CN205152957U - Foundation concrete pours self -supporting chute device - Google Patents
Foundation concrete pours self -supporting chute device Download PDFInfo
- Publication number
- CN205152957U CN205152957U CN201520938294.2U CN201520938294U CN205152957U CN 205152957 U CN205152957 U CN 205152957U CN 201520938294 U CN201520938294 U CN 201520938294U CN 205152957 U CN205152957 U CN 205152957U
- Authority
- CN
- China
- Prior art keywords
- chute
- support
- supporting
- base
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
- 230000007704 transition Effects 0.000 claims description 8
- 238000010276 construction Methods 0.000 abstract description 12
- 238000004519 manufacturing process Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 8
- 238000000034 method Methods 0.000 description 5
- 230000008569 process Effects 0.000 description 5
- 230000001105 regulatory effect Effects 0.000 description 4
- 238000005266 casting Methods 0.000 description 3
- 238000005452 bending Methods 0.000 description 2
- 230000008602 contraction Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 241000168254 Siro Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000009987 spinning Methods 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Chutes (AREA)
Abstract
The utility model provides a foundation concrete pours self -supporting chute device, this chute device include that chute group supports with being used for the support frame of chute group, the chute that chute group is increased by a plurality of inside width sizes in proper order cup joints and constitutes, each festival chute all lies in rather than the lower a lesson chute that cup joints, and chute group can freely adjust its length according to the construction demand in the certain degree, the support frame includes U type fork and supports the base, U type fork sets up support the top of base, U type fork has flexible function, can adjust the erection height of chute according to the construction demand in the certain degree, the utility model discloses the simple structure, easily production processing, the range of application is wide to have and erect fastly, conveniently deposit and transport advantages such as convenient.
Description
Technical field
The utility model relates to a kind of concreting chute device, particularly relates to a kind of base concrete and builds self-supporting chute device.
Background technology
There is the multiple structural forms such as bearing platform type, rim of a cup formula, stone bolt formula in current transformer-station concrete basis, in existing Substation Construction Project, according to Construction Design Schemes, need to build a fairly large number of concrete foundation platform, and concrete foundation platform distribution comparatively dense, residing construction landform is more complicated.In the process of construction of some basic platforms, comparatively greatly because concrete unloading position and concrete foundation platform enter difference of height between mould position, cannot realize using concrete mixer to build, pouring construction can only be carried out by chute.
The chute used in site operation, majority uses wooden form field fabrication to form, and this kind of chute mostly is single use, and utilization rate is lower, causes use cost higher; When concrete discharging, chute Chang Suiyi places, and does not have fixed support, and concrete easy splash during blanking, cause concrete to waste; The chute volume that wooden form makes is comparatively large, the chute that some length are longer transport not easy to store.
Utility model content
For above-mentioned wooden form chute, build at base concrete that the utilization rate existed in application is lower, chute does not have secure support and be inconvenient to store the problems such as transport, the utility model provides a kind of base concrete and builds self-supporting chute device, this chute device can regulate chute length according to construction casting demand, this chute device carries supporting mechanism simultaneously, in casting process, play stable supporting role to chute.
The technical scheme in the invention for solving the technical problem is: a kind of base concrete builds self-supporting chute device, this device comprises chute group and the bracing frame for supporting described chute group, the socket of chute that described chute group is increased successively by multiple inner width size is formed, and each joint chute described is all positioned at and saves chute with next of its socket; Described chute comprises U-type groove and is symmetricly set on the lapping plate of two both sides, riser upper end of described U-type groove, described lapping plate is provided with the support otic placode of through hole, chute guide rail and guide peg, described support otic placode to be symmetricly set on outside described lapping plate two ends and to be positioned at the described chute guide rail of plane on described lapping plate adjacent, and described guide peg is symmetricly set on described lapping plate lower plane one end.
Support frame as described above comprises U-shaped fork and base for supporting, and described U-shaped fork is arranged on the top of described base for supporting; Described U-shaped fork comprises U-shaped bar and is positioned at the expansion link immediately below described U-shaped bar, two vertical rods of described U-shaped bar are symmetrically arranged with respectively the chute rotational support support be connected with described support otic placode, described expansion link axial direction are provided with multiple upper and lower equally spaced through hole; Described base for supporting comprises telescopic sleeving rod, support plate and support leg, described telescopic sleeving rod is positioned at the top of described support plate, described support leg is arranged on the below of described gripper shoe, bearing pin through the through hole that the through hole that described telescopic sleeving rod is offered and described expansion link are offered by fixedly sleeved for described expansion link in described telescopic sleeving rod.
Preferably, described guide peg is made up of a cylinder and the round handle be arranged on directly over cylinder, and the round handle on described guide peg is connected in the chute guide rail of the chute of next socket.
Preferably, two risers and base plate of described U-type groove are provided with groove face.
Preferably, described chute rotational support support comprises U-shaped draw-in groove, support rim and bearing pin, described chute rotational support support is fixedly linked by the vertical rod upper end of described U-shaped draw-in groove base plate and described U-shaped bar, described support rim is made up of boss base and the boss vertical rod be arranged on directly over boss base, bearing pin is by being hinged in described U-shaped draw-in groove through the through hole that the through hole on U-shaped draw-in groove two riser and described boss base are offered by described support rim, and described boss vertical rod is directly nested with in described support otic placode through hole.
Preferably, described support leg comprises supporting leg loop bar and landing leg stretching bar, and described landing leg stretching bar is nested with in supporting leg loop bar, the axial direction of described landing leg stretching bar offers multiple upper and lower equally spaced through hole, described supporting leg loop bar offers a through hole.
Preferably, the socket gap of the two chute both sides socket-connected described in is set to 25mm; Two lapping plates of described chute bond end are provided with two concentric circular orbits respectively, and described chute guide rail and described ring-shaped guide rail intersection are the free transition zone of described guide peg, without any bar in described free transition zone.
Further, two risers of described U-type groove are fixedly installed flexible arc plate, described flexible arc plate is fixedly installed rubber pad, described rubber pad is tightly pressed on two inside walls of the chute of next socket.
The utility model beneficial effect is:
1, the chute group in this chute device is that the chute successively increased by more piece inner width size connects together and forms, can free-extension in certain length range, its chute length can be regulated flexibly, to adapt to different construction casting demand in work progress.
2, the bracing frame in this chute device is provided with stretching device, just can realize regulating the height of chute by the height of telescopic supporting rod on adjustment stretching device, in work progress, can the height of free adjustment expansion link, what meet differing heights demand with this builds operation.
3, the chute group in this chute device after end of use, can realize more piece chute and be contracted in together, conveniently deposit transport.
4, the supporting leg in this chute device possesses Telescopic, and when setting up chute, erection place is uneven, and by regulating the expansion link on supporting leg, bracing frame can be made to obtain and stablize firm ground supports.
5, the end face often saving chute in this chute device is provided with ring-shaped guide rail, the chute that two joints are socket-connected can relatively rotate in certain scope, in work progress, regulate the rotational angle of the chute socket-connected successively, the bending of whole chute can be realized, with this meet must by chute bend could realize build engineering.
6, the rubber pad that this chute front end is arranged tightly is affixed with the chute interior walls socket-connected, and can clean out concrete residual on chute interior walls when chute group is shunk to a certain extent.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is part preferred embodiment of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is overall structure schematic diagram of the present utility model;
Fig. 2 is more piece chute contraction state schematic diagram;
Fig. 3 is chute overall structure schematic diagram;
Fig. 4 is chute overall structure lateral view;
Fig. 5 is chute second example structure schematic diagram;
Fig. 6 is more piece chute socket bending combination schematic diagram;
Fig. 7 is bracing frame overall structure schematic diagram;
Fig. 8 is bracing frame second example structure schematic diagram;
Fig. 9 is chute the 3rd example structure schematic diagram;
Figure 10 is A place enlarged drawing in Fig. 7;
Figure 11 is B place enlarged drawing in Fig. 3;
In figure: 1 first segment chute, 11 chute guide rails, 12 support otic placode, 13U type groove, 131 concrete entrances, 132 concrete outlet, 1321 groove faces, 14 lapping plates, 15 guide pegs, 16 ring-shaped guide rails, the free transition zone of 17 guide peg, 18 flexible arc plates, 181 flexible arc plate through holes, 19 rubber pads, 191 rubber pad through holes, 2 second section chutes, section 3 the 3rd, chutes, 4 bracing frames, 41 base for supporting, 411 telescopic sleeving rods, 4111 telescopic sleeving rod through holes, 412 support plate, 413 support leg, 4131 leg sleeve rod through-holes, 4132 supporting leg loop bars, 414 landing leg stretching bars, 4141 landing leg stretching rod through-holes, 42U type is pitched, 421 expansion links, 4211 expansion link through holes, 422U type bar, 423 chute rotational support supports, 4231U type draw-in groove, 4232 support rims, 4233 boss bases, 4234 boss vertical rods, 4235 bearing pins.
Detailed description of the invention
Below in conjunction with specific embodiment and Fig. 1-Figure 10, be clearly and completely described the technical scheme in the utility model embodiment, obviously, described embodiment is only a part of preferred embodiment of the present utility model, instead of whole embodiments.Those skilled in the art can when doing similar distortion without prejudice to when the utility model intension, and therefore the utility model is by the restriction of following public specific embodiment.
The utility model provides a kind of base concrete and builds self-supporting chute device, as shown in Figure 1, this base concrete is built self-supporting chute device and is comprised chute group and the bracing frame 4 for supporting described chute group, described chute group is by first segment chute 1, second section chute 2 and Section of three chute 3 are socketed to form successively, described first segment chute 1 is socketed in second section chute 2, second section chute 2 is socketed in Section of three chute 3, first segment chute 1 is 150mm with the overlap joint repeat region of second section chute 2, the overlap joint repeat region of second section chute 2 and Section of three chute 3 is 150mm, in sliding chute transportation process, together with first segment chute 1 second section chute 2 can be contracted in Section of three chute 3 (as shown in Figure 2), facilitate the transport of chute like this, first segment chute 1, second section chute 2 and Section of three chute 3 structure textural except the inner width size difference of chute other structure design all identical, below in conjunction with the form of structure of first segment chute 1, chute specific embodiment is described in detail, as shown in Figure 3 and shown in Fig. 4, chute comprises U-type groove 13 and is symmetricly set on the lapping plate 14 of both sides, described U-type groove 13 liang of riser upper ends, U-type groove 13 two-port is divided into concrete entrance 131 and concrete outlet 132, described lapping plate 14 is provided with the support otic placode 12 with through hole, chute guide rail 11 and guide peg 15, described support otic placode 12 has four, be symmetricly set on two ends outside described lapping plate 14 respectively adjacent with the chute guide rail 11 being positioned at plane on described lapping plate 14, chute guide rail 11 has two, to be symmetricly set on two lapping plates 14 in plane respectively, one end adjacent with concrete outlet 132 at two lapping plate 14 lower planes is symmetrically arranged with guide peg 15 respectively, guide peg 15 is made up of a cylinder and the round handle be arranged on directly over cylinder, when chute socket-connects, the round handle of guide peg 15 is stuck in the chute guide rail 11 on the chute that socket-connects with it, when arranging more piece chute and shrinking, concrete residual in the chute socket-connected with it can be removed for the ease of the chute walls be nested with in inside, two risers and base plate of concrete outlet 132 end are provided with groove face 1321 (as shown in figure 11).In concrete pouring construction, some needs the place of building could can only realize building by arc chute, in order to make chute group after trailing, can regulate in certain scope and build angle, at this, realize two chutes socket-connected by the inner width changing chute U-type groove 413 and can do relative rotary motion within the specific limits, as shown in Figure 6, first segment chute 1 and the socket gap of second section chute 2 both sides are set to 25mm, the gap of second section chute 2 and Section of three chute 3 both sides is set to 25mm, two lapping plates 14 at concrete arrival end 131 place of above-mentioned three joint chutes arrange two concentric circular orbits 16, circular orbit 16 and the intersection of chute guide rail 11 are the free transition zone 17 of guide peg 15, without any bar in free transition zone 17, guide peg 15 can be random in free transition zone 17 slide to chute guide rail 11 or ring-shaped guide rail 16, as shown in Figure 6, when second section chute 2 needs to rotate, two guide pegs 15 of the first chute 1 slide in two ring-shaped guide rails 16 of second section chute 2, when Section of three chute 2 needs to rotate, two guide pegs 15 of second section chute 2 slide in two ring-shaped guide rails 16 of Section of three chute 3.Because the socket gap of above-mentioned three joint chutes increases, when three joint chutes shrink, concrete residual on U-type groove 13 liang of risers can not be known by the riser of the U-type groove 13 of row socket, in order in three joint chute contraction processes, equally can by concrete residual on U-type groove 13 liang of risers cleaning point, two risers of concrete outlet 132 end of three joint chutes are fixedly installed the flexible arc plate 18 with two through hole, flexible arc plate 18 is fixedly installed the rubber pad 19 with through hole, bolt by flexible arc plate through hole 181 and rubber pad through hole 19 by rubber pad 19 together with flexible arc plate 18 compact siro spinning technology, no matter chute group is at rotation status or in straight line deployed condition, rubber pad 19 can both tightly be pressed on two inside walls of next socket chute by flexible arc plate 18, like this while chute group is shunk, the concrete remained on U-type groove 13 inwall can be disposed.
Bracing frame 4 comprises U-shaped fork 42 and base for supporting 41, and described U-shaped fork 42 is arranged on the top of described base for supporting 41; the expansion link 421 that described U-shaped fork 42 comprises U-shaped bar 422 and is positioned at immediately below described U-shaped bar 422, two vertical rods of described U-shaped bar 422 are symmetrically arranged with respectively the chute rotational support support 423 be connected with described support otic placode 12, described expansion link 421 axial direction is provided with multiple equally spaced through hole 4211, described chute rotational support support 423 comprises U-shaped draw-in groove 4231, support rim 4232 and bearing pin 4235, described chute rotational support support 423 is fixedly linked by the vertical rod upper end of described U-shaped draw-in groove 4231 base plate and described U-shaped bar 422, described support rim 4232 is made up of boss base 4234 and the boss vertical rod 4233 be arranged on directly over boss base 4234, described bearing pin 4235 is by being hinged in described U-shaped draw-in groove 4231 through the through hole that the through hole on U-shaped draw-in groove 4231 liang of risers and described boss base 4234 are offered by described support rim 4232, described boss vertical rod 4233 is directly nested with in described support otic placode 12 through hole, support rim 4232 can rotate around bearing pin 4235, each joint chute angle of inclination required in bridge joint process is realized with this.
Base for supporting 41 comprises telescopic sleeving rod 411, support plate 412 and support leg 413, described telescopic sleeving rod 411 is positioned at the top of described support plate 412, described three support leg 413 are arranged on the below of described gripper shoe 412 and the circumferencial direction along circular base slab 412 is uniformly distributed, by bearing pin through the expansion link through hole 521 that the telescopic sleeving rod through hole 4111 that described telescopic sleeving rod 411 is offered and described expansion link 421 are offered by fixedly sleeved for described expansion link 421 in described telescopic sleeving rod 411, by the relative position of adjustable telescopic rod 421 with telescopic sleeving rod 411, the height change of the chute on bracing frame 4 can be realized.The construction landform at concrete foundation place is uneven, in the also inconvenience of some decorating position bracing frames 4 erection, in order to improve the stability of strutting system of bracing frame 4 further, support leg 413 comprises supporting leg loop bar 4132 and is nested with the landing leg stretching bar 414 in supporting leg loop bar, support leg 414 is provided with multiple equally spaced landing leg stretching rod through-hole 4141, bearing pin is by being fixed on supporting leg loop bar 4132 through leg sleeve rod through-hole 4131 and a landing leg stretching rod through-hole 4141 by landing leg stretching bar 414, by regulating the relative position relation of landing leg stretching bar 414 and supporting leg loop bar 4132, the i.e. support scope of adjustable bracing frame 4, in chute erection process, regulate the length of three landing leg stretching bars 414 to realize the reliable and stable support of bracing frame 4 pairs of chutes successively according to existing landform.
When using this chute device; first the length of required chute is selected according to construction demand; after determining described chute length; bracing frame 4 corresponding for described chute length is set up; then by chute a group by a group be arranged on bracing frame 4; after installing chute group; trough joint one is saved and stretches out and be fixed on chute rotational support support 423; the angle of inclination of whole chute is adjusted, to guarantee that concrete can smooth outflow in chute by the expansion link 421 on bracing frame 4.
The above has made detailed description to preferred embodiment of the present utility model and embodiment by reference to the accompanying drawings; but the utility model is not limited to the above-described embodiment and examples; for those skilled in the art; without departing from the concept of the premise utility; can also make some improvement and modification, these improve and modification also should be considered as protection domain of the present utility model.
Claims (7)
1. a base concrete builds self-supporting chute device, it is characterized in that, this device comprises chute group and the bracing frame for supporting described chute group, the socket of chute that described chute group is increased successively by multiple inner width size is formed, and each joint chute described is all positioned at and saves chute with next of its socket; Described chute comprises U-type groove and is symmetricly set on the lapping plate of two both sides, riser upper end of described U-type groove, described lapping plate is provided with the support otic placode of through hole, chute guide rail and guide peg, described support otic placode to be symmetricly set on outside described lapping plate two ends and to be positioned at the described chute guide rail of plane on described lapping plate adjacent, and described guide peg is symmetricly set on described lapping plate lower plane one end;
Support frame as described above comprises U-shaped fork and base for supporting, and described U-shaped fork is arranged on the top of described base for supporting; Described U-shaped fork comprises U-shaped bar and is positioned at the expansion link immediately below described U-shaped bar, two vertical rods of described U-shaped bar are symmetrically arranged with respectively the chute rotational support support be connected with described support otic placode, described expansion link axial direction are provided with multiple upper and lower equally spaced through hole; Described base for supporting comprises telescopic sleeving rod, support plate and support leg, described telescopic sleeving rod is positioned at the top of described support plate, described support leg is arranged on the below of described gripper shoe, bearing pin through the through hole that the through hole that described telescopic sleeving rod is offered and described expansion link are offered by fixedly sleeved for described expansion link in described telescopic sleeving rod.
2. base concrete according to claim 1 builds self-supporting chute device, it is characterized in that, described guide peg is made up of a cylinder and the round handle be arranged on directly over cylinder, and the round handle on described guide peg is connected in the chute guide rail of the chute of next socket.
3. base concrete according to claim 1 builds self-supporting chute device, it is characterized in that, two risers and base plate of described U-type groove are provided with groove face.
4. base concrete according to claim 1 builds self-supporting chute device, it is characterized in that, described chute rotational support support comprises U-shaped draw-in groove, support rim and bearing pin, described chute rotational support support is fixedly linked by the vertical rod upper end of described U-shaped draw-in groove base plate and described U-shaped bar, described support rim is made up of boss base and the boss vertical rod be arranged on directly over boss base, described bearing pin is by being hinged in described U-shaped draw-in groove through the through hole that the through hole on U-shaped draw-in groove two riser and described boss base are offered by described support rim, described boss vertical rod is directly nested with in described support otic placode through hole.
5. base concrete according to claim 1 builds self-supporting chute device, it is characterized in that, described support leg comprises supporting leg loop bar and landing leg stretching bar, described landing leg stretching bar is nested with in supporting leg loop bar, the axial direction of described landing leg stretching bar is offered multiple equidistant through hole up and down, described supporting leg loop bar offers a through hole.
6. base concrete according to claim 1 builds self-supporting chute device, it is characterized in that, described in the socket gap of two chute both sides that socket-connects be set to 25mm; Two lapping plates of described chute bond end are provided with two concentric circular orbits respectively, and described chute guide rail and described ring-shaped guide rail intersection are the free transition zone of described guide peg, without any bar in described free transition zone.
7. base concrete according to claim 6 builds self-supporting chute device, it is characterized in that, two risers of described U-type groove are fixedly installed flexible arc plate, described flexible arc plate is fixedly installed rubber pad, and described rubber pad is tightly pressed on two inside walls of the chute of next socket.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520938294.2U CN205152957U (en) | 2015-11-20 | 2015-11-20 | Foundation concrete pours self -supporting chute device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520938294.2U CN205152957U (en) | 2015-11-20 | 2015-11-20 | Foundation concrete pours self -supporting chute device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205152957U true CN205152957U (en) | 2016-04-13 |
Family
ID=55688669
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520938294.2U Withdrawn - After Issue CN205152957U (en) | 2015-11-20 | 2015-11-20 | Foundation concrete pours self -supporting chute device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205152957U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105442609A (en) * | 2015-11-20 | 2016-03-30 | 山东送变电工程公司 | Self-supporting chute device for pouring of foundation concrete |
CN106088097A (en) * | 2016-07-07 | 2016-11-09 | 郑楚英 | The construction method of delivering concrete and fog chute device under gentle slope and abrupt slope |
CN107447986A (en) * | 2017-09-22 | 2017-12-08 | 中国水利水电第四工程局有限公司 | A kind of construction method of concrete chute device and the chute device |
CN108894507A (en) * | 2018-08-13 | 2018-11-27 | 武汉冶建筑安装工程有限责任公司 | Adjustable concrete pours chute device |
-
2015
- 2015-11-20 CN CN201520938294.2U patent/CN205152957U/en not_active Withdrawn - After Issue
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105442609A (en) * | 2015-11-20 | 2016-03-30 | 山东送变电工程公司 | Self-supporting chute device for pouring of foundation concrete |
CN105442609B (en) * | 2015-11-20 | 2017-06-23 | 山东送变电工程公司 | Base concrete pours self-supporting chute device |
CN106088097A (en) * | 2016-07-07 | 2016-11-09 | 郑楚英 | The construction method of delivering concrete and fog chute device under gentle slope and abrupt slope |
CN106088097B (en) * | 2016-07-07 | 2018-01-16 | 郑楚英 | Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope |
CN107447986A (en) * | 2017-09-22 | 2017-12-08 | 中国水利水电第四工程局有限公司 | A kind of construction method of concrete chute device and the chute device |
CN108894507A (en) * | 2018-08-13 | 2018-11-27 | 武汉冶建筑安装工程有限责任公司 | Adjustable concrete pours chute device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105442609A (en) | Self-supporting chute device for pouring of foundation concrete | |
CN205152957U (en) | Foundation concrete pours self -supporting chute device | |
CN106522582A (en) | Supporting frame applicable to poured floor | |
CN107795120B (en) | Multi-curved-surface free-telescopic building formwork system equipment | |
US2671697A (en) | Portable shoring | |
US20190383039A1 (en) | Height-Adjustable Jack and Vertical Modular Component Support using the same | |
CN206581636U (en) | A kind of support frame for being applied to pour build floor | |
CN209276917U (en) | A kind of suspension type monorail traffic system and its pillarwork | |
CN207260638U (en) | Independent vertical supporting frame | |
CN112377218B (en) | Tunnel formwork support combined sliding rail truss support lattice system | |
CN201033943Y (en) | Integral hoistway formwork | |
CN211228151U (en) | Novel template support frame is used in public road bridge roof beam construction | |
US3614050A (en) | Reusable forming unit | |
CN210651274U (en) | Precast beam positioning device | |
CN210263827U (en) | Scaffold for building construction | |
CN205046572U (en) | Bulky concrete removes over -and -under type construction platform | |
CN210216169U (en) | A suspension type handling frame for construction outside concrete barrier | |
KR100367518B1 (en) | Concrete transfer and distributor | |
CN218059930U (en) | Steel pipe concrete arch bridge arch rib vertical splicing hydraulic jig frame | |
CN106522107B (en) | A kind of variable arc bridge floor stand device | |
CN107905530A (en) | A kind of adjustable support for shuttering of movement for groove construction column | |
CN220599171U (en) | Floor passes material mouth and pours template strutting arrangement | |
RU132107U1 (en) | SUPPORTS | |
CN213951962U (en) | Cast-in-place diaphragm operation platform of precast beam with adjustable | |
CN215366716U (en) | New and old road bed links up construction with reinforcing bar net piece and lays and uses device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20160413 Effective date of abandoning: 20170623 |
|
AV01 | Patent right actively abandoned |
Granted publication date: 20160413 Effective date of abandoning: 20170623 |