CN205442067U - Over -and -under type steel ore bin - Google Patents
Over -and -under type steel ore bin Download PDFInfo
- Publication number
- CN205442067U CN205442067U CN201520936201.2U CN201520936201U CN205442067U CN 205442067 U CN205442067 U CN 205442067U CN 201520936201 U CN201520936201 U CN 201520936201U CN 205442067 U CN205442067 U CN 205442067U
- Authority
- CN
- China
- Prior art keywords
- funnel
- support
- storage bin
- ore storage
- ore bin
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)
Abstract
The utility model relates to a metallurgical mine engineering equipment field specifically is an over -and -under type steel ore bin, including support, ore bin body, funnel, ore bin body bottom discharge mouth below is located to the funnel, and vibration feeder conveying equipment locates the below of funnel bottom discharge mouth, characterized by: the support includes upper portion support, lower support and funnel support, and the upper portion support cup joints with lower support and the ascending or decline of lower support can be followed to the upper portion support, fixes through the pin joint of bolt and the threaded connection of bolt between upper portion support and the lower support, and the ore bin body is fixed in upper portion support central authorities, the last funnel support that is equipped with of lower support, and funnel and ore bin body overlap joint are located in the funnel support. This steel ore bin adopts above -mentioned design, passes through the steel ore bin of traditional field fabrication installation on the support of liftable and realizes holistic modularization to reach the purpose that reduces steel ore bin self focus, reduced size, is convenient for the transportation and installs again, finally bring the facility for steel ore bin's installation.
Description
Technical field
This utility model relates to metallurgical mine engineering equipment field, specifically a kind of lift steel ore storage bin.
Background technology
In metallurgical mine Process of Engineering Construction, owing to steel ore storage bin volume is big, weight is not easy to greatly whole Transporting, therefore how to build with modular transportation, field erected mode.And when the steel ore storage bin each several part transporting destination through modularity is re-assemblied, need to use many bracing reinforcement parts and binding piece to be supported, carry out centre of gravity adjustment make it consolidate and it also requires take a significant amount of time, the most existing steel ore storage bin in transport, have that high cost, installation accuracy be the highest, the problem of set-up time length in terms of assembly.
Summary of the invention
The purpose of this utility model is, it is provided that a kind of liftable steel ore storage bin, and so, it can reduce volume so that whole Transporting, and is also convenient for carrying out restoration in destination and builds.
In order to achieve the above object, this utility model is achieved in that
A kind of lift steel ore storage bin, including support, ore storage bin body, funnel and vibrating feed conveying equipment, wherein, funnel is located at below ore storage bin body bottom portion discharging opening, the lower section of funnel bottom discharging opening is located at by vibrating feed conveying equipment, support includes upper bracket, lower bracket and funnel stand, upper bracket can rise or fall along lower bracket with lower bracket socket and upper bracket, connect by lock bolt between upper bracket and lower bracket and fix with the threaded of bolt, ore storage bin body is fixed on upper bracket central authorities, lower bracket is provided with funnel stand, funnel and ore storage bin body overlap and are located in funnel stand.
Described lift steel ore storage bin, upper bracket, lower bracket all include four root posts and for four root posts surround the crossbeam of rectangular frame structure, and four root posts of upper bracket are socketed on four root posts of lower bracket.
Described lift steel ore storage bin, funnel realizes threadeding by connecting bolt with ore storage bin body lap-joint.
This steel ore storage bin uses above-mentioned design, the steel ore storage bin of conventional on-site fabrication and installation is realized overall modularity by liftable support, thus reducing self center of gravity of steel ore storage bin, the purpose reducing volume, being readily transported and install again, the final installation for steel ore storage bin offers convenience.
Accompanying drawing explanation
Fig. 1 is this steel ore storage bin completion status schematic diagram.
Fig. 2 is this steel ore storage bin travel position schematic diagram.
Fig. 3 is the attachment structure schematic diagram of upper bracket and lower bracket.
Detailed description of the invention
This utility model is further illustrated below by way of specific embodiment.
Such as Fig. 1, shown in Fig. 2, a kind of lift steel ore storage bin, including support 4, ore storage bin body 1, funnel 2 and vibrating feed conveying equipment 5, wherein, funnel 2 is located at below ore storage bin body 1 bottom discharge mouth, the lower section of funnel 2 bottom discharge mouth is located at by vibrating feed conveying equipment 5, support 4 includes upper bracket 6, lower bracket 7 and funnel stand 3, upper bracket 6 is socketed with lower bracket 7 and upper bracket can rise or fall along lower bracket, as shown in Figure 3, fixed by the pin joint of latch 8 and the threaded of bolt 9 between upper bracket 6 and lower bracket 7, ore storage bin body 1 is fixed on upper bracket 6 central authorities, lower bracket 7 is provided with funnel stand 3, funnel 2 and ore storage bin body 1 overlap and are located in funnel stand 3.
Described lift steel ore storage bin, upper bracket 6, lower bracket 7 all include four root posts and for four root posts surround the crossbeam of rectangular frame structure, and four root posts of upper bracket 6 are socketed on four root posts of lower bracket 7.
Described lift steel ore storage bin, funnel 2 realizes threadeding by connecting bolt with ore storage bin body 1 lap-joint.
The assembly and disassembly methods of described lift steel ore storage bin, comprises the steps;
Step 1, make support, ore storage bin body, funnel respectively by design drawing steel section, and prepare vibrating feed conveying equipment;
Step 2, pre-assembled;
Carry out pre-assembled successively by lower bracket, vibrating feed conveying equipment, funnel stand, funnel, upper bracket, the order of ore storage bin body;
Step 2.1, by lower bracket central authorities by vibrating feed conveying equipment bolt connect,
Step 2.2, funnel stand is connected with lower bracket bolt and makes funnel stand be positioned at above vibrating feed conveying equipment;
Step 2.3, funnel is connected with funnel stand bolt;
Step 2.4, upper bracket set is received in lower bracket and realize pin joint and bolt respectively with bearing pin and bolt and connect;
Step 2.5, ore storage bin body is connected with upper bracket bolt and makes ore storage bin body be positioned at above funnel;
Step 3, partition transport;
Step 3.1, with loop wheel machine, ore storage bin body is hung, make lifting rope tighten but ore storage bin body of not slinging;
Step 3.2, unclamp upper bracket and be connected with bearing pin and the bolt of lower bracket;
Step 3.3, the connecting bolt unclamped between ore storage bin body and funnel;
Step 3.4, with loop wheel machine by the upper bracket with ore storage bin body along the downward downhill race of lower bracket, make ore storage bin body set fall on steel funnel top;
Step 3.5, again by bearing pin and bolt, upper bracket and lower bracket being realized pin joint and bolt is connected, the steel ore storage bin forming centre of gravity is overall;
Step 4, formally set up;
Step 4.1, the bearing pin unclamped between upper bracket and lower bracket and connecting bolt;
Step 4.2, it is lifted up ore storage bin body with loop wheel machine or Lifting Equipment to design work position;
Step 4.3, again upper bracket and lower bracket are realized pin joint by bearing pin and bolt and bolt is connected and arranges herringbone between ore storage bin body and support supports,
Step 4.4, connection ore storage bin body and funnel;
Step 4.5, adjustment ore storage bin body, the relative position of funnel, fasten all connecting bolts, installation.
Steel ore storage bin body that traditional field fabrication is installed by this steel ore storage bin and steel funnel etc. are combined as five submodules, and assemble them into as a kind of liftable non-detachable mold massing steel ore storage bin, bring following advantage for the transport of steel ore storage bin and installation:
1, by non-detachable mold massing and lower the center of gravity, it is possible to ensure the sea-freight safety of tall and big steel ore storage bin equipment, and extra bracing reinforcement and binding piece are greatly decreased, reduce transport, make and installation cost and unsafe factor;
2, process without scene completely and make and reduce field erected workload, and then reduction of erection time to greatest extent, improving work efficiency, make full use of resource, protect environment;
3, the making of all submodules, installation all can complete in the pre-assembled base of the preferable modularity of condition, improve installation accuracy and quality, it is to avoid the equipment installation difficulty caused because of transport deformation and site operation error even cannot be installed.
Claims (3)
1. a lift steel ore storage bin, including support, ore storage bin body, funnel and vibrating feed conveying equipment, wherein, funnel is located at below ore storage bin body bottom portion discharging opening, the lower section of funnel bottom discharging opening is located at by vibrating feed conveying equipment, it is characterized in that: support includes upper bracket, lower bracket and funnel stand, upper bracket can rise or fall along lower bracket with lower bracket socket and upper bracket, connect by lock bolt between upper bracket and lower bracket and fix with the threaded of bolt, ore storage bin body is fixed on upper bracket central authorities, lower bracket is provided with funnel stand, funnel and ore storage bin body overlap and are located in funnel stand.
Lift steel ore storage bin the most according to claim 1, it is characterized in that: upper bracket, lower bracket all include four root posts and for four root posts surround the crossbeam of rectangular frame structure, and four root posts of upper bracket are socketed on four root posts of lower bracket.
Lift steel ore storage bin the most according to claim 1, is characterized in that: funnel realizes threadeding by connecting bolt with ore storage bin body lap-joint.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520936201.2U CN205442067U (en) | 2015-11-23 | 2015-11-23 | Over -and -under type steel ore bin |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520936201.2U CN205442067U (en) | 2015-11-23 | 2015-11-23 | Over -and -under type steel ore bin |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205442067U true CN205442067U (en) | 2016-08-10 |
Family
ID=57180470
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520936201.2U Active CN205442067U (en) | 2015-11-23 | 2015-11-23 | Over -and -under type steel ore bin |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205442067U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105417203A (en) * | 2015-11-23 | 2016-03-23 | 中国二十冶集团有限公司 | Lifting type steel ore bin and disassembly and assembly method thereof |
-
2015
- 2015-11-23 CN CN201520936201.2U patent/CN205442067U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105417203A (en) * | 2015-11-23 | 2016-03-23 | 中国二十冶集团有限公司 | Lifting type steel ore bin and disassembly and assembly method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104929148B (en) | The upside-down mounting hardened system of generation power foundation of wind power ring group plinth and reinforcement means thereof | |
CN105586833B (en) | Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method | |
CN203728398U (en) | Transporting device with lifting and overturning functions | |
CN105298139A (en) | Modular mounting method of large space division cooling box steel structure | |
CN105464216A (en) | Construction method for ultrahigh oblique post with super-large cross section based on integral lifting formwork reinforcing system | |
CN205295950U (en) | High mound steel reinforcement cage of cast -in -place thin wall installation strength nature location skeleton body system | |
CN205442067U (en) | Over -and -under type steel ore bin | |
CN105417203B (en) | Lift steel ore storage bin | |
CN103303789B (en) | Adjustable buttress for supporting running rail of tunnel track laying gantry crane | |
CN206014221U (en) | A kind of escalator guide rail connection structure | |
CN214267774U (en) | Auxiliary frame assembly and concrete pump truck | |
CN205296829U (en) | Superelevation super large cross -section batter post integrally lift up formula template reinforcerment system | |
CN103920600B (en) | Off-line assembling method for rotor of large-sized flotation machine | |
CN203779680U (en) | Turnover supporting framework device | |
CN203412104U (en) | Container module connection reinforcer | |
CN208132821U (en) | A kind of mill support device | |
CN206734398U (en) | A kind of platform skeleton structure of quarry tipper | |
CN110939473A (en) | Prefabricated framework pillar for underground coal mine | |
CN206607580U (en) | A kind of steel reinforcement cage hanging steel bar of reusable edible | |
CN102464284B (en) | Partitioning lifting and transporting method for thickener | |
CN206591898U (en) | A kind of installation conversion base for drawing substation framework | |
CN206310984U (en) | A kind of barrel dismounts support | |
CN203284006U (en) | Spiced elevator car bottom structure | |
CN217173079U (en) | Ground transportation device for large-diameter steel pipes | |
CN203922531U (en) | A kind of improved climbing support supporting construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180420 Address after: 201900 Shanghai city Baoshan District Pangu Road No. 777 Co-patentee after: China Nerin Engineering Co., Ltd. Patentee after: China Twenty Metallurgical Group Co., Ltd. Address before: 201900 Shanghai city Baoshan District Pangu Road No. 777 Patentee before: China Twenty Metallurgical Group Co., Ltd. |
|
TR01 | Transfer of patent right |