CN206106844U - Rear overhang swing arm circle tubular beams installation component - Google Patents

Rear overhang swing arm circle tubular beams installation component Download PDF

Info

Publication number
CN206106844U
CN206106844U CN201620483503.3U CN201620483503U CN206106844U CN 206106844 U CN206106844 U CN 206106844U CN 201620483503 U CN201620483503 U CN 201620483503U CN 206106844 U CN206106844 U CN 206106844U
Authority
CN
China
Prior art keywords
swing arm
crossbeam
pipe beam
mounting bracket
strut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620483503.3U
Other languages
Chinese (zh)
Inventor
唐春柳
瞿刚
曾蔚
谢贵山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SAIC GM Wuling Automobile Co Ltd
Original Assignee
SAIC GM Wuling Automobile Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SAIC GM Wuling Automobile Co Ltd filed Critical SAIC GM Wuling Automobile Co Ltd
Priority to CN201620483503.3U priority Critical patent/CN206106844U/en
Application granted granted Critical
Publication of CN206106844U publication Critical patent/CN206106844U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Vehicle Body Suspensions (AREA)

Abstract

The utility model discloses a rear overhang swing arm circle tubular beams installation component, including left rear crossbeam, right rear crossbeam, swing arm installation assembly, circle tubular beams, first crossbeam, second crossbeam and circle tubular beams support piece, the both ends of second crossbeam set up perpendicularly respectively in a left side rear crossbeam with right side rear crossbeam's tip, first crossbeam is on a parallel with the second crossbeam sets up a left side rear crossbeam with right side rear crossbeam middle part, first crossbeam both ends with second crossbeam both ends respectively with a left side rear crossbeam with right side rear crossbeam fixed connection, circle tubular beams is through circle tubular beams support frame and second crossbeam fixed connection, the total complete set of swing arm installation is established and is fixed on the circle tubular beams. Like this, satisfy the installation requirement of rear overhang swing arm, improve the quiet rigidity of rear overhang swing arm mounting point, improve the nature controlled, the travelling comfort driven, improve the whole dynamic stiffness of rear overhang swing arm installation crossbeam department, improve the NVH performance.

Description

A kind of rear overhang swing arm pipe beam mounting assembly
Technical field
This utility model is related to body structure technical field, more particularly to a kind of rear overhang swing arm pipe beam mounting assembly.
Background technology
At present, rear overhang swing arm beam mounting structure mainly by crossbeam, longeron, rear overhang swing arm mounting bracket and correlation plus Brutal assembly, by realizing vibration damping, supporting the effect of vehicle body with the Rigidity Matching of bushing in rear overhang swing arm.Rear overhang swing arm crossbeam is pacified Assembling structure can directly influence the handling and comfortableness of automobile.
Existing rear overhang swing arm mounting structure is primarily present uneven, rigidity distribution impact car load NVH performances of part stress etc. Problem:Two unilateral suspension swing arm mounting brackets are little with the overlapping area of crossbeam, longeron, are unfavorable for that rear overhang swing arm passes through rear overhang Oscillating arm bracket causes NVH poor performances to longeron, crossbeam power transmission;Two unilateral suspension swing arm mounting brackets are connected by crossbeam Together, but crossbeam is blocked by longeron, cause one side two suspension swing arm mounting bracket globality poors;Dangle arm mount point Liftoff plate face installs dynamic stiffness at crossbeam apart from big problem, the not enough problem of the arm mount point that dangles Static stiffness and rear overhang swing arm Not enough problem.
Utility model content
This utility model is completed to solve of the prior art not enough, and the purpose of this utility model is to provide one Rear overhang swing arm pipe beam mounting assembly is planted, the installation requirement of rear overhang swing arm is met;The Static stiffness of rear overhang swing arm mount point is improved, is carried High handling, the comfortableness for driving;The overall dynamic stiffness at rear overhang swing arm installation crossbeam is improved, NVH performances are improved.
Crossbeam, swing arm after a kind of rear overhang swing arm pipe beam mounting assembly of the present utility model, including left back crossbeam, the right side is installed Assembly, pipe beam, first crossbeam, second cross beam and pipe beam support member, the two ends of the second cross beam are respectively perpendicular and are arranged at The end of crossbeam after the left back crossbeam and the right side, the first crossbeam is arranged on described left back parallel to the second cross beam After crossbeam and the right side in the middle part of crossbeam, the first crossbeam two ends and the second cross beam two ends respectively with the left back crossbeam and Behind the right side, crossbeam is fixedly connected, and the pipe beam is fixedly connected with second cross beam by pipe beam bracing frame, the swing arm peace Dress assembly is arranged and is fixed on the pipe beam.
A kind of rear overhang swing arm pipe beam mounting assembly of the present utility model can also be:
The distance of the pipe beam to the second cross beam and the first crossbeam to the distance of the second cross beam and institute The length ratio for stating pipe beam to the distance of the first crossbeam is 3:3:2.
The swing arm installation assembly includes:First swing arm mounting bracket, the second swing arm mounting bracket, the 3rd swing arm are installed and are propped up Frame and the 4th swing arm mounting bracket, first swing arm mounting bracket, the second swing arm mounting bracket, the 3rd swing arm mounting bracket and 4th swing arm mounting bracket is set on the pipe beam, and the first swing arm mounting bracket lower surface is connected with left back crossbeam Connect, the second swing arm mounting bracket lower surface is connected with first crossbeam, the 3rd swing arm mounting bracket lower surface and first Crossbeam connects, and the 4th swing arm mounting bracket lower surface is connected with crossbeam behind the right side.
The first swing arm mounting bracket lower surface is connected with left back crossbeam by bolt, second swing arm mounting bracket Lower surface is connected with first crossbeam by bolt, and the 3rd swing arm mounting bracket lower surface is connected with first crossbeam by bolt Connect, the 4th swing arm mounting bracket lower surface is connected with crossbeam behind the right side by bolt.
Pipe beam connection is provided with the first crossbeam, cover plate in the middle part of the pipe beam, is provided with, the cover plate with The pipe beam connection position, form and dimension correspondence, the cover plate are detachably fixed with the pipe beam connection and are connected.
The cover plate and the pipe beam connection bolt connection.
The pipe beam connection is provided with the lengthways of rod for vertically extending.
The pipe beam support member includes that the first strut and the second strut, first strut and the second strut are arranged on institute The top for stating the lower section of pipe beam, first strut and second strut is connected with the pipe beam, first support Bar and the second strut bottom are detachably fixed with the second cross beam and are connected.
First strut and the second strut bottom are connected with the second cross beam by bolt.
In the middle part of first strut and second strut, upper surface is provided with brake pipe installing rack.
Crossbeam, pendulum after a kind of rear overhang swing arm pipe beam mounting assembly of offer of the present utility model, including left back crossbeam, the right side Arm installation assembly, pipe beam, first crossbeam, second cross beam and pipe beam support member, the two ends of the second cross beam are respectively perpendicular The end of crossbeam behind the left back crossbeam and the right side is arranged at, the first crossbeam is arranged on institute parallel to the second cross beam State behind left back crossbeam and the right side in the middle part of crossbeam, the first crossbeam two ends and the second cross beam two ends are left back with described respectively Crossbeam is fixedly connected with crossbeam behind the right side, and the pipe beam is fixedly connected with second cross beam by pipe beam bracing frame, described Swing arm installation assembly is arranged and is fixed on the pipe beam.So, by setting up pipe beam, swing arm installation assembly is set in pipe Install on beam, after position determines, swing arm installation assembly is welded with pipe beam, swing arm installation assembly is formed with pipe beam One entirety, improves the bonding strength of swing arm installation assembly and pipe beam, and advantage in terms of existing technologies is:Swing arm is pacified Structure at dress is more stable, strengthens the structural strength and rigidity of swing arm installation site.
Description of the drawings
Fig. 1 is the schematic view of the mounting position of this utility model embodiment rear overhang swing arm pipe beam mounting assembly;
Fig. 2 is the pipe girder construction schematic diagram of this utility model embodiment rear overhang swing arm pipe beam mounting assembly;
Fig. 3 is the second swing arm mounting bracket position section of this utility model embodiment rear overhang swing arm pipe beam mounting assembly Schematic diagram.
In figure:1:Left back crossbeam;2:Crossbeam behind the right side;3:Pipe beam;4:First crossbeam;5:Second cross beam;6:First swing arm Mounting bracket;7:Second swing arm mounting bracket;8:3rd swing arm mounting bracket;9:4th swing arm mounting bracket;10:Cover plate;11: Lengthways of rod;12:First strut;13:Second strut;14:Brake pipe installing rack.
Specific embodiment
With reference to the accompanying drawings and examples a kind of rear overhang swing arm pipe beam mounting assembly of this utility model is embodied as Mode is described in further detail.Following examples are used to illustrate this utility model, but are not limited to model of the present utility model Enclose.
As Figure 1-3, after a kind of rear overhang swing arm pipe beam mounting assembly of the present utility model, including left back crossbeam 1, the right side Crossbeam 2, swing arm installation assembly, pipe beam 3, first crossbeam 4,3 support member of second cross beam 5 and pipe beam, the second cross beam 5 Two ends be respectively perpendicular be arranged at the left back crossbeam 1 and it is described the right side after crossbeam 2 end, the first crossbeam 4 is parallel to described Second cross beam 5 is arranged on behind the left back crossbeam 1 and the right side in the middle part of crossbeam 2,4 two ends of the first crossbeam and described second horizontal 5 two ends of beam are fixedly connected with crossbeam 2 after the left back crossbeam 1 and the right side respectively, and the pipe beam 3 is supported by pipe beam 3 Frame is fixedly connected with second cross beam 5, and the swing arm installation assembly is arranged and is fixed on the pipe beam 3.So, by setting up circle Pipe beam 3, swing arm installation assembly are set on pipe beam 3 and install, and after position determines, swing arm installation assembly are entered with pipe beam 3 Row welding, swing arm installation assembly form an entirety with pipe beam 3, improve the bonding strength of swing arm installation assembly and pipe beam 3, Advantage in terms of existing technologies is:The structure of swing arm installation place is more stable, and the structure for strengthening swing arm installation site is strong Degree and rigidity.
A kind of rear overhang swing arm pipe beam mounting assembly of the present utility model, as shown in Figure 1 to Figure 3, in previously described skill Can also be on the basis of art scheme:The distance of the pipe beam 3 to the second cross beam 5 and the first crossbeam 4 are to described The distance of second cross beam 5 is 3 with the length ratio of the pipe beam 3 to the distance of the first crossbeam 4:3:2.So, triangle Structure has a very high structural stability, and 3 mounting assembly of rear overhang swing arm pipe beam of the present utility model by the pipe beam 3 with The distance between first crossbeam 4 and second cross beam 5 are designed as isosceles triangle, and the structure that reinforcement pipe beam 3 is installed herein is steady It is qualitative, according to 3:3:2 understand, this structure is acute angle isosceles triangle, and acute triangle can ensure that the height of pipe beam 3 to floor Degree will not be too high, it is to avoid as 3 locating distance of pipe beam is too far away, and causes structural strength not enough, relative and prior art, its knot Structure stability is higher.
A kind of rear overhang swing arm pipe beam mounting assembly of the present utility model, as shown in Figure 1 to Figure 3, in previously described skill Can also be on the basis of art scheme:The swing arm installation assembly includes:First swing arm mounting bracket 6, the second swing arm are installed and are propped up Frame 7, the 3rd swing arm mounting bracket 8 and the 4th swing arm mounting bracket 9, first swing arm mounting bracket 6, the second swing arm are installed and are propped up Frame 7, the 3rd swing arm mounting bracket 8 and the 4th swing arm mounting bracket 9 are set on the pipe beam 3, the first swing arm peace Dress 6 lower surface of support is connected with left back crossbeam 1, and 7 lower surface of the second swing arm mounting bracket is connected with first crossbeam 4, described 3rd swing arm mounting bracket, 8 lower surface is connected with first crossbeam 4, crossbeam 2 after 9 lower surface of the 4th swing arm mounting bracket and the right side Connection.So, by arranging four groups of swing arm mounting brackets, a swing arm is hinged per two groups, with swing arm mounting bracket installation site Structure it is more stable.Preferred technical scheme is:First swing arm mounting bracket, 6 lower surface is big with left back by bolt Beam 1 connects, and 7 lower surface of the second swing arm mounting bracket is connected with first crossbeam 4 by bolt, and the 3rd swing arm is installed and propped up 8 lower surface of frame is connected with first crossbeam 4 by bolt, and 9 lower surface of the 4th swing arm mounting bracket is big after bolt with the right side Beam 2 connects.So, four groups of swing arm mounting brackets are connected with each part by bolt, due to each part not in the same plane, So after mounting, bolt fixed position forms staged stress point structure, and such staged stress point structure makes pipe beam 3 Stress can be with dispersed, and relative to prior art, the ability of holding capacity is strong, and service life can be guaranteed.
A kind of rear overhang swing arm pipe beam mounting assembly of the present utility model, as shown in Figure 1 to Figure 3, in previously described skill Can also be on the basis of art scheme:3 connector of pipe beam is provided with the first crossbeam 4, is arranged in the middle part of the pipe beam 3 There is the cover plate 10 of corresponding 3 connector of pipe beam, the cover plate 10 is detachably fixed with 3 connector of pipe beam and is connected.So, The pipe beam 3 is fixed with 3 connector of pipe beam by cover plate 10 with the first crossbeam 4, is further ensured that the peace of pipe beam 3 Dress stability.Preferred technical scheme is:The cover plate 10 is bolted with 3 connector of pipe beam, convenient to justify The dismounting of pipe beam 3, changes after being easy to damage, there is provided efficiency, also the more efficient power disperseed suffered by the pipe beam 3, it is ensured that Structural stability.Preferred technical scheme is:3 connector of pipe beam is provided with the lengthways of rod for vertically extending 11.So, 3 connector of pipe beam is by arranging lengthways of rod 11 in its surface so that 3 connector of pipe beam is in longitudinal stress In the case of, structural strength is higher, prevents from causing 3 connecting-piece structure of pipe beam to damage due to stress, relative to prior art, carries High structural stability.
A kind of rear overhang swing arm pipe beam mounting assembly of the present utility model, as shown in Figure 1 to Figure 3, in previously described skill Can also be on the basis of art scheme:3 supporting construction of pipe beam includes the first strut 12 and the second strut 13, described first Strut 12 and the second strut 13 are arranged on the upper of the lower section of the pipe beam 3, first strut 12 and second strut 13 Portion is connected with the pipe beam 3, and first strut 12 and 13 bottom of the second strut are detachable with the second cross beam 5 It is fixedly connected.So, the first strut 12 and the second strut 13 are respectively provided with 3 both sides of pipe beam, circle is caused by two groups of struts 3 uniform stressed of pipe beam, makes 3 overall uniform force of pipe beam, will not cause malformation, destruction circle because local pressure is excessive 3 structural stability of pipe beam, and ensure this part of rigidity.
A kind of rear overhang swing arm pipe beam mounting assembly of the present utility model, as shown in Figure 1 to Figure 3, in previously described skill Can also be on the basis of art scheme:First strut 12 and second strut, 13 middle part upper surface are provided with brake pipe peace Shelve 14.So, the installation site of brake pipe is specified, according to the architectural characteristic of the application, the installation site at brake pipe is more Abundant, with miscellaneous part without interference, hinge structure, installation site are more flexible.
The above is only preferred implementation of the present utility model, it is noted that for the common skill of the art For art personnel, on the premise of without departing from this utility model know-why, some improvement and modification can also be made, these change Enter protection domain of the present utility model is also should be regarded as with modification.

Claims (10)

1. a kind of rear overhang swing arm pipe beam mounting assembly, it is characterised in that:Install total including crossbeam, swing arm behind left back crossbeam, the right side Into, pipe beam, first crossbeam, second cross beam and pipe beam support member, the two ends of the second cross beam are respectively perpendicular and are arranged at institute The end of crossbeam behind left back crossbeam and the right side is stated, the first crossbeam is arranged on described left back big parallel to the second cross beam After beam and the right side in the middle part of crossbeam, the first crossbeam two ends and the second cross beam two ends respectively with the left back crossbeam and institute After stating the right side, crossbeam is fixedly connected, and the pipe beam is fixedly connected with second cross beam by pipe beam bracing frame, and the swing arm is installed Assembly is arranged and is fixed on the pipe beam.
2. a kind of rear overhang swing arm pipe beam mounting assembly according to claim 1, it is characterised in that:The pipe beam is to institute State the distance of second cross beam with the distance of the first crossbeam to the second cross beam with the pipe beam to the first crossbeam Distance length ratio be 3:3:2.
3. a kind of rear overhang swing arm pipe beam mounting assembly according to claim 1, it is characterised in that:The swing arm is installed total Into including:First swing arm mounting bracket, the second swing arm mounting bracket, the 3rd swing arm mounting bracket and the 4th swing arm mounting bracket, First swing arm mounting bracket, the second swing arm mounting bracket, the 3rd swing arm mounting bracket and the 4th swing arm mounting bracket cover It is located on the pipe beam, the first swing arm mounting bracket lower surface is fixed with left back crossbeam, second swing arm is installed and propped up Frame lower surface is fixed with first crossbeam, and the 3rd swing arm mounting bracket lower surface is fixed with first crossbeam, the 4th swing arm Mounting bracket lower surface with the right side after crossbeam fix.
4. a kind of rear overhang swing arm pipe beam mounting assembly according to claim 3, it is characterised in that:The first swing arm peace Dress support lower surface is connected with left back crossbeam by bolt, and the second swing arm mounting bracket lower surface is horizontal with first by bolt Beam connects, and the 3rd swing arm mounting bracket lower surface is connected with first crossbeam by bolt, the 4th swing arm mounting bracket Lower surface is connected with crossbeam behind the right side by bolt.
5. a kind of rear overhang swing arm pipe beam mounting assembly according to claim 1, it is characterised in that:On the first crossbeam Pipe beam connection is provided with, cover plate, the cover plate and the pipe beam connection position, shape in the middle part of the pipe beam, is provided with Shape and size correspondence, the cover plate are detachably fixed with the pipe beam connection and are connected.
6. a kind of rear overhang swing arm pipe beam mounting assembly according to claim 5, it is characterised in that:The cover plate and institute State pipe beam connection bolt connection.
7. a kind of rear overhang swing arm pipe beam mounting assembly according to claim 6, it is characterised in that:The pipe beam connection Part is provided with the lengthways of rod for vertically extending.
8. a kind of rear overhang swing arm pipe beam mounting assembly according to claim 1-7 any one claim, its feature exist In:The pipe beam support member includes that the first strut and the second strut, first strut and the second strut are arranged on the circle The top of the lower section of Guan Liang, first strut and second strut is connected with the pipe beam, first strut and The second strut bottom is detachably fixed with the second cross beam and is connected.
9. a kind of rear overhang swing arm pipe beam mounting assembly according to claim 8, it is characterised in that:First strut and The second strut bottom is connected with the second cross beam by bolt.
10. a kind of rear overhang swing arm pipe beam mounting assembly according to claim 8, it is characterised in that:First strut Upper surface in the middle part of second strut is provided with brake pipe installing rack.
CN201620483503.3U 2016-05-24 2016-05-24 Rear overhang swing arm circle tubular beams installation component Expired - Fee Related CN206106844U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620483503.3U CN206106844U (en) 2016-05-24 2016-05-24 Rear overhang swing arm circle tubular beams installation component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620483503.3U CN206106844U (en) 2016-05-24 2016-05-24 Rear overhang swing arm circle tubular beams installation component

Publications (1)

Publication Number Publication Date
CN206106844U true CN206106844U (en) 2017-04-19

Family

ID=58509509

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620483503.3U Expired - Fee Related CN206106844U (en) 2016-05-24 2016-05-24 Rear overhang swing arm circle tubular beams installation component

Country Status (1)

Country Link
CN (1) CN206106844U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107415610A (en) * 2016-05-24 2017-12-01 上汽通用五菱汽车股份有限公司 A kind of rear overhang swing arm pipe beam mounting assembly

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107415610A (en) * 2016-05-24 2017-12-01 上汽通用五菱汽车股份有限公司 A kind of rear overhang swing arm pipe beam mounting assembly
CN107415610B (en) * 2016-05-24 2023-11-10 上汽通用五菱汽车股份有限公司 Rear suspension arm circular tube beam installation assembly

Similar Documents

Publication Publication Date Title
CN204526813U (en) A kind of rearmounted CNG fixing device for gas cylinder unit
CN107471944B (en) Integrated mounting bracket for modular independent suspension and bridge
CN206106844U (en) Rear overhang swing arm circle tubular beams installation component
CN202319797U (en) Independent suspension mounting bracket connecting structure
CN110406596B (en) Rear axle section frame for passenger car
CN201317260Y (en) Engine suspending mechanism of medium-sized truck
CN201254082Y (en) Novel engine front suspension beam assembly
CN210027391U (en) Optimized commercial vehicle air cylinder and dryer integrated frame
CN204845511U (en) Suspension support assembly
CN202685899U (en) Support structure for automobile suspension mounting bracket
CN202413919U (en) Transversely-mounted reinforced beam
CN202782675U (en) Suspension assembly behind gearbox underlying vehicle
CN205010324U (en) A inflating pump bracket for [electric] motor coach
CN206465763U (en) A kind of engine-mounting bracket
CN109911016B (en) Bear new forms of energy passenger train tail section frame entirely
CN202175099U (en) Vehicle frame of truck
CN205675105U (en) Cantalever tube beam fixed structure
CN205469538U (en) Motor vehicle support and motorcycle of using thereof
CN217514926U (en) Novel driving and hanging combined type rear torsion beam assembly for vehicle
CN107415610A (en) A kind of rear overhang swing arm pipe beam mounting assembly
CN206589671U (en) A kind of expansion tank and the integrated support assembly of air filter
CN206367374U (en) A kind of engine-mounting bracket and a kind of automobile
CN213322640U (en) Motor suspension mounting bracket
CN219621958U (en) Steel structure beam column
CN220315107U (en) Front auxiliary frame with high structural stability

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170419