CN205861111U - Power boiler burning optimization parameter experiment analyzes system - Google Patents

Power boiler burning optimization parameter experiment analyzes system Download PDF

Info

Publication number
CN205861111U
CN205861111U CN201620721656.7U CN201620721656U CN205861111U CN 205861111 U CN205861111 U CN 205861111U CN 201620721656 U CN201620721656 U CN 201620721656U CN 205861111 U CN205861111 U CN 205861111U
Authority
CN
China
Prior art keywords
temperature
flue gas
differential pressure
pressure gauge
optimization parameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620721656.7U
Other languages
Chinese (zh)
Inventor
王泽璞
王博
王然
刘岩
刘曜恺
邢红涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Datang Corp Science and Technology Research Institute Co Ltd
Original Assignee
China Datang Corp Science and Technology Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Datang Corp Science and Technology Research Institute Co Ltd filed Critical China Datang Corp Science and Technology Research Institute Co Ltd
Priority to CN201620721656.7U priority Critical patent/CN205861111U/en
Application granted granted Critical
Publication of CN205861111U publication Critical patent/CN205861111U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Regulation And Control Of Combustion (AREA)

Abstract

This utility model relates to a kind of power boiler burning optimization parameter experiment and analyzes system, including flue gas analyzer, distributed temperature collection system, electronics differential pressure gauge, coal fines screening instrument and comprehensive analysis processing device, described flue gas analyzer is installed on the exhaust opening of boiler, described distributed temperature collection system includes multiple temperature sensor, multiple described temperature sensors are respectively arranged in each Temperature-control Monitoring point of steam generator system, described electronics differential pressure gauge is installed on boiler exhaust gas pipeline, described coal fines screening instrument is installed on the coal pulverizing system in power station, described flue gas analyzer, distributed temperature collection system, electronics differential pressure gauge and coal fines screening instrument are electrically connected described comprehensive analysis processing device, described comprehensive analysis processing device is the processor of steam generator system industrial computer.Boiler operating parameter can be monitored, collects and analyze by this utility model, thus automatically generates optimization operating scheme, can make up the weak point that Traditional Man experience optimizes.

Description

Power boiler burning optimization parameter experiment analyzes system
Technical field
This utility model relates to boiler operatiopn data monitoring technical field, particularly relates to one and carries out boiler operating parameter Monitoring, the pilot system collected and analyze.
Background technology
In recent years, the thermoelectricity installed capacity of China persistently rises, and the competition situation of GENERATION MARKET is the severeest.The opposing party Face, the constraint that coal price cost is ascended to heaven and domestic various environmental protection specifications are tightened up, within following a period of time, how electricity power enterprise carries High burning efficiency, reduces pollutant emission, reduces cost of electricity-generating and will become one of problem of its emphasis consideration.
The technological means analysis relied on is run, mainly according to the burning optimization Adjustment Tests knot of boiler from current combustion Really, operations staff artificial burning combustion adjustment is carried out according to the operating experience of oneself.There is asking of the following aspects in this Topic:
Due to the time of being put to the test and the restriction of condition, combustion adjustment test the most only carries out limited load point, the most not Consider coal type change and the situation of many combustion of mixed coals;Secondly, performance and the plant characteristic of boiler plant elapse in time, unit The situations such as maintenance change.Therefore boiler actual operating mode is general and operating condition of test has larger difference, causes original excellent Change result of the test deviation optimal value the most invalid.Adjust if operations staff carries out burning still according to original optimization Test result Whole, bigger deviation will necessarily be caused;From the point of view of operations staff, objectively there is the biggest difference in the level of each operations staff Different, even same boiler main behaviour, affected by subjective factors, in the different time, its operation level also likely to be present difference, Therefore the boiler combustion carried out with operating experience adjusts operation and has certain randomness.
Because above-mentioned defect, the design people, the most in addition research and innovation, excellent to founding a kind of power boiler burning Change parameter experiment and analyze system, to reach boiler operating parameter to be monitored, collect and analyzes, thus optimize boiler operatiopn Purpose.
Utility model content
For solving above-mentioned technical problem, the purpose of this utility model is to provide a kind of power boiler burning optimization parameter experiment Analysis system, it is possible to boiler operating parameter is monitored, collects and analyzes, thus automatically generate optimization operating scheme, permissible Make up the weak point that Traditional Man experience optimizes.
A kind of power boiler burning optimization parameter experiment of the present utility model analyzes system, including flue gas analyzer, distribution Formula temperature acquisition system, electronics differential pressure gauge, coal fines screening instrument and comprehensive analysis processing device, described flue gas analyzer is installed on pot The exhaust opening of stove, described distributed temperature collection system includes that multiple temperature sensor, multiple described temperature sensors are pacified respectively Being loaded on each Temperature-control Monitoring point of steam generator system, described electronics differential pressure gauge is installed on boiler exhaust gas pipeline, described pulverized coal sieve Point instrument is installed on the coal pulverizing system in power station, described flue gas analyzer, distributed temperature collection system, electronics differential pressure gauge and Coal fines screening instrument is electrically connected described comprehensive analysis processing device, and described comprehensive analysis processing device is the place of steam generator system industrial computer Reason device.
Further, described flue gas analyzer is integrated with electrochemical sensor and infrared sensor.
Further, the temperature sensor of described distributed temperature collection system is DS18820 digital temperature sensor.
Further, the temperature sensor of described distributed temperature collection system is provided with 5-30.
Further, described electronics differential pressure gauge is SwemaMan 7.
Further, the temperature sensor of described distributed temperature collection system is provided with 15-25.
By such scheme, this utility model at least has the advantage that power boiler burning optimization of the present utility model Parameter experiment is analyzed system and is mainly by flue gas analyzer, distributed temperature collection system, electronics differential pressure gauge, coal fines screening The parameters such as flue gas pollutant parameter, temperature-controlled parameter, oxygen pressure parameter and the fineness of pulverized coal of steam generator system are carried out in real time by instrument respectively Monitoring, and send data to comprehensive analysis processing device and be analyzed, draws steam generator system prioritization scheme, Automatic Control, The weak point that Traditional Man experience optimizes can be made up.
Described above is only the general introduction of technical solutions of the utility model, in order to better understand skill of the present utility model Art means, and can being practiced according to the content of description, below with preferred embodiment of the present utility model and coordinate accompanying drawing detailed Describe in detail bright as after.
Accompanying drawing explanation
Fig. 1 is principle schematic of the present utility model.
Detailed description of the invention
Below in conjunction with the accompanying drawings and embodiment, detailed description of the invention of the present utility model is described in further detail.Below Embodiment is used for illustrating this utility model, but is not limited to scope of the present utility model.
Seeing Fig. 1, a kind of power boiler burning optimization parameter experiment described in this utility model one preferred embodiment is analyzed System, including flue gas analyzer 1, distributed temperature collection system 2, electronics differential pressure gauge 3, coal fines screening instrument 4 and comprehensively analyzes Processor 5, described flue gas analyzer is installed on the exhaust opening of boiler, and described distributed temperature collection system includes that multiple temperature passes Sensor 21, multiple described temperature sensors are respectively arranged in each Temperature-control Monitoring point of steam generator system, described electronics differential pressure gauge Being installed on boiler exhaust gas pipeline, described coal fines screening instrument is installed on the coal pulverizing system in power station, described flue gas analyzer, point Cloth temperature acquisition system, electronics differential pressure gauge and coal fines screening instrument are electrically connected described comprehensive analysis processing device, described comprehensive Close the processor that analysis processor is steam generator system industrial computer.
Described flue gas analyzer is integrated with electrochemical sensor and infrared sensor.
The temperature sensor of described distributed temperature collection system is DS18820 digital temperature sensor.
Described electronics differential pressure gauge is SwemaMan 7.
The temperature sensor of described distributed temperature collection system is provided with 15-25.
Operation principle of the present utility model is as follows: by flue gas analyzer, distributed temperature collection system, electronics differential pressure Flue gas pollutant parameter, temperature-controlled parameter, oxygen pressure parameter and the fineness of pulverized coal etc. of steam generator system are joined by meter, coal fines screening instrument respectively Number monitors in real time, and sends data to comprehensive analysis processing device and be analyzed, and draws steam generator system prioritization scheme, complete from Dynamicization controls, and can make up the weak point that Traditional Man experience optimizes.
The above is only preferred implementation of the present utility model, is not limited to this utility model, it is noted that For those skilled in the art, on the premise of without departing from this utility model know-why, it is also possible to do Going out some improvement and modification, these improve and modification also should be regarded as protection domain of the present utility model.

Claims (6)

1. a power boiler burning optimization parameter experiment analyzes system, it is characterised in that: include flue gas analyzer, distributed temperature Degree acquisition system, electronics differential pressure gauge, coal fines screening instrument and comprehensive analysis processing device, described flue gas analyzer is installed on boiler Exhaust opening, described distributed temperature collection system includes that multiple temperature sensor, multiple described temperature sensors are respectively arranged in Each Temperature-control Monitoring point of steam generator system, described electronics differential pressure gauge is installed on boiler exhaust gas pipeline, described coal fines screening instrument It is installed on the coal pulverizing system in power station, described flue gas analyzer, distributed temperature collection system, electronics differential pressure gauge and coal dust Pulp classifier is electrically connected described comprehensive analysis processing device, and described comprehensive analysis processing device is the process of steam generator system industrial computer Device.
Power boiler burning optimization parameter experiment the most according to claim 1 analyzes system, it is characterised in that: described flue gas Analyser is integrated with electrochemical sensor and infrared sensor.
Power boiler burning optimization parameter experiment the most according to claim 1 analyzes system, it is characterised in that: described distribution The temperature sensor of formula temperature acquisition system is DS18820 digital temperature sensor.
Power boiler burning optimization parameter experiment the most according to claim 1 analyzes system, it is characterised in that: described distribution The temperature sensor of formula temperature acquisition system is provided with 5-30.
Power boiler burning optimization parameter experiment the most according to claim 1 analyzes system, it is characterised in that: described electronics Differential pressure gauge is SwemaMan 7.
Power boiler burning optimization parameter experiment the most according to claim 4 analyzes system, it is characterised in that: described distribution The temperature sensor of formula temperature acquisition system is provided with 15-25.
CN201620721656.7U 2016-07-08 2016-07-08 Power boiler burning optimization parameter experiment analyzes system Expired - Fee Related CN205861111U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620721656.7U CN205861111U (en) 2016-07-08 2016-07-08 Power boiler burning optimization parameter experiment analyzes system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620721656.7U CN205861111U (en) 2016-07-08 2016-07-08 Power boiler burning optimization parameter experiment analyzes system

Publications (1)

Publication Number Publication Date
CN205861111U true CN205861111U (en) 2017-01-04

Family

ID=57646878

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620721656.7U Expired - Fee Related CN205861111U (en) 2016-07-08 2016-07-08 Power boiler burning optimization parameter experiment analyzes system

Country Status (1)

Country Link
CN (1) CN205861111U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112113610A (en) * 2020-08-24 2020-12-22 广东省特种设备检测研究院顺德检测院 Boiler energy-saving and environment-friendly detection system and method based on Internet of things

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112113610A (en) * 2020-08-24 2020-12-22 广东省特种设备检测研究院顺德检测院 Boiler energy-saving and environment-friendly detection system and method based on Internet of things

Similar Documents

Publication Publication Date Title
CN102734782B (en) Coal burning boiler energy efficiency monitoring method
CN101839496B (en) Method for monitoring layering interfaces of multiple coal ranks in raw coal bunker
CN104374675B (en) A kind of coal pulverizer fineness of pulverized coal on-line monitoring method
CN109557869A (en) A kind of fired power generating unit carbon emission on-line monitoring management system
CN104633765B (en) Energy-conservation control system and method
CN102880795A (en) Method for acquiring target values of boiler optimized operation economic parameters
Makonese et al. Influence of fire-ignition methods and stove ventilation rates on gaseous and particle emissions from residential coal braziers
CN109541168A (en) A kind of economic fineness of pulverized coal on-line monitoring and method of adjustment
CN105318348A (en) Thermal power generating unit coal feeding amount feedback correction method based on coal-air ratio coal thermal value correction
CN111522323A (en) Boiler energy efficiency online diagnosis and intelligent control method based on Internet of things technology
CN105573261A (en) Optimized monitoring method for power plant boiler combustion
CN205861111U (en) Power boiler burning optimization parameter experiment analyzes system
CN105004688A (en) Exhaust gas monitoring system of thermal power station
Masondo et al. Influence of coal-particle size on emissions using the top-lit updraft ignition method
CN205879240U (en) Coal -fired power plant boiler combustion parameter optimization test analysis system based on wireless transmission
CN110506245A (en) Diagnostic device and diagnostic method
CN112486044A (en) Physical network-based monitoring control system for water boiling of coal gas
CN205861220U (en) The distributed pilot system without cable temperature monitoring of steam generator system
CN103629690B (en) The scattered control system of boiler-burner
CN106918464B (en) Opposed firing boiler operational diagnostics method and device before and after 600MW ultra supercritical
CN106405416B (en) A kind of adjustable output on-line analysis of unit based on the identification of ature of coal fluctuation status
CN205173023U (en) Portable digital fan observes and controls appearance
CN204903492U (en) Waste gas detector
CN109813860A (en) A kind of mpdal/analysis of boiler coal elemental composition
Kuai et al. Temporal and spatial variation characteristics of air pollution and prevention and control measures: evidence from Anhui Province, China

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170104

Termination date: 20170708