CN107447986A - A kind of construction method of concrete chute device and the chute device - Google Patents

A kind of construction method of concrete chute device and the chute device Download PDF

Info

Publication number
CN107447986A
CN107447986A CN201710868409.9A CN201710868409A CN107447986A CN 107447986 A CN107447986 A CN 107447986A CN 201710868409 A CN201710868409 A CN 201710868409A CN 107447986 A CN107447986 A CN 107447986A
Authority
CN
China
Prior art keywords
chute
concrete
bottom plate
fixed
baffle plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710868409.9A
Other languages
Chinese (zh)
Inventor
阎海平
贺登华
练松涛
马正斌
胡伶勇
郭万福
谢先鹏
邢世孝
刘根英
黄未来
葛红恩
路瑞博
皇甫帅
杨东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Engineering Bureau 4 Co Ltd
Original Assignee
Sinohydro Engineering Bureau 4 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Engineering Bureau 4 Co Ltd filed Critical Sinohydro Engineering Bureau 4 Co Ltd
Priority to CN201710868409.9A priority Critical patent/CN107447986A/en
Publication of CN107447986A publication Critical patent/CN107447986A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/04Devices for both conveying and distributing
    • E04G21/0481Concrete chutes

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention relates to field of civil engineering, and in particular to a kind of concrete chute device and construction technology.A kind of concrete chute device, it is arranged on the cross bar of scaffold, first group of chute body includes the first chute, first bottom plate, second group of chute body includes the second chute, second bottom plate, first bottom plate, second bottom plate is fixed on cross bar by U bolt, first chute is fixed on the first bottom plate by U-shaped reinforcing bar, second chute is fixed on the first bottom plate by U-shaped reinforcing bar, in first chute and the second chute convex baffle plate is provided with close to concrete discharge outlet, the top of convex baffle plate is connected by spring with the inwall of the first chute and the second chute, live and connect with the inwall of the first chute and the second chute in the lower end of convex baffle plate, connection living between first bottom plate and the second bottom plate, connected between first chute and the second chute by balata belt.Present invention is especially suited for the heavy construction that concrete square amount is larger and the gradient is relatively steep.

Description

A kind of construction method of concrete chute device and the chute device
Technical field
The present invention relates to field of civil engineering, and in particular to a kind of concrete chute device and construction technology.
Background technology
Concrete construction occupies very big proportion always in civil engineering industry, on concrete conveyance side in concrete construction The shortcomings that method traditional approach is mainly conveyed or pumped using tower crane tank, and these conventional methods are common is equipment arrangement, builds week Phase is long, construction cost is high, and by the strict limitation of construction site, this method be only applicable to concrete square amount it is smaller and The more slow mini engineering of the gradient, and without special construction prediction scheme, it is impossible to meet larger and the gradient is relative for concrete square amount Steeper large-scale upper engineering.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of concrete chute device and construction technology, effective system Solve on the premise of concrete quality is ensured for concrete square amount is larger and the gradient is relatively steep heavy construction Concrete conveyance problem.
To achieve these goals, technical scheme provided by the invention is:
A kind of concrete chute device, is arranged on the cross bar of scaffold, including at least first group of chute body and second group Chute body, first group of chute body include the first chute, the first bottom plate, and second group of chute body includes the second chute, the second bottom plate, the One bottom plate, the second bottom plate are fixed on cross bar by U bolt,
First chute is fixed on the first bottom plate by U-shaped reinforcing bar, and the second chute is fixed on the first bottom plate by U-shaped reinforcing bar On,
In first chute and the second chute convex baffle plate, the top of convex baffle plate are provided with close to concrete discharge outlet Be connected by spring with the inwall of the first chute and the second chute, the lower end of convex baffle plate and the first chute and the second chute it is interior Wall, which is lived, to be connected,
Connection living between first bottom plate and the second bottom plate,
Connected between first chute and the second chute by balata belt.
Specifically, the U-shaped reinforcing bar opening is fixed on the first bottom plate and the second bottom plate towards concrete feeding mouth and standing On, it is reserved with through hole on first chute and the second chute, the through hole on first chute and the second chute is mounted on U-shaped On reinforcing bar.
Specifically, first chute and the second chute inner bottom surface fixed setting fixed support, keep off between fixed with convex Connected between plate by loose-leaf, the top of convex baffle plate passes through spring and the first chute and the second chute concrete feeding mouth direction Inwall be connected.
Preferably, spring is connected with convex baffle plate respectively by suspension ring, and spring is slipped by suspension ring and the first chute and second The inwall connection of groove.
Specifically, the end set of one end that the first bottom plate is connected with the second bottom plate has tenon, the second bottom plate and the first bottom The connected one end of plate is provided with tongue-and-groove, and tenon is connected with tongue and groove fit.
Specifically, connected between the first bottom plate and the second bottom plate by universal joint.
Specifically, the first chute fixes one end of balata belt by screw, the second chute fixes rubber peel by screw The other end of band, balata belt are wrapped in the first chute, the outside of the second chute.
Specifically, the bottom of the first bottom plate and the second bottom plate buckles rectangular steel tube, and opened hole on rectangular steel tube, rectangular steel tube Block is inside provided with, block is fixed with connecting bracket, and the protruding rectangular steel tube of connecting bracket, connecting bracket passes through U bolt And the fixed structure that pad is formed is fixedly connected with cross bar.
Specifically, protection network is arranged on the both sides edge of the first bottom plate and the second bottom plate.
Present invention also offers a kind of construction method of concrete chute device,
On abrupt slope during concrete construction, knot is cast for the concrete clinker being stirred is transported to from coagulation discharge position Structure position, the construction of concrete chute device include following five steps:
The first step:Landform is examined on the spot, measured
The discrepancy in elevation of steep slope section, domatic angle are grasped comprehensively, basic bearing capacity, also need to consider that rock is special for mountain area abrupt slope Property, prepared to set up chute support scaffolding in next step;
Second step:Set up chute support scaffolding
Reconnoitred according to the first step, measurement result sets up scaffold, scaffold should be set up in strict accordance with specification, set up width should The control is convenient in 10m or so, guarantee construction safety, work;It should also be reserved for mountain area scaffold building in rock slopeReinforcing bar;Scaffold operation load must not exceed 3KN/m2;
3rd step:Concrete chute device is installed
Concrete chute is U-shaped structure, and top is provided with protection network, and protection network can prevent concrete spluttering, chute installation Carried out, examined on the spot according to the first step, measurement result selects appropriate number of chute to carry out tilting using sectional mode Installation, is placed into the U bolt below bottom plate on the cross bar of scaffold, is fixed with bolt by pad, then selected first Suitable bottom plate quantity is assembled, and chute is hung over followed by the through hole reserved on chute the U-shaped reinforcing bar of bottom plate welding On, select suitable chute quantity to be installed according to bottom plate quantity, be connected or adopt with tongue and groove fit using tenon between base It is attached with universal joint, the arrangement space position of chute can be modified, fixed support is fixed on to the discharging of chute At mouthful, then it will be attached between the bottom of convex baffle plate and fixed support by loose-leaf, the top of convex baffle plate passes through bullet Spring is connected with the inwall of the first chute and the second chute concrete feeding mouth direction,
Concrete is flow at chute feeding mouth first from the outflow of concrete tank car, because chute is in tilted layout, concrete exists It is flow in the presence of gravity along chute toward flowing down at convex baffle plate, concrete is accumulated at convex baffle plate, convex can be driven to keep off Being rotated at the top of plate along concrete flow direction, concrete can cross convex baffle plate and fall on next chute when reaching a certain amount, After concrete flow quantity is reduced, convex baffle plate can return to origin-location under the action of the spring, make concrete under such repeated action It is transported to and is cast position, can makes concrete is more economical safe on the premise of quality is ensured to be delivered to by chute device It is cast structure position;
4th step, safety inspection when concrete is poured into a mould:
Inspection is timed to chute, each connecting portion of bottom plate and scaffold connecting portion when pouring into a mould concrete, Scent a hidden danger timely elimination;
5th step, chute, bottom plate, scaffold are removed after casting complete
The concrete material stock cleaned with water on chute, turns on the bolt fastened to balata belt, chute from bottom plate On take down;The bolt of connecting bottom board is turned on, segmentation dismounting is carried out to bottom plate;Scaffold will be removed from top to bottom when removing, Dismounting operation is carried out in strict accordance with specification.
The technical advantage of the present invention, it is simple in construction, easy for construction, solve in big drop landform concrete construction In, ensure fast and effectively to convey concrete on the premise of concrete conveyance quality.
Brief description of the drawings
Fig. 1 is concrete chute construction flow chart
Fig. 2 is concrete chute structure top view
Fig. 3 is concrete chute structure rearview
Fig. 4 is concrete chute structure right view
Fig. 5 is convex baffle plate and the first chute connection diagram
Fig. 6 is Fig. 3 A-A to sectional view
Parts title in accompanying drawing is:
1st, the first chute, the 2, second chute, the 3, first bottom plate, the 4, second bottom plate, 5, cross bar, 6, fixed support, 7, bullet Spring, 8, suspension ring, 9, convex baffle plate, 10, balata belt, 11, protection network, 12, U-shaped reinforcing bar, 13, rectangular steel tube, 14, block, 15, U bolt, 16, connecting bracket, 17, pad.
Embodiment
To make structure of the present invention and function more easily understand, with reference to specific implementation method, this hair is further illustrated It is bright.
A kind of concrete chute device, is arranged on the cross bar 5 of scaffold, including at least first group of chute body and second group Chute body, first group of chute body include the first chute 1, the first bottom plate 3, and second group of chute body includes the second chute 2, the second bottom plate 4, the first bottom plate 3, the second bottom plate 4 are fixed on cross bar 5 by U bolt 15,
First chute 1 is fixed on the first bottom plate 3 by U-shaped reinforcing bar 12, and the second chute 2 is fixed on by U shapes reinforcing bar 12 On first bottom plate 4,
Convex baffle plate 9 is provided with close to concrete discharge outlet in first chute 1 and the second chute 2, convex baffle plate 9 Top is connected by spring 7 with the inwall of the first chute 1 and the second chute 2, the lower end of convex baffle plate 9 and the first chute 1 and the The inwall of two chutes 2, which is lived, to be connected,
Connection living between first bottom plate 3 and the second bottom plate 4,
Connected between first chute 1 and the second chute 2 by balata belt 10.
The U-shaped reinforcing bar 12 is open to be fixed on the first bottom plate 3 and the second bottom plate 4 towards concrete feeding mouth and standing, It is reserved with through hole on the chute 3 of first chute 1 and second, the through hole on the chute 3 of the first chute 1 and second is mounted on U On shape reinforcing bar 12.
The inner bottom surface of first chute, 1 and second chute 3 is fixedly installed fixed support 6, it is fixed between 6 with convex baffle plate 9 Between connected by loose-leaf, the top of convex baffle plate 9 passes through the chute 1 of spring 7 and first and the concrete feeding mouth side of the second chute 2 To inwall be connected.
Spring 7 is connected with convex baffle plate 9 respectively by suspension ring 8, and spring 7 passes through the chute 1 of suspension ring 8 and first and the second chute 2 inwall connection.
The end set of one end that the first bottom plate 3 is connected with the second bottom plate 4 has tenon, the second bottom plate and the phase of the first bottom plate 3 One end even is provided with tongue-and-groove, and tenon is connected with tongue and groove fit.
It can also be connected between first bottom plate 3 and the second bottom plate 4 by universal joint.Realize the first bottom plate 3 and the second bottom plate 4 Carry out the adjustment of spatial relation.
First chute 1 fixes one end of balata belt 10 by screw, and the second chute 2 fixes balata belt 10 by screw The other end, balata belt 10 is wrapped in the first chute 1, the outside of the second chute 2.
The bottom of first bottom plate 3 and the second bottom plate 4 buckles rectangular steel tube 13, opened hole on rectangular steel tube 13, rectangular steel tube Block 14 is provided with 13, block 14 is fixed with connecting bracket 16, the protruding rectangular steel tube 13 of connecting bracket 16, connection branch The fixed structure that frame 16 is formed by U bolt 15 and pad 17 is fixedly connected with cross bar 5.
Protection network 11 is arranged on the both sides edge of the first bottom plate 3 and the second bottom plate 4.
A kind of construction method of concrete chute device,
On abrupt slope during concrete construction, knot is cast for the concrete clinker being stirred is transported to from coagulation discharge position Structure position, the construction of concrete chute device include following five steps:
The first step:Landform is examined on the spot, measured
The discrepancy in elevation of steep slope section, domatic angle are grasped comprehensively, basic bearing capacity, also need to consider that rock is special for mountain area abrupt slope Property, prepared to set up chute support scaffolding in next step;
Second step:Set up chute support scaffolding
Reconnoitred according to the first step, measurement result sets up scaffold, scaffold should be set up in strict accordance with specification, set up width should The control is convenient in 10m or so, guarantee construction safety, work;It should also be reserved for mountain area scaffold building in rock slopeReinforcing bar;Scaffold operation load must not exceed 3KN/m2;
3rd step:Concrete chute device is installed
Concrete chute is U-shaped structure, and top is provided with protection network 11, and protection network 11 can prevent concrete spluttering, chute Installation is carried out using sectional mode, is examined on the spot according to the first step, measurement result selects appropriate number of chute to be inclined Inclined is installed, and the U bolt 15 below bottom plate is placed on the cross bar 5 of scaffold first, fixed by pad 17 with bolt, Then select suitable bottom plate quantity to be assembled, chute is hung over bottom plate welding followed by the through hole reserved on chute On U-shaped reinforcing bar 12, select suitable chute quantity to be installed according to bottom plate quantity, tenon and tongue and groove fit are used between base Connection is attached using universal joint, the arrangement space position of chute can be modified, fixed support 6 is fixed on and slipped The discharge outlet of groove, then it will be attached between the bottom of convex baffle plate 9 and fixed support 6 by loose-leaf, convex baffle plate 9 Top is connected by spring 7 with the inwall of the first chute 1 and the concrete feeding mouth direction of the second chute 2,
Concrete is flow at chute feeding mouth first from the outflow of concrete tank car, because chute is in tilted layout, concrete exists It is flow in the presence of gravity along chute toward flowing down at convex baffle plate 9, concrete is accumulated at convex baffle plate 9, can drive convex The top of baffle plate 9 rotates along concrete flow direction, and concrete can cross convex baffle plate 9 and fall on next slip when reaching a certain amount Groove, after concrete flow quantity is reduced, convex baffle plate 9 can return to origin-location under the effect of spring 7, make to mix under such repeated action Solidifying soil, which is transported to, is cast position, by chute device can make concrete on the premise of quality is ensured more economical safety it is defeated Deliver to and be cast structure position;
4th step, safety inspection when concrete is poured into a mould:
Inspection is timed to chute, each connecting portion of bottom plate and scaffold connecting portion when pouring into a mould concrete, Scent a hidden danger timely elimination;
5th step, chute, bottom plate, scaffold are removed after casting complete
The concrete material stock cleaned with water on chute, turns on the bolt fastened to balata belt 10, chute the bottom of from Taken down on plate;The bolt of connecting bottom board is turned on, segmentation dismounting is carried out to bottom plate;Scaffold will be torn open from top to bottom when removing Remove, dismounting operation is carried out in strict accordance with specification.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement made within refreshing and principle etc., should be included in the scope of the protection.

Claims (10)

1. a kind of concrete chute device, it is arranged on the cross bar (5) of scaffold, it is characterised in that slipped including at least first group Cell body and second group of chute body, first group of chute body include the first chute (1), the first bottom plate (3), and second group of chute body includes the Two chutes (2), the second bottom plate (4), the first bottom plate (3), the second bottom plate (4) are fixed on cross bar (5) by U bolt (15),
First chute (1) is fixed on the first bottom plate (3) by U-shaped reinforcing bar (12), and the second chute (2) passes through U-shaped reinforcing bar (12) It is fixed on the first bottom plate (4),
In first chute (1) and the second chute (2) convex baffle plate (9), convex baffle plate are provided with close to concrete discharge outlet (9) top is connected by spring (7) with the inwall of the first chute (1) and the second chute (2), the lower end of convex baffle plate (9) with The inwall of first chute (1) and the second chute (2), which is lived, to be connected,
Connection living between first bottom plate (3) and the second bottom plate (4),
It is connected between first chute (1) and the second chute (2) by balata belt (10).
A kind of 2. concrete chute device according to claim 1, it is characterised in that U-shaped reinforcing bar (12) the opening direction Concrete feeding mouth and standing be fixed on the first bottom plate (3) and the second bottom plate (4), first chute (1) and the second chute (3) it is reserved with through hole on, the through hole on first chute (1) and the second chute (3) is mounted on U-shaped reinforcing bar (12).
3. a kind of concrete chute device according to claim 1, it is characterised in that first chute (1) and second is slipped Groove (3) inner bottom surface fixed setting fixed support (6), it is connected between fixed between (6) and convex baffle plate (9) by loose-leaf, convex The top of baffle plate (9) is connected by spring (7) with the inwall of the first chute (1) and the second chute (2) concrete feeding mouth direction Connect.
A kind of 4. concrete chute device according to claim 3, it is characterised in that spring (7) by suspension ring (8) respectively with Convex baffle plate (9) is connected, and spring (7) is connected by suspension ring (8) with the inwall of the first chute (1) and the second chute (2).
5. a kind of concrete chute device according to claim 1, it is characterised in that the first bottom plate (3) and the second bottom plate (4) The end set of connected one end has tenon, and one end that the second bottom plate is connected with the first bottom plate (3) is provided with tongue-and-groove, tenon and tenon Groove is connected.
6. a kind of concrete chute device according to claim 1, it is characterised in that the first bottom plate (3) and the second bottom plate (4) Between connected by universal joint.
7. a kind of concrete chute device according to claim 1, it is characterised in that the first chute (1) is fixed by screw One end of balata belt (10), the second chute (2) fix the other end of balata belt (10), balata belt (10) bag by screw It is wrapped in the first chute (1), the outside of the second chute (2).
8. a kind of concrete chute device according to claim 1, it is characterised in that the first bottom plate (3) and the second bottom plate (4) Bottom buckle rectangular steel tube (13), opened hole on rectangular steel tube (13), is provided with block (14), block in rectangular steel tube (13) (14) fixed with connecting bracket (16), connecting bracket (16) protruding rectangular steel tube (13), connecting bracket (16) passes through U-shaped spiral shell The fixed structure that bolt (15) and pad (17) are formed is fixedly connected with cross bar (5).
9. a kind of concrete chute device according to claim 1, it is characterised in that protection network (11) is arranged on the first bottom plate (3) with the both sides edge of the second bottom plate (4).
A kind of 10. construction method of concrete chute device, it is characterised in that
On abrupt slope during concrete construction, structure bit is cast for the concrete clinker being stirred is transported to from coagulation discharge position Put, the construction of concrete chute device includes following five steps:
The first step:Landform is examined on the spot, measured
The discrepancy in elevation of steep slope section, domatic angle are grasped comprehensively, basic bearing capacity, also need to consider rock behavio(u)r for mountain area abrupt slope, Prepared to set up chute support scaffolding in next step;
Second step:Set up chute support scaffolding
Reconnoitred according to the first step, measurement result sets up scaffold, scaffold should be set up in strict accordance with specification, and setting up width should control System is convenient in 10m or so, guarantee construction safety, work;It should also be reserved for mountain area scaffold building in rock slope Reinforcing bar;Scaffold operation load must not exceed 3KN/m2;
3rd step:Concrete chute device is installed
Concrete chute is U-shaped structure, and top is provided with protection network (11), and protection network (11) can prevent concrete spluttering, chute Installation is carried out using sectional mode, is examined on the spot according to the first step, measurement result selects appropriate number of chute to be inclined Inclined is installed, and the U bolt (15) below bottom plate is placed on the cross bar (5) of scaffold first, spiral shell is used by pad (17) Bolt is fixed, and then selects suitable bottom plate quantity to be assembled, and chute is hung over bottom followed by the through hole reserved on chute On the U-shaped reinforcing bar (12) of plate weld, select suitable chute quantity to be installed according to bottom plate quantity, tenon is used between base It is connected with tongue and groove fit or is attached using universal joint, the arrangement space position of chute can be modified, by fixed branch Frame (6) is fixed on the discharge outlet of chute, then will be entered between the bottom of convex baffle plate (9) and fixed support (6) by loose-leaf Row connection, the top of convex baffle plate (9) passes through spring (7) and the first chute (1) and the second chute (2) concrete feeding mouth direction Inwall be connected,
Concrete is flow at chute feeding mouth first from the outflow of concrete tank car, because chute is in tilted layout, concrete is in gravity In the presence of along chute toward flowing down, flow to convex baffle plate (9) place, concrete is accumulated at convex baffle plate (9) place, can drive convex Rotated at the top of baffle plate (9) along concrete flow direction, concrete can cross convex baffle plate (9) and fall on down when reaching a certain amount One chute, after concrete flow quantity is reduced, convex baffle plate (9) can return to origin-location under spring (7) effect, so make repeatedly Make concrete conveyance under to being cast position, by chute device can make concrete on the premise of quality is ensured it is more economical Being delivered to for safety is cast structure position;
4th step, safety inspection when concrete is poured into a mould:
Inspection is timed to chute, each connecting portion of bottom plate and scaffold connecting portion when pouring into a mould concrete, found Hidden danger eliminates in time;
5th step, chute, bottom plate, scaffold are removed after casting complete
The concrete material stock cleaned with water on chute, the bolt fastened to balata belt (10) is turned on, chute from bottom plate On take down;The bolt of connecting bottom board is turned on, segmentation dismounting is carried out to bottom plate;Scaffold will be removed from top to bottom when removing, Dismounting operation is carried out in strict accordance with specification.
CN201710868409.9A 2017-09-22 2017-09-22 A kind of construction method of concrete chute device and the chute device Pending CN107447986A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710868409.9A CN107447986A (en) 2017-09-22 2017-09-22 A kind of construction method of concrete chute device and the chute device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710868409.9A CN107447986A (en) 2017-09-22 2017-09-22 A kind of construction method of concrete chute device and the chute device

Publications (1)

Publication Number Publication Date
CN107447986A true CN107447986A (en) 2017-12-08

Family

ID=60497974

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710868409.9A Pending CN107447986A (en) 2017-09-22 2017-09-22 A kind of construction method of concrete chute device and the chute device

Country Status (1)

Country Link
CN (1) CN107447986A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119487A (en) * 2020-03-19 2020-05-08 中建一局集团建设发展有限公司 Double-layer chute concrete pouring system and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5186299A (en) * 1992-03-16 1993-02-16 Stimson Brian L Concrete chute apparatus
CN202970778U (en) * 2012-12-03 2013-06-05 云南建工水利水电建设有限公司 Sliding chute concrete delivery device for long inclined shaft
CN104032960A (en) * 2014-06-20 2014-09-10 中建五局第三建设有限公司 Suspension type concrete placement chute device
CN205152957U (en) * 2015-11-20 2016-04-13 山东送变电工程公司 Foundation concrete pours self -supporting chute device
CN205421939U (en) * 2016-03-16 2016-08-03 中冶建工集团有限公司 Concrete placement chute structure
CN206233242U (en) * 2016-12-02 2017-06-09 中国电建集团贵阳勘测设计研究院有限公司 Concrete conveying chute with automatic flap gate
CN207228640U (en) * 2017-09-22 2018-04-13 中国水利水电第四工程局有限公司 A kind of concrete chute device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5186299A (en) * 1992-03-16 1993-02-16 Stimson Brian L Concrete chute apparatus
CN202970778U (en) * 2012-12-03 2013-06-05 云南建工水利水电建设有限公司 Sliding chute concrete delivery device for long inclined shaft
CN104032960A (en) * 2014-06-20 2014-09-10 中建五局第三建设有限公司 Suspension type concrete placement chute device
CN205152957U (en) * 2015-11-20 2016-04-13 山东送变电工程公司 Foundation concrete pours self -supporting chute device
CN205421939U (en) * 2016-03-16 2016-08-03 中冶建工集团有限公司 Concrete placement chute structure
CN206233242U (en) * 2016-12-02 2017-06-09 中国电建集团贵阳勘测设计研究院有限公司 Concrete conveying chute with automatic flap gate
CN207228640U (en) * 2017-09-22 2018-04-13 中国水利水电第四工程局有限公司 A kind of concrete chute device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119487A (en) * 2020-03-19 2020-05-08 中建一局集团建设发展有限公司 Double-layer chute concrete pouring system and construction method thereof
CN111119487B (en) * 2020-03-19 2023-10-24 中建一局集团建设发展有限公司 Double-layer chute concrete pouring system and construction method thereof

Similar Documents

Publication Publication Date Title
US8308958B2 (en) Fluid clarification system, method, and apparatus
CN203145473U (en) Concrete pouring distributing device
US4190144A (en) Concrete discharge chutes
BRPI0616278A2 (en) drilling debris storage and transport system, and method for storing and transporting drilling debris
CN107447986A (en) A kind of construction method of concrete chute device and the chute device
CN207228640U (en) A kind of concrete chute device
EP2346617A2 (en) Apparatus and method for reclaiming material
US20130213762A1 (en) Concrete Wall Chute
CN102091776B (en) Ladle nozzle casting combined drainage plug
CN203403420U (en) Concrete vertical conveying pouring system
CN202970778U (en) Sliding chute concrete delivery device for long inclined shaft
CN108867400B (en) Bridge maintenance equipment
CN207418118U (en) A kind of Combined tower crane hopper
CN206408905U (en) A kind of skyscraper garbage transporting device
CN212421758U (en) Mortar storage tank
CN103088826B (en) Concrete vertical conveying pouring system
CN207027896U (en) Ash system under well head not decoupling device screw delivery pump
CN216342189U (en) Feeding pipe conveying device capable of slowing down concrete segregation
CN109025306A (en) Concreting buffering vertical slip cylinder in civil construction
DE102012213975A1 (en) Rail vehicle with an internal tank
CN208122867U (en) A kind of tunnel double-lining divides storehouse cloth system
CN215206736U (en) Mining ash chute
CN105865211B (en) Smelting furnace slag charge collection system
JP2008202273A (en) Equipment and method for regenerating removed mud
JP2004232985A (en) Device and method for charging powder and granular explosives

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171208

RJ01 Rejection of invention patent application after publication