CN102409701A - Concrete wall construction joint processing method and structure - Google Patents
Concrete wall construction joint processing method and structure Download PDFInfo
- Publication number
- CN102409701A CN102409701A CN2011102314673A CN201110231467A CN102409701A CN 102409701 A CN102409701 A CN 102409701A CN 2011102314673 A CN2011102314673 A CN 2011102314673A CN 201110231467 A CN201110231467 A CN 201110231467A CN 102409701 A CN102409701 A CN 102409701A
- Authority
- CN
- China
- Prior art keywords
- joint
- concrete wall
- concrete
- pouring
- steel plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Building Environments (AREA)
Abstract
The invention discloses a concrete wall construction joint processing method, characterized in that: two adjacent concrete wall sections comprise a former poured concrete wall section and a later poured concrete wall section, a water stop steel plate is embedded in the formerly poured concrete wall section, and the water stop steel plate is positioned in the middle position of the construction joint of the two adjacent concrete wall sections; a pouring gate with a corbel-shaped elevation is erected at the upper part of the later poured concrete wall section, the pouring gate is higher than the construction joint of the two adjacent concrete wall sections; concrete is poured from the pouring gate to form the later poured concrete wall section and a concrete body with a corbel-shaped elevation in the pouring gate, the concrete body is protruded out of the two adjacent concrete wall sections and covers the construction joint between the two concrete wall sections; one part of the water stop steel plate is embedded in the former poured concrete wall section, and the other part of the water stop steel plate is poured in the later poured concrete wall section. The invention also discloses a construction joint structure formed by the processing method, and the construction joint structure processed by the processing method has compactness and good water stop property without leakage.
Description
Technical field
The present invention relates to a kind of treatment of construction joints method and constuction joint structure, particularly relate to a kind of concrete wall treatment of construction joints method and structure.
Background technology
Wen Feng mountains and rivers, Tangshan wheel hub Co., Ltd 4300 special heavy plate engineering-cyclone wells are circular underground structure, mainly by inside and outside tube; Platform, compositions such as slag runner, urceolus external diameter ¢ 14m; Urceolus wall thickness 1m, inner core external diameter ¢ 4.1m, inner core wall thickness 300mm; Absolute altitude-25.750m at the bottom of the base plate plate, base plate thickness 2m.Bed course C10 concrete, the cyclone well main body adopts the C30.P8 waterproof concrete, and back-grouting adopts C35.
The cyclone well urceolus adopts the reverse construction order, all skirt piles of construction earlier, treat its reach design strength after soil excavation to being preced with the beam absolute altitude, construction ring beam and first segment outer tube wall.Treat that intensity reaches the second joint earthwork of continued excavation, carries out the construction of second joint.The treatment of construction joints of the first segment barrel and the second joint barrel link position is to guarantee the whether key of seepage of outer tube wall during this sequence construction.
Summary of the invention
The present invention provides a kind of non-leakage concrete wall treatment of construction joints method and structure for solving the technical problem that exists in the known technology.
The technical scheme that the present invention takes for the technical problem that exists in the solution known technology is: a kind of concrete wall treatment of construction joints method; This concrete wall comprises some joint concrete wall joints of first after-pouring; Adjacent two joint concrete walls joints comprise the concrete wall joint of formerly building and at the concrete wall joint of after-pouring; Pre-buried steel plate for sealing water in the concrete wall joint of formerly building said, said steel plate for sealing water are positioned at the centre position at the constuction joint place of said adjacent two joint concrete walls joints; Install the cast gate that facade is bracket shape on said concrete wall joint top at after-pouring, said cast gate is higher than the constuction joint that said two adjacent joint concrete walls save; Build concrete from said cast gate, form said at after-pouring concrete wall joint and in cast gate, to form facade be the concrete body of bracket shape, said concrete body protrusion and covers the constuction joint between them outside said two adjacent joint concrete walls joints; The part of said steel plate for sealing water is embedded in the said concrete wall joint of formerly building, and another part is cast in said in the concrete wall joint of after-pouring.
This method is further comprising the steps of: treat after the concrete strength of the concrete wall of after-pouring joint reaches designing requirement, be that the concrete body of bracket shape cuts with the facade that forms in the cast gate, and use cement sand plaster.
Another technical scheme that the present invention takes for the technical problem that exists in the solution known technology is: a kind of concrete wall constuction joint structure; This concrete wall comprises some joint concrete wall joints of first after-pouring; Adjacent two joint concrete walls joints comprise the concrete wall joint of formerly building and at the concrete wall joint of after-pouring; This constuction joint structure is included in pre-buried steel plate for sealing water in the said concrete wall joint of formerly building, and said steel plate for sealing water is positioned at the centre position at the constuction joint place of said adjacent two joint concrete walls joints; The part of said steel plate for sealing water is embedded in the said concrete wall joint of formerly building, and another part is cast in said in the concrete wall joint of after-pouring.
The concrete body that any side of the constuction joint that said two adjacent joint concrete walls save is coated with bracket shape.
Advantage and good effect that the present invention has are: in constuction joint, adopt steel plate for sealing water and adopt bracket shape cast gate to be cast in the concrete wall joint of after-pouring, the density of constuction joint and sealing property are good, and be non-leakage.And easy construction of the present invention, cost is low.
Description of drawings
Fig. 1 is for using the sketch map of a kind of concrete wall of the present invention treatment of construction joints method.
Among the figure: the concrete wall of 1, formerly building joint, 2, steel plate for sealing water, 3, at the concrete wall joint of after-pouring, 4, cast gate.
The specific embodiment
For further understanding summary of the invention of the present invention, characteristics and effect, the following examples of giving an example now, and conjunction with figs. specifies as follows:
See also Fig. 1; A kind of concrete wall constuction joint structure; This concrete wall comprises some joint concrete wall joints of first after-pouring; Adjacent two joint concrete walls joints comprise the concrete wall joint 1 of formerly building and at the concrete wall joint 3 of after-pouring, this constuction joint structure is included in pre-buried steel plate for sealing water 2 in the concrete wall joint 1 of formerly building, and steel plate for sealing water 2 is positioned at the centre position at the constuction joint place of two adjacent joint concrete walls joints; The part of steel plate for sealing water 2 is embedded in the concrete wall joint 1 of formerly building, and another part is cast in the concrete wall joint 3 of after-pouring.
In order further to improve anti-permeability performance, the concrete body that any side of the constuction joint of two adjacent joint concrete wall joints is coated with bracket shape.
Above-mentioned concrete wall treatment of construction joints method, first pre-buried steel plate for sealing water 2 in the concrete wall joint 1 of formerly building makes steel plate for sealing water 2 be positioned at the centre position at the constuction joint place of above-mentioned adjacent two joint concrete walls joints; Save 3 tops at the concrete wall at after-pouring and install the cast gate 4 that facade is bracket shape, cast gate 4 is higher than the constuction joint that above-mentioned two adjacent joint concrete walls save; Build concrete from cast gate 4, being formed on the concrete wall joint 3 of after-pouring and in cast gate, forming facade is the concrete body of bracket shape, and the concrete body protrudes outside above-mentioned two adjacent joint concrete walls joints, and covers the constuction joint between them; The part of steel plate for sealing water 3 is embedded in the concrete wall joint 1 of formerly building, and another part is cast in the concrete wall joint 3 of after-pouring.
In the present embodiment, the concrete wall is a barrel, and cast gate 4 is an annular; Width is 200mm, is higher than constuction joint 300mm, is used to be cast in the concrete wall joint that the back forms; Make the concrete of building be easy to be filled into after the steel plate for sealing water 2 and be convenient to vibrate, thereby make concrete closely knit, guarantee the quality of constuction joint.After treating that concrete strength reaches designing requirement, the facade that will in cast gate, form is that the concrete body of bracket shape cuts, and with 1: 2 cement sand plaster.
If the concrete body that the above-mentioned facade that in cast gate, forms is a bracket shape does not influence the structure and the function of use of cyclone well, can it not cut, can save a large amount of people, material resources, speed up the work, can be used as the impervious reserve safeguard measure of constuction joint again.
Although combine accompanying drawing that the preferred embodiments of the present invention are described above; But the present invention is not limited to the above-mentioned specific embodiment, and the above-mentioned specific embodiment only is schematically, is not restrictive; Those of ordinary skill in the art is under enlightenment of the present invention; Not breaking away under the scope situation that aim of the present invention and claim protect, can also make a lot of forms, these all belong within protection scope of the present invention.
Claims (4)
1. concrete wall treatment of construction joints method; This concrete wall comprises some joint concrete wall joints of first after-pouring; It is characterized in that; Adjacent two joint concrete walls joints comprise the concrete wall joint of formerly building and at the concrete wall joint of after-pouring, and pre-buried steel plate for sealing water in said concrete wall joint of formerly building, said steel plate for sealing water are positioned at the centre position at the constuction joint place of said adjacent two joint concrete walls joints; Install the cast gate that facade is bracket shape on said concrete wall joint top at after-pouring, said cast gate is higher than the constuction joint that said two adjacent joint concrete walls save; Build concrete from said cast gate, form said at after-pouring concrete wall joint and in cast gate, to form facade be the concrete body of bracket shape, said concrete body protrusion and covers the constuction joint between them outside said two adjacent joint concrete walls joints; The part of said steel plate for sealing water is embedded in the said concrete wall joint of formerly building, and another part is cast in said in the concrete wall joint of after-pouring.
2. concrete wall treatment of construction joints method according to claim 1; It is characterized in that; This method is further comprising the steps of: treat after the concrete strength of the concrete wall of after-pouring joint reaches designing requirement, be that the concrete body of bracket shape cuts with the facade that forms in the cast gate, and use cement sand plaster.
3. concrete wall constuction joint structure; This concrete wall comprises some joint concrete wall joints of first after-pouring; It is characterized in that; Adjacent two joint concrete walls joints comprise the concrete wall joint of formerly building and at the concrete wall joint of after-pouring, this constuction joint structure is included in pre-buried steel plate for sealing water in the said concrete wall joint of formerly building, and said steel plate for sealing water is positioned at the centre position at the constuction joint place of said adjacent two joint concrete walls joints; The part of said steel plate for sealing water is embedded in the said concrete wall joint of formerly building, and another part is cast in said in the concrete wall joint of after-pouring.
4. concrete wall constuction joint structure according to claim 3 is characterized in that, the concrete body that any side of the constuction joint that said two adjacent joint concrete walls save is coated with bracket shape.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102314673A CN102409701A (en) | 2011-08-12 | 2011-08-12 | Concrete wall construction joint processing method and structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102314673A CN102409701A (en) | 2011-08-12 | 2011-08-12 | Concrete wall construction joint processing method and structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102409701A true CN102409701A (en) | 2012-04-11 |
Family
ID=45912020
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102314673A Pending CN102409701A (en) | 2011-08-12 | 2011-08-12 | Concrete wall construction joint processing method and structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102409701A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103161181A (en) * | 2013-04-02 | 2013-06-19 | 中建城市建设发展有限公司 | Underground outer wall construction joint water-stopping structure and construction method thereof |
CN104032841A (en) * | 2014-07-02 | 2014-09-10 | 中冶天工集团有限公司 | Treatment method for horizontal construction joint of concrete walls |
CN105040730A (en) * | 2015-06-29 | 2015-11-11 | 上海市基础工程集团有限公司 | Connection processing method for enclosure bored concrete pile and cellar structure floor slab in reversed foundation pit |
CN106545034A (en) * | 2015-09-17 | 2017-03-29 | 中国二十冶集团有限公司 | Contrary sequence method exterior wall horizontal construction joint steel plate water stopper concreting method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1784612A1 (en) * | 1968-08-26 | 1971-08-12 | Solstabil Ag | Process for covering foundation structures and support beams made with in-situ concrete slotted walls for carrying out this process |
CN101403218A (en) * | 2008-11-12 | 2009-04-08 | 天津二十冶建设有限公司 | Processing method for basement water-proof concrete construction joint |
CN101457526A (en) * | 2009-01-07 | 2009-06-17 | 中冶天工建设有限公司 | Circular deep foundation ditch concrete pile arranging support and major structure inversing construction method |
CN101672041A (en) * | 2009-09-18 | 2010-03-17 | 天津二十冶建设有限公司 | Top-down construction method of large underground structure outer wall |
CN202284334U (en) * | 2011-08-12 | 2012-06-27 | 天津二十冶建设有限公司 | Construction joint structure of concrete wall |
-
2011
- 2011-08-12 CN CN2011102314673A patent/CN102409701A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1784612A1 (en) * | 1968-08-26 | 1971-08-12 | Solstabil Ag | Process for covering foundation structures and support beams made with in-situ concrete slotted walls for carrying out this process |
CN101403218A (en) * | 2008-11-12 | 2009-04-08 | 天津二十冶建设有限公司 | Processing method for basement water-proof concrete construction joint |
CN101457526A (en) * | 2009-01-07 | 2009-06-17 | 中冶天工建设有限公司 | Circular deep foundation ditch concrete pile arranging support and major structure inversing construction method |
CN101672041A (en) * | 2009-09-18 | 2010-03-17 | 天津二十冶建设有限公司 | Top-down construction method of large underground structure outer wall |
CN202284334U (en) * | 2011-08-12 | 2012-06-27 | 天津二十冶建设有限公司 | Construction joint structure of concrete wall |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103161181A (en) * | 2013-04-02 | 2013-06-19 | 中建城市建设发展有限公司 | Underground outer wall construction joint water-stopping structure and construction method thereof |
CN104032841A (en) * | 2014-07-02 | 2014-09-10 | 中冶天工集团有限公司 | Treatment method for horizontal construction joint of concrete walls |
CN105040730A (en) * | 2015-06-29 | 2015-11-11 | 上海市基础工程集团有限公司 | Connection processing method for enclosure bored concrete pile and cellar structure floor slab in reversed foundation pit |
CN105040730B (en) * | 2015-06-29 | 2017-04-19 | 上海市基础工程集团有限公司 | Connection processing method for enclosure bored concrete pile and cellar structure floor slab in reversed foundation pit |
CN106545034A (en) * | 2015-09-17 | 2017-03-29 | 中国二十冶集团有限公司 | Contrary sequence method exterior wall horizontal construction joint steel plate water stopper concreting method |
CN106545034B (en) * | 2015-09-17 | 2019-01-11 | 中国二十冶集团有限公司 | Contrary sequence method exterior wall horizontal construction joint steel plate water stopper concreting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204343312U (en) | A kind of plugging device of precipitation well in foundation pit | |
CN105862722A (en) | Three-dimensional treatment method of subway deep foundation pit in karst intense development region | |
CN104389608B (en) | The construction method of shield crossing ventilating shaft | |
CN103161172B (en) | Elevator shaft bottom precipitation construction method | |
CN108086328A (en) | A kind of dynamic sealing, assembled building enclosure and its construction method from recharge | |
CN106593470A (en) | High-permeability water-rich sand shield terminal reinforcing system and construction method thereof | |
CN209339169U (en) | A kind of precipitation well in foundation pit plugging device | |
CN103498486A (en) | Method for blocking post-cast strip downcast pipe well through sleeve pipe | |
CN105421497A (en) | Water-proof construction method for connected nodes of foundation slab and ground wall in composite surround system | |
CN102409701A (en) | Concrete wall construction joint processing method and structure | |
CN104652495B (en) | Internal support of foundation pit column and base plate node waterproof construction technology | |
CN104264700A (en) | Seepage prevention construction method for light-weight precipitation well point post-cast strip of underground construction | |
CN104988914A (en) | Cast-in-situ bored pile breakage processing method under water area environment | |
CN103572764A (en) | Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof | |
CN203160254U (en) | Pit support structure | |
CN104695980B (en) | For the regional Lining of Power Tunnel structure of high buried depth, High-geotemperature, high stress rock burst | |
CN203768925U (en) | Seal device for dewatering well in foundation pit | |
CN204492847U (en) | A kind of supporting and protection structure of underground space reverse construction | |
CN202284334U (en) | Construction joint structure of concrete wall | |
CN105756100A (en) | Basement post-pouring belt system and making method thereof | |
CN204959781U (en) | Dewatering well plugging device | |
CN104594367B (en) | A kind of combined type cofferdam structure and construction method | |
CN203514332U (en) | Casing for blocking dewatering tube well of post-cast strip | |
CN106088758A (en) | A kind of double-deck assembled underground granary | |
CN216342124U (en) | Disposal structure of tunnel side lower part karst cave |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120411 |