. additional cuff back-up sand building stones prefabricated pile as claimed in claim 1, it is characterised in that:It is empty on the inside of described expanding cuff The shape in heart section matches with pile body cross section, expanding cuff laminating is fixed on pile body, expanding cuff and prefabricated pile stake Interstitial channels are provided between body, vertical drainage passage is used as.
3. additional cuff back-up sand building stones prefabricated pile as claimed in claim 1, it is characterised in that:Described expanding cuff passes through solid Determine part to be detachably secured on prefabricated pile pile body.
4. additional cuff back-up sand building stones prefabricated pile as claimed in claim 1, it is characterised in that:Described expanding cuff is in pile body Fixed position can up and down adjust.
5. additional cuff back-up sand building stones prefabricated pile as claimed in claim 1, it is characterised in that:Described stake bottom expand pile top with The junction of prefabricated pile pile body is in filling type or hoop type.
CN201621319100.1U 2016-12-03 2016-12-03 A kind of additional cuff back-up sand building stones prefabricated pile Expired - Fee Related CN206319314U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621319100.1U CN206319314U (en) 2016-12-03 2016-12-03 A kind of additional cuff back-up sand building stones prefabricated pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621319100.1U CN206319314U (en) 2016-12-03 2016-12-03 A kind of additional cuff back-up sand building stones prefabricated pile

Publications (1)

Publication Number Publication Date
CN206319314U true CN206319314U (en) 2017-07-11

Family

ID=59265909

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621319100.1U Expired - Fee Related CN206319314U (en) 2016-12-03 2016-12-03 A kind of additional cuff back-up sand building stones prefabricated pile

Country Status (1)

Country Link
CN (1) CN206319314U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114875886A (en) * 2022-06-09 2022-08-09 中国电建集团成都勘测设计研究院有限公司 Construction method of expanding vibroflotation gravel pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114875886A (en) * 2022-06-09 2022-08-09 中国电建集团成都勘测设计研究院有限公司 Construction method of expanding vibroflotation gravel pile

Similar Documents

Publication Publication Date Title
CN108560542B (en) Waste tire coated building slag bidirectional reinforcement and construction method thereof
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN105625294A (en) Composite foundation and construction method thereof
CN104594361B (en) A kind of I shape fender post and building enclosure also serve as the construction method of agent structure
CN105672307A (en) Expanded-base combination end pile bearing foundation
CN206220085U (en) A kind of permeable pile tube system for accelerating to consolidate
CN111501771B (en) Application method of multi-elliptical-ring combined support in deep large-sludge foundation pit engineering
CN107012861A (en) A kind of discrete material core expansive concrete stake and its construction method
CN210459256U (en) Double-wall hollow assembled root type open caisson foundation
CN203160254U (en) Pit support structure
CN106480878A (en) A kind of upper and lower part expansion type soil cement is combined pile tube
CN106592586B (en) Additional cuff back-up sand building stones prefabricated pile and its construction method
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN106013834A (en) Device and method for storey addition of basement
CN203729309U (en) Support system with combined double-row piles combined with vertical prestressed anchor bolts
CN206319314U (en) A kind of additional cuff back-up sand building stones prefabricated pile
CN102966109A (en) Method for constructing zonal deep foundation pit bottom sealing of soft soil foundation
CN103573002A (en) Ultra-large dual-layer steel plate concrete silo prestressed technology and structure of ultra-large dual-layer steel plate concrete silo
CN208137097U (en) Prefabricated seepage well
CN207211176U (en) A kind of big open caisson of superelevation
CN207794067U (en) Compound mini pile is perfused in concrete filled steel tube borehole
CN206233232U (en) A kind of upper and lower part expansion type soil cement is combined pile tube
CN203498828U (en) Top reinforced cast-in-place concrete thin-wall pipe pile
CN102409701A (en) Concrete wall construction joint processing method and structure
CN206368375U (en) A kind of electric power pylon basis

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170711

Termination date: 20201203