CN203213622U - Construction material handling equipment - Google Patents

Construction material handling equipment Download PDF

Info

Publication number
CN203213622U
CN203213622U CN 201320213973 CN201320213973U CN203213622U CN 203213622 U CN203213622 U CN 203213622U CN 201320213973 CN201320213973 CN 201320213973 CN 201320213973 U CN201320213973 U CN 201320213973U CN 203213622 U CN203213622 U CN 203213622U
Authority
CN
China
Prior art keywords
construction material
construction
material platform
platform
dolly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320213973
Other languages
Chinese (zh)
Inventor
苏亚武
王四久
刘勇
蔡庆军
韩寿松
陈卫国
黄高琦
陆会景
马驰
诸葛仲彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN 201320213973 priority Critical patent/CN203213622U/en
Application granted granted Critical
Publication of CN203213622U publication Critical patent/CN203213622U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses construction material handling equipment. A handling method includes steps of loading the construction materials into a construction material trolley; pushing the construction material trolley to a construction material platform to be fixed onto the same; lifting the construction material platform to a target floor and fixing one end of the construction material platform on the floor; pulling the construction material trolley to a floor slab of the floor; pushing the construction material trolley to the construction material platform to be fixed onto the same; lifting the construction material platform to the ground by the aid of a tower crane. The handling method uses the construction material platform and the construction material trolley as construction equipment. By the technical scheme, handling positions of construction materials can be adjusted at any time according to different distributions of the construction materials and requirements of other professional construction operation surfaces, and the construction material handling equipment is completely unaffected by the various professional construction operation surfaces.

Description

The construction material handling equipment
Technical field
The utility model relates to a kind of construction implement, especially a kind of handling facilities of the material of constructing.
Background technology
Traditional fixed construction material platform, the material platform of will constructing are encorbelmented and are fixed in construction floor edge, utilize crane gear such as the tower crane material of will construct to be promoted in the construction material platform, and the back utilizes and manually is transported in the floor of constructing.Because in high building structure construction, particularly in the super-high building structure construction, all kinds of pipe lengths are long, quantity is many, Heavy Weight, have a very wide distribution.The material transhipment if the traditional fixed construction material platform of employing is constructed, construction material platform need repeatedly be installed, dismantle, the construction material cycling often, waste time and energy, and it is longer that fixed construction material platform takies the floor scope of operation time, influences its construction speed thereby may take other professional construction scope of operations.
The utility model content
The technical problems to be solved in the utility model provides a kind of construction material handling equipment, it can be along with the distributing position difference of construction material is adjusted discharge position at any time, can not influenced by each professional construction scope of operation along with other professional construction scope of operations require to change discharge position at any time yet.
In order to achieve the above object, major technique means of the present utility model are: a kind of construction material handling equipment is provided, and this equipment comprises: a construction material platform, and described construction material platform is provided with first track and Heave Here; One construction material dolly, described construction material dolly is arranged on first track of described construction material platform.
The utility model further improves and is: described equipment also includes a movable extension, and described movable extension is provided with second track that cooperates described first track.
The utility model further improves and is: described construction material platform is provided with a plurality of Heave Heres, be provided with construction material platform around the described construction material platform and go along with sb. to guard him face, be provided with a construction material platform at the described construction material platform face of going along with sb. to guard him near the one side of building and go along with sb. to guard him door.
The utility model further improves and is: described construction material dolly bottom is provided with the wheel that cooperates with described first track and second track, is provided with construction material dolly in the both sides of described construction material dolly and goes along with sb. to guard him face.
The utility model further improves and is: described construction material dolly is provided with towing pad, and described construction material dolly is along described first track and second orbital motion during traction.
The utility model is owing to adopted technique scheme, make the loading and unloading of construction material to adjust discharge position at any time along with the distributing position difference of construction material, can not influenced by each professional construction scope of operation along with other professional construction scope of operations require to change discharge position at any time yet.
Description of drawings
Fig. 1 is the general illustration of the utility model construction material handling platform
Fig. 2 is the elevation of the utility model construction material platform
Fig. 3 is the lateral view of the utility model construction material platform
Fig. 4 is the opposite side view of the utility model construction material platform
Fig. 5 is the vertical view of the movable extension of the utility model construction material platform
Fig. 6 is the lateral view of the utility model construction material dolly
Fig. 7 is the utility model construction material dolly and construction material platform joint portion partial enlarged drawing
Fig. 8 works the process that winches to destination for the utility model material platform of will constructing
Fig. 9 draws process to destination for the utility model material dolly of will constructing
Figure 10 is pushed into the process of construction material platform for the utility model material dolly of will constructing
Figure 11 works the process that winches to order ground for the utility model material platform of will constructing
The specific embodiment
The utility model is described in further detail below in conjunction with the drawings and specific embodiments.
As shown in Figure 1, construction material handling apparatus of the present utility model mainly comprises construction material platform 10 and construction material dolly 20.
As shown in Figure 2, the bottom of construction material platform 10 is construction material platform stress frames 11 of being made by the i iron welding.Construction material platform stress frame 11 is provided with the parallel rail beam of twice 12, and rail beam 12 is made by i iron, is welded on the construction material platform stressed 11.Be welded with by reinforcing bar at rail beam 12 and make first track 13.At the construction material platform operations face 14 that construction material platform stress frame 11 is laid and welding is made by steel plate.Omitted the face of going along with sb. to guard him 18 of construction material platform 10 among Fig. 2.
As shown in Figure 3, construction material platform stress frame 11 both sides are welded with a plurality of hangers 15, wherein the hanger 15 near building is used for construction material platform is fixed on the destination layer floor, is distributed in construction material platform hanger 15 all around as the Heave Here of construction material platforms.In rail beam 12 fixed dam 16 of end welding away from building, the movement of this baffle plate and sideboard 17 engagement limits dollies in the lifting process of construction material platform 10.
As shown in Figure 4, around construction material platform 10, be welded with construction material platform and go along with sb. to guard him face 18.Be provided with a construction material platform in the side of material platform maintenance panel near building of constructing and go along with sb. to guard him door 19.
As shown in Figure 5, the bottom of movable extension 101 is the extensions of being made by i iron, is welded with the track of being made by reinforcing bar 102 above movable extension 101.
As Fig. 6 and shown in, the bottom of construction material dolly 20 is dolly stress frames 21 of being made by steel work, respectively is welded with 3 wheels 22 in the both sides of dolly stress frame 21, is provided with towing pad 23 at an end of dolly stress frame 21.Be welded with construction material dolly in construction material dolly 20 both sides and go along with sb. to guard him face 24.
As shown in Figure 7, construction material dolly 20 is erected on first track 13 of construction material platform 10 by wheel 22.Traction construction material dolly 20, construction material dolly 20 will slide along first track 13.
Utilize said apparatus to realize that the method for the loading and unloading of construction material comprises:
The material of will constructing is installed in a construction material dolly 20, and binding is fixing.
The material dolly 20 of will constructing is placed postive stop baffle in material dolly 20 front and back after being pushed into construction material platform 10, and construction material dolly is fixed in the process of lifting on first track 13 of construction material platform 10.
Lifting construction material platform 10 is to destination layer floor next door as shown in Figure 8, is fixed on the edge of destination layer floor by will construct two Heave Heres 15 of material platform 10 close buildings of wire rope then.After fixing construction material platform 10, movable extension 19 is connected to construction material platform 10, first track 13 on the construction material platform 10 and second track 192 on the movable extension 19 are combined together the orbit as construction material dolly 20, and the material dolly 20 of will constructing as shown in Figure 9 then is drawn on the movable extension 19 that is positioned on the destination layer floor from construction material platform 10.
After construction material on the construction material dolly 20 was unloaded to the destination layer floor, the material dolly of will construct as shown in figure 10 pushed back to construction material platform 10, and then the front and back placement postive stop baffle of construction material dolly.
Movable extension 19 is separated with construction material platform 10, and the material platform 10 of will constructing then separates with the destination layer floor, will construct 10 liftings of material platform to ground with tower crane as shown in figure 11 at last.
Below the utility model of embodiment has been described in detail by reference to the accompanying drawings, and those skilled in the art can make the many variations example to the present invention according to the above description.Thereby some details among the embodiment should not constitute limitation of the invention, and the scope that the utility model will define with appended claims is as protection domain of the present utility model.

Claims (5)

1. construction material handling equipment is characterized in that described equipment comprises: a construction material platform, and described construction material platform is provided with first track and Heave Here; One construction material dolly, described construction material dolly is arranged on first track of described construction material platform.
2. construction material handling equipment as claimed in claim 1 is characterized in that described equipment also includes a movable extension, and described movable extension is provided with second track that cooperates described first track.
3. construction material handling equipment as claimed in claim 1, it is characterized in that described construction material platform is provided with a plurality of Heave Heres, be provided with construction material platform around the described construction material platform and go along with sb. to guard him face, be provided with a construction material platform at the described construction material platform face of going along with sb. to guard him near the one side of building and go along with sb. to guard him door.
4. construction material handling equipment as claimed in claim 1 is characterized in that described construction material dolly bottom is provided with the wheel that cooperates with described first track and second track, is provided with construction material dolly in the both sides of described construction material dolly and goes along with sb. to guard him face.
5. construction material handling equipment as claimed in claim 1 is characterized in that described construction material dolly is provided with towing pad, and described construction material dolly is along described first track and second orbital motion during traction.
CN 201320213973 2013-04-25 2013-04-25 Construction material handling equipment Expired - Fee Related CN203213622U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320213973 CN203213622U (en) 2013-04-25 2013-04-25 Construction material handling equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320213973 CN203213622U (en) 2013-04-25 2013-04-25 Construction material handling equipment

Publications (1)

Publication Number Publication Date
CN203213622U true CN203213622U (en) 2013-09-25

Family

ID=49203170

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320213973 Expired - Fee Related CN203213622U (en) 2013-04-25 2013-04-25 Construction material handling equipment

Country Status (1)

Country Link
CN (1) CN203213622U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103216092A (en) * 2013-04-25 2013-07-24 中国建筑第八工程局有限公司 Method and device of loading and unloading construction materials
CN105672675A (en) * 2016-03-28 2016-06-15 中国建筑第二工程局有限公司 Size-adjustable material lifting device and construction method thereof
CN106320716A (en) * 2015-07-01 2017-01-11 上海宝冶集团有限公司 Adjustable sectionalized discharging platform for high-rise building construction
CN111392600A (en) * 2020-04-03 2020-07-10 中国一冶集团有限公司 Novel steel structure carrying device and carrying method
CN114380185A (en) * 2021-12-13 2022-04-22 中建八局浙江建设有限公司 Construction hanging basket system with built-in truck and hoisting construction method thereof
CN114380185B (en) * 2021-12-13 2024-07-19 中建八局浙江建设有限公司 Construction hanging basket system of built-in truck and hoisting construction method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103216092A (en) * 2013-04-25 2013-07-24 中国建筑第八工程局有限公司 Method and device of loading and unloading construction materials
CN103216092B (en) * 2013-04-25 2016-01-20 中国建筑第八工程局有限公司 Construction material handling method and equipment thereof
CN106320716A (en) * 2015-07-01 2017-01-11 上海宝冶集团有限公司 Adjustable sectionalized discharging platform for high-rise building construction
CN105672675A (en) * 2016-03-28 2016-06-15 中国建筑第二工程局有限公司 Size-adjustable material lifting device and construction method thereof
CN111392600A (en) * 2020-04-03 2020-07-10 中国一冶集团有限公司 Novel steel structure carrying device and carrying method
CN114380185A (en) * 2021-12-13 2022-04-22 中建八局浙江建设有限公司 Construction hanging basket system with built-in truck and hoisting construction method thereof
CN114380185B (en) * 2021-12-13 2024-07-19 中建八局浙江建设有限公司 Construction hanging basket system of built-in truck and hoisting construction method thereof

Similar Documents

Publication Publication Date Title
CN203213622U (en) Construction material handling equipment
CN203269274U (en) Slope section rail type conveying device
CN203834373U (en) Lifting movement mold carriage trolley for box culvert side wall formwork
CN203247031U (en) Hoisting device for curtain board transporting
CN103216092B (en) Construction material handling method and equipment thereof
CN202483180U (en) Movable building material loading and unloading platform
CN202645022U (en) Drawer type building receiving platform
CN206554524U (en) A kind of construction discharging platform
CN102661033B (en) Drawer type building receiving platform
CN204282843U (en) The sliding hoisted in position device of steel girder erection in a kind of stiffness combination construction
CN204585194U (en) A kind of floor discharge rack
DE112014000114B4 (en) Adjustable false floor of a large double-decker conveyor basket and adjustment and movement of the same
CN203581022U (en) GIS (geographic information system) equipment conveying device
CN110282579A (en) The Lift-on/Lift-off System and hanging method of prefabricated pipe trench in height-limited small space
CN207063484U (en) Movable operating platform for corridor construction
CN103206076A (en) Movable building loading and unloading platform and moving method
CN103287986A (en) Curtain board transport lifting device and method for mounting curtain board by using device
CN206940278U (en) A kind of O shapes gantry handling apparatus
CN105731268A (en) Cargo transportation, hoisting and transferring device
CN104294763A (en) Steel bar mesh transfer device for movable formwork
CN205474639U (en) A rail travelling bogie that is used for bridge floor railway to lay rail welding rail production line
CN103498418B (en) Device for shifting hanging basket assembly pieces and construction method
CN204098493U (en) The dismantled and assembled input and output material movable platform of a kind of modular for building
CN204139067U (en) A kind of mobile formwork reinforced mesh transporter
CN203625731U (en) Ballastless track line center distance unequal-width section track board movement in-position device in tunnel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130925

Termination date: 20190425

CF01 Termination of patent right due to non-payment of annual fee