CN204919356U CN201520655588.4U CN201520655588U CN204919356U CN 204919356 U CN204919356 U CN 204919356U CN 201520655588 U CN201520655588 U CN 201520655588U CN 204919356 U CN204919356 U CN 204919356U
Authority
CN
China
Prior art keywords
truss girder
girder
steel truss
mould platform
peg
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520655588.4U
Other languages
Chinese (zh)
Inventor
曾明雄
周叶飞
李晓坤
吴浪
侯宝磊
贾卫亮
唐策
赵向国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
City Construction Co Ltd Of China Railway 15th Bureau Group
China Railway 15th Bureau Group Co Ltd
Original Assignee
7th Construction Co Ltd Of China 15th Corp
China Railway 15th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 7th Construction Co Ltd Of China 15th Corp, China Railway 15th Bureau Group Co Ltd filed Critical 7th Construction Co Ltd Of China 15th Corp
Priority to CN201520655588.4U priority Critical patent/CN204919356U/en
Application granted granted Critical
Publication of CN204919356U publication Critical patent/CN204919356U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a steel truss girder concrete decking construction hangs mould platform, including the horizontal bracket of array between the fixed mounting girder, every horizontal bracket of group includes parallel arrangement's bracket beam, be equipped with the peg on the same side in bracket beam's both ends, the upper end of peg is equipped with the level to the outside and bends, the level is bent a portion and is hung the dress at the girder up end to with girder up end welding together. By adopting the structure, the construction method of the existing upper hanger is replaced, the steel truss girder is ensured to be stressed evenly in the processes of erecting a steel truss girder hanging mould platform and pouring concrete, the deformation is symmetrical and uniform, and the repair period is reduced; the laying efficiency of the square wood and bamboo plywood is improved; meanwhile, the material turnover period and the manual application amount are reduced, the construction period is shortened, the construction cost is reduced, and good economic benefits are obtained; and the influence on the traffic of the upper surface of the steel truss girder is small in the actual construction process, and the normal operation of other processes is not influenced.

Description

Mould platform is hung in a kind of steel truss girder concrete slab construction
Technical field
The utility model belongs to steel truss girder concrete slab laying technology field, particularly relates to the construction of a kind of steel truss girder concrete slab and hangs mould platform.
Background technology
In steel truss girder concrete-bridge building course, bridge deck are laid is vital part in work progress after steel truss girder is built, its difficult problem is how to guarantee steel work producing balanced forces in casting process, steel work is avoided to produce local inhomogeneous deformation, cause the change of bridge force-bearing model, bridge deck concrete is caused to ftracture, produce quality accident, even structure is overturned, in practice of construction, unit in charge of construction is through repeatedly studying demonstration, finally determine that employing is hung modulus method and built bridge deck, the modulus method that hangs conventional at present adopts the suspension bracket be covered with at steel truss girder upper surface, refer to Fig. 5, the laying lumps of wood is carried out in the below of suspension bracket, bamboo slab rubber, and then carry out concreting, although this kind of mode solves the construction method of original full framing, decrease the turnover of material and artificial consumption, but need after laying by the angle bar frame being welded on steel truss girder upper surface one by one sawing fall, part angle steel is left in concrete after sawing, then repair one by one, workload is added in the middle of invisible like this, because upper surface lays suspension bracket, by the restriction in space when laying the lumps of wood in practice of construction process, laying the lumps of wood can only insert from suspension bracket one end, so greatly reduces operating efficiency.
Summary of the invention
The utility model provides the steel truss girder concrete slab construction that is simple, easy to install, that increase work efficiency of a kind of structure to hang mould platform for solving in known technology the technical problem that exists.
The technical scheme that the utility model is taked for the technical problem existed in solution known technology is:
Mould platform is hung in a kind of steel truss girder concrete slab construction, comprise the array horizontal tray between fixed installation girder, often organize horizontal tray comprise be arranged in parallel truss girder, the same side, both ends of described truss girder is provided with peg, the upper end of described peg is provided with horizontal bending laterally, described horizontal bending part is mounted on girder upper surface, and welds together with girder upper surface.
The utility model can also adopt following technical measures:
The same side, both ends of described truss girder is welded with center sleeve, and described peg is inserted in described center sleeve, and the bottom of described peg is provided with thread segment, and described thread segment stretches out the lower surface of center sleeve, equipped adjusting nut and pad on thread segment.
Described truss girder is embedded with bubble and scale.
The advantage that the utility model has and good effect are: because the utility model adopts said structure, namely adopt and hang mould platform in the soffit laying of steel truss girder, the application of this kind of structure instead of the construction method of existing over sling, ensure that steel truss girder hangs steel truss girder producing balanced forces in mould putting up platform, concreting process, distortion is symmetrical, even, only by sawing peg, need reserve within it after sawing, need not repair in the later stage after having built; Owing to there is no other component interference hanging above mould platform, thus the laying lumps of wood and bamboo slab rubber convenient and swift; Decrease turn around time and the manual application amount of material simultaneously, shorten the duration, reduce construction cost and achieve good economic benefit; And less to the traffic impact of steel truss girder upper surface in practice of construction process, do not affect normally carrying out of other operation.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model embodiment 1;
Fig. 2 is the utility model construction connection layout;
Fig. 3 is the structural representation of the utility model embodiment 1;
The structural representation of Fig. 4 the utility model embodiment 3;
Fig. 5 is prior art structural representation.
In figure: 1, horizontal tray; 1-1, truss girder; 1-2, peg; 1-20, horizontal bending; 1-21, thread segment; 2, center sleeve; 3, adjusting nut; 4, pad; 5, bubble and scale; 6, girder; 7, the lumps of wood; 8, bamboo slab rubber.
Detailed description of the invention
For summary of the invention of the present utility model, Characteristic can be understood further, hereby exemplify following examples, and coordinate accompanying drawing to be described in detail as follows:
Embodiment 1, refer to Fig. 1 and Fig. 2, mould platform is hung in a kind of steel truss girder concrete slab construction, comprise the array horizontal tray 1 between fixed installation girder, often organize horizontal tray comprise be arranged in parallel truss girder 1-1, the same side, both ends of described truss girder is welded with peg 1-2, and the upper end of described peg is provided with horizontal bending 1-20 laterally, described horizontal bending part is mounted on girder upper surface, and welds together with girder upper surface.
Embodiment 2, refer to Fig. 3, in order to improve the levelness adjusting the lumps of wood after laying the lumps of wood, center sleeve 2 is welded with in the same side, both ends of described truss girder, described peg is inserted in described center sleeve, the bottom of described peg is provided with thread segment 1-21, and described thread segment stretches out the lower surface of center sleeve, equipped adjusting nut 3 and pad 4 on thread segment.All the other features are identical with embodiment 1.
Embodiment 3, refers to Fig. 4, in order to improve the levelness of truss girder further, described truss girder is embedded with bubble and scale 5, like this can directly by the Realize of the direct reaction bracket beam of bubble and scale.All the other features are identical with embodiment 2.
Adopt said structure, namely adopt and hang mould platform in the soffit laying of steel truss girder, the application of this kind of structure instead of the construction method of existing over sling, ensure that steel truss girder hangs steel truss girder producing balanced forces in mould putting up platform, concreting process, distortion is symmetrical, even, only by sawing peg, need reserve within it after sawing, need not repair in the later stage after having built; Owing to there is no other component interference hanging above mould platform, thus the laying lumps of wood 7 and bamboo slab rubber 8 convenient and swift; Decrease turn around time and the manual application amount of material simultaneously, shorten the duration, reduce construction cost and achieve good economic benefit; And less to the traffic impact of steel truss girder upper surface in practice of construction process, do not affect normally carrying out of other operation.
The above is only to preferred embodiment of the present utility model, not any pro forma restriction is done to the utility model, every according to technical spirit of the present utility model to any simple modification made for any of the above embodiments, equivalent variations and modification, all belong in the scope of technical solutions of the utility model.

Claims (3)

1. mould platform is hung in a steel truss girder concrete slab construction, comprise the array horizontal tray between fixed installation girder, often organize horizontal tray comprise be arranged in parallel truss girder, the same side, both ends of described truss girder is provided with peg, the upper end of described peg is provided with horizontal bending laterally, described horizontal bending part is mounted on girder upper surface, and welds together with girder upper surface.
2. mould platform is hung in steel truss girder concrete slab construction according to claim 1, it is characterized in that: the same side, both ends of described truss girder is welded with center sleeve, described peg is inserted in described center sleeve, the bottom of described peg is provided with thread segment, described thread segment stretches out the lower surface of center sleeve, equipped adjusting nut and pad on thread segment.
3. mould platform is hung in steel truss girder concrete slab construction according to claim 1, it is characterized in that: described truss girder is embedded with bubble and scale.
CN201520655588.4U 2015-08-27 2015-08-27 Steel truss concrete decking construction hangs mould platform Active CN204919356U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520655588.4U CN204919356U (en) 2015-08-27 2015-08-27 Steel truss concrete decking construction hangs mould platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520655588.4U CN204919356U (en) 2015-08-27 2015-08-27 Steel truss concrete decking construction hangs mould platform

Publications (1)

Publication Number Publication Date
CN204919356U true CN204919356U (en) 2015-12-30

Family

ID=54968500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520655588.4U Active CN204919356U (en) 2015-08-27 2015-08-27 Steel truss concrete decking construction hangs mould platform

Country Status (1)

Country Link
CN (1) CN204919356U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114232508A (en) * 2022-01-29 2022-03-25 腾达建设集团股份有限公司 Cast-in-place decking construction strutting arrangement of steel-concrete composite beam
CN114481846A (en) * 2022-01-29 2022-05-13 北京航空航天大学 Cast-in-place construction method of bridge concrete bridge deck and bridge construction formwork
CN114541272A (en) * 2022-03-31 2022-05-27 临沂市政集团有限公司 Steel-concrete bridge deck structure for municipal construction and construction process thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114232508A (en) * 2022-01-29 2022-03-25 腾达建设集团股份有限公司 Cast-in-place decking construction strutting arrangement of steel-concrete composite beam
CN114481846A (en) * 2022-01-29 2022-05-13 北京航空航天大学 Cast-in-place construction method of bridge concrete bridge deck and bridge construction formwork
CN114541272A (en) * 2022-03-31 2022-05-27 临沂市政集团有限公司 Steel-concrete bridge deck structure for municipal construction and construction process thereof

Similar Documents

Publication Publication Date Title
CN103485283B (en) Hanging bracket supporting system of side-span cast-in-place section and implementation method thereof
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN204212286U (en) A kind of reinforced steel plate-concrete combined shear wall with ribbing
CN204919356U (en) Steel truss concrete decking construction hangs mould platform
CN204530421U (en) For the prefabricated case beam that the bent cap of falling T bridge floor continuous structure construction pedestal beam body is closely connected
CN103306371B (en) Assembled-type house PC prefabricated units fabrication and installation structure
CN201567787U (en) Form-traveler steel formwork
CN209194353U (en) It is a kind of to ride integral type bracket suitable for the construction of Bridge High-pier 0# block
CN202000265U (en) Concrete construction formwork for high pier of bridge
CN206902566U (en) A kind of arch rib bridge girder cantilever construction Hanging Basket
CN206554500U (en) Steel structure concrete, which is poured, uses adjustable transverse support bar
CN205857691U (en) A kind of basement haunch wall form supports
CN204475145U (en) Self-anchored suspension bridge anchoring is across cast-in-place box beam
CN208586899U (en) A kind of support frame with oblique jacking
CN104746434B (en) Closure segment formwork system without dismantling outer formwork
CN207847086U (en) A kind of tall and big beam form support frame
CN202899522U (en) Mounting structure for small-dimension veneering building materials
CN109252879A (en) A kind of vcehicular tunnel gutter liner tool-typed formwork and construction method
CN205171382U (en) Hyperboloid case beam side combination structure support device
CN104499435A (en) Bracket used for mounting self-anchored suspension bridge splay saddle base
CN204040485U (en) Bars In Poured Concrete Slab thickness and reinforcement cover control support
CN207452730U (en) A kind of irregular box-girder strutting system
CN203684106U (en) Hinge joint rebar structure based on pipeline conveying bridge
CN209163831U (en) A kind of vcehicular tunnel gutter liner tool-typed formwork
CN202611077U (en) Light steel keel boom back supporting member

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 200431 new road, Jingan District, Jingan District, Shanghai, 6

Co-patentee after: THE CITY CONSTRUCTION COMPANY LTD. OF CHINA RAILWAY 15TH BUREAU Group

Patentee after: CHINA RAILWAY 15TH BUREAU GROUP Co.,Ltd.

Address before: No. 666, Zhabei District republic new road, Shanghai City, Shanghai

Co-patentee before: THE 7TH CONSTRUCTION COMPANY LTD. OF CHINA 15TH Corp.

Patentee before: CHINA RAILWAY 15TH BUREAU GROUP Co.,Ltd.

CP03 Change of name, title or address