CN205711696U - A kind of drag-line and the overpass encircleing combined system - Google Patents

A kind of drag-line and the overpass encircleing combined system Download PDF

Info

Publication number
CN205711696U
CN205711696U CN201620634897.8U CN201620634897U CN205711696U CN 205711696 U CN205711696 U CN 205711696U CN 201620634897 U CN201620634897 U CN 201620634897U CN 205711696 U CN205711696 U CN 205711696U
Authority
CN
China
Prior art keywords
bridge
drag
line
auxiliary
cable stayed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620634897.8U
Other languages
Chinese (zh)
Inventor
雷笑
王杰
曹实
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN201620634897.8U priority Critical patent/CN205711696U/en
Application granted granted Critical
Publication of CN205711696U publication Critical patent/CN205711696U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses the overpass of a kind of drag-line and arch combined system, including main bridge and two the auxiliary bridges being arranged at main bridge both sides, main bridge is bowstring arch bridge, and each auxiliary bridge is equipped with two Tower Column of A Cable Stayed Bridge;Each Tower Column of A Cable Stayed Bridge all includes a bridge tower being vertically arranged and three drag-lines, fixes with auxiliary bridge bridge plate or basis and be connected bottom bridge tower, and one end of every drag-line is fixing with bridge tower top to be connected, and the other end of every drag-line is fixing with auxiliary bridge bridge plate to be connected.Two Tower Column of A Cable Stayed Bridge on each auxiliary bridge are followed successively by outer Tower Column of A Cable Stayed Bridge and interior Tower Column of A Cable Stayed Bridge from outside to inside, and outer Tower Column of A Cable Stayed Bridge includes a vertical high post and three root length drag-lines, and interior Tower Column of A Cable Stayed Bridge includes a vertical low post and three short drag-lines.After using said structure, in whole work progress, it is not necessary to suspend traffic, the impact on traffic is little, can improve efficiency of construction, accelerates construction progress, reduces construction cost;And it being applicable to the overpass of various version, the suitability is wide.

Description

A kind of drag-line and the overpass encircleing combined system
Technical field
This utility model relates to bridge construction field, a kind of drag-line and the overpass encircleing combined system.
Background technology
Along with the continuous propelling of urbanization, the vehicle on road surface gets more and more, and traffic pressure increases day by day, more and more City selects to build overpass.Overpass is typically built in the location that vehicle flowrate is big, pedestrian is dense, or crossing, wide Above field and railway.Overpass only allows pedestrian to pass through, the conflict in time avoiding wagon flow and people's plane of flow to intersect, and ensures people Safety pass through, improve speed, reduce vehicle accident.But the construction of overpass can run into situation about suspending traffic, Work progress can bring no small pressure to road traffic.Overpass span requires the most increasing now, existing people Row overline bridge span can not meet demand.And, it is the most attractive in appearance that existing overpass there is also external form, with the city of surrounding Environment is incompatible with, and fabrication and installation cost is high, the problem of long construction period.
Utility model content
The technical problems to be solved in the utility model is for above-mentioned the deficiencies in the prior art, and provides a kind of drag-line and arch The overpass of combined system, the overpass of this drag-line and arch combined system is in whole work progress, it is not necessary to suspend traffic, Impact on traffic is little, can improve efficiency of construction, accelerates construction progress, reduces construction cost;And it is applicable to various version Overpass, the suitability is wide.
For solving above-mentioned technical problem, the technical solution adopted in the utility model is:
The overpass of a kind of drag-line and arch combined system, including being positioned at middle part and in horizontally disposed main bridge be arranged at Two auxiliary bridges of main bridge both sides, host bridge is bowstring arch bridge, and each auxiliary bridge is provided with two Tower Column of A Cable Stayed Bridge;Each oblique pull Bridge tower all includes a bridge tower being vertically arranged and three drag-lines, fixes with auxiliary bridge bridge plate or basis and be connected bottom bridge tower, every One end of drag-line is fixing with bridge tower top to be connected, and the other end of every drag-line is fixing with auxiliary bridge bridge plate to be connected.
Two Tower Column of A Cable Stayed Bridge on each auxiliary bridge are followed successively by outer Tower Column of A Cable Stayed Bridge and interior Tower Column of A Cable Stayed Bridge, outer cable-stayed bridge from outside to inside Tower includes a high post being vertically arranged and three root length drag-lines, interior Tower Column of A Cable Stayed Bridge include a low post being vertically arranged and three short Drag-line.
Two outer Tower Column of A Cable Stayed Bridge are arranged symmetrically with about main bridge, and two interior Tower Column of A Cable Stayed Bridge are also arranged symmetrically with about main bridge.
The step of one auxiliary bridge is spiral terrace, and the step of another auxiliary bridge is vertical step.
After this utility model uses said structure, have the advantages that the People's Bank of China of above-mentioned drag-line and arch combined system Overline bridge, uses drag-line to be connected with bridge plate by bridge tower, preferably coordinates mutually with surrounding, improve overall aesthetics;In construction During, only need to set up enclosing, pretensioning drag-line at the two ends of auxiliary bridge, then bridge plate lifting is put in place, whole process is without interrupting Traffic, the impact on traffic is the least, also improves efficiency of construction, accelerates construction progress, reduces construction cost;The present invention fits For the overpass of various versions, the suitability is wide;And due to the existence of drag-line, can preferably help overpass to be subject to Power, is conducive to developing the overpass of large span.
Accompanying drawing explanation
Fig. 1 is the structural representation of a kind of drag-line of this utility model and the overpass of arch combined system.
Wherein have: the most main bridge;The most auxiliary bridge;Outer Tower Column of A Cable Stayed Bridge;31. Gao Zhu;32. long drag-lines;33. bases;4. oblique pull in Bridge;41. low posts;42. short drag-lines.
Detailed description of the invention
With concrete better embodiment, this utility model is described in further detail below in conjunction with the accompanying drawings.
As it is shown in figure 1, a kind of drag-line and the overpass of arch combined system, including being positioned at middle part and in horizontally disposed master Bridge 1 and two the auxiliary bridges 2 being arranged at main bridge both sides.
Above-mentioned main bridge uses bowstring arch bridge, can give full play to bowstring arch bridge self beam by curved, the advantage of arch pressurized.
Two Tower Column of A Cable Stayed Bridge, the bullet that Tower Column of A Cable Stayed Bridge is preferably vertically arranged it is provided with on each auxiliary bridge.
Each Tower Column of A Cable Stayed Bridge all includes a bridge tower being vertically arranged and three drag-lines, with auxiliary bridge bridge plate or base bottom bridge tower Plinth is fixing to be connected, and one end of every drag-line is fixing with bridge tower top to be connected, and the other end of every drag-line is fixing with auxiliary bridge bridge plate even Connect.
Two Tower Column of A Cable Stayed Bridge on each auxiliary bridge are followed successively by outer Tower Column of A Cable Stayed Bridge 3 and interior Tower Column of A Cable Stayed Bridge 4 from outside to inside.
Outer Tower Column of A Cable Stayed Bridge includes a high post being vertically arranged 31 and three root length drag-lines 32, high column bottom preferably be embedded in The basis 33 of underground is fixing to be connected, and one end of every root length drag-line is fixing with high capital end to be connected, the other end of every root length drag-line and Auxiliary bridge bridge plate is fixing to be connected.
Interior Tower Column of A Cable Stayed Bridge includes a low post being vertically arranged 41 and three short drag-lines 42, low column bottom preferably with auxiliary bridge bridge Plate is fixing to be connected, and one end of every short drag-line is fixing with low capital end to be connected, and the other end of every short drag-line is solid with auxiliary bridge bridge plate Fixed connection.
Two outer Tower Column of A Cable Stayed Bridge are arranged symmetrically with about main bridge, and two interior Tower Column of A Cable Stayed Bridge are also arranged symmetrically with about main bridge, thus In picturesque disorder, more aesthetically pleasing.
One auxiliary bridge, preferably the step of the auxiliary bridge in left side is spiral terrace, another auxiliary bridge, and the preferably step of the auxiliary bridge in right side is Vertically step.
Above-mentioned drag-line and the overpass encircleing combined system, work progress is as follows:
The first step, arranges enclosing: only need to arrange enclosing in the both sides of auxiliary bridge in overpass.
Second step, outer Tower Column of A Cable Stayed Bridge of constructing: first holding up two Gao Zhu, every high post is all by three root length drag-lines and People's Bank of China sky Auxiliary bridge bridge plate in bridge is fixing to be connected.
3rd step, Tower Column of A Cable Stayed Bridge in construction: first holding up two low posts, every low post is all by three short drag-lines and People's Bank of China sky Auxiliary bridge bridge plate in bridge is fixing to be connected.
4th step, main bridge of constructing: at main bridge portion, use the form of bowstring arch bridge, beam can be given full play to by curved, arch pressurized Advantage.
In above-mentioned whole work progress, only enclosing need to be set in overpass both sides, and without suspending traffic, to current shadow Ring the least;Due to the existence of drag-line, the more preferable stress of overpass can be helped, be conducive to developing the overpass of large span.
Preferred implementation of the present utility model described in detail above, but, this utility model is not limited to above-mentioned reality Execute the detail in mode, in technology concept of the present utility model, the technical solution of the utility model can be entered The multiple equivalents of row, these equivalents belong to protection domain of the present utility model.

Claims (4)

1. an overpass for drag-line and arch combined system, including being positioned at middle part and in horizontally disposed main bridge be arranged at master Two auxiliary bridges of bridge both sides, it is characterised in that: host bridge is bowstring arch bridge, and each auxiliary bridge is provided with two cable-stayed bridges Tower;Each Tower Column of A Cable Stayed Bridge all includes a bridge tower being vertically arranged and three drag-lines, solid with auxiliary bridge bridge plate or basis bottom bridge tower Fixed connection, one end of every drag-line is fixing with bridge tower top to be connected, and the other end of every drag-line is fixing with auxiliary bridge bridge plate to be connected.
Drag-line the most according to claim 1 and the overpass encircleing combined system, it is characterised in that: two on each auxiliary bridge Individual Tower Column of A Cable Stayed Bridge is followed successively by outer Tower Column of A Cable Stayed Bridge and interior Tower Column of A Cable Stayed Bridge from outside to inside, and outer Tower Column of A Cable Stayed Bridge includes a height being vertically arranged Post and three root length drag-lines, high column bottom is fixing with basis to be connected, and one end of every root length drag-line is fixing with high capital end to be connected, every The other end of long drag-line is fixing with auxiliary bridge bridge plate to be connected;Interior Tower Column of A Cable Stayed Bridge include a low post being vertically arranged and three short draw Rope, low column bottom is fixing with auxiliary bridge bridge plate to be connected, and one end of every short drag-line is fixing with low capital end to be connected, every short drag-line The other end is fixing with auxiliary bridge bridge plate to be connected.
Drag-line the most according to claim 2 and the overpass encircleing combined system, it is characterised in that: two outer Tower Column of A Cable Stayed Bridge Being arranged symmetrically with about main bridge, two interior Tower Column of A Cable Stayed Bridge are also arranged symmetrically with about main bridge.
Drag-line the most according to claim 1 and the overpass encircleing combined system, it is characterised in that: the step of an auxiliary bridge For spiral terrace, the step of another auxiliary bridge is vertical step.
CN201620634897.8U 2016-06-24 2016-06-24 A kind of drag-line and the overpass encircleing combined system Expired - Fee Related CN205711696U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620634897.8U CN205711696U (en) 2016-06-24 2016-06-24 A kind of drag-line and the overpass encircleing combined system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620634897.8U CN205711696U (en) 2016-06-24 2016-06-24 A kind of drag-line and the overpass encircleing combined system

Publications (1)

Publication Number Publication Date
CN205711696U true CN205711696U (en) 2016-11-23

Family

ID=57315163

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620634897.8U Expired - Fee Related CN205711696U (en) 2016-06-24 2016-06-24 A kind of drag-line and the overpass encircleing combined system

Country Status (1)

Country Link
CN (1) CN205711696U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106758837A (en) * 2016-12-24 2017-05-31 中铁十八局集团有限公司 A kind of Inclined cable-stayed construction system of combination spandrel column
CN107012797A (en) * 2017-05-26 2017-08-04 中铁十八局集团有限公司 Construction system and method that a kind of Support Method is combined with stayed knotting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106758837A (en) * 2016-12-24 2017-05-31 中铁十八局集团有限公司 A kind of Inclined cable-stayed construction system of combination spandrel column
CN107012797A (en) * 2017-05-26 2017-08-04 中铁十八局集团有限公司 Construction system and method that a kind of Support Method is combined with stayed knotting method

Similar Documents

Publication Publication Date Title
CN106149768B (en) A kind of float Structure and its construction method of the underground structure of fender post combination Guan Liang
CN204282187U (en) A kind of novel Butterfly Arch Bridge
CN108774948A (en) A kind of segment free cantilever erection pier cap beam and its assembling method
CN206553961U (en) The short light-duty expanded letter combined type Hanging Basket of tower cable-stayed bridge
CN102797218A (en) Large-span railway desk type concrete arch bridge structure
CN101187197A (en) Steel-concrete combined structure double-deck continuous girder bridge
CN105839511B (en) A kind of cable-stayed bridge in the double rope faces of the only tower of curve
CN201416148Y (en) Symmetrical anchoring rope pull rod shuttering for oblique post
CN107100064B (en) A kind of butterfly cable-stayed bridge system
CN205711696U (en) A kind of drag-line and the overpass encircleing combined system
CN104532749A (en) Support used for construction of upper beam of main tower of suspension bridge
CN111945541A (en) Half-through tied arch bridge
CN102268858B (en) Cradle for suspension pouring of arch-type bridge
CN205205640U (en) Spiral diplopore continuous arch bridge
CN202466431U (en) Bridge specific model vase pier construction device
CN110130203A (en) A kind of deck type arch-rigid frame-continuous girder composite bridge and construction method
CN201411627Y (en) Steel-concrete composite tower-beam consolidation kilometer grade multi-span suspension bridge
CN102002912A (en) Simultaneous construction type wide-flanged guyed traveler
CN204385629U (en) A kind of support for the construction of suspension bridge king-tower top rail
CN203755127U (en) Pre-stress high-performance concrete continuous box girder bridge
CN205329550U (en) Suspension bridge catwalk system
CN203654194U (en) Quick construction structure for bridge
CN105971117A (en) Pseudo-classic architecture steel-frame structure with box type cross-section girders
CN205741869U (en) A kind of guy system overpass
CN202450450U (en) Reinforcement and reconstruction structure of suspension bridge

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161123

Termination date: 20190624