CN204781274U - Tunnel portal faces upward on limit sloping catch water drain structure - Google Patents

Tunnel portal faces upward on limit sloping catch water drain structure Download PDF

Info

Publication number
CN204781274U
CN204781274U CN201520342527.2U CN201520342527U CN204781274U CN 204781274 U CN204781274 U CN 204781274U CN 201520342527 U CN201520342527 U CN 201520342527U CN 204781274 U CN204781274 U CN 204781274U
Authority
CN
China
Prior art keywords
catchwater
rock
limit
tunnel
face
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520342527.2U
Other languages
Chinese (zh)
Inventor
尤鸿波
邹金杰
胡建华
江湛瑛
童育聪
顾鑫杰
叶卡尔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201520342527.2U priority Critical patent/CN204781274U/en
Application granted granted Critical
Publication of CN204781274U publication Critical patent/CN204781274U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Revetment (AREA)

Abstract

The utility model relates to a tunnel portal faces upward on limit sloping catch water drain structure. The utility model aims at providing a tunnel portal faces upward on limit sloping catch water drain structure to phase reaches reduces construction cost, improvement efficiency of construction, simple and convenient safe mesh. The utility model provides a: tunnel portal faces upward on limit sloping catch water drain structure is applied to hard rock condition, tunnel mouth limit, faces upward sloping opening line and has basement rock face, its characterized in that outward: on the limit, face upward sloping opening line outside 3 -5m department carry out plain noodles rock mass chisel hair to the basement rock face or broken rock mass chisel removes, arrange in the basement rock face that mortar stock and one end expose to exerted mortar stock founds mould concreting catch water drain ditch body for the joint bar. The utility model is suitable for an it is waterproof that the side slope is the earth's surface of hard rock, belongs to highway drainage technology field.

Description

A kind of upward slope at exit of tunnel catchwater structure
Technical field
The utility model relates to a kind of tunnel portal limit, faces upward slope catchwater structure, is applicable to the earth's surface waterproof that side slope is hard rock, belongs to highway drainage technical field.
Background technology
Washing away hole and limit, hole for preventing surface water, facing upward the water on slope and flow into tunnel, generally at upward slope at exit of tunnel aperture lines 3 ~ 5m with peripheral hardware catchwater, outside underground water ejectment to hole scope.Current catchwater section generally adopts rectangular cross section or trapezoidal cross-section, and ditch stature material adopts mortar flag stone, needs adopt machinery or manually excavate groove body before catchwater construction.
For soil condition limit, face upward slope catchwater, construction technology is ripe, but builds position general vehicle by laying bricks or stones because of catchwater and cannot arrive, and needs a dead lift stone, has that construction cost is large, speed of application slow, potential safety hazard distinct issues; For hard rock condition limit, face upward slope catchwater, except having except Similar Problems with soil condition, also there are the following problems: catchwater headroom is less, generally once excavate shaping, need according to on-the-spot rock behavio(u)r design blasting parameter, carry out loosening blasting, and after explosion completes, adopt pneumatic pick to repair catchwater side slope, time-consuming, effort.
Summary of the invention
The technical problems to be solved in the utility model is: for solving the problem, and provides a kind of upward slope at exit of tunnel catchwater structure, the object reduce construction cost to reaching, improving efficiency of construction, handy and safe.
The technical scheme that the utility model adopts is: upward slope at exit of tunnel catchwater structure, be applied to hard rock condition, tunnel mouth limit, face upward outside the aperture lines of slope there is bedrock surface, it is characterized in that: on limit, face upward slope aperture lines outer 3-5m place and light face rock mass dabbing is carried out to bedrock surface or fragmented rock body cuts, arrange grouting rock bolt in bedrock surface and one expose, with the grouting rock bolt exposed for joint bar formwork erection concreting catchwater ditch body.
Described grouting rock bolt is C22 grouting rock bolt, and longitudinal arrangement pitch 1m, long 2m, enter rock 1m, and expose 1m and pour into C20 concrete catchwater ditch body, anchor pole tilt angled down is 10-20 °.
Described concrete catchwater ditch is as trapezoidal transverse face, and ditch body top width is 20cm, and inside furrow bank, ratio of slope is 1:0.3, is vertical plane outside furrow bank.
The beneficial effects of the utility model are: the utility model is carrying out the rear directly concreting of cleaning as catchwater to bedrock surface, and the grouting rock bolt by bedrock surface is arranged, by catchwater and the domatic compact siro spinning technology of basement rock.The utility model, under hard rock condition, need not carry out Blasting Excavation to catchwater groove, and is suitable for rough landform, can accelerating construction progress, reduces construction cost and difficulty of construction.
Accompanying drawing explanation
Fig. 1 is sectional view of the present utility model.
Detailed description of the invention
As shown in Figure 1, the present embodiment is applied to hard rock condition, tunnel mouth limit, faces upward outside slope aperture lines 4 and has bedrock surface 3, on limit, faces upward the outer 3-5m place of slope aperture lines 4 and carries out light face rock mass dabbing to bedrock surface 3 or fragmented rock body cuts process; Then apply grouting rock bolt 2 as joint bar to bedrock surface 3, anchor pole half inserts bedrock surface 3, and second half exposes, and with the grouting rock bolt exposed for joint bar formwork erection concreting catchwater ditch body 1, makes bedrock surface and concrete catchwater ditch body connect into entirety.
Described grouting rock bolt 2 is C22 grouting rock bolt, and longitudinal arrangement pitch 1m, long 2m, enter rock 1m, and expose 1m and pour into C20 concrete catchwater ditch body 1, anchor pole tilt angled down is 10-20 °.
Described concrete catchwater ditch body 1 is trapezoidal transverse face, and adopt C20 concrete to build, ditch body top width is 20cm, and inside furrow bank, ratio of slope is 1:0.3, is vertical plane outside furrow bank.Bottom of trench width b and ditch height degree h generally adopts 50cm, and reality can adjust according to concrete landform and catchment area.
The construction sequence of the present embodiment is as follows:
(1) on limit, face upward the outer 3 ~ 5m of slope aperture lines and intend applying catchwater position bedrock surface is processed, the rock mass more broken for scar should cut, and the rock mass smooth for scar should carry out dabbing;
(2) C22 grouting rock bolt is applied as joint bar;
(3) build C20 concrete and form catchwater.

Claims (3)

1. a upward slope at exit of tunnel catchwater structure, be applied to hard rock condition, tunnel mouth limit, face upward outside slope aperture lines (4) there is bedrock surface (3), it is characterized in that: on limit, face upward slope aperture lines (4) outer 3-5m place and light face rock mass dabbing is carried out to bedrock surface (3) or fragmented rock body cuts, arrange grouting rock bolt (2) in bedrock surface (3) and one expose, with the grouting rock bolt exposed for joint bar formwork erection concreting catchwater ditch body (1).
2. upward slope at exit of tunnel catchwater structure according to claim 1, it is characterized in that: described grouting rock bolt (2) is C22 grouting rock bolt, longitudinal arrangement pitch 1m, long 2m, enter rock 1m, expose 1m and pour into C20 concrete catchwater ditch body (1), anchor pole tilt angled down is 10-20 °.
3. upward slope at exit of tunnel catchwater structure according to claim 1 and 2, it is characterized in that: described concrete catchwater ditch body (1) is trapezoidal transverse face, ditch body top width is 20cm, and inside furrow bank, ratio of slope is 1:0.3, is vertical plane outside furrow bank.
CN201520342527.2U 2015-05-25 2015-05-25 Tunnel portal faces upward on limit sloping catch water drain structure Active CN204781274U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520342527.2U CN204781274U (en) 2015-05-25 2015-05-25 Tunnel portal faces upward on limit sloping catch water drain structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520342527.2U CN204781274U (en) 2015-05-25 2015-05-25 Tunnel portal faces upward on limit sloping catch water drain structure

Publications (1)

Publication Number Publication Date
CN204781274U true CN204781274U (en) 2015-11-18

Family

ID=54521353

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520342527.2U Active CN204781274U (en) 2015-05-25 2015-05-25 Tunnel portal faces upward on limit sloping catch water drain structure

Country Status (1)

Country Link
CN (1) CN204781274U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339838A (en) * 2018-08-15 2019-02-15 福建陆海工程勘察设计有限公司 A kind of reinforcement means of prestressed anchor
CN110777821A (en) * 2019-11-14 2020-02-11 中钢集团马鞍山矿山研究院有限公司 Method for treating water burst disaster of fissures of weathered rock slope

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339838A (en) * 2018-08-15 2019-02-15 福建陆海工程勘察设计有限公司 A kind of reinforcement means of prestressed anchor
CN110777821A (en) * 2019-11-14 2020-02-11 中钢集团马鞍山矿山研究院有限公司 Method for treating water burst disaster of fissures of weathered rock slope
CN110777821B (en) * 2019-11-14 2021-05-25 中钢集团马鞍山矿山研究总院股份有限公司 Method for treating water burst disaster of fissures of weathered rock slope

Similar Documents

Publication Publication Date Title
CN105839643B (en) A kind of tunnel construction method of use pattern foundation pit supporting structure
CN203308470U (en) Cover arch structure suitable for large-section unsymmetrical loading tunnel portal section
CN102061923B (en) Tunnel construction method capable of protecting existing building
CN105421470B (en) Assembled anchor pole arched framework combined type ecological revetment construction method
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN205134331U (en) Foundation ditch excavation bearing structure
CN110043264B (en) Construction method for jacking prefabricated rectangular vertical shaft structural type
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN101769154A (en) Excavation supporting method for tunnel construction
CN102953737B (en) Construction method for inverted arch of VI-level water-enriched surrounding rock tunnel
CN104533446A (en) Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN110700841B (en) Double-side-wall guide pit type excavation method for tunnel excavation
CN102400694A (en) Reinforcement method for combined part of shield tunnel and mining-method tunnel
CN105649653B (en) Circle special cross section Tunneling by mining method structure and its construction method are not waited up and down
CN107725064A (en) Tunnel partition wall structure and the method that tunnel step excavation is realized using middle-wall method
CN104653195B (en) A kind of coombe landforms tunnel portal structure and its construction method
CN102817621B (en) Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions
CN206204972U (en) A kind of prefabricated tubular pile as well-points dewatering
CN104141500A (en) Hardened sand gravel stratum cavern construction method
CN103939115A (en) Semi-subsurface excavation method construction shed tunnel method and structure
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN106120822B (en) A kind of method for protecting support and device that prevent mud stone from coming down
CN204781274U (en) Tunnel portal faces upward on limit sloping catch water drain structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant