CN205839672U CN201620717255.4U CN201620717255U CN205839672U CN 205839672 U CN205839672 U CN 205839672U CN 201620717255 U CN201620717255 U CN 201620717255U CN 205839672 U CN205839672 U CN 205839672U
Authority
CN
China
Prior art keywords
pipeline
construction site
pipe
spray dust
reducing system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620717255.4U
Other languages
Chinese (zh)
Inventor
王智
刘耀军
余虎
周涛
王宏旭
李运闯
苏微
丁惠杰
毕航
毕一航
候飞
张康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201620717255.4U priority Critical patent/CN205839672U/en
Application granted granted Critical
Publication of CN205839672U publication Critical patent/CN205839672U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Nozzles (AREA)

Abstract

The utility model discloses a reusable assembly type spraying dust-settling system for a building construction site, which comprises a water inlet control unit and a spraying dust-settling unit; the water inlet control unit comprises a first pipeline, a filtering ball valve, a switch valve and a second pipeline which are sequentially connected and used for being connected with the fire fighting pipe; the spraying dust-settling unit comprises N spray heads which are sequentially arranged at intervals, every two adjacent spray heads are connected through a third pipeline, and each third pipeline is fixed on the road ground through a support piece; n is an integer greater than or equal to 2; and the second pipeline in the water inlet control unit is communicated with the third pipeline in the spray dust settling unit through a right-angle elbow. The utility model discloses system simple structure can realize facing the rapid assembly construction installation of building, and green is energy-conserving, and demountable installation circulation is utilized many times, practices thrift and faces this, and the technology installation is convenient, practices thrift the input of manpower, material, has good convenience and economic benefits.

Description

Construction site reusable assembled spray dust-reducing system
Technical field
This utility model relates to streets watering field, job site, reusable particularly to a kind of construction site Assembled spray dust-reducing system.
Background technology
Along with building trade improve constantly to job site dust-proof, control the requirement of the civilized constructions such as haze, face and build road Depositing dust is considered as that one time-consuming, laborious and the problem of DeGrain.Therefore, on-the-spot face when building road construction corresponding Depositing dust faces in saving how build on the premise of input can better services be a question of common concern in job site.At present Need badly and a kind of install convenient, save manpower, the input of material, have and facing of good convenience and economic benefit build road and automatically spray Mist measurements for reduction.
Utility model content
The purpose of this utility model is to provide a kind of construction site reusable assembled atomizing de-dusting system System, its installation is convenient, saves manpower and the input of material, has good convenience and economic benefit.
This utility model embodiment provides a kind of construction site reusable assembled spray dust-reducing system, bag Include into water control unit and atomizing de-dusting unit;Described water inlet control unit includes building road vertical direction from lower to upper along facing Be linked in sequence successively for the first pipeline, Filtering ball valve, controlled valve and the second pipe that are connected with extinguishing pipe;Described spraying Depositing dust unit includes building the most spaced N number of shower nozzle in road level direction along facing, and all passes through between adjacent two shower nozzles 3rd pipeline connects, and each described 3rd pipeline is all fixed on road ground by support member;N is the integer more than or equal to 2;Institute State described 3rd pipe connecting in described atomizing de-dusting unit by elbow bend into the described second pipe in water control unit Road.
Optionally, described first pipeline is connected with described extinguishing pipe by threeway.
Optionally, each described shower nozzle is respectively by the 4th pipeline and described 3rd pipeline communication.
Further, each described 4th pipeline is by reducing tee and described 3rd pipeline communication;Wherein said reducing The two ends that in threeway, diameter is big connect respectively with the 3rd adjacent pipeline, and one end that diameter is little is connected with described 4th pipeline.
Further, described N number of shower nozzle is built road level direction and is positioned at same linear position along facing, described 4th pipe Road is arranged along described straight line in predetermined angular obliquely, so that described N number of shower nozzle is arranged in predetermined angular obliquely.
Further, described predetermined angular is 45 °.
Optionally, described support member is coating steel pipe, described coating steel pipe and described 3rd pipeline screwed connection.
Further, described coating steel pipe is fixed on road ground by concrete pedestal;Wherein said concrete pedestal On be bolted sleeve pipe, described coating steel pipe is sheathed in described sleeve pipe.
Optionally, described first pipeline, second pipe, the 3rd pipeline and the 4th pipeline are coating steel pipe.
Optionally, described shower nozzle is fan nozzle.
Compared with prior art, the beneficial effects of the utility model:
This utility model scheme arranges water inlet control unit and atomizing de-dusting unit, described water inlet control unit include along Face build that road vertical direction is linked in sequence the most successively for the first pipeline being connected with extinguishing pipe, Filtering ball valve, open Closing valve and second pipe;Described atomizing de-dusting unit includes building the most spaced N number of spray in road level direction along facing Head, is all connected by the 3rd pipeline between adjacent two shower nozzles, and each described 3rd pipeline is all fixed on road by support member Ground;Described second pipe in described water inlet control unit by elbow bend connect in described atomizing de-dusting unit described 3rd pipeline.So can be fetched water by extinguishing pipe, be controlled along facing the N number of shower nozzle building the setting of road level direction by controlled valve Water spray, reaches depositing dust purpose.This system structure is simple, can realize facing the rapid assembling construction and installation built, and green energy conservation is removable Unload installation circulation repeatedly to utilize, save to face and build up this, and process Installation is convenient, save manpower, the input of material, right by putting into practice Ratio has good convenience and economic benefit.
Accompanying drawing explanation
Fig. 1 is the reusable assembled spray dust-reducing system of the construction site shown in this utility model embodiment Schematic diagram;
Fig. 2 is the site plan of spray dust-reducing system shown in Fig. 1;
Fig. 3 is the water inlet control unit schematic diagram in spray dust-reducing system shown in Fig. 1;
Fig. 4 is that the support member in spray dust-reducing system shown in Fig. 1 fixes schematic diagram.
Detailed description of the invention
Below in conjunction with detailed description of the invention, this utility model is described in further detail.But this should be interpreted as this The scope of the above-mentioned theme of utility model is only limitted to below example, and all technology realized based on this utility model content all belong to In scope of the present utility model.
As Figure 1-3, a kind of construction site of the present embodiment proposition reusable assembled atomizing de-dusting system System, including entering water control unit and atomizing de-dusting unit;Described water inlet control unit include along face build road vertical direction by Under be linked in sequence the most successively for the first pipeline 3 being connected with extinguishing pipe 14, Filtering ball valve 4, controlled valve 5 and the second pipe Road 6, the most described first and second pipelines can use a pipeline, arrange Filtering ball valve and switch valve thereon Door;Described atomizing de-dusting unit includes building road level direction (as along link length direction) and being spaced (as all successively along facing Even interval is arranged) N number of shower nozzle 10 of arranging, all connected by the 3rd pipeline 7 between adjacent two shower nozzles 10, each described 3rd Pipeline 7 is all fixed on road ground by support member 12;N is the integer more than or equal to 2;Described in described water inlet control unit Second pipe 3 connects described 3rd pipeline 7 in described atomizing de-dusting unit by elbow bend 2.
The present embodiment scheme arranges water inlet control unit and atomizing de-dusting unit, and described water inlet control unit includes along facing Build that road vertical direction is linked in sequence the most successively for the first pipeline being connected with extinguishing pipe, Filtering ball valve, switch Valve and second pipe;Described atomizing de-dusting unit includes building the most spaced N number of shower nozzle in road level direction along facing, All being connected by the 3rd pipeline between adjacent two shower nozzles, each described 3rd pipeline is all fixed on road ground by support member Face;Described second pipe in described water inlet control unit connects described in described atomizing de-dusting unit by elbow bend Three pipelines.So can be fetched water by extinguishing pipe, be controlled along facing the N number of shower nozzle spray building the setting of road level direction by controlled valve Water, reaches depositing dust purpose.This system structure is simple, can realize facing the rapid assembling construction and installation built, green energy conservation, detachably Circulation is installed repeatedly utilize, saves to face and build up this, and process Installation is convenient, save manpower, the input of material, contrasted by practice There is good convenience and economic benefit.
Concrete, in one embodiment, described shower nozzle 10 is fan nozzle, and spray area is big, and dust-laying effect is good.Described First pipeline 3 passes sequentially through threeway 1 and connects with described extinguishing pipe 14 with elbow bend 2, easy for installation, it is simple to system construction is pacified Dress.Each described shower nozzle 10 is connected with described 3rd pipeline 7 by the 4th pipeline 9 respectively.First pipeline described in the present embodiment 3, second pipe the 6, the 3rd pipeline 7 and the 4th pipeline 9 are coating steel pipe, and concrete size and/or length are arranged as required to, no It is restricted.Each described 4th pipeline 9 is connected with described 3rd pipeline 7 by reducing tee 8;In wherein said reducing tee 8 The two ends that diameter is big connect respectively with the 3rd adjacent pipeline 7, and one end that diameter is little is connected (referring to figure with described 4th pipeline 9 2).So arrange and can increase shower nozzle 10 irrigation pressure, can spray farther out, to reach preferable dust-laying effect.
Further, described N number of shower nozzle 10 is built road level direction and is positioned at (the most all sprays of same linear position along facing 10 are positioned at sustained height, consistent with the tip height of the described second pipe 6 in water inlet control unit in the present embodiment), Described 4th pipeline 9 is arranged along described straight line in predetermined angular obliquely, so that described N number of shower nozzle 10 is in making a reservation for obliquely Angle is arranged.Described predetermined angular is preferably 45 °, it is possible to is 30 ° or 60 ° etc., is not restricted this, can be arranged as required to. Arranging 45 ° can make water spray effect preferable, essentially parabolic path, and spray area is bigger, and dust-laying effect is good.
Optionally, described support member 12 is coating steel pipe, described coating steel pipe and described 3rd pipeline 7 screwed connection.This Sample prescription just removes and installs, it is achieved the assembled of system is installed, and repeatable utilization is cost-effective.
Further, for the most described coating steel pipe of preferably securing supports 12(), the most described coating steel pipe is by mixed Solidifying soil matrix seat 13 is fixed on road ground.Referring to Fig. 4, by bolt 16 fixed sleeving 15 on wherein said concrete pedestal 13, Described coating steel pipe is sheathed in described sleeve pipe 15.When being embodied as, bolt 16 part is embedded in concrete pedestal 13, separately A part is exposed, and is bolted part and is fixed by sleeve pipe, and described coating steel pipe is sheathed in described sleeve pipe 15 again.Described sleeve pipe 15 also select coating steel pipe, naturally it is also possible to be other pipelines, be not restricted this.
Referring to Fig. 1-4, specifically illustrate spray dust-reducing system of the present utility model below in conjunction with one.This system is suitable for In on-the-spot 6 meters and the dedusting of following temporary road, the construction controlling haze sprinkling system.
The present embodiment System Working Principle is: after system assembles, starts on-the-spot feeding spraying pump, main pipeline (extinguishing pipe) near water Supply water to spraying lateral, all size dust granule in energy rapid adsorption air in atomizer is sprayed onto air, Being formed and effectively control dirt, build good pure and fresh air, reach the multi-efficiency such as depositing dust, humidification, the water droplet simultaneously fallen plays punching The effect on brush road surface.
The parts that in this example, spray dust-reducing system uses are as follows:
1) during coating steel pipe DN32, DN15 uses existing national standards " low-pressure fluid conveying welded still pipe " GB/T3091 Regulation, its quality should meet the regulation of Q235-A level steel in existing national standards " carbon structural steels " GB/T700.
2) valve uses DN32 copper ball valve bore pressure-bearing to be: its quality of 1.6MPa meets GB/T15185-1994 " ferrum System and copper ball valve ", filter uses 60/ cun of Y type drainage screen specification mesh.
3) elbow bend, threeway and the Fan spray head that shower connects.
4) construction site can have enough to meet the need the assembled spray dust-reducing system of use and is divided into two component units: a unit and Unit two.Unit one is water inlet control unit, and Unit two are atomizing de-dusting unit, can be as required by the route of atomizing de-dusting Length increases, and the quantity i.e. increasing atomizing de-dusting unit spray head and connection pipeline realizes.
In this example, cellular construction size: unit 3000 × 200 × 2000(length, width and height), two unit 6000 × 200 × 2000(length, width and height).Concrete parts and corresponding label or installation are listed as follows:
Concrete assembling mode is as follows: the connection of each component is screw thread and connects in succession, in order to realizes assembled and can have enough to meet the need.
First it is installed into water control unit, connects Filtering ball valve and controlled valve is allowed to and inlet channel UNICOM, install the One spraying nozzle, the parts order of connection is: 14 → 1 → 2 → 3 → 4 → 3 → 5 → 6 → 2 → 7 → 8 → 9 → 10;Then order Connecting atomizing de-dusting unit, connected by wire connection mode, the vertical rod (i.e. support member) of fixing horizontal pipe (the i.e. the 3rd pipeline) is solid On concrete pedestal 13, bottom sleeve pipe is attached, and vertical rod and horizontal tube use screw thread type to be attached, and parts connect Sequentially: 7 → 11 → 12 → 13 → 7 → 8 → 9 → 10.
3rd, optionally, increase atomizing de-dusting unit spray head quantity according to the length of road, will be by plug at end Threeway at later spray head blocks.It should be noted that parts listed above and model thereof are merely illustrative, this area Technical staff can use the parts of other models and/or material to constitute this system as required.
The scheme that this utility model provides, this spray dust-reducing system simple in construction, can realize facing the rapid assembling built and execute Work is installed, green energy conservation, detachably installs circulation and repeatedly utilizes, and saves to face and builds up this, and process Installation is convenient, saving manpower, The input of material, has good convenience and economic benefit by putting into practice contrast.
Above in conjunction with accompanying drawing, detailed description of the invention of the present utility model is described in detail, but this utility model is not It is limited to above-mentioned embodiment, in the case of without departing from the spirit and scope of claims hereof, those skilled in the art Member may be made that various amendment or remodeling.

Claims (10)

1. a construction site reusable assembled spray dust-reducing system, it is characterised in that include into water control Unit and atomizing de-dusting unit;
Described water inlet control unit include along face build that road vertical direction is linked in sequence the most successively for fire-fighting The first pipeline, Filtering ball valve, controlled valve and the second pipe that pipe connects;
Described atomizing de-dusting unit includes building the most spaced N number of shower nozzle in road level direction along facing, adjacent two sprays All being connected by the 3rd pipeline between Tou, each described 3rd pipeline is all fixed on road ground by support member;N is for being more than In the integer of 2;
Described second pipe in described water inlet control unit by elbow bend connect in described atomizing de-dusting unit described 3rd pipeline.
Construction site the most according to claim 1 reusable assembled spray dust-reducing system, its feature exists In, described first pipeline is connected with described extinguishing pipe by threeway.
Construction site the most according to claim 1 and 2 reusable assembled spray dust-reducing system, its feature Being, each described shower nozzle is respectively by the 4th pipeline and described 3rd pipeline communication.
Construction site the most according to claim 3 reusable assembled spray dust-reducing system, its feature exists In, each described 4th pipeline is by reducing tee and described 3rd pipeline communication;In wherein said reducing tee, diameter is big Two ends connect respectively with the 3rd adjacent pipeline, and one end that diameter is little is connected with described 4th pipeline.
Construction site the most according to claim 4 reusable assembled spray dust-reducing system, its feature exists Building road level direction in, described N number of shower nozzle and be positioned at same linear position along facing, described 4th pipeline is along described straight line Arrange in predetermined angular obliquely, so that described N number of shower nozzle is arranged in predetermined angular obliquely.
Construction site the most according to claim 5 reusable assembled spray dust-reducing system, its feature exists In, described predetermined angular is 45 °.
Construction site the most according to claim 5 reusable assembled spray dust-reducing system, its feature exists In, described support member is coating steel pipe, described coating steel pipe and described 3rd pipeline screwed connection.
Construction site the most according to claim 7 reusable assembled spray dust-reducing system, its feature exists In, described coating steel pipe is fixed on road ground by concrete pedestal;It is bolted on wherein said concrete pedestal Sleeve pipe, described coating steel pipe is sheathed in described sleeve pipe.
Construction site the most according to claim 8 reusable assembled spray dust-reducing system, its feature exists In, described first pipeline, second pipe, the 3rd pipeline and the 4th pipeline are coating steel pipe.
Construction site the most according to claim 9 reusable assembled spray dust-reducing system, its feature exists In, described shower nozzle is fan nozzle.
CN201620717255.4U 2016-07-08 2016-07-08 Reusable assembled spraying dust-settling system for construction site Expired - Fee Related CN205839672U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620717255.4U CN205839672U (en) 2016-07-08 2016-07-08 Reusable assembled spraying dust-settling system for construction site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620717255.4U CN205839672U (en) 2016-07-08 2016-07-08 Reusable assembled spraying dust-settling system for construction site

Publications (1)

Publication Number Publication Date
CN205839672U true CN205839672U (en) 2016-12-28

Family

ID=58149950

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620717255.4U Expired - Fee Related CN205839672U (en) 2016-07-08 2016-07-08 Reusable assembled spraying dust-settling system for construction site

Country Status (1)

Country Link
CN (1) CN205839672U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107158852A (en) * 2017-07-07 2017-09-15 上海格林曼环境技术有限公司 A kind of wet dust separater for job site
CN109925775A (en) * 2019-04-25 2019-06-25 前行者(厦门)智能科技有限责任公司 It is atomized dust suppression lamp water supply pipe purification system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107158852A (en) * 2017-07-07 2017-09-15 上海格林曼环境技术有限公司 A kind of wet dust separater for job site
CN109925775A (en) * 2019-04-25 2019-06-25 前行者(厦门)智能科技有限责任公司 It is atomized dust suppression lamp water supply pipe purification system

Similar Documents

Publication Publication Date Title
CN205839672U (en) Reusable assembled spraying dust-settling system for construction site
CN205056328U (en) Multifunctional road washs water jet equipment of car
CN207042128U (en) The system that construction site carries out spraying and dedusting using climbing frame and fire main
CN204844444U (en) Concrete tower crane high altitude sprays maintenance system
CN203834943U (en) Mobile building wall and floorslab water atomizing and spraying device
CN206045664U (en) Tower crane spray dust system
CN204690662U (en) A kind of building site atomizing de-dusting apparatus
CN107155824A (en) A kind of agricultural Multifunctional sprinkler irrigation device
CN207803041U (en) A kind of adjustable for height rainer of greening
CN107242111B (en) Efficient lawn watering device
CN208137448U (en) A kind of construction dust suppression system
CN202843527U (en) Building cleaning and cooling device
CN207739195U (en) A kind of greenbelt cleaning device
CN206868471U (en) A kind of environmental project sprayer unit
CN207244516U (en) A kind of more nozzle washers of high pressure
CN202991105U (en) Roadway spraying device
CN205475034U (en) Movable type sprays dust device
CN211036847U (en) A dust device for construction
CN107211842A (en) Vegetation watering appliance
CN203091163U (en) Spraying gun of grout spraying machine
CN207913417U (en) A kind of depositing dust spray system
CN209438271U (en) Metro station excavation construction sprinkling dust-removing device
CN206851589U (en) A kind of agricultural Multifunctional sprinkler irrigation device
CN208494642U (en) A kind of spray equipment for trunk whitewashing
CN207461022U (en) A kind of efficient treegarden irrigation water jet

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161228

CF01 Termination of patent right due to non-payment of annual fee