A kind of mould for preparing muscle prefabricated component
Technical field
This utility model belong to architectural prefab production technical field and in particular to a kind of for preparing muscle prefabricated component
Mould.
Background technology
In assembled architecture prefabricated components production process, precast concrete cast needs to reserve to stretch out reinforcing bar often, therefore
Setting in die station is needed to be easy to the side mould of muscle.During production, muscle side mould or punching block are produced according to the size of prefabricated components,
Again it is placed on fixed station mould and is produced.During the demoulding, by the artificial connector separating each assembly in mould, then pass through
Mould is removed by artificial or boom hoisting.In prior art, for preparing the mould often complex structure of muscle prefabricated component, no
Only assemble loaded down with trivial details, and be difficult the demoulding, bring larger inconvenience to installation and production, increase extensive work amount.
In sum, need badly provide a kind of structure simple, easy to use, be easy to the demoulding for preparing muscle prefabricated component
Mould.
Utility model content
The purpose of this utility model be provide that a kind of structure is simple, easy to use, be easy to the demoulding be used for that to prepare muscle pre-
The mould of product.
Above-mentioned purpose is to be achieved through the following technical solutions: a kind of mould for preparing muscle prefabricated component, at least includes
The locating part going out gusset, connecting plate and connecting gusset and connecting plate, described go out gusset and connecting plate be oppositely arranged, described go out
Gusset is provided with wears muscle hole, and described wearing in muscle hole is provided with sealing strip, and described sealing strip is provided with wears seam, the bottom of described connecting plate
Higher than described go out gusset bottom.This utility model goes out gusset and goes out reinforced concrete face and contact, and connecting plate is connected with rib mould
And be fixed on bed die by fixture.It is arranged such, stretches out reinforcing bar and wear muscle hole, and wear seam by extruding and crossing, rise
To preferable sealing effectiveness;The bottom of connecting plate is higher than the bottom gusset, so, after this utility model installation forming, connects
There is certain difference in height, so, during the demoulding, applying a downward power to this utility model can use between plate and bed die
Gusset is departed from prefabricated component concrete surface, facilitates dismounting of the present utility model, improves demoulding efficiency.
Further, described locating part is the top board being arranged on out gusset and connecting plate top.The setting of locating part is it is ensured that go out
Form accommodation space between gusset and connecting plate and stretch out reinforcing bar it will be appreciated that the width of top board is not less than stretches out steel in order to accommodate
Muscle stretches out the length of prefabricated component part;Meanwhile, during the setting of top board can prevent casting concrete, concrete is splashed into this reality
With new interior.
Further, described locating part at least includes being arranged on out the limiting plate of gusset and connecting plate two ends.It is arranged such, limit
Position plate one side plays the effect limiting distance between gusset and connecting plate, on the other hand can play booster action, this practicality
New structure is more firm.
Further, described limiting plate offers through hole.It is arranged such, not only saves material, reduce cost, significantly simultaneously
Alleviate weight of the present utility model, be easy to the operation of workmen;Now limiting plate can use as handle, is easy to carry.
Further, also include top board, described top board be located at described go out gusset and connecting plate top, described top board one end with
Go out gusset to be connected, the other end is connected with connecting plate.During the setting of top board can prevent casting concrete, concrete is splashed into this
In utility model.
Further, the described hole wall wearing muscle hole is provided with cannelure, and described sealing strip embeds in described cannelure.So set
Put, sealing strip is reliably connected with wearing muscle hole and being formed, and easy to connect, it is to avoid when reinforcing bar passes through sealing member, sealing strip is from wearing muscle hole
Come off, affect sealing effectiveness.
Further, described sealing strip is prepared by flexible material, described sealing strip with wear muscle hole interference fit.It is arranged such,
Simple installation, sealing effectiveness is preferable;Described sealing strip can be rubber or silica gel.
Further, described connecting plate is provided with installing hole or draw-in groove.It is arranged such, be easy to connecting plate solid with the connection of rib mould
Fixed, described connecting plate can be connected with rib mould by bolt, locking part or shackle member with rib mould.As during using locking part,
Described locking part includes eccentric compressive bar, connecting rod and locking block, and described connecting rod one end is connected with eccentric compressive bar by bearing pin, the other end
It is connected with locking block;Described connecting rod is worn and is connect described installing hole, and described locking block makes it along installing hole by adjusting eccentric compressive bar
Axial movement.
Further, described go out gusset be detachably connected with locating part.It is arranged such, can different to go out muscle prefabricated according to producing
Part and change the gusset that of different model or specification, increase the suitability of the present utility model.
Further, described go out to be provided between gusset and connecting plate and stretch out the fixture of reinforcing bar for fixation.It is arranged such, keep away
Stretch out reinforcing bar Oscillation Amplitude during exempting from prefabricated component vibration moulding excessive, lead to concrete slurry edge to wear seepage in muscle hole.
Further, described go out the outer wall of side that contacts with prefabricated component of gusset be provided with flexible material.It is arranged such, can
To reduce the cohesive force gusset and concrete, both can protect mould, be also beneficial to form removal.Described flexible material both can be with
Go out gusset with the spraying method rubber combining or the polyurethane sheet being bolted, certainly should also be as including it
He can achieve above-mentioned technical purpose technical scheme.
Brief description
The accompanying drawing constituting a part of the present utility model is used for providing further understanding to of the present utility model, and this practicality is new
The schematic description and description of type is used for explaining this utility model, does not constitute to improper restriction of the present utility model.
Fig. 1 and Fig. 2 is respectively being used for involved by a kind of embodiment of this utility model and prepares muscle prefabricated-member mould not
Structural representation during sealing strip is installed;
Fig. 3 is the structural representation for preparing muscle prefabricated-member mould involved by a kind of embodiment of this utility model
Figure;
Fig. 4 is involved in Fig. 3 not install structural representation during sealing strip for preparing muscle prefabricated-member mould;
Fig. 5 is the involved end view for preparing muscle prefabricated-member mould in Fig. 4;
Fig. 6 is the schematic diagram of the involved fixation for preparing muscle prefabricated-member mould or use state in Fig. 4;
Fig. 7 is the profile in Fig. 6 along a a section;
Fig. 8 is the structural representation of involved locking part in Fig. 6 and Fig. 7;
Fig. 9 is for preparing fixing or making of muscle prefabricated-member mould involved by this utility model another embodiment
End view with state.
In figure:
1 goes out gusset 2 connecting plate 3 wears muscle hole 4 sealing strip
5 wear seam 6 top board, 7 limiting plate 8 through hole
9 installing hole, 10 rib mould, 11 locking part 12 eccentric compressive bar
13 connecting rod, 14 locking block, 15 bolt 16 cushion block
17 head 18 bearing pin
Specific embodiment
Below in conjunction with the accompanying drawings this utility model is described in detail, the description of this part is only exemplary and explanatory,
Should not there is any restriction effect to protection domain of the present utility model.Additionally, those skilled in the art's retouching according to presents
State, respective combination can be carried out to the feature in embodiment in presents and in different embodiment.
This utility model embodiment is as follows, with reference to Fig. 1~4 and Fig. 7, a kind of mould for preparing muscle prefabricated component, extremely
Include gusset 1, connecting plate 2 less and connect gusset 1 and the locating part of connecting plate 2, described go out gusset 1 and connecting plate 2 phase
To setting, described go out gusset 1 be provided with and wear muscle hole 3, described wearing is provided with sealing strip 4 in muscle hole 3, described sealing strip 4 is provided with to wear and connects
Seam 5, the bottom of described connecting plate 2 be higher than described go out gusset 1 bottom.This utility model goes out gusset 1 and goes out reinforced concrete face phase
Contact, connecting plate 2 is connected with rib mould 10 and is fixed on bed die by fixture.It is arranged such, stretch out reinforcing bar and wear muscle
Hole 3, and wear seam 5 by extruding and crossing, play preferable sealing effectiveness;The bottom of connecting plate 2 is higher than the bottom gusset 1,
So, after this utility model installation forming, between connecting plate 2 and bed die, there is certain difference in height, so, during the demoulding, to this
Utility model applies a downward power and can use gusset 1 and the disengaging of prefabricated component concrete surface, facilitates of the present utility model tearing open
Unload, improve demoulding efficiency.
On the basis of above-described embodiment, in another embodiment of this utility model, such as Fig. 2, described locating part is to be arranged on
Go out gusset 1 and the top board 6 at connecting plate 2 top.The setting of locating part is it is ensured that go out formation accommodation space between gusset 1 and connecting plate 2
Stretch out reinforcing bar in order to accommodate it will be appreciated that the width of top board 6 is not less than stretches out the length that reinforcing bar stretches out prefabricated component part;Meanwhile,
During the setting of top board 6 can prevent casting concrete, concrete is splashed in this utility model.
On the basis of above-described embodiment, in another embodiment of this utility model, such as Fig. 1, described locating part at least includes
It is arranged on out gusset 1 and the limiting plate 7 at connecting plate 2 two ends.It is arranged such, limiting plate 7 one aspect plays and limits gusset 1 and connect
The effect of distance between fishplate bar 2, on the other hand can play booster action, and this utility model structure is more firm.
On the basis of above-described embodiment, in another embodiment of this utility model, such as Fig. 1 and Fig. 5, described limiting plate 7 is opened
It is provided with through hole 8.It is arranged such, not only saves material, reduce cost, significantly reduce weight of the present utility model, just simultaneously
Operation in workmen;Now limiting plate 7 can use as handle, is easy to carry.
On the basis of above-described embodiment, in another embodiment of this utility model, such as Fig. 3, also include top board 6, described top
Plate 6 be located at described go out gusset 1 and connecting plate 2 top, described top board 6 one end is connected with going out gusset 1, the other end and connecting plate 2
It is connected.During the setting of top board 6 can prevent casting concrete, concrete is splashed in this utility model.
On the basis of above-described embodiment, in another embodiment of this utility model, the described hole wall wearing muscle hole 3 is provided with annular
Groove, described sealing strip 4 embeds in described cannelure.It is arranged such, sealing strip 4 is reliably connected with wearing muscle hole 3 formation, and connection side
Just, it is to avoid when reinforcing bar passes through sealing member, sealing strip 4 comes off from wearing muscle hole 3, affect sealing effectiveness.
On the basis of above-described embodiment, in another embodiment of this utility model, described sealing strip 4 is by flexible material system
Standby, described sealing strip 4 with wear muscle hole 3 interference fit.It is arranged such, simple installation, sealing effectiveness is preferable;Described sealing strip 4 can
For rubber or silica gel.
On the basis of above-described embodiment, in another embodiment of this utility model, such as Fig. 6~9, described connecting plate 2 is provided with
Installing hole 9 or draw-in groove.It is arranged such, be easy to being connected of connecting plate 2 and rib mould 10, described connecting plate 2 and rib mould 10
Can be connected with rib mould 10 by bolt 15, locking part 11 or shackle member, described bolt 15, locking part 11 or shackle member are worn and connect
Described installing hole 9.As during using locking part 11, such as Fig. 8, described locking part 11 includes eccentric compressive bar 12, connecting rod 13 and locking block
14, described connecting rod 13 one end is connected with eccentric compressive bar 12 by bearing pin 18, and the other end is connected with locking block 14;Described connecting rod 13 is worn
Connect described installing hole 9, described locking block 14 passes through regulation eccentric compressive bar 12 makes it along the axial movement of installing hole 9.
As Fig. 8, described eccentric compressive bar 12 includes head 17, and described head 17 is provided with eccentric pivoted hole, described bearing pin 18 pivot
It is connected to described bias pivoted hole.By adjusting eccentric compressive bar so that thickness between eccentric pivoted hole and connecting plate 2 for the head 17
Become big, and then drive locking block mobile to connecting plate 2, lock baffle plate template.
As Fig. 8, described connecting rod 13 is socketed with cushion block 16, described head 17 is close in the side of described cushion block 16.Cushion block 16
Setting, play certain cushioning effect, it is to avoid head 17 directly contacts with connecting plate 2 and locked, it is to avoid damage head 17 He
Connecting plate 2, increases the service life.
On the basis of above-described embodiment, in another embodiment of this utility model, described go out gusset 1 detachable with locating part
Connect.Be arranged such, can according to produce different go out muscle prefabricated component and change different model or specification go out gusset 1, increase this
The suitability of utility model.
On the basis of above-described embodiment, in another embodiment of this utility model, described go out between gusset 1 and connecting plate 2
It is provided with the fixture stretching out reinforcing bar for fixation.It is arranged such, it is to avoid during prefabricated component vibration moulding, stretch out reinforcing bar vibration width
Spend big, lead to concrete slurry edge to wear seepage in muscle hole 3.
On the basis of above-described embodiment, in another embodiment of this utility model, described go out gusset 1 contact with prefabricated component
The outer wall of side be provided with flexible material.It is arranged such, the cohesive force gusset 1 and concrete can be reduced, both can protect
Mould, is also beneficial to form removal.Described flexible material both can be with go out the rubber that gusset 1 combines with spraying method it is also possible to
It is the polyurethane sheet being connected by bolt 15, certainly should also be as can achieve above-mentioned technical purpose technical scheme including other.
The above is only preferred implementation of the present utility model it is noted that common skill for the art
For art personnel, on the premise of without departing from this utility model principle, some improvements and modifications can also be made, these improve and
Retouching also should be regarded as protection domain of the present utility model.