CN204679074U - Novel surface observation pier structure - Google Patents
Novel surface observation pier structure Download PDFInfo
- Publication number
- CN204679074U CN204679074U CN201520404770.2U CN201520404770U CN204679074U CN 204679074 U CN204679074 U CN 204679074U CN 201520404770 U CN201520404770 U CN 201520404770U CN 204679074 U CN204679074 U CN 204679074U
- Authority
- CN
- China
- Prior art keywords
- reinforced concrete
- pvc pipe
- dowel steel
- template
- joint bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 28
- 239000004567 concrete Substances 0.000 claims abstract description 11
- 239000011435 rock Substances 0.000 claims abstract description 9
- 230000003014 reinforcing effect Effects 0.000 claims description 9
- 238000000034 method Methods 0.000 abstract description 3
- 238000012544 monitoring process Methods 0.000 abstract description 3
- 230000002787 reinforcement Effects 0.000 abstract description 3
- 238000007493 shaping process Methods 0.000 abstract description 2
- 229910000831 Steel Inorganic materials 0.000 abstract 4
- 239000010959 steel Substances 0.000 abstract 4
- 238000010276 construction Methods 0.000 description 8
- 238000009416 shuttering Methods 0.000 description 4
- 238000005266 casting Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 2
- 230000007423 decrease Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a novel pier structure is surveyed on surface, including setting up the reinforced concrete base on the basement rock, be provided with the round dowel steel around the center of reinforced concrete base, dowel steel one end insert the basement rock after-fixing on reinforced concrete base, the other end has a set of structural reinforcement according to certain interval bundling, has the PVC pipe at the cover of dowel steel outside, has pour the concrete in the PVC pipe, concrete and the intraductal dowel steel of PVC and structural reinforcement form the reinforced concrete pier, have at the top fixed mounting of reinforced concrete pier and force centering base. The utility model discloses a PVC pipe need not to demolish it after the reinforced concrete mound shaping as the template of reinforced concrete mound, consequently has removed the process of founding the template from, tearing open the template, has saved man-hour, can popularize and apply in the deformation monitoring field of high steep side slope.
Description
Technical field
The utility model relates to a kind of novel surface observation pier structure, belongs to safety monitoring technology field.
Background technology
In order to monitor the deformation of a part, run (safety) situation to grasp it, simply and effectively way arranges surface observation pier to monitor at this position.The method for making of the surface observation pier of current routine is in position ground grading, then makes reinforced concrete plinth, pedestal plugs muscle, and colligation observation pier structure reinforcing bar, then shuttering, casting concrete, last form removal, the construction of whole surface observation pier is complete.But, limitation is there is in the construction method of above-mentioned routine to Special zone construction, as more difficult or because limiting to the place of inconvenient Construction of Supporting template in construction site in arrived high and steep, personnel, implement relatively loaded down with trivial details and difficult in the operation of these local shutterings, form removal, increase workload, extended time consumption.This novel surface observation pier.
Utility model content
The purpose of this utility model is: provide a kind of novel surface to observe pier structure, not only structure is simple, easy construction, and the operation can removing shuttering, form removal from, saves workload, decreases man-hour, to overcome the deficiencies in the prior art.
The technical solution of the utility model: a kind of novel surface observation pier structure, comprise the reinforced concrete plinth be arranged on basement rock, center around reinforced concrete plinth is provided with a circle joint bar, described joint bar one end is fixed on reinforced concrete plinth after inserting basement rock, the other end has one group of structure reinforcing bars by the binding of certain interval, outside joint bar, cover has pvc pipe, concrete has been built in pvc pipe, joint bar in described concrete and pvc pipe and structure reinforcing bars form reinforced concrete knoll, are installed with forced centering base at the top of reinforced concrete knoll.
The internal diameter of described pvc pipe is φ 200 ~ 300mm.
Owing to adopting technique scheme, the utility model has the advantage of: the utility model adopts pvc pipe as the template of reinforced concrete knoll, without the need to being removed after reinforced concrete knoll is shaping, therefore the operation of shuttering, form removal is eliminated, save man-hour, can be applicable in the deformation monitoring field of high gradient slope.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the vertical view of Fig. 1.
Description of reference numerals: 1-forced centering base, 2-structure reinforcing bars, 3-PVC manages, 4-reinforced concrete plinth, 5-joint bar.
Embodiment
In order to make the utility model object, technical scheme and advantage clearly, below in conjunction with accompanying drawing, the utility model is described in further detail.
The structural representation of a kind of novel surface observation pier structure of the present utility model as shown in Figures 1 and 2, comprise the reinforced concrete plinth 4 be arranged on basement rock, center around reinforced concrete plinth 4 is provided with a circle joint bar 5, described joint bar 5 one end is fixed on reinforced concrete plinth 4 after inserting basement rock, the other end has one group of structure reinforcing bars 2 by the interval binding of 100mm, outside joint bar 5, cover has internal diameter to be the pvc pipe 3 of φ 300mm, concrete has been built in pvc pipe 3, joint bar 5 in described concrete and pvc pipe 3 and structure reinforcing bars 2 form reinforced concrete knoll, forced centering base 1 is installed with at the top of reinforced concrete knoll.
Can carry out according to the following steps during construction: the first step, ground grading, then pouring reinforcement concrete pedestal 4; Second step, squeezes into basement rock by joint bar 5 and by observation pier height binding structure reinforcing bar 2 on joint bar 5; 3rd step, installs pvc pipe 3 and is fixed, as the construction formwork of surface observation pier; 4th step, in pvc pipe, casting concrete is to initial set, forms reinforced concrete knoll; 5th step, installs forced centering base 1 at the top of reinforced concrete knoll, and so far, surface observation pier makes complete.
Claims (2)
1. a novel surface observation pier structure, comprise the reinforced concrete plinth (4) be arranged on basement rock, it is characterized in that: the center around reinforced concrete plinth (4) is provided with a circle joint bar (5), described joint bar (5) one end is fixed on reinforced concrete plinth (4) after inserting basement rock, the other end has one group of structure reinforcing bars (2) by the binding of certain interval, in joint bar (5) outside, cover has pvc pipe (3), concrete has been built in pvc pipe (3), joint bar (5) in described concrete and pvc pipe (3) and structure reinforcing bars (2) form reinforced concrete knoll, forced centering base (1) is installed with at the top of reinforced concrete knoll.
2. novel surface observation pier structure according to claim 1, is characterized in that: the internal diameter of described pvc pipe (3) is φ 200 ~ 300mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520404770.2U CN204679074U (en) | 2015-06-12 | 2015-06-12 | Novel surface observation pier structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520404770.2U CN204679074U (en) | 2015-06-12 | 2015-06-12 | Novel surface observation pier structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204679074U true CN204679074U (en) | 2015-09-30 |
Family
ID=54178759
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520404770.2U Active CN204679074U (en) | 2015-06-12 | 2015-06-12 | Novel surface observation pier structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204679074U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107131862A (en) * | 2017-06-23 | 2017-09-05 | 中国电建集团贵阳勘测设计研究院有限公司 | Rock-fill dam panel deformation monitoring device and construction method |
CN109870150A (en) * | 2019-03-19 | 2019-06-11 | 中国电建集团贵阳勘测设计研究院有限公司 | Open-air surface observation mound structure |
-
2015
- 2015-06-12 CN CN201520404770.2U patent/CN204679074U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107131862A (en) * | 2017-06-23 | 2017-09-05 | 中国电建集团贵阳勘测设计研究院有限公司 | Rock-fill dam panel deformation monitoring device and construction method |
CN109870150A (en) * | 2019-03-19 | 2019-06-11 | 中国电建集团贵阳勘测设计研究院有限公司 | Open-air surface observation mound structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103669655B (en) | Deformation joint both walls body concrete pouring construction process | |
CN104631512A (en) | Post-cast strip beam and slab construction method adopting formwork hanging method | |
CN107989620B (en) | Construction method of three-hole small-spacing tunnel | |
CN204151823U (en) | Along building the one-sided cantilever hydraulic template trolley of side wall under covered back-digging structural slab | |
CN204679074U (en) | Novel surface observation pier structure | |
CN202913697U (en) | Core model of reserved hole | |
CN205063330U (en) | Close clearance double shear wall movement joint template | |
CN202247938U (en) | Wedge-shaped foundation bolt preformed hole core formwork device | |
CN205036077U (en) | Shear force wall formwork support suitable for narrow and small space usage | |
CN203200719U (en) | Hanging type slope pouring template device | |
CN205062818U (en) | Deep basal pit internal branch supporting beam formula is traded and is propped structure | |
CN204590584U (en) | Architectural template structure | |
CN204781931U (en) | Early support system that tears open of plastic formwork | |
CN103410344B (en) | A kind of steel concrete wall beam strengthen device and wall beam Enhancement Method | |
CN103628684B (en) | A kind of construction method of simultaneously watering build floor and shear wall | |
CN202370249U (en) | Cantilever corbel template with prefabricated slab | |
CN206815804U (en) | A kind of new builder's jack girder steel built-in fitting | |
CN205134546U (en) | But quick detachable I -steel built -in fitting of encorbelmenting of cyclic utilization | |
CN203769789U (en) | Shield constructs quick-witted reaction unit that starts in hole | |
CN204899949U (en) | Bow -shaped steel pipe back up support | |
CN204080820U (en) | A kind of concrete structure foundation ditch support replacement device | |
CN102071692A (en) | Construction method for performing bottom plate support replacement on foundation pit by using annular plate | |
CN203684275U (en) | Simple support for cantilever type retaining wall | |
CN204080821U (en) | A kind of steel work foundation ditch support replacement device | |
CN103104099A (en) | Method for constructing wall pulling steel bars in frame column and structure thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |