CN204899930U - Secretly dig leading dry out well in subway hole - Google Patents

Secretly dig leading dry out well in subway hole Download PDF

Info

Publication number
CN204899930U
CN204899930U CN201520491996.0U CN201520491996U CN204899930U CN 204899930 U CN204899930 U CN 204899930U CN 201520491996 U CN201520491996 U CN 201520491996U CN 204899930 U CN204899930 U CN 204899930U
Authority
CN
China
Prior art keywords
pilot tunnel
dry out
well
construction
out well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520491996.0U
Other languages
Chinese (zh)
Inventor
郭永伟
武明静
张隽
王鹏程
张卫业
沈春盛
张勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority to CN201520491996.0U priority Critical patent/CN204899930U/en
Application granted granted Critical
Publication of CN204899930U publication Critical patent/CN204899930U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model belongs to the technical field of the subway tunnel excavation, specifically a secretly dig leading dry out well in subway hole. The problem of sand cobble stratum tradition construction precipitation effect not good is solved, a secretly dig leading dry out well in subway hole, the upper pilot tunnel that finishes including being under construction and lower floor's pilot tunnel of treating the construction, the excavation has a plurality of dry out wells on the upper pilot tunnel, and the dry out well runs through in whole lower floor's pilot tunnel of treating the construction, and dry out well top is equipped with the dado, and the dado periphery is provided with the isolation layer, and dry out shaft bottom portion is equipped with the suction pump.

Description

Dewatering by leading level well in tunneling subway hole
Technical field
The utility model belongs to metro tunnel excavation technical field, specifically Dewatering by leading level well in a kind of tunneling subway hole.
Background technology
In recent years, along with the fast development of subway, process of construction is faced with day by day complicated underground environment.Adopt cut and cover method that large-area earth clearance and traffic must be brought to lead to change, and shield method can only be applied to standard section, is not suitable for section and changes more underground tunnel structure.Shallow burial hidden digging, have natural advantage, floor space is few, does not affect traffic above-ground, and digging mode is flexible, therefore, in subway construction under the new situation, obtains more application.
In excavation of subway process when passing through sand-pebble layer, needing in advance at ground construction dewatering well, by well point method water-pumping/draining, making water level drop to below the scope of operation, in the hope of reaching the condition of anhydrous excavation.But dewatering well (conventional caliber is 200mm) can only make water level reduce in subrange, water level can not be dropped to the height of expection.When especially running into interfacial water or perched water, dewatering well will be at a complete loss as to what to do.Therefore, when tunneling pilot tunnel is constructed, under upper strata pilot tunnel is in anhydrous condition, just can construct very soon; But when constructing the lower floor's pilot tunnel below groundwater table, due to main based on cobble, circle gravel, fine sand in stratum, permeability is strong, inevitably runs into underground water problem.Sometimes face or sidewall there will be larger stock current, run into layer of sand also with quicksand, and form significant threat to the safety of constructor, therefore digging process often plants seepage and suspend.Measure conventional is at present grouting for water blocking, after finding seepage point, it is injected to the cement-silicate dual slurry of rapid solidification, is stoped beyond excavation face by current.Although the method is effective in theory, in practical operation, many problems are there is, such as: current cause more greatly the slurries injected to be diluted by current, waste material and do not have due effect; Because of the uncertainty of formation void, fast solidifying slurries may inject dewatering well and cause the problems such as dewatering well inefficacy.
Summary of the invention
The utility model, in order to solve the not good problem of sand-pebble layer traditional construction dewatering effect, provides Dewatering by leading level well in a kind of tunneling subway hole.
The utility model takes following technical scheme: Dewatering by leading level well in a kind of tunneling subway hole, comprise the complete upper strata pilot tunnel of construction and lower floor's pilot tunnel to be onstructed, on the pilot tunnel of upper strata, excavation has some drainage wells, drainage well is through whole lower floor's pilot tunnel to be onstructed, drainage well top is provided with retaining wall, retaining wall periphery is provided with separation layer, and drainage bottom is provided with suction pump.
Described drainage well cross-distribution is on the pilot tunnel of upper strata.
Described drainage well stake footpath is 1 meter, and the degree of depth is 3-4 rice.
The base plate of the upper strata pilot tunnel of having constructed excavates artificial drainage well, efficiently collects the underground water within the scope of about 3 meters, periphery, reach the object of advance water discharge to the face of lower floor's pilot tunnel.Because drainage well location is before face, while excavation drainage well, serves again the effect of geologic prediction, provide reference to the personnel excavated, to select more efficiently, reasonable manner is excavated, and is kill two birds with one stone.
Compared with prior art, maximum two days of the utility model manually digging hole just can pore-forming, safe, convenient, fast, do not need big machinery and new high-tech material, the difficult problem that sand-pebble layer dewatering effect difference is brought can be overcome, excavation is carried out smoothly, ensure that the duration.Obtain larger duration benefit with few input, therefore, there is high promotional value.
Accompanying drawing explanation
Fig. 1 is the utility model profile;
Fig. 2 is the utility model plan view;
1-upper strata pilot tunnel in figure, 2-lower floor pilot tunnel, 3-drainage well.
Detailed description of the invention
In Practical Project is built.The Beijing Metro undertaken the construction of by middle Tie Shierju group No. 16 lines 17 mark east gate, Yuyuan Lake erect-position immediately below Xicheng District of Beijing and intersection Sanlihe Road, Haidian District, adopt PBA shallow mining method, this station is mainly positioned at alluvial-proluvial plain second-order terrace, be positioned at ancient stream channel, ancient Jin Gou river, the sandy gravel deposited containing a large amount of ancient stream channel in tunneling stratum and Extra-fine sand, permeability is strong.
No. 1, station, east gate, Yuyuan Lake ventilating shaft transverse passage-way levels pilot tunnel is all arranged in sand-pebble layer, and upper strata pilot tunnel is in anhydrous stratum and more stable, can normally excavate.When construct lower floor's pilot tunnel the 4th layer time, because excavation causes underground water to collect to the place of hollowing out, one deck interface current (dewatering well cannot carry out pump drainage to it) at the place of topping bar are topped bar along interface from third layer and are gushed out, and hydraulic pressure is comparatively greatly and with fine sand.Because excavation exists larger risk, cause construction to stop several times, progress is slow.The delayed of transverse passage-way progress will directly cause the main body duration delayed.
Dewatering by leading level well in a kind of tunneling subway hole, comprise the complete upper strata pilot tunnel 1 of construction and lower floor's pilot tunnel 2 to be onstructed, on upper strata pilot tunnel 1, excavation has some drainage wells 3, drainage well 3 is through whole lower floor's pilot tunnel 2 to be onstructed, drainage well 3 top is provided with retaining wall, retaining wall periphery is provided with separation layer, is provided with suction pump bottom drainage well 3.
Described drainage well 3 cross-distribution is on upper strata pilot tunnel 1.
Described drainage well 3 footpaths are 1 meter, and the degree of depth is 3-4 rice.
After drainage well construction completes, the water yield according to every mouthful of well arranges suction pump, ensures that the water flow energy collected is drained in time.After taking above measure, underground water have found passage more efficiently, and face is water burst no longer.The excavation of drainage well has verified again the geological condition of front of tunnel heading to a certain extent, for follow-up excavation provides true and reliable foundation.

Claims (3)

1. Dewatering by leading level well in a tunneling subway hole, it is characterized in that: comprise the complete upper strata pilot tunnel (1) of construction and lower floor's pilot tunnel (2) to be onstructed, lower floor's pilot tunnel (2) is positioned at the below of upper strata pilot tunnel (1), the upper excavation of upper strata pilot tunnel (1) has some drainage wells (3), drainage well (3) is through whole lower floor's pilot tunnel (2) to be onstructed, drainage well (3) top is provided with retaining wall, and retaining wall periphery is provided with separation layer, and drainage well (3) bottom is provided with suction pump.
2. Dewatering by leading level well in tunneling subway hole according to claim 1, is characterized in that: described drainage well (3) cross-distribution is on upper strata pilot tunnel (1).
3. Dewatering by leading level well in tunneling subway hole according to claim 2, is characterized in that: described drainage well (3) stake footpath is 1 meter, and the degree of depth is 3-4 rice.
CN201520491996.0U 2015-07-09 2015-07-09 Secretly dig leading dry out well in subway hole Expired - Fee Related CN204899930U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520491996.0U CN204899930U (en) 2015-07-09 2015-07-09 Secretly dig leading dry out well in subway hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520491996.0U CN204899930U (en) 2015-07-09 2015-07-09 Secretly dig leading dry out well in subway hole

Publications (1)

Publication Number Publication Date
CN204899930U true CN204899930U (en) 2015-12-23

Family

ID=54922116

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520491996.0U Expired - Fee Related CN204899930U (en) 2015-07-09 2015-07-09 Secretly dig leading dry out well in subway hole

Country Status (1)

Country Link
CN (1) CN204899930U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107227961A (en) * 2017-06-29 2017-10-03 中铁十二局集团有限公司 Heavy caliber dewatering well construction method in metro built by mining method hole
CN108661662A (en) * 2018-05-17 2018-10-16 中铁十二局集团有限公司 Water rich strata increases tunnel boring Cheng Jing newly and harnesses the river method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107227961A (en) * 2017-06-29 2017-10-03 中铁十二局集团有限公司 Heavy caliber dewatering well construction method in metro built by mining method hole
CN108661662A (en) * 2018-05-17 2018-10-16 中铁十二局集团有限公司 Water rich strata increases tunnel boring Cheng Jing newly and harnesses the river method

Similar Documents

Publication Publication Date Title
AU2013252230B2 (en) Method for distributed storage and use of underground water in mine
CN106351660B (en) A method of descend water resource to be regulated and controled over the ground for coal mining region
CN102493822A (en) Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN109593957B (en) Active extraction method for in-situ leaching of ionic rare earth ore
CN104694746A (en) Ion-adsorption-type rare earth in-situ leaching method and leaching system thereof
CN102425421B (en) Novel water control method suitable for mine shafts
CN105179011B (en) A kind of tunnel closure facility and its method for blocking
CN105821889A (en) Loess platform landslip comprehensive treatment method based on underground water level control
CN102383412A (en) Construction method by adopting dewatering and water recharging to control sedimentation surrounding deep foundation pit
CN109441450A (en) A kind of double resource pit mining modes of lower coal water of overlying strata hydrogeologic condition disturbance
CN103939109B (en) The permanent shutoff inclined shaft structure of isolating with tunnel
CN106087953B (en) A kind of drainage and construction method for preventing and treating mountain area large size spoil ground mud-rock flow
CN109026010A (en) A kind of mine seepage well slip casting type sinking shaft construction method
CN110130376A (en) A kind of method of tailing back production ground water drainage
CN105064380B (en) Harnessed the river anti-skid structure rich in diving high slope
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN102808627A (en) Underground excavation construction method of steel pipe shed
CN103343690B (en) Construction method of shaft antiseep structure used when large section of inclined shaft passes through aquifer
CN106120822B (en) A kind of method for protecting support and device that prevent mud stone from coming down
CN114134877B (en) Treatment method for mining ground cracks of shallow coal seam in hilly and hilly areas of peaked landform
CN105112652B (en) A kind of rare earth ore in-situ leaching disposing mother liquor canal body structure
CN204899930U (en) Secretly dig leading dry out well in subway hole
CN113027522B (en) Coal mine drainage same-layer recharging method
CN1130712A (en) Drainage cut-off (deep ditch high-building method) drainage and supplying optimization combination for preventing and harnessing groud water
CN110500112A (en) Earth pressure balanced shield, EPBS is parallel with shallow burial hidden digging tunnel to overlap construction method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151223

CF01 Termination of patent right due to non-payment of annual fee