CN205743958U - Tunnel construction ventilation system - Google Patents

Tunnel construction ventilation system Download PDF

Info

Publication number
CN205743958U
CN205743958U CN201620419472.5U CN201620419472U CN205743958U CN 205743958 U CN205743958 U CN 205743958U CN 201620419472 U CN201620419472 U CN 201620419472U CN 205743958 U CN205743958 U CN 205743958U
Authority
CN
China
Prior art keywords
air
tunnel
construction
unit
ventilation system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620419472.5U
Other languages
Chinese (zh)
Inventor
霍利刚
张浩平
金鑫
孙慧强
程帅
刁玉石
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Fifth Engineering Co Ltd
Original Assignee
CCCC First Highway Fifth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Fifth Engineering Co Ltd filed Critical CCCC First Highway Fifth Engineering Co Ltd
Priority to CN201620419472.5U priority Critical patent/CN205743958U/en
Application granted granted Critical
Publication of CN205743958U publication Critical patent/CN205743958U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ventilation (AREA)

Abstract

This utility model provides a kind of Tunnel Construction Ventilation System, installs n air-supply arrangement at tunnel portal extenal fixation;Along the length direction of construction tunnel, it is installed with air supply duct in tunnel-side;Along the length direction of construction tunnel, equidistantly it is installed with jet blower at tunnel roof;In all sides of construction tunnel face, by movable supporting frame, gaseous mass detector is installed;Outside at construction tunnel installs monitoring host computer;The input of monitoring host computer is connected with gaseous mass detector;The outfan of monitoring host computer is connected with air-supply arrangement and jet blower respectively.Advantage is: can be according to the air quality situation of construction tunnel face, timely automated quick adjustment intake, so that the air quality of construction tunnel face meets construction requirement, ensures that operating personnel is healthy;Also have arrangement, easy care use, simple in construction, low cost are easily installed, energy-conservation, drafting efficiency is high, high intelligent control degree advantages of higher, can be widely popularized use.

Description

Tunnel Construction Ventilation System
Technical field
This utility model belongs to tunnel ventilation technical field, is specifically related to a kind of Tunnel Construction Ventilation System.
Background technology
Construction ventilation of tunnel is to ensure that the important procedure that operating personnel is healthy in tunnel.Existing tunnel is executed Work ventilating system, has the problems such as drafting efficiency is low, energy consumption is high, the most delayed, high intelligent control degree is low.
Utility model content
The defect existed for prior art, this utility model provides a kind of Tunnel Construction Ventilation System, can have Effect solves the problems referred to above.
The technical solution adopted in the utility model is as follows:
This utility model provides a kind of Tunnel Construction Ventilation System, installs n air-supply dress at tunnel portal extenal fixation Put;N is natural number;Along the length direction of construction tunnel, it is installed with air supply duct (1) in tunnel-side, Further, the air inlet of described air supply duct (1) connects with the air outlet of air-supply arrangement each described respectively;Institute State the air outlet of air supply duct (1) near construction tunnel face (3);Along the length direction of construction tunnel, Jet blower (2) equidistantly it is installed with at tunnel roof;In all sides of construction tunnel face, by moving Dynamic bracing frame is provided with gaseous mass detector;Outside at construction tunnel installs monitoring host computer;
The input of described monitoring host computer is connected with described gaseous mass detector;The output of described monitoring host computer End is connected with described air-supply arrangement and described jet blower (2) respectively.
Preferably, each described air-supply arrangement all includes: drainage hood, air filtration clean unit and axial flow Blower fan;The air vent of described drainage hood is connected with the air inlet of described axial flow blower by air-suction duct;Described The air vent of axial flow blower is connected with described air supply duct (1);Described air filtration clean unit is fixed on institute State the pipe interior of air-suction duct.
Preferably, described air filtration clean unit includes udst separation unit and cleaning harmful gas unit; By gas flow direction, set gradually described udst separation unit and described cleaning harmful gas unit.
Preferably, described cleaning harmful gas unit is activated carbon filter element.
Preferably, the both sides at described air filtration clean unit be separately installed with the 1st pressure measurement sensor and 2nd pressure measurement sensor;Described 1st pressure measurement sensor and described 2nd pressure measurement sensor are all connected with To described monitoring host computer.
Preferably, described air supply duct (1) is the telescopic pipeline of length.
Preferably, described gaseous mass detector includes: dust concentration detector unit, harmful gas concentration are examined Survey unit, oxygen content detection unit, air volume test unit and wind speed measurement unit.
Preferably, the power supply of described monitoring host computer is wind-force and solar combined power generating power supply.
Preferably, described monitoring host computer connects display, alarm, GPS position finder and telecommunication circuit.
The Tunnel Construction Ventilation System that this utility model provides has the advantage that
This utility model can according to the air quality situation of construction tunnel face, timely automated quick adjust into Air quantity, so that the air quality of construction tunnel face meets construction requirement, ensures that operating personnel's health is good for Health;
Have easily install arrangement, easy care use, simple in construction, low cost, energy-conservation, drafting efficiency is high, High intelligent control degree advantages of higher, can be widely popularized use.
Accompanying drawing explanation
The structural representation of the Tunnel Construction Ventilation System that Fig. 1 provides for this utility model.
Detailed description of the invention
In order to make this utility model be solved the technical problem that, technical scheme and beneficial effect clearer, Below in conjunction with drawings and Examples, this utility model is further elaborated.Should be appreciated that herein Described specific embodiment, only in order to explain this utility model, is not used to limit this utility model.
In conjunction with Fig. 1, this utility model provides a kind of Tunnel Construction Ventilation System, installs at tunnel portal extenal fixation N air-supply arrangement;N is natural number;Each air-supply arrangement all includes: drainage hood, air filtration clean unit And axial flow blower;The air vent of drainage hood is connected with the air inlet of axial flow blower by air-suction duct;Axial flow The air vent of blower fan is connected with air supply duct 1;Wherein, air filtration clean unit is fixed on the pipe of air-suction duct Inside road.Air filtration clean unit includes udst separation unit and cleaning harmful gas unit;By gas stream Dynamic direction, sets gradually udst separation unit and cleaning harmful gas unit.Wherein, cleaning harmful gas list Unit is activated carbon filter element, for filtering the harmful gas in extraneous air.For above-mentioned air-supply arrangement, Its operation principle is: under the effect of axial flow blower, makes air-suction duct produce negative pressure, thus by tunnel outer Air be incorporated into air-suction duct by drainage hood, and, by air filtration clean unit, filter air In dust granule and harmful gas, finally give fresh air, and be transported to ajutage by axial flow blower Road 1.In actual application, it is separately installed with the 1st pressure measurement sensor in the both sides of air filtration clean unit With the 2nd pressure measurement sensor;1st pressure measurement sensor and the 2nd pressure measurement sensor are all connected to monitoring Main frame.Therefore, monitoring host computer can monitoring state to air filtration clean unit in real time, when its both sides When pressure differential is bigger, representing and need to change air filtration clean unit, therefore, monitoring host computer can send in time Information warning, reminds staff to change air filtration clean unit, it is ensured that air filtration effect.
Along the length direction of construction tunnel, being installed with air supply duct 1 in tunnel-side, air supply duct 1 is The telescopic pipeline of length, reason is: along with tunnel constantly excavates, and construction tunnel face is constantly to depths Extend, and owing to air supply duct is designed as Collapsible structure, therefore, can be at any time along with construction tunnel face Extension and adjust the length of air supply duct, make air supply duct be constantly in the position near construction tunnel face Put, it is ensured that near construction tunnel face, carry fresh air.The air inlet of air supply duct 1 respectively with each The air outlet connection of air-supply arrangement;The air outlet of air supply duct 1 is near construction tunnel face 3;
Along the length direction of construction tunnel, equidistantly it is installed with jet blower 2 at tunnel roof, passes through jet Blower fan, when the contaminated air of tunnel internal is discharged to tunnel outer.In all sides of construction tunnel face, logical Cross movable supporting frame and gaseous mass detector is installed;Wherein, gaseous mass detector includes but not limited to: Dust concentration detector unit, harmful gas concentration detector unit, oxygen content detection unit, air volume test list Unit and wind speed measurement unit.Outside at construction tunnel installs monitoring host computer;The input of monitoring host computer and gas Weight detector connects;The outfan of monitoring host computer is connected with air-supply arrangement and jet blower 2 respectively.
Above-mentioned Tunnel Construction Ventilation System, its operation principle is: monitoring host computer can by gaseous mass detector The air quality situation near construction tunnel face detected in real time, and according to the sky near tunnel tunnel face Gas quality condition, controls startup quantity and the operating power of air-supply arrangement, and the startup of jet blower flexibly Quantity and operating power, thus adjust the amount injecting fresh air in tunnel, make near tunnel tunnel face Air quality meets code requirement, safeguard work person works's environment.
For energy efficient, the power supply of monitoring host computer is wind-force and solar combined power generating power supply.Additionally, Monitoring host computer connects display, alarm, GPS position finder and telecommunication circuit.By telecommunication circuit, The function remotely monitored can be realized.
In sum, the Tunnel Construction Ventilation System that this utility model provides has the advantage that
This utility model can according to the air quality situation of construction tunnel face, timely automated quick adjust into Air quantity, so that the air quality of construction tunnel face meets construction requirement, ensures that operating personnel's health is good for Health;
Have easily install arrangement, easy care use, simple in construction, low cost, energy-conservation, drafting efficiency is high, High intelligent control degree advantages of higher, can be widely popularized use.
The above is only preferred implementation of the present utility model, it is noted that for the art For those of ordinary skill, on the premise of without departing from this utility model principle, it is also possible to make some improvement And retouching, these improvements and modifications also should regard protection domain of the present utility model.

Claims (9)

1. a Tunnel Construction Ventilation System, it is characterised in that install n air-supply at tunnel portal extenal fixation Device;N is natural number;Along the length direction of construction tunnel, it is installed with air supply duct (1) in tunnel-side, Further, the air inlet of described air supply duct (1) connects with the air outlet of air-supply arrangement each described respectively;Institute State the air outlet of air supply duct (1) near construction tunnel face (3);Along the length direction of construction tunnel, Jet blower (2) equidistantly it is installed with at tunnel roof;In all sides of construction tunnel face, by moving Dynamic bracing frame is provided with gaseous mass detector;Outside at construction tunnel installs monitoring host computer;
The input of described monitoring host computer is connected with described gaseous mass detector;The output of described monitoring host computer End is connected with described air-supply arrangement and described jet blower (2) respectively.
Tunnel Construction Ventilation System the most according to claim 1, it is characterised in that each described air-supply Device all includes: drainage hood, air filtration clean unit and axial flow blower;The air vent of described drainage hood Connected by the air inlet of air-suction duct with described axial flow blower;The air vent of described axial flow blower send with described Wind pipeline (1) connects;Described air filtration clean unit is fixed on the pipe interior of described air-suction duct.
Tunnel Construction Ventilation System the most according to claim 2, it is characterised in that described air filtration Clean unit includes udst separation unit and cleaning harmful gas unit;By gas flow direction, set gradually Described udst separation unit and described cleaning harmful gas unit.
Tunnel Construction Ventilation System the most according to claim 3, it is characterised in that described harmful gas Clean unit is activated carbon filter element.
Tunnel Construction Ventilation System the most according to claim 3, it is characterised in that in described air mistake The both sides of filter clean unit are separately installed with the 1st pressure measurement sensor and the 2nd pressure measurement sensor;Described 1st pressure measurement sensor and described 2nd pressure measurement sensor are all connected to described monitoring host computer.
Tunnel Construction Ventilation System the most according to claim 1, it is characterised in that described air supply duct (1) it is the telescopic pipeline of length.
Tunnel Construction Ventilation System the most according to claim 1, it is characterised in that described gaseous mass Detector includes: dust concentration detector unit, harmful gas concentration detector unit, oxygen content detection unit, Air volume test unit and wind speed measurement unit.
Tunnel Construction Ventilation System the most according to claim 1, it is characterised in that described monitoring host computer Power supply be wind-force and solar combined power generating power supply.
Tunnel Construction Ventilation System the most according to claim 1, it is characterised in that described monitoring host computer Connect and have display, alarm, GPS position finder and telecommunication circuit.
CN201620419472.5U 2016-05-10 2016-05-10 Tunnel construction ventilation system Expired - Fee Related CN205743958U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620419472.5U CN205743958U (en) 2016-05-10 2016-05-10 Tunnel construction ventilation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620419472.5U CN205743958U (en) 2016-05-10 2016-05-10 Tunnel construction ventilation system

Publications (1)

Publication Number Publication Date
CN205743958U true CN205743958U (en) 2016-11-30

Family

ID=57367471

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620419472.5U Expired - Fee Related CN205743958U (en) 2016-05-10 2016-05-10 Tunnel construction ventilation system

Country Status (1)

Country Link
CN (1) CN205743958U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116085028A (en) * 2023-04-13 2023-05-09 山西工程技术学院 Tunnel ventilation control system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116085028A (en) * 2023-04-13 2023-05-09 山西工程技术学院 Tunnel ventilation control system

Similar Documents

Publication Publication Date Title
CN103499512B (en) Air-pressure-adjustable performance testing device for air filtering material and application thereof
CN104879839B (en) Night shift room modular air cleaning system and method in a kind of Extra-long Highway Tunnel hole
CN208871749U (en) Combined type air purification filter equipment
CN103759988B (en) Atmospheric particulates collecting device
CN206330716U (en) A kind of live air-tightness detection device of external window of building
CN205743958U (en) Tunnel construction ventilation system
CN206291407U (en) Central ventilation system air filter
CN216691144U (en) Cooling and dedusting equipment for tunnel ventilation
CN206122302U (en) Rubber laboratory ventilation device
CN106422609A (en) Full-automatic multi-purpose energy-saving and environment-friendly equipment with self-cleaning function
CN101769832B (en) Radiation environment iodine automatic sampling device
CN201845011U (en) Purification performance detector of ozone filter
CN206725292U (en) A kind of gas capture devices of carbon emission on-line measuring device
CN206653889U (en) A kind of automobile-used purifier
CN103776108B (en) Large-sized workshop welding smaze Intelligent purifying system
CN204632230U (en) A kind of fly-ash separator comprehensive training system
CN207623077U (en) A kind of air detection sampler
CN107064431B (en) A kind of air negative oxgyen ion monitoring instrument optimization structure and application method
CN206113157U (en) Air monitoring device
CN206095718U (en) Sampling device suitable for low concentration particulate matter
CN204943728U (en) Smart Home air optimizing system
CN205340425U (en) Automatic outdoor haze purger of response wind direction
CN206973820U (en) A kind of VMC
CN208642102U (en) A kind of micro moving dry dust removal apparatus
CN205957322U (en) Household air purifier

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161130