CN205591358U - Rear -mounted connecting elements between building prefab - Google Patents

Rear -mounted connecting elements between building prefab Download PDF

Info

Publication number
CN205591358U
CN205591358U CN201620347355.2U CN201620347355U CN205591358U CN 205591358 U CN205591358 U CN 205591358U CN 201620347355 U CN201620347355 U CN 201620347355U CN 205591358 U CN205591358 U CN 205591358U
Authority
CN
China
Prior art keywords
box body
connecting elements
hole
cuboid box
prefab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620347355.2U
Other languages
Chinese (zh)
Inventor
郑智洪
欧长红
伍丹
雷雨田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Dongfanghong Construction Group Co., Ltd.
Hunan Dongfanghong residential industry Co., Ltd.
Original Assignee
HUNAN DONGFANGHONG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN DONGFANGHONG CONSTRUCTION GROUP CO Ltd filed Critical HUNAN DONGFANGHONG CONSTRUCTION GROUP CO Ltd
Priority to CN201620347355.2U priority Critical patent/CN205591358U/en
Application granted granted Critical
Publication of CN205591358U publication Critical patent/CN205591358U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a rear -mounted connecting elements between building prefab, including the top side long cubic box body of open -ended with connect the fasteners on a pair of curb plate of long cubic box body perpendicularly, the reservation installation slot position of two prefabs is striden to the bottom surface of long cubic box body, and the fasteners of both sides is connected the fastening with the pre -buried connecting piece of corresponding prefab respectively. Easy operation, the atress performance is good. Connecting easy operation for further messenger, seting up the round hole at one of a pair of side of box body, U type hole or slotted hole are seted up to the opposite side. May there be certain error in the pre -buried position of built -in fitting on the prefab, and this error just can be adjusted through U type hole or slotted hole. In order to make better whole of formation of mounting groove department of reserving on box body and the prefab, in the bottom surface of box body with there is not fasteners's a pair of side to set up slotted hole and rectangular hole respectively, clog when handling the inside and outside concrete of box body like this and form wholly, can improve the the stress performance of junction.

Description

A kind of rear-mounted connecting elements between architectural prefab
Technical field
This utility model relates to a kind of architectural prefab, the rear-mounted connecting elements being specifically related between a kind of architectural prefab.
Background technology
Traditional cast-in-place concrete building structure, needs to build pouring of substantial amounts of construction steel frame and safety guard net, concrete wall and floor and also needs to substantial amounts of forming panel.Concrete material needs site setup mixing plant or by vehicle transport to on-the-spot, if site setup mixing plant, equipment investment is big, and a project also needs after completing to transport equipment Removal, there is the possibility damaged in equipment during removing transhipment, and on the other hand cost of wheeling is the most of a relatively high.Vehicle transport on the one hand cost is high, on the other hand there is also certain waste.
The cast in situs of concrete is also required to relatively large equipment, because casting process must be continuous print, in addition it is also necessary to field personnel's continuous duty in evening on daytime, the especially operator on duty in evening are easily tired and fall asleep, pouring quality is possible to go wrong, and consequence is the most serious.
Additionally the concrete cast in situs of body of wall and floor is required for certain curing period after completing, and causes the prolongation in construction cycle, labor intensive material resources.
Input cost and the cost of wheeling of forming panel are the highest, and additionally erection and the dismounting of forming panel not only needs substantial amounts of manpower, there is also potential safety hazard.
So occurring in that the mode of production of full prefabricated panel and floor at present, by first prefabricated by design requirement in factory to wallboard and floor, on-the-spot need to connect using connecting elements between prefabricated wallboard, between wallboard and floor, thus overcome aforementioned poured in place concrete forming wall plate and the defect of floor.
Utility model content
When the purpose of this utility model is to provide one to make prefabricated component pour, embedded part structure is simple, attended operation simple rear-mounted connecting elements when moulding prefabricated part connects.
The utility model discloses the rear-mounted connecting elements between a kind of architectural prefab, cuboid box body and the connection securing member being vertically connected in cuboid box body pair of side plates including open top, the bottom surface of cuboid box body is across the reserved mounting groove position of two prefabricated components, and the securing member built-in connection respectively with corresponding prefabricated component that connects of both sides is connected fastening.
As preferably, the corresponding position of described cuboid box body pair of side plates offers circular hole and U-shaped hole respectively, and the opening in U-shaped hole is located therein the upper surface of side plate, and described connection securing member connects in circular hole and U-shaped hole respectively.
As preferably, described connection securing member is bolt, nut and gasket assembly, the body of rod of bolt through after the corresponding mounting hole on rectangular box with corresponding side prefabricated component mounting groove at built-in connection be connected as a single entity.
Slotted hole is offered in the another pair of side plates of described cuboid box body.
Rectangular opening is offered on the base plate of described cuboid box body.
Described cuboid box body connects the structure that also can take circular hole and the slotted hole offering concentrically line respectively in the pair of side plates of described connection securing member, and the length direction of slotted hole is along the short transverse of this side plate.The alternative U-shaped hole of slotted hole, regulates the site error between the built-in fitting of two prefabricated components.
Described cuboid box body is metal case, to ensure good stress performance.
This utility model bridges the mounting groove of two prefabricated components by a cuboid box body, is connected fastening by being connected to the securing member that connects of box body one opposite side with the built-in connection of corresponding prefabricated component, and simple to operate, stress performance is good.
In order to make attended operation simple further, the opposite side at cuboid box body offers circular hole and U-shaped hole respectively.During because prefabricated component pours, on two prefabricated components may there is certain error in the pre-buried position of built-in fitting, and this error just can be regulated by U-shaped hole.Certain U-shaped hole can also substitute with slotted hole.
Because after the built-in fitting of whole rear-mounted connecting elements and prefabricated component connects, need to use self-compacting concrete its filling to be processed, finally do not see link position from the appearance of prefabricated component.
In order to make more preferably to form an entirety at mounting groove reserved on cuboid box body and prefabricated component, in the bottom surface of cuboid box body with do not connect an opposite side of securing member and offer slotted hole and rectangular opening respectively, when so filling processes, the concrete inside and outside box body forms entirety, can improve the holistic resistant behavior of junction.
Accompanying drawing explanation
Fig. 1 is the structure for amplifying schematic diagram of one embodiment of this utility model.
Fig. 2 is the left view enlarged diagram of Fig. 1.
Fig. 3 is the vertical view enlarged diagram of Fig. 1.
Fig. 4 is a kind of use state diagram of the present utility model.
Detailed description of the invention
As shown in Figures 1 to 4, present embodiment discloses the rear-mounted connecting elements between a kind of architectural prefab, the connection being primarily adapted for use between prefabricated panel.
This connecting elements includes cuboid box body 1, connecting bolt 2 and pad 3.
Cuboid box body 1 is metal case, and its top side is open side, and the corresponding position of one opposite side offers circular hole and U-shaped hole respectively, and the opening in U-shaped hole is located therein the upper surface of side plate.
Offer in the another pair of side plates of cuboid box body 1 and on slotted hole 11, base plate, offer rectangular opening 12.
During prefabricated panel, reserve mounting groove in the corresponding position of wall-plate level direction side, built-in fitting threaded steel pipe is set at mounting groove.
After prefabricated panel scene erects, the seam crossing between two adjacent prefabricated panels is connected as a single entity with corresponding pre-buried corrugated tubing by this connecting elements.During connection, the bottom surface of cuboid box body is placed across two mounting grooves, make to offer simultaneously the opposite side in circular hole and U-shaped hole respectively with corresponding pre-buried corrugated tubing centering, then realize connecting fastening by bolt and pad.As shown in Figure 4.
The installing hole connecting securing member in cuboid box body 1 pair of side plates also can use circular hole and the structure of slotted hole pairing, say, that U-shaped hole can substitute with slotted hole.
The present embodiment bridges the mounting groove of two prefabricated components by a cuboid box body, is connected fastening by being connected to the securing member that connects of box body one opposite side with the built-in connection of corresponding prefabricated component, and simple to operate, stress performance is good.
In order to make attended operation simple further, the opposite side at cuboid box body offers circular hole and U-shaped hole respectively.During because prefabricated component pours, on two prefabricated components may there is certain error in the pre-buried position of built-in fitting corrugated tubing, and this error just can be regulated by U-shaped hole.Certain U-shaped hole can also substitute with slotted hole.
Because after the built-in fitting of whole rear-mounted connecting elements and prefabricated component connects, need to use self-compacting concrete its filling to be processed, finally do not see link position from the appearance of prefabricated component.
In order to make more preferably to form an entirety at mounting groove reserved on cuboid box body and prefabricated component, in the bottom surface of cuboid box body with do not connect an opposite side of securing member and offer slotted hole and rectangular opening respectively, so concrete inside and outside filling handling duration cube shape box body forms entirety, can improve the holistic resistant behavior of junction.

Claims (7)

1. the rear-mounted connecting elements between an architectural prefab, it is characterized in that: the cuboid box body that it includes open top and the connection securing member being vertically connected in cuboid box body pair of side plates, the bottom surface of cuboid box body is across the reserved mounting groove position of two prefabricated components, and the securing member built-in connection respectively with corresponding prefabricated component that connects of both sides is connected fastening.
2. the rear-mounted connecting elements between architectural prefab as claimed in claim 1, it is characterized in that: the corresponding position of described cuboid box body pair of side plates offers circular hole and U-shaped hole respectively, the opening in U-shaped hole is located therein the upper surface of side plate, and described connection securing member connects in circular hole and U-shaped hole respectively.
3. the rear-mounted connecting elements between architectural prefab as claimed in claim 2, it is characterized in that: described connection securing member is bolt, nut and gasket assembly, the body of rod of bolt through after the corresponding mounting hole on rectangular box with corresponding side prefabricated component mounting groove at built-in connection be connected as a single entity.
4. the rear-mounted connecting elements between architectural prefab as claimed in claim 1, it is characterised in that: offer slotted hole in the another pair of side plates of described cuboid box body.
5. the rear-mounted connecting elements between architectural prefab as claimed in claim 4, it is characterised in that: offer rectangular opening on the base plate of described cuboid box body.
6. the rear-mounted connecting elements between architectural prefab as claimed in claim 1, it is characterized in that: the corresponding position of the pair of side plates that described cuboid box body connects described connection securing member offers circular hole and slotted hole respectively, and the length direction of slotted hole is along the short transverse of this side plate.
7. the rear-mounted connecting elements between the architectural prefab as described in one of claim 1-6, it is characterised in that: described cuboid box body is metal case.
CN201620347355.2U 2016-04-25 2016-04-25 Rear -mounted connecting elements between building prefab Active CN205591358U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620347355.2U CN205591358U (en) 2016-04-25 2016-04-25 Rear -mounted connecting elements between building prefab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620347355.2U CN205591358U (en) 2016-04-25 2016-04-25 Rear -mounted connecting elements between building prefab

Publications (1)

Publication Number Publication Date
CN205591358U true CN205591358U (en) 2016-09-21

Family

ID=56935451

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620347355.2U Active CN205591358U (en) 2016-04-25 2016-04-25 Rear -mounted connecting elements between building prefab

Country Status (1)

Country Link
CN (1) CN205591358U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107662273A (en) * 2017-10-18 2018-02-06 北京城建长城建筑装饰工程有限公司 Assembled wallboard producing device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107662273A (en) * 2017-10-18 2018-02-06 北京城建长城建筑装饰工程有限公司 Assembled wallboard producing device

Similar Documents

Publication Publication Date Title
KR101182536B1 (en) Prefabricated double wall precast concrete pannel having surface material, reinforcing rod according to the purpose
CN206616862U (en) Formwork root bracing means
CN106638943A (en) Connecting node for steel pipe constrained steel recycled concrete column and steel beam and construction method thereof
CN206625428U (en) Floor closed system is poured after a kind of pipe well
CN104294920B (en) The node component of a kind of U-shaped steel-concrete combination beam and special-shaped steel pipe concrete post and preparation method
CN204112525U (en) Band perps precast shear wall structure in strong concrete precast frame
JP5785340B1 (en) Manhole construction lining material
CN206233560U (en) Wall formwork erecting structure
CN206157913U (en) Assembled square steel tube concrete post and girder steel connected node
CN205591358U (en) Rear -mounted connecting elements between building prefab
KR101334071B1 (en) The needless filling structure in the junction of pc beam and vertical member
CN206667933U (en) A kind of assembled construction wall
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
CN107237448B (en) The prefabricated interior fill concrete wallboard of one kind and its manufacturing method
CN209163167U (en) A kind of precast floor slab connecting node construction
CN207362884U (en) Underground pipe gallery template
CN205712715U (en) A kind of low-rise building lattice heat insulation prefabricated board member
CN205502058U (en) Pin -connected panel tower crane foundation
CN201915420U (en) Foundation of temporary gate building
CN209941967U (en) T-shaped wallboard connecting structure
KR100612938B1 (en) A construction system of the wall/dome and the the method thereof it
CN210529735U (en) Building steel structure platform base
CN112663788A (en) Assembled rapid construction method
CN206971529U (en) Light gauge cold-formed steel shape integration beam slab
CN208202549U (en) A kind of kitchen and bath's drop plate shaper

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170421

Address after: West Industrial Park in Hunan province 410217 Changsha Double Road No. 1

Co-patentee after: Hunan Dongfanghong residential industry Co., Ltd.

Patentee after: Hunan Dongfanghong Construction Group Co., Ltd.

Address before: West Industrial Park in Hunan province 410217 Changsha Double Road No. 1

Patentee before: Hunan Dongfanghong Construction Group Co., Ltd.