CN204875393U - III type track boards of CRTS fill grouting collection device - Google Patents

III type track boards of CRTS fill grouting collection device Download PDF

Info

Publication number
CN204875393U
CN204875393U CN201520606940.5U CN201520606940U CN204875393U CN 204875393 U CN204875393 U CN 204875393U CN 201520606940 U CN201520606940 U CN 201520606940U CN 204875393 U CN204875393 U CN 204875393U
Authority
CN
China
Prior art keywords
track plates
track
concrete
bed plate
track board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520606940.5U
Other languages
Chinese (zh)
Inventor
范茂才
杨俊�
刘跃
曹建凯
董逢春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of CTCE Group
Original Assignee
First Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of CTCE Group filed Critical First Engineering Co Ltd of CTCE Group
Priority to CN201520606940.5U priority Critical patent/CN204875393U/en
Application granted granted Critical
Publication of CN204875393U publication Critical patent/CN204875393U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a III type track boards of CRTS fill grouting collection device, including the bed plate, the bed plate top is equipped with the track board, is equipped with the concrete between bed plate and the track board and fills space, its characterized in that: it has left and right observation hole to open on the track board, is equipped with the straight tube in the left and right observation hole respectively soon, all overlaps on the straight tube and is equipped with the three -way pipe, and the side pipe mouth below of three -way pipe is equipped with the basin that gathers materials. The utility model discloses a track board self -compaction concrete fills grouting collection device makes the closely knit degree of track board concrete and come -up volume obtain effectual control, and area is little, simple structure, and it is convenient, with low costs that the clearance is dismantled in the installation for on -the -spot civilization construction is protected, and later stage track board track self -compaction concrete fills the quality and obtains control like this, makes the completion that the construction is swift, guarantee the quality.

Description

The perfusion of a kind of CRTS III type track plates is overflow and is starched gathering-device
Technical field
The utility model relates to self-compacting concrete perfusion equipment technical field, is more particularly a kind of track plates self-compacting concrete perfusion excessive slurry gathering-device.
Background technology
At present in China, CRTSIII plate-type non-fragment orbit be China in conjunction with existing non-fragment orbit technology, by original innovation, integrated innovation with assimilate advanced foreign technologies and further refine them, the up-to-date track system of proposition, has complete independent intellectual property right.So we will greatly develop scientific and technical innovation engineering method at construction link, improve CRTS III type track plates pouring quality and efficiency.
Along with the fast development that China Railway High-speed (Line for Passenger Transportation, inter-city passenger rail) is built, the plate-type ballastless track complete set technology that research and development have independent intellectual property right has become the task of top priority embodying China's high ferro technical level, show national strength, and Ye Shi China high ferro technology is gone abroad necessary.The Ministry of Railways in 2009 in Chengdu to Dujiang weir intercity railways special line, carried out the plate-type ballastless track complete set technology engineering experiment and design innovation work with perfect knowledge property right, and achieved successfully, be formally fixed to CRTS III type track plates in December, 2010.Its test result is intercity in Hubei, Panjin is applied and practice to Yingkou and Shenyang to Dandong passenger dedicated railway line.
CRTS III plate-type non-fragment orbit General structure scheme is the Novel unit platy ballastless track structure of shouldered, primarily of part compositions such as the self-compacting concrete of rail, fastener, precast track plate, arrangement of reinforcement, limited impression, intermediate isolating layer (geotextiles) and reinforced concrete footings.
Track structure adopts unit fraction block structure, at roadbed, all adopts unconnected sectional type block construction between bridge and location, tunnel track plates.Bed plate arranges two limiting block platforms (groove structure) within the scope of every block track plates, and bed plate and self-leveling concrete interlayer arrange intermediate isolating layer.Fastener adopts WJ-8C type fastener.
At present, in non-fragment orbit high-speed railway construction, in self-compacting concrete pouring construction there is following problem in concrete compaction and floating: not adopting an effective measure in 1, traditional self-compacting concrete pouring construction remains that filling concrete has certain height and pressure: otherwise influx height is little, pressure is inadequate, causes plate chamber leakiness; Influx height is large, and pressure is large, track plates floats and exceeds standard 2, traditional self-compacting concrete pouring construction time by manual control influx height, workman's workload is large, and manual operation uncertain factor increases, and takes a lot of work, time-consuming, accurately cannot control, inefficiency, easily occur pouring quality defect.The concrete cleaning difficulty of overflowing during 3, traditional self-compacting concrete pouring construction, pollutes track plates, can not accomplish effective civilized construction.
Utility model content
The purpose of this utility model is the requirement in order to the accuracy and on-the-spot civilized construction improving the control of self-compacting concrete influx height, provides a kind of track plates self-compacting concrete to pour into excessive slurry gathering-device.
The purpose of this utility model is achieved through the following technical solutions:
The perfusion of a kind of CRTS III type track plates is overflow and is starched gathering-device, include bed plate, track plates is provided with above bed plate, filling concrete space is provided with between bed plate and track plates, it is characterized in that: track plates has left and right peep hole, be installed with straight tube respectively in left and right peep hole, straight tube is all set with tee piece, below the side pipe mouth of tee piece, be provided with the basin that gathers materials.
The perfusion of a kind of CRTS III type track plates is overflow and is starched gathering-device, and it is characterized in that: the annular outer wall of described straight tube is provided with external screw thread, straight tube outer wall is provided with scale.
The perfusion of a kind of CRTS III type track plates is overflow and is starched gathering-device, it is characterized in that: the basin that gathers materials is placed on track plates.
During self-compacting concrete perfusion, require that concrete will keep certain height in filling process, can not greatly can not be little, highly large easily cause track plates float-amount supergage, defective; Highly little track plate cavity pressure is little, and self-compaction perfusion leakiness, causes quality accident.
The utility model is after self-compacting concrete is filled into certain altitude for this reason, is discharged by unnecessary concrete, can ensure certain injection pressure, also can ensure that float-amount does not exceed standard.
When unnecessary concrete is discharged by observing, can pollute track plates, cleaning difficulty, can not meet on-the-spot civilized construction, therefore arrange a concrete gathering-device.
The utility model respectively arranges the threeway pvc pipe of 1 Φ 160mm at 2 peep holes of CRTSIII track plates, by taking off plate test, we show that filling concrete height is 15 ~ 20mm, namely require that track plates is 15 ~ 20mmmm to the wide open height of threeway, we adopt screw thread to connect at the threeway mouth of pipe, length scale is had to show above, can free adjustment.
Arrange the basin that gathers materials at threeway mouth of pipe place, requirement can hold certain amount of concrete, adopts diameter 50cm by testing us, the white rust steel basin of degree of depth 10cm.
The utility model has the advantage of:
The utility model can keep filling concrete height effectively accurately, keeps track plate cavity to have constant pressure; Gathering-device effectively can ensure that concrete does not pollute plate face, and concrete is easily cleared up, and ensures the requirement of on-the-spot civilized construction; Floor space is little, and structure is simple, and installing/dismounting cleaning is convenient, and cost is low; The self-compacting concrete pouring quality of such later stage track plates is effectively controlled, and makes quick construction, completing of guaranteeing the quality.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
The perfusion of a kind of CRTS III type track plates is overflow and is starched gathering-device, include bed plate 1, track plates 2 is provided with above bed plate 1, filling concrete space 3 is provided with between bed plate 1 and track plates 2, track plates 2 has left and right peep hole 4, be installed with straight tube 5 respectively in left and right peep hole 4, straight tube 5 is all set with tee piece 6, below the side pipe mouth of tee piece 6, be provided with the basin 7 that gathers materials.
The annular outer wall of straight tube is provided with external screw thread, and straight tube 5 outer wall is provided with scale.
The basin that gathers materials is put 7 and is put on track plates.

Claims (3)

1. a CRTS III type track plates perfusion is overflow and is starched gathering-device, include bed plate, track plates is provided with above bed plate, filling concrete space is provided with between bed plate and track plates, it is characterized in that: track plates has left and right peep hole, be installed with straight tube respectively in left and right peep hole, straight tube is all set with tee piece, below the side pipe mouth of tee piece, be provided with the basin that gathers materials.
2. a kind of CRTS III type track plates perfusion according to claim 1 is overflow and is starched gathering-device, and it is characterized in that: the annular outer wall of described straight tube is provided with external screw thread, straight tube outer wall is provided with scale.
3. a kind of CRTS III type track plates perfusion according to claim 1 is overflow and is starched gathering-device, it is characterized in that: the basin that gathers materials is placed on track plates.
CN201520606940.5U 2015-08-13 2015-08-13 III type track boards of CRTS fill grouting collection device Expired - Fee Related CN204875393U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520606940.5U CN204875393U (en) 2015-08-13 2015-08-13 III type track boards of CRTS fill grouting collection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520606940.5U CN204875393U (en) 2015-08-13 2015-08-13 III type track boards of CRTS fill grouting collection device

Publications (1)

Publication Number Publication Date
CN204875393U true CN204875393U (en) 2015-12-16

Family

ID=54819787

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520606940.5U Expired - Fee Related CN204875393U (en) 2015-08-13 2015-08-13 III type track boards of CRTS fill grouting collection device

Country Status (1)

Country Link
CN (1) CN204875393U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112359655A (en) * 2020-09-27 2021-02-12 北京鸿锐嘉科技发展有限公司 Ballastless track self-compacting concrete pouring intelligent management system and pouring method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112359655A (en) * 2020-09-27 2021-02-12 北京鸿锐嘉科技发展有限公司 Ballastless track self-compacting concrete pouring intelligent management system and pouring method

Similar Documents

Publication Publication Date Title
CN104131498B (en) A kind of for curved section sedimentation non-fragment orbit lifting restorative procedure
CN104400898B (en) The vertical integrally forming mould in precast concrete section of jurisdiction and forming method
CN113802424B (en) Sedimentation bag type grouting lifting repair method for ballastless track of high-speed railway
CN210507142U (en) Positioning adjustment device for concrete assembled bridge pier
CN104153259A (en) Rapid repairing method for sunken ballastless track through grouting lifting
CN104404844A (en) Method for repairing and reinforcing open joint of filling layer of slab ballastless track
CN110439286A (en) A kind of liner is put more energy into joint steel pipe concrete column drag reduction jack-up construction method of weakening
CN102286988A (en) Grouting shim plate construction method
CN110424194B (en) Prefabricated ballast bed structure of vibration isolator on bridge and construction method thereof
CN105133487A (en) Combined type bridge temporary support and construction method for rapidly building continuous beams by virtue of same
CN101994292A (en) Rapid construction of high bridge pier by efficient combination
CN104060590B (en) The reinforcement leakage preventing structure of a kind of pressure diversion tunnel and construction method thereof
CN107191006B (en) Dismantling and repairing method for refractory concrete layer of diversion trench
CN204282140U (en) A kind of self-compacting concrete perfusion gate-type crimping device
CN106087671A (en) A kind of concreting template
CN204875393U (en) III type track boards of CRTS fill grouting collection device
CN117758549A (en) Construction process of ballastless track of urban railway
CN202090619U (en) Combination reinforcing structure of building roofing concrete beam
CN204401377U (en) Adjustable ballastless track self-compacting concrete perfusion gang form
CN204023527U (en) A kind of reinforcement leakage preventing structure of pressure diversion tunnel
CN104453235B (en) Current conversion station fire wall construction technology
CN102352581B (en) Wide joint device for slab ballastless track
CN202247539U (en) Wide seaming device of plate-type ballastless track
CN204530345U (en) A kind of track plates self-compacting concrete pours into anti-sideslip hold down gag
CN115256615A (en) Intelligent shower maintenance standard construction system for prefabricated box girder of expressway

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151216

Termination date: 20200813