CN205678799U - The water resource heat pump heater that cooling water heat reclaims - Google Patents

The water resource heat pump heater that cooling water heat reclaims Download PDF

Info

Publication number
CN205678799U
CN205678799U CN201620237744.XU CN201620237744U CN205678799U CN 205678799 U CN205678799 U CN 205678799U CN 201620237744 U CN201620237744 U CN 201620237744U CN 205678799 U CN205678799 U CN 205678799U
Authority
CN
China
Prior art keywords
water
air
water pipe
conditioning box
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620237744.XU
Other languages
Chinese (zh)
Inventor
韩超
张敏杰
郭文昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI AIR-SYS AIR CONDITIONER SYSTEM SERVICE Co Ltd
Original Assignee
SHANGHAI AIR-SYS AIR CONDITIONER SYSTEM SERVICE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI AIR-SYS AIR CONDITIONER SYSTEM SERVICE Co Ltd filed Critical SHANGHAI AIR-SYS AIR CONDITIONER SYSTEM SERVICE Co Ltd
Priority to CN201620237744.XU priority Critical patent/CN205678799U/en
Application granted granted Critical
Publication of CN205678799U publication Critical patent/CN205678799U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Other Air-Conditioning Systems (AREA)

Abstract

This utility model relates to hot water heating field, the water resource heat pump heater that a kind of cooling water heat reclaims.The water resource heat pump heater that a kind of cooling water heat reclaims, including fresh air conditioner case (1), return air air-conditioning box (2), air-conditioning box refrigeration coil (3), air-conditioning box hot coil again (4), air-conditioning box preheating coil pipe (5), chilled water pump (9), vaporizer (10), condenser (11), handpiece Water Chilling Units (12), cooling tower (13) and cooling water pump (14) and heating equipment (40), it is characterized in that: also include heat-exchanger pump (6), cryogenic heat exchanger (15), high-temperature heat-exchanging (16), water source heat pump units (17), valve, water pipe and heating equipment (40).This utility model heat exchanger effectiveness is high, and heat utilization rate is high.

Description

The water resource heat pump heater that cooling water heat reclaims
Technical field
This utility model relates to field of heat exchange, the water resource heat pump heater that a kind of cooling water heat reclaims.
Background technology
Owing to industrial circle production process caloric value is big, and require Environmental Incubator constant humidity, if so being configured with in workshop Dry platform fresh air conditioner case and return air air-conditioning box, these air-conditioning equipment whole year operations ensure temperature and the relative humidity of environment.Newly Wind air-conditioning box summer and transition season refrigeration coil and reheating coil pipe are run, and preheat coil pipe winter and run.Return air air-conditioning box is annual Refrigeration coil and reheating coil pipe run.
Industrial circle conventional thermostatic constant wetting air conditioner systematic schematic diagram is as it is shown in figure 1, specifically include that fresh air conditioner case 1, return air Air-conditioning box 2, preheating coil pipe 5, refrigeration coil 3, reheating coil pipe 4, hot-water circulating pump 6, vapor-water heat exchanger 7, hot-water boiler 8, cold Freeze water pump 9, vaporizer 10, condenser 11, handpiece Water Chilling Units 12, cooling tower 13, cooling water pump 14, wherein: vaporizer 10, condenser 11, handpiece Water Chilling Units 12, chilled water pump 9, cooling water pump 14 and cooling tower 13 constitute concentration cold source system, vaporizer 10, freezing Water pump 9 and refrigeration coil 3 have been combined into chilled water circuit, and condenser 11, cooling water pump 14 and cooling tower 13 have been combined into cooling Water loop.
The 12 DEG C of backwater returned from the refrigeration coil 3 of fresh air conditioner case 1 and return air air-conditioning box 2 are pressurizeed by chilled water pump 9, Enter the vaporizer 10 of handpiece Water Chilling Units 12, circulate and vaporizer 10 heat exchange through internal refrigeration storage, vaporizer 10 supply water temperature 7 DEG C, 7 The refrigeration coil 3 of DEG C chilled water supply fresh air conditioner case 1 and return air air-conditioning box 2 realizes one for SAPMAC method.Fresh air conditioner case 1 The inflow temperature of refrigeration coil 37 DEG C, leaving water temperature 12 DEG C, only summer and transition season need to supply 7 DEG C of chilled waters.Return air is empty Adjust the inflow temperature 7 DEG C of the refrigeration coil 3 of case 2, leaving water temperature 12 DEG C, need the whole year to supply 7 DEG C of chilled waters.
Vapor-water heat exchanger 7, hot-water boiler 8 and hot-water circulating pump 6 constitute central heat source system, this heat source system winter Supplying hot water to the preheating coil pipe 5 of fresh air conditioner case 1, summer and transition season supplying hot water to the reheating coil pipe 4 of fresh air conditioner case 1. This heat source system supplying hot water whole year is to the reheating coil pipe 4 of return air air-conditioning box 2.In winter, go out from the preheating coil pipe 5 of fresh air conditioner case 1 The 40 DEG C of backwater come, pressurize through hot-water circulating pump 6, enter vapor-water heat exchanger 7 or hot-water boiler 8 is heated to 45 DEG C, 45 DEG C Hot water is fed into the preheating coil pipe 5 of fresh air conditioner case 1, and after the hot water in preheating coil pipe 5 exchanges with new wind heat, new wind is heated Heat up, complete the heating process in winter of fresh air conditioner case 1.Summer and transition season, from the reheating coil pipe 4 of fresh air conditioner case 1 40 DEG C of backwater out, pressurize through hot-water circulating pump 6, enter vapor-water heat exchanger 7 or hot-water boiler 8 is heated to 45 DEG C, and 45 DEG C hot water is supplied to the reheating coil pipe 4 of fresh air conditioner case 1, after the hot water in reheating coil pipe 4 and low-temperature airflow heat exchange, and low wet Stream is heated up, and completes the thermal process again in summer of fresh air conditioner case 1.The whole year is from the reheating coil pipe 4 of return air air-conditioning box 2 out 40 DEG C of backwater, pressurize through hot-water circulating pump 6, enter vapor-water heat exchanger 7 or hot-water boiler 8 and be heated to 45 DEG C, 45 DEG C of heat After water is supplied to the reheating coil pipe 4 of return air air-conditioning box 2, the hot water in reheating coil pipe 4 and low-temperature airflow heat exchange, low-temperature airflow quilt Heat temperature raising, completes the thermal process again of return air air-conditioning box 2.
Original fresh air conditioner box function section is: wind inlet section, fillter section, preheating section, refrigerating section, again hot arc, blower section. The preheating coil pipe of fresh air conditioner case preheating section in winter runs and heats the new wind of heating, summer and transition season refrigerating section and again hot arc Refrigeration coil and reheating coil pipe run refrigerated dehumidification and reheating.Original return air air-conditioning box functional section is: wind inlet section, fillter section, Refrigerating section, again hot arc, blower section.The refrigeration coil of the refrigerating section of return air air-conditioning box and again hot arc and reheating coil pipe whole year operation Refrigerated dehumidification and reheating.In preheating coil pipe, again hot coil, the thermal source of circulating hot water is soda pop plate type heat exchanger or hot-water boiler, heat Water heating apparatus can select electric hot water, oil-fired water-boiler, gas-fired water heating boiler, coal-burning boiler etc..
Original return air air-conditioning box needs cooling and heat supply, fresh air conditioner case to need heat supply throughout the year, lead throughout the year Cause annual energy consumption and operating cost is the most high.
Utility model content
In order to overcome the defect of prior art, it is provided that a kind of heat exchanger effectiveness is high, heat utilization rate is high, reduce the work of energy consumption Skill equipment heat energy utilization equipment, the utility model discloses the water resource heat pump heater that a kind of cooling water heat reclaims.
This utility model reaches goal of the invention by following technical solution:
The water resource heat pump heater that a kind of cooling water heat reclaims, including fresh air conditioner case, return air air-conditioning box, air-conditioning box system Cooling coil, air-conditioning box heating coil, air-conditioning box preheating coil pipe, chilled water pump, vaporizer, condenser, handpiece Water Chilling Units, cooling tower and Cooling water pump,
It is characterized in that: also include heat-exchanger pump, cryogenic heat exchanger, high-temperature heat-exchanging, water source heat pump units, valve, water pipe and Heating equipment,
The outlet of the air-conditioning box preheating coil pipe of fresh air conditioner case connects the first water pipe by the water pipe of V6 valve of having connected, The water inlet of the air-conditioning box preheating coil pipe of fresh air conditioner case connects the second water pipe by the water pipe of V5 valve of having connected;Fresh air conditioner The outlet of the air-conditioning box heating coil of case connects the first water pipe, the air-conditioning of fresh air conditioner case by the water pipe of V8 valve of having connected The water inlet of case heating coil connects the second water pipe by the water pipe of V7 valve of having connected;The air-conditioning box of return air air-conditioning box adds hot plate The outlet of pipe connects the first water pipe by the water pipe of V12 valve of having connected, and the water inlet of the heating coil of return air air-conditioning box leads to The water pipe crossing V11 valve of having connected connects the second water pipe;
The outlet of the air-conditioning box refrigeration coil of fresh air conditioner case connects the 3rd water by the water pipe of V10 valve of having connected Pipe, the water inlet of the air-conditioning box refrigeration coil of fresh air conditioner case connects the 4th water pipe by the water pipe of V9 valve of having connected;Return air The outlet of the air-conditioning box refrigeration coil of air-conditioning box connects the 3rd water pipe, return air air-conditioning box by the water pipe of V14 valve of having connected Air-conditioning box refrigeration coil water inlet by connected V13 valve water pipe connect the 4th water pipe;
Handpiece Water Chilling Units includes the air-conditioning box chill plate of both vaporizer and condenser, fresh air conditioner case and return air air-conditioning box The water inlet of pipe and outlet connect outlet and water inlet, the condenser of vaporizer respectively by the 4th water pipe and the 3rd water pipe Water inlet and outlet connected outlet and water inlet, the 3rd water pipe of cooling tower respectively by the 5th water pipe and the 6th water pipe On be in series with chilled water pump, the 5th water pipe is in series with cooling water pump;
Water source heat pump units includes cryogenic heat exchanger and high-temperature heat-exchanging, and the water inlet of cryogenic heat exchanger and outlet are respectively Connected outlet pipe and the water inlet pipe of the condenser of handpiece Water Chilling Units by the 8th water pipe and the 7th water pipe, the 5th water pipe is in series with cold But water pump;The water inlet of high-temperature heat-exchanging and outlet connect the first water pipe and second by the 9th water pipe and the tenth water pipe respectively Water pipe, the first water pipe is in series with heat-exchanger pump;
The water inlet of heating equipment plate type heat exchanger and hot-water boiler connects the first water pipe, and the outlet of heating equipment connects Second water pipe;
Series connection V4 valve on first water pipe, V3 valve that the second water pipe is connected, V1 valve that the 9th water pipe is connected, the tenth water Series connection V2 valve on pipe.
The water resource heat pump heater that described cooling water heat reclaims, is characterized in that: heating equipment selects vapor-water heat exchanger Or hot-water boiler;Handpiece Water Chilling Units is as cooling equipment.
When this utility model uses, the water source heat pump units of cooling water heat recovery, the condenser of handpiece Water Chilling Units, cooling water Pump, cooling tower, heat-exchanger pump, the air-conditioning box heating coil of fresh air conditioner case, air-conditioning box preheating coil pipe, each valve of fresh air conditioner case Door and respective line constitute the water resource heat pump heating system that cooling water heat reclaims.
Winter, handpiece Water Chilling Units operation, chilled water pump, the operation of cooling water pump, cooling tower, the air-conditioning box refrigeration of return air air-conditioning box Coil pipe runs, and the vaporizer of handpiece Water Chilling Units provides 7 DEG C of chilled waters to the air-conditioning box refrigeration coil of return air air-conditioning box, 7 DEG C of chilled waters It is warming up to 12 DEG C, simultaneously through air-conditioning box after flowing through the air heat-exchange of air-conditioning box refrigeration coil through air-conditioning box refrigeration coil The air of refrigeration coil by cool-down dehumidification, pressurizes through chilled water pump from the water of air-conditioning box refrigeration coil out 12 DEG C, returns to The evaporator refrigeration of handpiece Water Chilling Units is cooled to 7 DEG C, completes a refrigerative circle system.
In winter, the water source heat pump units operation that cooling water heat reclaims, the water inlet of the cryogenic heat exchanger of water source heat pump units is The cooling water of a handpiece Water Chilling Units condenser part out, handpiece Water Chilling Units condenser cooling moisture out is for two parts: one The cryogenic heat exchanger cooling of part supply water source heat pump units, another part cooling current cooled tower cooling, this two parts quilt Pressurize through supercooling water pump after the cooling hydration stream of cooling, enter the condenser of handpiece Water Chilling Units, temperature after heat exchange in condenser Raise, then split into two parts respectively enter water source heat pump units cryogenic heat exchanger cooling and cooling tower lower the temperature, complete cooling Water is by the cyclic process of recuperation of heat.When water source heat pump units is run, V3 valve and V4 valve closing, V1 valve is beaten with V2 valve Open, the water of air-conditioning box preheating coil pipe out 40 DEG C that the water inlet of water source heat pump units high-temperature heat-exchanging is fresh air conditioner case, with And the water from the air-conditioning box heating coil of return air air-conditioning box out 40 DEG C, after heat-exchanger pump pressurizes, enter through V1 valve High-temperature heat-exchanging, heats circulation inside water source heat pump units, and the water of 40 DEG C is temperature rising after heat exchange in high-temperature heat-exchanging To 45 DEG C, the air-conditioning box of the air-conditioning box preheating coil pipe and return air air-conditioning box 1 that entered fresh air conditioner case after entering V2 valve adds hot plate Pipe, completes a warming cycle.
Summer and transition season, handpiece Water Chilling Units operation, the operation of chilled water pump, cooling water pump, cooling tower, return air air-conditioning box Air-conditioning box refrigeration coil runs, and the air-conditioning box refrigeration coil of fresh air conditioner case runs, and the vaporizer of handpiece Water Chilling Units provides 7 DEG C of freezings The water air-conditioning box refrigeration coil to return air air-conditioning box and the air-conditioning box refrigeration coil of fresh air conditioner case, 7 DEG C of chilled waters are through air-conditioning Case refrigeration coil and flow through air-conditioning box refrigeration coil air heat-exchange after be warming up to 12 DEG C, simultaneously through air-conditioning box refrigeration coil Air by cool-down dehumidification, pressurize through chilled water pump from the water of air-conditioning box refrigeration coil out 12 DEG C, return to handpiece Water Chilling Units Evaporator refrigeration be cooled to 7 DEG C, complete a refrigerative circle system.
Summer and transition season, the water source heat pump units operation that cooling water heat reclaims, water source heat pump units cryogenic heat exchanger Water inlet be the cooling water of a handpiece Water Chilling Units condenser part out, handpiece Water Chilling Units condenser cooling moisture out is for two Part: the cryogenic heat exchanger cooling of part supply water source heat pump units, another part cooling current cooled tower cooling, these are two years old Pressurize through supercooling water pump after the cooling hydration stream that part is lowered the temperature, enter the condenser of handpiece Water Chilling Units, heat exchange in condenser Rear temperature raise, then split into two parts respectively enter water source heat pump units cryogenic heat exchanger cooling and cooling tower lower the temperature, complete Become cooling water by the cyclic process of recuperation of heat.When water source heat pump units is run, V3 valve and V4 valve closing, V1 valve and V2 Valve is opened, the air-conditioning box heating coil that water inlet is fresh air conditioner case of water source heat pump units high-temperature heat-exchanging and return air air-conditioning box The water of air-conditioning box heating coil out 40 DEG C, after heat-exchanger pump pressurizes, enter high-temperature heat-exchanging through V1 valve, pass through Heat circulation inside water source heat pump units, the water of 40 DEG C in high-temperature heat-exchanging after heat exchange temperature be increased to 45 DEG C, entered V2 valve Enter air-conditioning box heating coil and the air-conditioning box heating coil of return air air-conditioning box of fresh air conditioner case behind the door, complete a heating Cyclic process.
This utility model relates to the most complete in industrial circle of water source heat pump units heating system that cooling water heat reclaims New opplication, this utility model runs supplying hot water to the preheating plate of fresh air conditioner case by the water source heat pump units that cooling water heat reclaims Pipe, again hot coil and the hot coil again of return air air-conditioning box, prominent, may be implemented in annual stopping vapor-water heat exchanger or water bath The operation of stove, thus it is substantially reduced system energy consumption, energy-saving effect is notable.This utility model reduces the energy consumption of original system, has Good Social benefit and economic benefit.
It is big that this utility model produces equipment heating amount in being applicable to industrial circle Factory Building, and Factory Building needs constant temperature and humidity the whole year Air conditioner surroundings, Factory Building is configured with handpiece Water Chilling Units cold supply system and vapor-water heat exchanger or hot-water boiler heating system, and Factory Building configures Having return air air-conditioning box and the fresh air conditioner case of constant temperature and humidity, handpiece Water Chilling Units whole year operation provides chilled water, vapor-water heat exchanger and heat Homogeneous solution-type reactor whole year operation provides the place of hot water.
The purpose of this utility model is to realize being return air air-conditioning box and fresh air conditioner case carries to the handpiece Water Chilling Units of prior art The improvement of hot-water heating system is provided for return air air-conditioning box and fresh air conditioner case for chilled water system, vapor-water heat exchanger or hot-water boiler, Make acquisition energy-saving effect.Handpiece Water Chilling Units whole year operation provides chilled water, vapor-water heat exchanger and hot-water boiler whole year operation to provide heat Water.The refrigeration coil whole year operation of return air air-conditioning box needs handpiece Water Chilling Units to run refrigeration provides chilled water, and return air air-conditioning box is again Hot coil whole year operation needs vapor-water heat exchanger or hot-water boiler to run provides hot water;Fresh air conditioner case summer and conditioning in Transition Season restraining Cooling coil runs needs handpiece Water Chilling Units to run refrigeration offer chilled water, and fresh air conditioner case summer and transition season reheating coil pipe run Needing vapor-water heat exchanger or hot-water boiler to run and provide hot water, fresh air conditioner case preheats coil pipe winter and runs and need vapor-water heat exchanger Or hot-water boiler runs and provides hot water.This utility model devises the water resource heat pump heating system that a kind of cooling water heat reclaims, bag Include water source heat pump units, heat-exchanger pump, switch valve, relevant pipe-line system, also include handpiece Water Chilling Units, vaporizer, condenser, cold But tower, cooling water pump, chilled water pump, fresh air conditioner case, return air air-conditioning box.Water source heat pump units can absorb heat from low level heat energy Amount, then heat is transported to high-order thermal source, use the cooling water of water cooled chiller as the low level heat energy of water resource heat pump, have Water temperature compared with high, fluctuating temperature is little, water intaking is convenient, water processes simple, invests little, the advantages such as operating cost is low.Therefore, in conjunction with whole The use of constant temperature and humidity air-conditioning system, uses water source heat pump units to reclaim the heat of water cooled chiller cooling water, empty for return air Case and fresh air conditioner case is adjusted to provide preheating to be the most energy-efficient heating system with the hot water of reheating.The water that cooling water heat reclaims Source source pump recycles condensation heat effectively, can obtain a certain amount of hot water and substitute vapor-water heat exchanger or hot-water boiler Run and reduce energy resource consumption, the operation of cooling tower can be reduced again and increase the weight of the impact on environment of the city tropical island effect in summer, at one stroke two ?.
The technical scheme that the utility model proposes is: when handpiece Water Chilling Units is run, will discharge a large amount of condensation heat;Handpiece Water Chilling Units Condensation heat be approximately equal to the refrigerating capacity of unit and compressor horsepower sum, condensation heat is up to 1.25~1.3 times of refrigerating capacity.Adopt During with handpiece Water Chilling Units cooling water as the low level heat energy of water resource heat pump, the COP value of water resource heat pump may be up to more than 5.Condensation heat is returned In the time receiving, handpiece Water Chilling Units runs the condensation heat produced must be more than or equal to the heating capacity of source pump, the condensation heat that handpiece Water Chilling Units is unnecessary It is dispersed in air by cooling tower.The water inlet pipe and water outlet pipe of handpiece Water Chilling Units condenser is connected to the low-temperature side heat exchanger of source pump On water inlet pipe and water outlet pipe.It flow in the cryogenic heat exchanger of source pump from condenser cooling water out, the partial heat in cooling water After being absorbed by the cryogenic heat exchanger of source pump, cooling water temperature reduces.The cooling water of low temperature flows back to again the condensation of handpiece Water Chilling Units Device, after absorption condensation heat, cooling water temperature is raised again, completes a cyclic process.During water source heat pump units is run, from low temperature Heat exchanger absorb the water of high-order thermal source is reheated in high-temperature heat-exchanging by heat plus the acting of compressor, thus obtain High-temperature-hot-water.High-temperature-hot-water supplies the hot coil again of return air air-conditioning box, summer and transition season supply fresh air conditioner case the whole year Hot coil again, supplies the preheating coil pipe of fresh air conditioner case winter.
Accompanying drawing explanation
The structural representation of Fig. 1 prior art;
Fig. 2 is structural representation of the present utility model;
Fig. 3 is the partial enlarged drawing in I region in Fig. 2;
Fig. 4 is the partial enlarged drawing in II region in Fig. 2;
Fig. 5 is the partial enlarged drawing in III region in Fig. 2;
Fig. 6 is the partial enlarged drawing in IV region in Fig. 2.
Detailed description of the invention
This utility model is further illustrated below by way of specific embodiment.
Embodiment 1
The water resource heat pump heater that a kind of cooling water heat reclaims, including fresh air conditioner case 1, return air air-conditioning box 2, air-conditioning box Refrigeration coil 3, air-conditioning box heating coil 4, air-conditioning box preheating coil pipe 5, heat-exchanger pump 6, chilled water pump 9, vaporizer 10, condenser 11, handpiece Water Chilling Units 12, cooling tower 13, cooling water pump 14, cryogenic heat exchanger 15, high-temperature heat-exchanging 16, water source heat pump units 17, valve Door, water pipe and heating equipment 40, as shown in Fig. 2~Fig. 6, concrete structure is:
The outlet of the air-conditioning box preheating coil pipe 5 of fresh air conditioner case 1 connects first by the water pipe of V6 valve 306 of having connected Water pipe 21, the water inlet of the air-conditioning box preheating coil pipe 5 of fresh air conditioner case 1 connects second by the water pipe of V5 valve 305 of having connected Water pipe 22;The outlet of the air-conditioning box heating coil 4 of fresh air conditioner case 1 connects first by the water pipe of V8 valve 308 of having connected Water pipe 21, the water inlet of the air-conditioning box heating coil 4 of fresh air conditioner case 1 connects second by the water pipe of V7 valve 307 of having connected Water pipe 22;The outlet of the air-conditioning box heating coil 4 of return air air-conditioning box 2 connects first by the water pipe of V12 valve 312 of having connected Water pipe 21, the water inlet of the heating coil 4 of return air air-conditioning box 2 connects the second water pipe by the water pipe of V11 valve 311 of having connected 22;
The outlet of the air-conditioning box refrigeration coil 3 of fresh air conditioner case 1 connects the by the water pipe of V10 valve 310 of having connected Three water pipes 23, the water inlet of the air-conditioning box refrigeration coil 3 of fresh air conditioner case 1 connects the by the water pipe of V9 valve 309 of having connected Four water pipes 24;The outlet of the air-conditioning box refrigeration coil 3 of return air air-conditioning box 2 connects the by the water pipe of V14 valve 314 of having connected Three water pipes 23, the water inlet of the air-conditioning box refrigeration coil 3 of return air air-conditioning box 2 connects the by the water pipe of V13 valve 313 of having connected Four water pipes 24;
Handpiece Water Chilling Units 12 includes the air-conditioning of both vaporizer 10 and condenser 11, fresh air conditioner case 1 and return air air-conditioning box 2 The water inlet of case refrigeration coil 3 and outlet connect the outlet of vaporizer 10 respectively by the 4th water pipe 24 and the 3rd water pipe 23 And water inlet, the water inlet of condenser 11 and outlet connect cooling tower 13 by the 5th water pipe 25 and the 6th water pipe 26 respectively Outlet and water inlet, the 3rd water pipe 23 is in series with chilled water pump 9, and the 5th water pipe 25 is in series with cooling water pump 14;
Water source heat pump units 17 includes cryogenic heat exchanger 15 and high-temperature heat-exchanging 16, the water inlet of cryogenic heat exchanger 15 and going out The mouth of a river connects outlet pipe and the water inlet pipe of the condenser 11 of handpiece Water Chilling Units 12 respectively by the 8th water pipe 28 and the 7th water pipe 27, the It is in series with cooling water pump 14 on five water pipes 25;The water inlet of high-temperature heat-exchanging 16 and outlet are respectively by the 9th water pipe 29 and the Ten water pipes 30 connect the first water pipe 21 and the second water pipe 22, and the first water pipe 21 is in series with heat-exchanger pump 6;
The water inlet of heating equipment 40 connects the first water pipe 21, and the outlet of heating equipment 40 connects the second water pipe 22;
Series connection V4 valve 304 on first water pipe 21, V3 valve 303 that the second water pipe 22 is connected, the 9th water pipe 29 is connected V1 valve 301, V2 valve 302 that the tenth water pipe 30 is connected.
In the present embodiment: heating equipment 40 selects vapor-water heat exchanger 7 or hot-water boiler 8;Handpiece Water Chilling Units 12 sets as cooling Standby.
When the present embodiment uses, the water source heat pump units 17 of cooling water heat recovery, the condenser 11 of handpiece Water Chilling Units 12, cooling Water pump 14, cooling tower 13, heat-exchanger pump 6, the air-conditioning box heating coil 4 of fresh air conditioner case 1, the air-conditioning box preheating of fresh air conditioner case 1 Coil pipe 5, each valve and respective line constitute the water resource heat pump heating system that cooling water heat reclaims.
In winter, handpiece Water Chilling Units 12 runs, chilled water pump 9, and cooling water pump 14, cooling tower 13 run, the sky of return air air-conditioning box 2 Adjusting case refrigeration coil 3 to run, the vaporizer 10 of handpiece Water Chilling Units 12 provides 7 DEG C of chilled waters to freeze to the air-conditioning box of return air air-conditioning box 2 Coil pipe 3,7 DEG C of chilled waters are warming up to 12 through air-conditioning box refrigeration coil 3 after flowing through the air heat-exchange of air-conditioning box refrigeration coil 3 DEG C, simultaneously through the air of air-conditioning box refrigeration coil 3 by cool-down dehumidification, from the water warp of air-conditioning box refrigeration coil 3 out 12 DEG C Crossing chilled water pump 9 to pressurize, vaporizer 10 refrigeration returning to handpiece Water Chilling Units 12 is cooled to 7 DEG C, completes a refrigerative circle system.
Winter, cooling water heat reclaim water source heat pump units 17 run, the cryogenic heat exchanger 15 of water source heat pump units 17 Water inlet is the cooling water of handpiece Water Chilling Units 12 condenser 11 part out, handpiece Water Chilling Units 12 condenser 11 cooling moisture out For two parts: the cryogenic heat exchanger 15 of part supply water source heat pump units 17 is lowered the temperature, and another part cooling current are cooled Tower 13 is lowered the temperature, and pressurizes through supercooling water pump 14, enter the condensation of handpiece Water Chilling Units 12 after the cooling hydration stream that these two parts are lowered the temperature Device 11, in condenser 11, after heat exchange, temperature raises, then splits into two parts and respectively enter the low temperature of water source heat pump units 17 and change The cooling of hot device 15 and cooling tower 13 are lowered the temperature, and complete to cool down water by the cyclic process of recuperation of heat.When water source heat pump units is run, V3 Valve 303 is closed with V4 valve 304, and V1 valve 301 is opened with V2 valve 302, water source heat pump units 17 high-temperature heat-exchanging 16 The water of air-conditioning box preheating coil pipe 5 out 40 DEG C that water inlet is fresh air conditioner case 1, and add from the air-conditioning box of return air air-conditioning box 2 The water of hot coil 4 out 40 DEG C, after heat-exchanger pump 6 pressurizes, enters high-temperature heat-exchanging 16, Jing Guoshui through V1 valve 301 Source source pump 17 is internal heats circulation, the water of 40 DEG C in high-temperature heat-exchanging 16 after heat exchange temperature be increased to 45 DEG C, entered V2 Enter air-conditioning box preheating coil pipe 5 and the air-conditioning box heating coil 4 of return air air-conditioning box 1 of fresh air conditioner case 1 after valve 302, complete One warming cycle.
Summer and transition season, handpiece Water Chilling Units 12 runs, and chilled water pump 9, cooling water pump 14, cooling tower 13 run, return air The air-conditioning box refrigeration coil 3 of air-conditioning box 2 runs, and the air-conditioning box refrigeration coil 3 of fresh air conditioner case 1 runs, the steaming of handpiece Water Chilling Units 12 Send out device 10 and 7 DEG C of chilled waters air-conditioning box refrigeration coil 3 to return air air-conditioning box 2 and the air-conditioning box chill plate of fresh air conditioner case 1 are provided Pipe 3,7 DEG C of chilled waters are warming up to 12 through air-conditioning box refrigeration coil 3 after flowing through the air heat-exchange of air-conditioning box refrigeration coil 3 DEG C, simultaneously through the air of air-conditioning box refrigeration coil 3 by cool-down dehumidification, from the water warp of air-conditioning box refrigeration coil 3 out 12 DEG C Crossing chilled water pump 9 to pressurize, vaporizer 10 refrigeration returning to handpiece Water Chilling Units 12 is cooled to 7 DEG C, completes a refrigerative circle system.
Summer and transition season, cooling water heat reclaim water source heat pump units 17 run, water source heat pump units 17 low temperature changes The water inlet of hot device 15 is the cooling water of handpiece Water Chilling Units 12 condenser 11 part out, and handpiece Water Chilling Units 12 condenser 11 is out Cooling moisture is for two parts: the cryogenic heat exchanger 15 of part supply water source heat pump units 17 is lowered the temperature, another part cooling water Flow through cooling tower 13 to lower the temperature, pressurize through supercooling water pump 14 after the cooling hydration stream that these two parts are lowered the temperature, enter handpiece Water Chilling Units The condenser 11 of 12, in condenser 11, after heat exchange, temperature raises, then splits into two parts and respectively enter water source heat pump units 17 Cryogenic heat exchanger 15 cooling and cooling tower 13 lower the temperature, complete cool down water by the cyclic process of recuperation of heat.Work as water source heat pump units During 17 operation, V3 valve 303 is closed with V4 valve 304, and V1 valve 301 is opened with V2 valve 302, water source heat pump units 17 high temperature The air-conditioning box heating coil 4 that water inlet is fresh air conditioner case 1 of heat exchanger 16 and the air-conditioning box heating coil 4 of return air air-conditioning box 2 go out The water of 40 DEG C come, after heat-exchanger pump 6 pressurizes, enters high-temperature heat-exchanging 16 through V1 valve 301, through water source heat pump units 17 internal heat circulation, the water of 40 DEG C in high-temperature heat-exchanging 16 after heat exchange temperature be increased to 45 DEG C, entered V2 valve 302 laggard Enter the air-conditioning box heating coil 4 of fresh air conditioner case 1 and the air-conditioning box heating coil 4 of return air air-conditioning box 2, complete a heat cycles Process.

Claims (2)

1. the water resource heat pump heater that cooling water heat reclaims, including fresh air conditioner case (1), return air air-conditioning box (2), air-conditioning Case refrigeration coil (3), air-conditioning box heating coil (4), air-conditioning box preheating coil pipe (5), chilled water pump (9), vaporizer (10), condensation Device (11), handpiece Water Chilling Units (12), cooling tower (13) and cooling water pump (14),
It is characterized in that: also include heat-exchanger pump (6), cryogenic heat exchanger (15), high-temperature heat-exchanging (16), water source heat pump units (17), Valve, water pipe and heating equipment (40),
The outlet of air-conditioning box preheating coil pipe (5) of fresh air conditioner case (1) connects the by the water pipe of V6 valve (306) of having connected One water pipe (21), the water inlet of air-conditioning box preheating coil pipe (5) of fresh air conditioner case (1) water by V5 valve (305) of having connected Pipe connects the second water pipe (22);The outlet of the air-conditioning box heating coil (4) of fresh air conditioner case (1) is by having connected V8 valve (308) water pipe connects the first water pipe (21), and the water inlet of the air-conditioning box heating coil (4) of fresh air conditioner case (1) is by series connection The water pipe of V7 valve (307) connects the second water pipe (22);The outlet of the air-conditioning box heating coil (4) of return air air-conditioning box (2) The first water pipe (21) is connected, the water inlet of the heating coil (4) of return air air-conditioning box (2) by the water pipe of V12 valve (312) of having connected Mouth connects the second water pipe (22) by the water pipe of V11 valve (311) of having connected;
The outlet of the air-conditioning box refrigeration coil (3) of fresh air conditioner case (1) is connected by the water pipe of V10 valve (310) of having connected 3rd water pipe (23), the water inlet of the air-conditioning box refrigeration coil (3) of fresh air conditioner case (1) is by having connected V9 valve (309) Water pipe connects the 4th water pipe (24);The outlet of the air-conditioning box refrigeration coil (3) of return air air-conditioning box (2) is by having connected V14 valve The water pipe of door (314) connects the 3rd water pipe (23), and the water inlet of the air-conditioning box refrigeration coil (3) of return air air-conditioning box (2) is by string The water pipe having joined V13 valve (313) connects the 4th water pipe (24);
Handpiece Water Chilling Units (12) includes both vaporizer (10) and condenser (11), fresh air conditioner case (1) and return air air-conditioning box (2) The water inlet of air-conditioning box refrigeration coil (3) and outlet connected by the 4th water pipe (24) and the 3rd water pipe (23) respectively and evaporate The outlet of device (10) and water inlet, the water inlet of condenser (11) and outlet are respectively by the 5th water pipe (25) and the 6th water Pipe (26) connects outlet and the water inlet of cooling tower (13), and the 3rd water pipe (23) is in series with chilled water pump (9), the 5th water pipe (25) cooling water pump (14) it is in series with on;
Water source heat pump units (17) includes cryogenic heat exchanger (15) and high-temperature heat-exchanging (16), the water inlet of cryogenic heat exchanger (15) Connected the water outlet of the condenser (11) of handpiece Water Chilling Units (12) respectively by the 8th water pipe (28) and the 7th water pipe (27) with outlet Pipe and water inlet pipe, the 5th water pipe (25) is in series with cooling water pump (14);Water inlet and the outlet of high-temperature heat-exchanging (16) divide The 9th water pipe (29) and the tenth water pipe (30) the first water pipe (21) and the second water pipe (22) Tong Guo not connected, on the first water pipe (21) It is in series with heat-exchanger pump (6);
The water inlet of heating equipment (40) connects the first water pipe (21), and the outlet of heating equipment (40) connects the second water pipe (22);
First water pipe (21) upper series connection V4 valve (304), the second water pipe (22) upper series connection V3 valve (303), the 9th water pipe (29) Upper series connection V1 valve (301), the tenth water pipe (30) upper series connection V2 valve (302).
2. the water resource heat pump heater that cooling water heat as claimed in claim 1 reclaims, is characterized in that: heating equipment (40) selects With vapor-water heat exchanger (7) or hot-water boiler (8);Handpiece Water Chilling Units (12) is as cooling equipment.
CN201620237744.XU 2016-03-25 2016-03-25 The water resource heat pump heater that cooling water heat reclaims Active CN205678799U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620237744.XU CN205678799U (en) 2016-03-25 2016-03-25 The water resource heat pump heater that cooling water heat reclaims

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620237744.XU CN205678799U (en) 2016-03-25 2016-03-25 The water resource heat pump heater that cooling water heat reclaims

Publications (1)

Publication Number Publication Date
CN205678799U true CN205678799U (en) 2016-11-09

Family

ID=57437927

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620237744.XU Active CN205678799U (en) 2016-03-25 2016-03-25 The water resource heat pump heater that cooling water heat reclaims

Country Status (1)

Country Link
CN (1) CN205678799U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106642608A (en) * 2017-02-22 2017-05-10 中国汽车工业工程有限公司 Coating workshop spray booth circulating air system
CN108286761A (en) * 2017-05-16 2018-07-17 南京可索环境科技有限公司 Planar radiation air-conditioner set
CN108332327A (en) * 2018-03-01 2018-07-27 清华大学 A kind of airhandling equipment
CN111720921A (en) * 2019-07-09 2020-09-29 上海朗脉洁净技术股份有限公司 Auxiliary cooling device for cooling water of refrigerator
CN113864920A (en) * 2021-09-24 2021-12-31 珠海格力电器股份有限公司 Dehumidification heat pump air conditioning system

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106642608A (en) * 2017-02-22 2017-05-10 中国汽车工业工程有限公司 Coating workshop spray booth circulating air system
CN106642608B (en) * 2017-02-22 2022-06-10 中国汽车工业工程有限公司 Paint spraying chamber circulating air system of coating workshop
CN108286761A (en) * 2017-05-16 2018-07-17 南京可索环境科技有限公司 Planar radiation air-conditioner set
CN108286761B (en) * 2017-05-16 2023-10-31 南京可索环境科技有限公司 Plane radiation air conditioner set
CN108332327A (en) * 2018-03-01 2018-07-27 清华大学 A kind of airhandling equipment
CN108332327B (en) * 2018-03-01 2023-11-10 清华大学 Air treatment equipment
CN111720921A (en) * 2019-07-09 2020-09-29 上海朗脉洁净技术股份有限公司 Auxiliary cooling device for cooling water of refrigerator
CN113864920A (en) * 2021-09-24 2021-12-31 珠海格力电器股份有限公司 Dehumidification heat pump air conditioning system

Similar Documents

Publication Publication Date Title
CN205678799U (en) The water resource heat pump heater that cooling water heat reclaims
CN110319617B (en) Gas heat pump device based on heat source tower
CN103983042B (en) The indoor cold-hot integrated system of a kind of solar energy
CN105135739A (en) Multifunctional heat pump type evaporative condensing air-conditioning unit
CN108895707A (en) Recovered steam compression type heat pump assembly condensation heat hot water cyclesystem and application method
CN102620489B (en) Air conditioner heat pump unit with antifreeze solution regenerated heat recovery device
CN205119549U (en) Multi -functional heat pump type evaporation formula condensation air conditioning unit
CN201016499Y (en) Solar energy stepping utilization type air-conditioning system
CN112113367B (en) Solar heat driven improved solution absorption heat pump system and dehumidifying air-conditioning system
CN204513624U (en) Heat pump driven dehumidification solution temperature control and domestic hot water preparation device
CN202101331U (en) Heat pump water-heating system using central air-conditioner cooling water and low-temperature flue gas afterheat
CN109186114A (en) A kind of heat-pump apparatus
CN205783497U (en) A kind of water energy storage system
CN106524590A (en) Energy storage type air source heat pump cooling and heating unit
CN203940546U (en) A kind of Ship Waste Heat absorption refrigeration runner two stage dehumidify aircondition
CN102620474B (en) Air conditioner cold-hot water unit with antifreeze solution regenerated heat recovery device
CN102410675A (en) Over-cooling device and over-cooling method for evaporative condensation type refrigeration system
CN109099614A (en) A kind of new type solar energy Frostless air-source heat pump system
CN205174922U (en) Air source hot and cold water unit
CN105423617B (en) A kind of air-source flexibility water chiller-heater unit and operation method
CN204830275U (en) Multi -functional central air -conditioning system
CN209027132U (en) A kind of heat-pump apparatus
CN205403244U (en) Fresh water (FW) heat recovery utilizes device
CN202675751U (en) Air-condition heat pump unit provided with anti-freezing solution regenerated heat recovery device
CN108518891B (en) Direct-fired lithium bromide absorption type cold and hot water unit with sanitary hot water for eliminating white smoke

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant