CN205576723U - Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier - Google Patents

Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier Download PDF

Info

Publication number
CN205576723U
CN205576723U CN201620120465.5U CN201620120465U CN205576723U CN 205576723 U CN205576723 U CN 205576723U CN 201620120465 U CN201620120465 U CN 201620120465U CN 205576723 U CN205576723 U CN 205576723U
Authority
CN
China
Prior art keywords
corrugated tube
pier
cushion cap
pier shaft
bellows
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620120465.5U
Other languages
Chinese (zh)
Inventor
葛继平
郑焕强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Institute of Technology
Original Assignee
Shanghai Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Institute of Technology filed Critical Shanghai Institute of Technology
Priority to CN201620120465.5U priority Critical patent/CN205576723U/en
Application granted granted Critical
Publication of CN205576723U publication Critical patent/CN205576723U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to an adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier, including pier shaft, cushion cap, the pier shaft setting is on the cushion cap, and pier shaft central point puts and presets the prestressing tendons bellows, has worn finish rolling twisted steel in the bellows, vertical pre -buried regular steel bar in the pier shaft, regular steel bar lower extreme stretch into set up in the cushion cap drive the bellows of horn mouth in, its tip mound is thick or weld fritter end board, opens and fills the fibre mortar that excels in in the bellows of horn mouth for increase regular steel bar's pull -out resistance. The utility model discloses a setting up the prestressing force spiral at the pier shaft, having improved anti -seismic performance and the runback potential energy after the earthquake power of pier greatly, the pier shaft is indulged the muscle end and is added slightly simultaneously, wears to establish in the cushion cap of bellows horn mouth form, adopts the fibre mortar that excels in to pour into, has also improved the shock resistance when having increased the pull -out resistance of reinforcing bar greatly. The event the utility model discloses be particularly useful for crowning earthquake intensity seismic area, and can be under construction fast, also have of great significance to the post -disaster reconstruction.

Description

Use the precast assembly bridge pier that high-intensity fiber mortar and corrugated tube connect
Technical field
This utility model relates to the assembled bridge pier in a kind of construction of road and bridge, particularly relates to a kind of precast assembly bridge pier using high-intensity fiber mortar and corrugated tube to connect.
Background technology
Concrete is the construction material that current consumption is maximum, and concrete production energy consumption is low, and raw material sources are wide, simple process, with low cost and have the features such as durable, fire prevention strong adaptability, application be convenient.But concrete is in work progress, the discharge of waste gas and dust is bigger, easily causes environmental pollution.Within significant period of time from now on, China is still in extensive civil engineering construction period, and along with to energy-saving and emission-reduction, the requirement of sustainable development improves constantly, the requirement to concrete performance and work progress also will be more and more higher.
The research report that current cement concrete develops to higher intensity is a lot, occurs in that the concrete of more than hundreds of MPa intensity, but some is because price is the highest, and some is because technology of preparing is the most complicated, some then some performance indications decline while intensity improves.Improve merely concrete crushing strength, the deficiency that its fragility is big, tensile strength is low can not be changed.
1994, very-high performance fiber concrete (Ultra High performance fiber
Concrete UHPFC) concept be suggested.Use fibre-reinforced method, create fibre reinforced concrete.Use conventional material and curing condition, can be prepared by the mortar more than 200Mpa, thus have broad application prospects.
Along with increasing severely and the increase of basis means of transportation Years Of Service of the volume of traffic, need the speed of application developing new system and method to improve highway bridge.Prefabricated subsection construction method is one of construction method that can substitute for existing cast-in-situ construction method.Use Precast Concrete Segmental Bridges method can reduce the interference to existing traffic to greatest extent, increase working security, minimizing environmental pollution, increase construction quality, improve speed of application, reduce the cost in the life operation phase.Bridge rapid construction technology, compared with conventional construction technology, can shorten on-site construction time, and the discharge of the waste water and gas dust of work progress can farthest be controlled.Rebar connecting technology is the key technology of prefabrication and assembly construction bridge rapid constructing method, needs to reach the standard of I grade of joint in " mechanical connection technique of reinforcement code " JGJ107.Current existing interconnection technique has the technology such as grout sleeve, mechanical sleeves, and grout sleeve is relatively costly, and mechanical sleeves needs upset reprocessing screw thread, destroys and is likely to occur near the screw thread of processing.Set forth herein the grouting corrugated tube interconnection technique that a kind of applicable cushion cap is connected with pier stud, construction can be met quickly simultaneously, connect the reliable and requirement of industrialized production.
The section assembling test specimen of this type is the highest to the performance requirement of grouting material.I.e. under seismic loading, vertical muscle must not be pulled out from corrugated tube, and before test specimen destroys, grouting material must not occur bond damage.Grouting corrugated tube uses UHPC(Ultra-High Performance Concrete ultra-high performance concrete) as grouting material, match ratio is shown in Table 1,3 days comprcssive strength about 73Mpa, and 7 days comprcssive strength about 85Mpa, within 28 days, comprcssive strength is about 140Mpa.
Table 1 UHPC match ratio
Metal bellows is circular corrugated stainless steel tubing, metal bellows meets the relevant regulations of country working standard " metal bellows for prestressed concrete " JG225, total length is no less than 24ds(ds for connected vertical muscle diameter), internal diameter is not preferably less than the little value of ds+40mm and 3ds.Wall thickness is not preferably less than 0.45mm.
Conventional grouting corrugated tube connection scheme needs enough vertical muscle bond lengths (i.e. the length of corrugated tube), uses UHPC high-intensity fiber concrete that bond length can be obviously reduced, meets the occasion that flat bent cap connects with basis.Anticipated total length can shorten to 18ds.
The important embodiment of design based on performance thought makes component have self-resetting capability exactly, has adopted no-cohesive prestressed reinforcement interconnection technique and bridge pier can be made to produce restoring force under geological process, can be returned to initial position at the end of earthquake.
Summary of the invention
For the drawbacks described above overcoming prior art to exist, this utility model provides a kind of precast assembly bridge pier using high-intensity fiber mortar and corrugated tube to connect.
For achieving the above object, the technical solution of the utility model is: a kind of precast assembly bridge pier using high-intensity fiber mortar and corrugated tube to connect, including pier shaft, cushion cap, pier shaft is arranged on cushion cap, described pier shaft center preset presstressed reinforcing steel corrugated tube, it is installed with finish rolling deformed bar in presstressed reinforcing steel corrugated tube, longitudinal pre-buried regular reinforcement in pier shaft, regular reinforcement lower end is stretched in the corrugated tube arranged in cushion cap, its regular reinforcement end is upset or welds fritter end plate, and the interior perfusion of corrugated tube is for increasing the mortar of the pull-out resistance of regular reinforcement.
Described finish rolling deformed bar end is provided with the big end plate and tie hoop being embedded in cushion cap.Described corrugated tube is for driving bell-mouthed metal bellows.Described mortar is high-intensity fiber mortar.
The beneficial effects of the utility model are:
The precast assembly bridge pier that high-intensity fiber mortar of the present utility model and corrugated tube connect, by being threaded reinforcing bar at pier shaft, substantially increase the self-resetting capability after the anti-seismic performance of bridge pier and earthquake, pier shaft indulges the overstriking of muscle termination simultaneously, it is located in the cushion cap of corrugated tube bell mouth shape, use high-intensity fiber mortar injection, while adding the pull-out resistance of reinforcing bar, also substantially increase shock resistance.Therefore this utility model is particularly suited for middle high intensity Zone, and this utility model energy rapid construction, is also significant post-disaster reconstruction.
Popularization of the present utility model is energy-saving and emission-reduction, the effective way of Air Pollution prevention and control, can promote construction quality, extends the life-span of building, promotes ability of preventing and reducing natural disasters.
Accompanying drawing explanation
Fig. 1 is that the present embodiment uses high-intensity fiber mortar and corrugated tube to connect and has the site plan of precast splice type bridge pier of self-resetting capability.
Fig. 2 is the assembled schematic diagram of the precast splice type bridge pier using high-intensity fiber mortar and corrugated tube to connect and having self-resetting capability,
Wherein: (a) pours into high-intensity fiber mortar schematic diagram for driving bell-mouthed corrugated tube, schematic diagram in bell-mouthed corrugated tube is driven after (b) inserts grouting for reserved vertical muscle.
Detailed description of the invention
Below with reference to accompanying drawing, the technique effect of design, concrete structure and the generation of utility model is described further, to be fully understood from the purpose of this utility model, feature and effect.
As shown in Figure 1, a kind of precast assembly bridge pier using high-intensity fiber mortar and corrugated tube to connect, mortar 5 upset 4 including presstressed reinforcing steel corrugated tube 1, regular reinforcement 2, finish rolling deformed bar 3, regular reinforcement end, opens bell-mouthed corrugated tube 6, cushion cap 7, tie hoop 8, pier shaft 9, bulk end plate 10.
Pier shaft 9 is arranged on cushion cap 7, pier shaft 9 center preset presstressed reinforcing steel corrugated tube 1, finish rolling deformed bar 3 it is installed with in presstressed reinforcing steel corrugated tube 1, longitudinal pre-buried regular reinforcement 2 in pier shaft 9, regular reinforcement 2 lower end stretch in cushion cap 7 arrange open in bell-mouthed corrugated tube 6, its regular reinforcement end upset 4 or weldering fritter end plate, open perfusion mortar 5 in bell-mouthed corrugated tube 6, for increasing the pull-out resistance of regular reinforcement 2.Finish rolling deformed bar 3 end is provided with the bulk end plate 10 and tie hoop 8 being embedded in cushion cap 7.Regular reinforcement 2 is high tensile reinforcement.Mortar 5 is high-intensity fiber mortar.
In this example, pier shaft 9 center arranges prestress pipe 1, and finish rolling deformed bar 3 is arranged in the duct of presstressed reinforcing steel corrugated tube 1, has a bulk of end plate 10 to be mechanically connected with finish rolling deformed bar 3 or weld in cushion cap 7.In pier shaft 9, longitudinally certain distance is stretched out in pre-buried regular reinforcement 2 and bottom, the regular reinforcement end upset 4 of pre-buried pier stud, increases the pull-out resistance of reinforcing bar.Cushion cap 7 is arranged drives bell-mouthed corrugated tube 6, perfusion mortar 5, for increasing the pull-out resistance of reinforcing bar.
When assembly, the first step, as shown in Figure 2 (a) shows, pre-buried in cushion cap 7 open perfusion mortar 5 in bell-mouthed corrugated tube 6;Second step, as shown in Fig. 2 (b), the reserved longitudinal regular reinforcement 2 of pier shaft 9 is pre-buried in inserting cushion cap 7 to be opened in bell-mouthed corrugated tube 6, it is not necessary to mud jacking, the reserved finish rolling deformed bar 3 of cushion cap 7 is arranged in the presstressed reinforcing steel corrugated tube 1 of pier shaft 9, stretch-draw.

Claims (4)

1. one kind uses the precast assembly bridge pier that high-intensity fiber mortar and corrugated tube connect, including pier shaft (9), cushion cap (7), pier shaft (9) is arranged on cushion cap (7), it is characterized in that: described pier shaft (9) center preset presstressed reinforcing steel corrugated tube (1), finish rolling deformed bar (3) it is installed with in presstressed reinforcing steel corrugated tube (1), longitudinal pre-buried regular reinforcement (2) in pier shaft (9), regular reinforcement (2) lower end is stretched in the corrugated tube (6) arranged in cushion cap (7), its regular reinforcement end upset (4) or weldering fritter end plate, in corrugated tube (6), perfusion is used for increasing the mortar (5) of the pull-out resistance of regular reinforcement (2).
The precast assembly bridge pier that employing high-intensity fiber mortar the most according to claim 1 and corrugated tube connect, it is characterised in that: described finish rolling deformed bar (3) end is provided with the bulk end plate (10) and tie hoop (8) being embedded in cushion cap (7).
The precast assembly bridge pier that employing high-intensity fiber mortar the most according to claim 1 and corrugated tube connect, it is characterised in that: described corrugated tube (6) is for driving bell-mouthed metal bellows.
The precast assembly bridge pier that employing high-intensity fiber mortar the most according to claim 1 and corrugated tube connect, it is characterised in that: described mortar (5) is high-intensity fiber mortar.
CN201620120465.5U 2016-02-15 2016-02-15 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier Expired - Fee Related CN205576723U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620120465.5U CN205576723U (en) 2016-02-15 2016-02-15 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620120465.5U CN205576723U (en) 2016-02-15 2016-02-15 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier

Publications (1)

Publication Number Publication Date
CN205576723U true CN205576723U (en) 2016-09-14

Family

ID=56869780

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620120465.5U Expired - Fee Related CN205576723U (en) 2016-02-15 2016-02-15 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier

Country Status (1)

Country Link
CN (1) CN205576723U (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760226A (en) * 2016-12-19 2017-05-31 上海应用技术大学 Attachment structure and the connection method of paddle grout sleeve, pier shaft and cushion cap can be mended
CN106906747A (en) * 2016-10-28 2017-06-30 上海市政工程设计研究总院(集团)有限公司 A kind of column and bent cap splicing structure
CN107100078A (en) * 2017-05-19 2017-08-29 中国五冶集团有限公司 A kind of packaged type bridges Precast Pier Columns component installation method
CN107190634A (en) * 2017-06-08 2017-09-22 上海应用技术大学 A kind of method of rapid construction bridge pier after macroseism shifted based on plastic hinge
CN107860638A (en) * 2017-12-22 2018-03-30 福州大学 It is a kind of to carry out reinforcing bar and the positioner of metal bellows grouting connection in batches
CN108560423A (en) * 2018-02-05 2018-09-21 四川动和工程咨询有限公司 A kind of construction method of regular reinforcement and finish rolling deformed bar hybrid reinforcement assembly pier
WO2019149270A1 (en) * 2018-02-05 2019-08-08 横琴共轭科技有限公司 Assembled pier for mixed reinforcement of normal steel rebar and finished threaded steel bar
CN110230319A (en) * 2019-07-05 2019-09-13 浙江省交通规划设计研究院有限公司 Prefabricated cushion cap and bridge pier
CN110258966A (en) * 2019-07-18 2019-09-20 西南科技大学 Material muscle connection sleeve is answered in a kind of resistance to plucking fiber reinforcement
CN110396918A (en) * 2019-07-22 2019-11-01 长安大学 A kind of equivalent cast-in-place assembled hollow pier system and its construction method
CN113585318A (en) * 2021-08-12 2021-11-02 上海应用技术大学 Prefabricated assembled hollow formwork connecting structure and construction method thereof

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106906747A (en) * 2016-10-28 2017-06-30 上海市政工程设计研究总院(集团)有限公司 A kind of column and bent cap splicing structure
CN106760226A (en) * 2016-12-19 2017-05-31 上海应用技术大学 Attachment structure and the connection method of paddle grout sleeve, pier shaft and cushion cap can be mended
CN107100078A (en) * 2017-05-19 2017-08-29 中国五冶集团有限公司 A kind of packaged type bridges Precast Pier Columns component installation method
CN107190634A (en) * 2017-06-08 2017-09-22 上海应用技术大学 A kind of method of rapid construction bridge pier after macroseism shifted based on plastic hinge
CN107190634B (en) * 2017-06-08 2018-12-21 上海应用技术大学 A method of rapid construction bridge pier after the macroseism based on plastic hinge transfer
CN107860638A (en) * 2017-12-22 2018-03-30 福州大学 It is a kind of to carry out reinforcing bar and the positioner of metal bellows grouting connection in batches
CN107860638B (en) * 2017-12-22 2024-02-09 福州大学 Positioning device capable of carrying out grouting connection of steel bars and metal corrugated pipes in batches
US11427975B2 (en) 2018-02-05 2022-08-30 Hengqin Gonge Technology Co., Ltd. Precast segmental pier reinforced with both conventional steel bars and high-strength steel bars
WO2019149270A1 (en) * 2018-02-05 2019-08-08 横琴共轭科技有限公司 Assembled pier for mixed reinforcement of normal steel rebar and finished threaded steel bar
CN108560423A (en) * 2018-02-05 2018-09-21 四川动和工程咨询有限公司 A kind of construction method of regular reinforcement and finish rolling deformed bar hybrid reinforcement assembly pier
CN110230319A (en) * 2019-07-05 2019-09-13 浙江省交通规划设计研究院有限公司 Prefabricated cushion cap and bridge pier
CN110258966A (en) * 2019-07-18 2019-09-20 西南科技大学 Material muscle connection sleeve is answered in a kind of resistance to plucking fiber reinforcement
CN110258966B (en) * 2019-07-18 2024-04-26 西南科技大学 Anti-pulling fiber reinforced composite bar connecting sleeve
CN110396918A (en) * 2019-07-22 2019-11-01 长安大学 A kind of equivalent cast-in-place assembled hollow pier system and its construction method
CN110396918B (en) * 2019-07-22 2024-03-12 长安大学 Assembled hollow pier system equivalent to cast-in-situ and construction method thereof
CN113585318A (en) * 2021-08-12 2021-11-02 上海应用技术大学 Prefabricated assembled hollow formwork connecting structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN205576723U (en) Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier
CN104675141B (en) A kind of FRP pipe constraint cement-base composite material reinforces pillarwork
CN102383418B (en) Anti-seismic prefabricated concrete solid square pile and production method thereof
CN103821677B (en) Prefabricated PC RPC wind power tower
CN103074941B (en) Assembling regeneration concrete node and the practice of steel bar girder beam are contained in a kind of end
CN108560544B (en) Sleeve connection assembled pile foundation and construction method thereof
CN101831875A (en) Precast assembly process of prestressed concrete cylindrical hollow pier
CN109056506A (en) Plug-in type post-tensioning prestressing without bondn section assembling concrete pier of steel tube
CN206467561U (en) Prefabricated assembled twin columns vase bridge pier
CN113373797B (en) Prefabricated assembled concrete anti-seismic pier structure and repairing method
CN202000251U (en) Cylindrical hollow prefabricated prestressed concrete pier structure
CN102121246A (en) Toughening prestressed centrifugal concrete pile
CN207714114U (en) A kind of prefabricated high-strength concrete bridge pier
CN109610311A (en) Prefabrication and assembly construction L-type floorings seam construction and implementation method
CN115045181A (en) Socket joint type node connection method and structure for prefabricated pier column and bearing platform in middle and high intensity region
CN201943070U (en) Toughened type prestress centrifugal concrete pile
CN204139054U (en) Pin-connected panel regeneration concrete filled steel tube Y type bridge pier
CN211689844U (en) Corrugated steel reinforcing arch utilizing high-strength grouting material
CN112921789A (en) Structure structure of self-resetting socket-and-spigot type ECC (error correction code) mixed bridge pier and splicing method thereof
CN219219334U (en) Prefabricated assembled ultra-high performance concrete T type roof beam
CN109972657A (en) Overall assembled steel reinforced concrete pipe gallery is contained in stake
CN206189456U (en) Three cabin piping lanes
CN212025899U (en) Concrete pipe and pier structure
CN103758122A (en) Environment-friendly modular concrete tubular column and construction method thereof
CN204590336U (en) A kind of overlapped shear wall based on half prefabricated ultra-tough steel concrete

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160914

Termination date: 20170215

CF01 Termination of patent right due to non-payment of annual fee