CN205957419U - Air film building position new trend system - Google Patents

Air film building position new trend system Download PDF

Info

Publication number
CN205957419U
CN205957419U CN201620906662.XU CN201620906662U CN205957419U CN 205957419 U CN205957419 U CN 205957419U CN 201620906662 U CN201620906662 U CN 201620906662U CN 205957419 U CN205957419 U CN 205957419U
Authority
CN
China
Prior art keywords
air
ajutage
pneumatic membrane
membrane building
vmc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620906662.XU
Other languages
Chinese (zh)
Inventor
于有成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Double Membrane Technology Co Ltd
Original Assignee
Shenzhen Double Membrane Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Double Membrane Technology Co Ltd filed Critical Shenzhen Double Membrane Technology Co Ltd
Priority to CN201620906662.XU priority Critical patent/CN205957419U/en
Application granted granted Critical
Publication of CN205957419U publication Critical patent/CN205957419U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Tents Or Canopies (AREA)

Abstract

The utility model relates to an air film building position new trend system, include: the blast pipe, enclose locate air film building in, the one end of blast pipe is fresh air intake, the part is provided with a plurality of air outlets on the blast pipe, reposition of redundant personnel wind cabinet sets up in air intake department to the intercommunication air intake, fan group sets up in air intake department, intercommunication reposition of redundant personnel wind cabinet. Use the utility model discloses air film building position new trend system will pass through the rest area who filters the uncontaminated air conditioning in back and directly send the customer to through the blast pipe to the part sets up a plurality of air outlets on lieing in rest area's blast pipe, only for rest area provides cold wind, satisfy rest area 3 rice within temperature control 26 28 the degree, the more outdoor reduction of whole venue temperature is 5 degrees. Comparing traditional directness and using air conditioner or air -cooler for the cooling of whole air film building, practiced thrift the energy consumption, further reduce air film building operation energy consumption, the same conditions air film is down construct air conditioner power and is descended 23 once more.

Description

Pneumatic membrane building point position VMC (Ventilation Mechanical Control System)
Technical field
This utility model is related to pneumatic membrane building field, more particularly, to a kind of pneumatic membrane building point position VMC (Ventilation Mechanical Control System).
Background technology
Pneumatic membrane building is also referred to as air and supports membrane structure (Air-Supported Structures), is to adopt high-performance PVC fabric coating building film material, according to design drawing welding fabrication, launches, surrounding is anchored with ground base at the construction field (site) Form confined space, after mechanical system is toward interior space inflation, whole knot is formed by inner air and outer air pressure reduction support membrane body Structure system, is equipped with wirerope system, intelligence control system, turnover door system, the functional module such as illuminator become and can resist wind, snow Novel closed-type construction style.
Existing pneumatic membrane building except be equipped with blowing device to ensure its internal air pressure in addition in addition it is also necessary to be equipped with air-conditioning, Temperature within pneumatic membrane building is adjusted by air-conditioning.Because air-conditioning needs to adjust the temperature within whole pneumatic membrane building, energy consumption is huge Greatly;And in actually used, the temperature in pneumatic membrane building does not need all regions to keep the same, only need to keep comfortable in rest area Temperature.
Utility model content
This utility model provides a kind of pneumatic membrane building point position VMC (Ventilation Mechanical Control System), to solve above-mentioned technical problem.
In order to achieve the above object, the technical solution of the utility model is realized in:A kind of pneumatic membrane building point position is new Wind system, including:Ajutage, encloses in pneumatic membrane building, and one end of ajutage is fresh air air inlet, and ajutage is locally arranged There are multiple air outlets;Shunting wind cabinet, is arranged at air inlet, and connects air inlet;Blower fan group, is arranged at air inlet, connection Shunting wind cabinet.
Further, ajutage includes ground ajutage and hangs ajutage, and the air outlet of ground ajutage is arranged on Side, the air outlet hanging ajutage is arranged on downside.
Further, hang ajutage apart from 3.5~4.5 meters of ground.
Further, shunting wind cabinet is provided with line air-valve.
Further, this pneumatic membrane building point position VMC (Ventilation Mechanical Control System) also includes PLC, and PLC is electrically connected with There are wind speed sensing instrument, differential pressure pickup and in line air-valve, PLC senses, according to wind speed, the prison that instrument and differential pressure pickup are passed back Survey the opening and closing of the in line air-valve of Data Control.
Further, ground ajutage includes telescopic section, and the caliber of telescopic section is slightly less than the caliber of ground ajutage.
Further, ajutage also includes embedded ajutage, is embedded in pneumatic membrane building bottom.
Further, this pneumatic membrane building point position VMC (Ventilation Mechanical Control System) also includes backwind tube, backwind tube connection pneumatic membrane building and blower fan Group.
Compared with prior art, the utility model has the advantage of:Using this utility model pneumatic membrane building point position fresh air system Clean cold air after filtering is directly sent to the rest area of client by ajutage by system, and in the air-supply positioned at rest area On pipe, multiple air outlets are locally set, only provide cold wind for rest area, within meeting 3 meters of rest area temperature control in 26-28 degree, Whole venue temperature reduces by 5 degree than outdoor.Comparing traditional directly use air-conditioning or air-cooler is whole pneumatic membrane building cooling, Save energy consumption, reduced pneumatic membrane building operation energy consumption further, the pneumatic membrane building air-conditioning power under equal conditions has declined 2/ again 3, steel building needs to be equipped with 320KW taking traditional steel building of 2000 square metres of careats and pneumatic membrane building as a example The air-conditioning of power, but pneumatic membrane building air-conditioning power configuration is in 80KW, and use this utility model pneumatic membrane building point position fresh air 2000 flat air-conditioning power only need to be scheduled on 25KW by system.
Brief description
In order to be illustrated more clearly that this utility model specific embodiment or technical scheme of the prior art, below will be right In specific embodiment or description of the prior art the accompanying drawing of required use be briefly described it should be apparent that, below describe In accompanying drawing be some embodiments of the present utility model, for those of ordinary skill in the art, do not paying creativeness On the premise of work, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of this utility model embodiment 1;
Fig. 2 is the structural representation of this utility model embodiment 2;
Fig. 3 is the structural representation of this utility model embodiment 3.
In figure:1st, pneumatic membrane building;2nd, ajutage;20th, air outlet;21st, ground ajutage;22nd, hang ajutage;23rd, bury If ajutage;24th, air inlet;3rd, shunt wind cabinet;31st, in line air-valve;4th, blower fan group;5th, PLC;6th, wind speed sensing instrument; 7th, differential pressure pickup;8th, telescopic section;9th, escape door;10th, backwind tube.
Specific embodiment
Below with reference to accompanying drawing, clear, complete description is carried out to the technical scheme of each embodiment of this utility model it is clear that Described embodiment is only a part of embodiment of the present utility model, rather than whole embodiments.New based on this practicality Embodiment in type, the obtained all other reality on the premise of not making creative work of those of ordinary skill in the art Apply example, broadly fall into the scope that this utility model is protected.
Below by specific embodiment and combine accompanying drawing this utility model is described in further detail.
Embodiment 1
As shown in figure 1, this utility model embodiment is related to a kind of pneumatic membrane building point position VMC (Ventilation Mechanical Control System), including:Ajutage 2, Enclose in pneumatic membrane building 1, one end of ajutage 2 is fresh air air inlet 24, and ajutage 2 is partially provided with multiple air outlets 20;Shunting wind cabinet 3, is arranged at air inlet 24, and connects air inlet 24;Blower fan group 4, is arranged at air inlet 24, connection point Stream wind cabinet 3.
Ajutage 2 is arranged on inside pneumatic membrane building 1, and the inwall setting around pneumatic membrane building 1, and blower fan group 4 is defeated by cold wind Deliver to the regional being then delivered to pneumatic membrane building 1 in shunting wind cabinet 3 after shunting wind cabinet 3 shunting by ajutage 2, Designated area, the such as ajutage 2 of rest area locally arrange multiple air outlets 20, make the cold wind in ajutage 2 pinpoint to Blown in rest area.The integrated air-conditioning of blower fan group 4, blower fan and switch board are in one.Ajutage 2 is typically three in pneumatic membrane building 1 Face is enclosed and is set, and the side arranging revolving door in pneumatic membrane building 1 is typically not provided with ajutage 2.
Using this utility model pneumatic membrane building point position VMC (Ventilation Mechanical Control System), by ajutage 2 by clean cold air after filtering It is directly sent to the rest area of client, and multiple air outlets 20 are locally being arranged on the ajutage 2 of rest area, be only rest area There is provided cold wind, within meeting 3 meters of rest area, in 26-28 degree, whole venue temperature reduces by 5 degree to temperature control than outdoor.Compare biography Directly being lowered the temperature for whole pneumatic membrane building 1 using air-conditioning or air-cooler of system, has saved energy consumption, reduces pneumatic membrane building 1 further Operation energy consumption, the pneumatic membrane building 1 air-conditioning power under equal conditions declines 2/3, again with the tradition of 2000 square metres of careats As a example steel building and pneumatic membrane building 1, steel building needs to be equipped with the air-conditioning of 320KW power, but pneumatic membrane building 1 air-conditioning work( Rate configuration is in 80KW, and uses this utility model pneumatic membrane building point position VMC (Ventilation Mechanical Control System) only need to be fixed by 2000 flat air-conditioning power In 25KW.
Preferably, ajutage 2 includes ground ajutage 21 and hangs ajutage 22, and the air outlet 20 of ground ajutage 21 sets Put in upside, the air outlet 20 hanging ajutage 22 is arranged on downside.
Ajutage 2 includes the ground ajutage 21 arranging as required on the ground and hangs on pneumatic membrane building 1 inwall Suspension ajutage 22, can be to designated area transporting cold wind, the air outlet 20 of ground ajutage 21 is opened in ground air-supply The upside of pipe 21, makes cold air be delivered up by ground;The air outlet 20 hanging ajutage 22 is opened under suspension ajutage 22 Side, makes cold air convey from top to bottom.It is provided that ground ajutage 21 in the present embodiment.In other embodiments can basis Need to arrange suspension ajutage 22 or both are respectively provided with.
Preferably, shunting wind cabinet 3 is provided with line air-valve 31.
In line air-valve 31 is used for directly to transporting cold wind in pneumatic membrane building 1, quick conveying gas in needs are to pneumatic membrane building 1 During body, open the in line air-valve 31 on shunting wind cabinet 3, the bore of in line air-valve 31 is more than the bore of the air inlet 24 of ajutage 2, The cold wind overwhelming majority that blower fan group 4 is delivered to shunting wind cabinet 3 is fed directly in pneumatic membrane building 1 by line air-valve 31, makes gas Body is quickly delivered in pneumatic membrane building 1.In line air-valve 31 is louver shape, convenient unlatching, and structure is simple.
Preferably, this pneumatic membrane building point position VMC (Ventilation Mechanical Control System) also includes PLC 5, and PLC 5 is electrically connected with There are wind speed sensing instrument 6, differential pressure pickup 7 and in line air-valve 31, PLC 5 senses instrument 6 and differential pressure pickup 7 according to wind speed The Monitoring Data passed back controls the opening and closing of in line air-valve 31.
PLC 5 is used for automatically controlling the opening and closing of in line air-valve 31, wind speed sensing instrument 6, differential pressure pickup 7 It is electrically connected with PLC 5, for monitoring the pressure difference of outdoor wind speed and indoor and outdoor in real time, record outdoor when wind speed senses instrument 6 When wind-force reaches setting value or indoor and outdoor pressure reduction less than 200pa, PLC 5 controls in line air-valve 31 to automatically turn on, cold Wind is directly discharged in pneumatic membrane building 1, reaches setting pressure reduction it is ensured that safety in the short time.
Preferably, ground ajutage 21 includes telescopic section 8, and the caliber of telescopic section 8 is slightly less than the caliber of ground ajutage 21.
Ground ajutage 21 is arranged on the ground, and the inwall setting around pneumatic membrane building 1, when through escape door 9, needs When escape door 9 to be considered is opened, ajutage 2 can hinder the traveling of personnel, so setting ground ajutage 21 at escape door 9 Put a section telescopic section 8, the caliber of telescopic section 8 is slightly less than the caliber of ground ajutage 21, when needing using escape door 9, will stretch In contracting section 8 retraction ground ajutage 21, do not affect the emergency evacuation of personnel;When needing normally to use ground ajutage 21, make With telescopic section 8 linking ground ajutage 21, do not affect the conveying of cold wind.
Preferably, this pneumatic membrane building point position VMC (Ventilation Mechanical Control System) also includes backwind tube 10, backwind tube 10 connection pneumatic membrane building 1 and wind Unit 4.
Embodiment 2
As shown in Fig. 2 the present embodiment is with the difference of embodiment 1:It is provided that suspension ajutage 22 in the present embodiment, Preferably, hang ajutage 22 apart from 3.5~4.5 meters of ground.It is provided in from the ground 3.5 by hanging ajutage 22 as required ~4.5 meters of distance preferably, is provided with from the ground 4 meters as optimal.
Embodiment 3
As shown in figure 3, the present embodiment is with the difference of embodiment 1 and 2:Ajutage 2 also includes embedded ajutage 23, buries Located at pneumatic membrane building 1 bottom.
Ground end ajutage 2 being embedded in below pneumatic membrane building 1 is embedded ajutage 23, and embedded ajutage 23 will not account for With ground space, same arranges multiple air outlets in designated area on embedded ajutage 23, and cold wind is delivered to specified area Domain.
The above, be only preferred embodiment of the present utility model, not this utility model is made any formal Restriction, any those skilled in the art, in the range of without departing from technical solutions of the utility model, when can be utilized above-mentioned The technology contents disclosing make a little Equivalent embodiments changing or be modified to equivalent variations, as long as being without departing from this utility model The content of technical scheme, any simple modification above example made according to technical spirit of the present utility model, equivalent change Change and modify, all still fall within the range of technical solutions of the utility model.

Claims (8)

1. a kind of pneumatic membrane building point position VMC (Ventilation Mechanical Control System) is it is characterised in that include:
Ajutage, encloses in pneumatic membrane building, and one end of described ajutage is fresh air air inlet, and described ajutage is locally arranged There are multiple air outlets;
Shunting wind cabinet, is arranged at described air inlet, and connects described air inlet;
Blower fan group, is arranged at described air inlet, connection described shunting wind cabinet.
2. pneumatic membrane building point position VMC (Ventilation Mechanical Control System) as claimed in claim 1 it is characterised in that:Described ajutage includes ground air-supply Pipe and suspension ajutage, the air outlet of described ground ajutage is arranged on upside, and the described air outlet hanging ajutage is arranged on Downside.
3. pneumatic membrane building point position VMC (Ventilation Mechanical Control System) as claimed in claim 2 it is characterised in that:Described suspension ajutage is apart from ground 3.5~4.5 meters.
4. pneumatic membrane building point position VMC (Ventilation Mechanical Control System) as claimed in claim 1 it is characterised in that:It is provided with straight on described shunting wind cabinet Exhaust valve.
5. pneumatic membrane building point position VMC (Ventilation Mechanical Control System) as claimed in claim 4 it is characterised in that:This pneumatic membrane building point position VMC (Ventilation Mechanical Control System) Also include PLC, described PLC has been electrically connected with wind speed sensing instrument, differential pressure pickup and described in line wind Valve, described PLC controls described in line according to the Monitoring Data that described wind speed sensing instrument and described differential pressure pickup are passed back The opening and closing of air-valve.
6. pneumatic membrane building point position VMC (Ventilation Mechanical Control System) as claimed in claim 2 it is characterised in that:Described ground ajutage includes stretching Section, the caliber of described telescopic section is slightly less than the caliber of described ground ajutage.
7. pneumatic membrane building point position VMC (Ventilation Mechanical Control System) as claimed in claim 1 it is characterised in that:Described ajutage also includes embedded sending Airduct, is embedded in pneumatic membrane building bottom.
8. pneumatic membrane building point position VMC (Ventilation Mechanical Control System) as claimed in claim 1 it is characterised in that:This pneumatic membrane building point position VMC (Ventilation Mechanical Control System) Also include backwind tube, described backwind tube connects described pneumatic membrane building and blower fan group.
CN201620906662.XU 2016-08-19 2016-08-19 Air film building position new trend system Expired - Fee Related CN205957419U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620906662.XU CN205957419U (en) 2016-08-19 2016-08-19 Air film building position new trend system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620906662.XU CN205957419U (en) 2016-08-19 2016-08-19 Air film building position new trend system

Publications (1)

Publication Number Publication Date
CN205957419U true CN205957419U (en) 2017-02-15

Family

ID=57977912

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620906662.XU Expired - Fee Related CN205957419U (en) 2016-08-19 2016-08-19 Air film building position new trend system

Country Status (1)

Country Link
CN (1) CN205957419U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110207754A (en) * 2019-06-24 2019-09-06 上海交通大学 A kind of large deformation Long-term Monitoring Systems of inflation film building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110207754A (en) * 2019-06-24 2019-09-06 上海交通大学 A kind of large deformation Long-term Monitoring Systems of inflation film building

Similar Documents

Publication Publication Date Title
CN105509162B (en) Constant temperature curtain wall system
CN101617176A (en) Air conditioning and ventilating device
CN107504614A (en) Fresh air introducing mechanism, mounting method and air conditioner
CN205957419U (en) Air film building position new trend system
CN206145847U (en) Domestic central air -conditioning system
CN208282277U (en) New blower
CN206361852U (en) A kind of Classroom air purifier
CN205976711U (en) Air film building exhaust system
CN107444604A (en) A kind of air-conditioning system and the ship comprising the air-conditioning system
CN206973758U (en) Fresh air introducing mechanism and air conditioner
CN207438811U (en) A kind of fresh air system suitable for compound building
CN106940062A (en) A kind of indoor ventilation system
CN207437115U (en) A kind of underground railway tunnel fire ventilation smoke extraction system
CN216665658U (en) Traffic tunnel air supply system
CN206338871U (en) Ceiling mounting type fresh air air conditioner humidifies dehumidifying integrated machine
CN205878440U (en) No computer lab column air conditioning system
CN208059203U (en) A kind of intelligent fresh air system
CN103604188B (en) Domestic indoor/outdoor air circulation system
CN107044708A (en) Indoor air-purification device and air conditioner and indoor air purification method
CN207196806U (en) One kind air-supply cooling system
CN207635531U (en) A kind of bathroom air interchanger
CN207395090U (en) Closed chamber with Humidity Detection control device
CN207350490U (en) A kind of cold air distribution energy-saving air conditioning system
CN206131171U (en) Intelligence building ventilation system
CN206973713U (en) A kind of air-conditioning returns air draft automaton

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170215

Termination date: 20170819

CF01 Termination of patent right due to non-payment of annual fee