CN204876630U - Interim supporting platform of super high -rise building equipment - Google Patents

Interim supporting platform of super high -rise building equipment Download PDF

Info

Publication number
CN204876630U
CN204876630U CN201520409931.7U CN201520409931U CN204876630U CN 204876630 U CN204876630 U CN 204876630U CN 201520409931 U CN201520409931 U CN 201520409931U CN 204876630 U CN204876630 U CN 204876630U
Authority
CN
China
Prior art keywords
crossbeam
welded
building equipment
longeron
supporting platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520409931.7U
Other languages
Chinese (zh)
Inventor
毛立臣
张伟
曹艳明
任书华
侯维
张雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Bureau Group Installation Engineering Co Ltd
Original Assignee
China Construction First Group Corp Ltd
China Construction First Bureau Group Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, China Construction First Bureau Group Installation Engineering Co Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201520409931.7U priority Critical patent/CN204876630U/en
Application granted granted Critical
Publication of CN204876630U publication Critical patent/CN204876630U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an interim supporting platform of super high -rise building equipment, it includes crossbeam, longeron, bracing, landing leg, support, connecting rod and connecting bolt, crossbeam and longeron welding form braced frame, the landing leg welding is in braced frame's bottom, the lateral part at the landing leg is welded to the one end of bracing, and the other end of bracing welds the bottom at crossbeam or longeron, the lower extreme welding of landing leg has the keysets, and the roof on the support passes through the bolt fastening with the keysets on the landing leg, and the bottom plate on the support welds the upper portion at the building construction roof beam, the crossbeam on the adjacent braced frame is connected to the connecting rod to it is fixed to use connecting bolt. The utility model provides an interim supporting platform of super high -rise building equipment, its simple structure, simple to operate under the uncompleted condition of building structure, utilizes perpendicular super high -rise building equipment to the equipment place layer of taking one's place of transporting of civil engineering tower crane, has solved the awkward situation that the perpendicular transportation of equipment is taken one's place among the super high -rise building, ensures the whole construction progress of building.

Description

A kind of super highrise building equipment temporary supporting platform
Technical field
The utility model relates to a kind of equipment vertical transport support platform in place, particularly relates to a kind of super highrise building equipment temporary supporting platform.
Background technology
At present, super highrise building is increasing, and the electro mechanical system device that super highrise building is relevant is also day by day complicated, huge.Electro mechanical system device in, Heavy Weight large for size and the high super highrise building of vertical distribution, general hydraulic hoisting apparatus cannot finishing equipment slinging work, and civil engineering tower crane need be utilized to carry out the vertical transport of equipment.For proterctive equipment, avoid colliding with building structure in equipment vertical transport process, need, when civil engineering structure not yet completes, utilize civil engineering tower crane to carry out equipment vertical transport.
Summary of the invention
The purpose of this utility model is for above-mentioned technical problem, the super highrise building equipment temporary supporting platform providing a kind of structure simple, easy to operate, for when civil engineering structure not yet completes, super highrise building equipment is unloaded in place temporarily, solves the awkward situation that in super highrise building, equipment vertical transport is in place.
The technical solution of the utility model:
For solving the problems of the technologies described above, the utility model provides a kind of super highrise building equipment temporary supporting platform, and this support platform comprises crossbeam, longeron, diagonal brace, supporting leg, bearing, connecting rod and connecting bolt.
Crossbeam and longitudinal beam welding form support frame; Supporting leg is welded on the bottom of support frame; One end of diagonal brace is welded on the sidepiece of supporting leg, and the other end of diagonal brace is welded on the bottom of crossbeam or longeron; Bearing is connected between supporting leg and fabric structure beam; Connecting rod is connected between the crossbeam of adjacent supports framework by connecting bolt.
The i iron that described crossbeam, longeron, diagonal brace, supporting leg, connecting rod select model identical.
Distance between the length of crossbeam and fabric structure beam adapts.
The lower end of described supporting leg is welded with keyset.
Described bearing comprises pillar, be welded on the top board of pillar upper end and be welded on lower rod end, and its B-C post is i iron, and the height of pillar exceeds storey floors surface 400 ~ 600mm.
Top board on described bearing and the keyset on supporting leg are bolted, and the base plate on bearing is welded on the top of fabric structure beam.
The utility model beneficial effect:
The super highrise building equipment temporary supporting platform that the utility model provides, structure is simple, solve Super High equipment when building structure does not complete, super highrise building equipment is unloaded in place temporarily, neither affect civil engineering operation, again can by equipment vertical transport to equipment place layer, easy to operate, ensure whole building construction speed.
Accompanying drawing explanation
Fig. 1 is the utility model structural representation;
Fig. 2 is the utility model bearing partial enlarged drawing;
Fig. 3 is the utility model front view;
Fig. 4 is the utility model left view;
Fig. 5 is the utility model top view.
Wherein:
1, crossbeam; 2, diagonal brace; 3, supporting leg; 4, bearing; 5, connecting rod; 6, connecting bolt; 7, keyset; 8, top board; 9, base plate; 10, pillar; 11, longeron.
Detailed description of the invention
Below in conjunction with specific embodiments and the drawings, the utility model super highrise building equipment temporary supporting platform is described in detail:
Shown in Fig. 1, a kind of super highrise building equipment temporary supporting platform comprises crossbeam 1, longeron 11, diagonal brace 2, supporting leg 3, bearing 4, connecting rod 5 and connecting bolt 6.
Crossbeam 1 and longeron 11 weld and form support frame; Supporting leg 3 is welded on the bottom of support frame; One end of diagonal brace 2 is welded on the sidepiece of supporting leg 3, and the other end of diagonal brace 2 is welded on the bottom of crossbeam 1 or longeron 11; Connecting rod 5 connects the crossbeam 1 on adjacent supports framework, and uses connecting bolt 6 to fix.
Fig. 2 is the partial enlarged drawing of bearing 4 in the utility model, the lower end of supporting leg 3 is welded with keyset 7, bearing 4 is provided with top board 8, base plate 9, pillar 10, top board 8, base plate 9 are welded on the two ends of pillar 10 respectively, top board 8 on bearing 4 is bolted with the keyset 7 on supporting leg 3, base plate 9 on bearing 4 is welded on the top of fabric structure beam, and the height of pillar 10 is higher than storey floors surface 500mm, in place to facilitate equipment to unload.
The i iron that crossbeam 1 shown in Fig. 1 to Fig. 2, longeron 11, diagonal brace 2, supporting leg 3, connecting rod 5, pillar 10 select model identical, to ensure that i iron width is consistent, facilitates welding operation.
When using super highrise building equipment temporary supporting platform to unload equipment in place, first, the length of crossbeam 1 is set according to the distance between fabric structure beam in advance, crossbeam 1 and longeron 11 welding is formed support frame, and supporting leg 3, diagonal brace 2, keyset 7 are welded on relevant position; Then, make bearing 4, and base plate 9 is welded on the top of the structural beams of building; Then, will treat that equipment in place is fixing on the support frame, use civil engineering tower crane vertical transport equipment, by the keyset 7 on supporting leg 3 and top board 8 centering on bearing 4; Finally, bolt is used keyset 7 and top board 8 to be fixed.
In the present embodiment, crossbeam 1, longeron 11, diagonal brace 2, supporting leg 3, connecting rod 5, pillar 10 select model to be the i iron of I16; Fig. 3 is the front view of the present embodiment, and connecting rod 5 connects adjacent supports framework; Fig. 4 is the left view of the present embodiment, and bearing 4 is fixed on fabric structure beam, and the base plate 9 be welded on supporting leg 3 is fixed with the top board 8 on bearing 4; Fig. 5 is the top view of the present embodiment.
The super highrise building equipment temporary supporting platform that the utility model provides, structure is simple, solve Super High equipment when building structure does not complete, super highrise building equipment is unloaded in place temporarily, neither affect civil engineering operation, again can by equipment vertical transport to equipment place layer, easy to operate, ensure whole building construction speed.

Claims (6)

1. a super highrise building equipment temporary supporting platform, for auxiliary civil engineering tower crane vertical transport super highrise building equipment, it is characterized in that, comprise crossbeam (1), longeron (11), diagonal brace (2), supporting leg (3), bearing (4), connecting rod (5) and connecting bolt (6); Crossbeam (1) and longeron (11) welding form support frame; Supporting leg (3) is welded on the bottom of support frame; One end of diagonal brace (2) is welded on the sidepiece of supporting leg (3), and the other end of diagonal brace (2) is welded on the bottom of crossbeam (1) or longeron (11); Bearing (4) is connected between supporting leg (3) and fabric structure beam; Connecting rod (5) is connected between the crossbeam (1) of adjacent supports framework by connecting bolt (6).
2. super highrise building equipment temporary supporting platform according to claim 1, is characterized in that, the i iron that described crossbeam (1), longeron (11), diagonal brace (2), supporting leg (3), connecting rod (5) select model identical.
3. super highrise building equipment temporary supporting platform according to claim 1, is characterized in that, the distance between the length of crossbeam (1) and fabric structure beam adapts.
4. super highrise building equipment temporary supporting platform according to claim 1, is characterized in that, the lower end of described supporting leg (3) is welded with keyset (7).
5. super highrise building equipment temporary supporting platform according to claim 4, it is characterized in that, described bearing (4) comprises pillar (10), is welded on the top board (8) of pillar upper end and is welded on (9) of lower rod end, its B-C post (10) is i iron, and the height of pillar (10) exceeds storey floors surface 400 ~ 600mm.
6. super highrise building equipment temporary supporting platform according to claim 5, it is characterized in that, top board (8) on described bearing (4) is bolted with the keyset (7) on supporting leg (3), and the base plate (9) on bearing (4) is welded on the top of fabric structure beam.
CN201520409931.7U 2015-06-15 2015-06-15 Interim supporting platform of super high -rise building equipment Expired - Fee Related CN204876630U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520409931.7U CN204876630U (en) 2015-06-15 2015-06-15 Interim supporting platform of super high -rise building equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520409931.7U CN204876630U (en) 2015-06-15 2015-06-15 Interim supporting platform of super high -rise building equipment

Publications (1)

Publication Number Publication Date
CN204876630U true CN204876630U (en) 2015-12-16

Family

ID=54821021

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520409931.7U Expired - Fee Related CN204876630U (en) 2015-06-15 2015-06-15 Interim supporting platform of super high -rise building equipment

Country Status (1)

Country Link
CN (1) CN204876630U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288353A (en) * 2017-07-11 2017-10-24 中建局集团安装工程有限公司 Equipment hoisting transition support platform and its construction method on a kind of super-high buildings floor
CN116290766A (en) * 2023-02-15 2023-06-23 中国十九冶集团有限公司 Method for transporting building materials

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288353A (en) * 2017-07-11 2017-10-24 中建局集团安装工程有限公司 Equipment hoisting transition support platform and its construction method on a kind of super-high buildings floor
CN116290766A (en) * 2023-02-15 2023-06-23 中国十九冶集团有限公司 Method for transporting building materials

Similar Documents

Publication Publication Date Title
CN106939707B (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
JP2012180693A (en) Removal method and new construction method for bridge
CN205804190U (en) A kind of travelling bridge for the guardrail construction that builds a bridge
CN205382435U (en) Water delivery box culvert roof template construction equipment
CN103243930A (en) System and method for modularized construction of super high-rise steel structures
CN207362720U (en) A kind of adjustable moulding bed of SPMT modular carts
CN106854941B (en) A kind of construction method of big section Stand Inclined Beams and batter post
CN204876630U (en) Interim supporting platform of super high -rise building equipment
CN203247031U (en) Hoisting device for curtain board transporting
CN103552800A (en) Translation method of large-scale canned equipment
CN203213622U (en) Construction material handling equipment
CN205387943U (en) Tunnel lining trolley
CN206800228U (en) Remove the frame mounting of arch bridge
CN206376561U (en) A kind of cladding glass transporting device
CN205172019U (en) Big shaped steel constructs horizontal migration device
CN204897102U (en) Electronic cat ladder of instrument formula
CN103287986A (en) Curtain board transport lifting device and method for mounting curtain board by using device
CN210195198U (en) Elevartor shaft moving platform
CN107237515A (en) The support meanss and its application method of circular steel truss structure
CN103216092A (en) Method and device of loading and unloading construction materials
CN203213090U (en) Transferring and hoisting device for ship reception chamber of ship lift
CN103669219B (en) Many limbs height pier is with sliding construction equipment
CN203701878U (en) Split-type bearing connection mechanism for vertical columns of platform screen door
CN204038986U (en) For removing the fork truck of inner support steel pipe
CN208617174U (en) A kind of building hoist base support formula bracing means

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151216

Termination date: 20160615

CF01 Termination of patent right due to non-payment of annual fee