CN204666135U - Highway subgrade settlement observer - Google Patents

Highway subgrade settlement observer Download PDF

Info

Publication number
CN204666135U
CN204666135U CN201520446094.5U CN201520446094U CN204666135U CN 204666135 U CN204666135 U CN 204666135U CN 201520446094 U CN201520446094 U CN 201520446094U CN 204666135 U CN204666135 U CN 204666135U
Authority
CN
China
Prior art keywords
inspection section
buried bar
projection
strip groove
subgrade settlement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520446094.5U
Other languages
Chinese (zh)
Inventor
葛清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Hydropower Construction Co., Ltd.
Original Assignee
Zhejiang Heyi Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Heyi Construction Co Ltd filed Critical Zhejiang Heyi Construction Co Ltd
Priority to CN201520446094.5U priority Critical patent/CN204666135U/en
Application granted granted Critical
Publication of CN204666135U publication Critical patent/CN204666135U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Repair (AREA)
  • Road Paving Structures (AREA)

Abstract

The utility model discloses a kind of highway subgrade settlement observer, comprise inspection section and pre-buried bar, embedded board is fixedly connected with bottom described pre-buried bar, this pre-buried bar is sheathed in inspection section, this inspection section two bottom sides is provided with base, described inspection section sidewall runs through and is provided with a strip groove, inspection section is provided with scale mark, this scale mark is positioned at outside strip groove, described pre-buried bar top side wall is connected with a projection, this projection stretches out by described strip groove, and the two ends of projection stretch out formation first flange and the second flange.The utility model structure is simple, accurately easyly measures the sedimentation situation of roadbed, and the situation for subgrade settlement is observed very convenient, for road agency takes safeguard measure to provide effective help.

Description

Highway subgrade settlement observer
Technical field
The utility model belongs to field of road construction, particularly relates to a kind of highway subgrade settlement observer.
Background technology
In the modern times of fast pace life, the trip of people was also developed into gradually by former walking is ridden instead of walk by the vehicles, and as automobile, train, aircraft, steamer etc., corresponding highway, railway etc. are that the road of class starts to occur.Former, road is all road, but because road road surface under wet weather or rainy day situation can become very muddy, vehicle body can be made to be foul with mud, affect attractive in appearance during driving.And during long-term rainfall, earth water cut is very large, and wheel is easily absorbed in and causes vehicle normally to travel, and affects traffic.So the highway built in recent years is all lay cement, and such highway, in the engineering of building, needs first to have roadbed and then lay cement, pitch etc. on roadbed, completes the construction of highway.And in long-term use procedure, roadbed usually too much can start to occur depression because load-bearing, result result in the phenomenons such as the cracking on road surface and depression.Vehicle, can because be the out-of-flatness on road surface and make vehicle body in driving conditions jolt not stop when by way of these road surfaces, and bearing circle is held unstable, there is larger potential safety hazard.So need to observe by arranging the sedimentation of highway subgrade settlement observer to roadbed, so that electronic map department Timeliness coverage problem, and take corresponding protection or maintain measure.And the liquid sedimentation instrument usually used in use, measurement result can be caused inaccurate because of there is bubble in liquid, for electronic map department reflects the information of mistake.
Utility model content
For the problems referred to above, the utility model provides a kind of highway subgrade settlement observer measured accurately, be convenient to observation.
To achieve these goals, the utility model is by the following technical solutions: a kind of highway subgrade settlement observer, comprise inspection section and pre-buried bar, embedded board is fixedly connected with bottom described pre-buried bar, this pre-buried bar is sheathed in inspection section, this inspection section two bottom sides is provided with base, described inspection section sidewall runs through and is provided with a strip groove, inspection section is provided with scale mark, this scale mark is positioned at outside strip groove, described pre-buried bar top side wall is connected with a projection, this projection stretches out by described strip groove, the two ends of projection stretch out formation first flange and the second flange.
Further, described base lower surface is set to rough surface, the friction factor between enlarged base lower surface and highway pavement, even make inspection section also can not be subjected to displacement when strong wind, makes the result of detection more accurate.
Further, described embedded board is arranged at intervals with through hole, makes contact area when pre-buried between embedded board and roadbed larger, can not there is relative movement, make testing result more accurate in pre-buried more solid of embedded board in roadbed.
In sum; the utility model has the following advantages: structure is simple; the sedimentation situation reflecting roadbed is carried out by scale; more accurately easy the sedimentation situation of roadbed to be measured; scale is directly arranged at sleeve surface; it is convenient to observe, for road agency takes safeguard measure to provide effective help.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Fig. 2 is side view of the present utility model.
Embodiment
In order to make those skilled in the art person better understand the utility model scheme, below in conjunction with the accompanying drawing in the utility model embodiment, clear, complete description is carried out to the technical scheme in the utility model embodiment.
As shown in Figure 1 and Figure 2, a kind of highway subgrade settlement observer, comprise inspection section 1 and pre-buried bar 2, inspection section 1 is set to the shapes such as cylindrical or rectangle, and top closes, bottom is opening, opening both sides are respectively connected with a strip base 5, and the lower surface of strip base 5 is set to rough surface, the friction factor between enlarged base lower surface and highway pavement, even make inspection section also can not be subjected to displacement when strong wind, make the result of detection more accurate.What run through in the middle part of the sidewall of inspection section 1 is provided with a strip groove 4, and sidewall is also provided with scale mark, and scale mark only can be positioned at the side of strip groove 4, also can have both sides.Be arranged with a pre-buried bar 2 in inspection section 1, the shape of pre-buried bar 2 is identical with the shape of inspection section 1, and its size is less than the size of inspection section 1 slightly.Be connected with a projection 6 in the top side wall of pre-buried bar 2, this projection 6 stretches out from strip groove 4, there is gap between the inside surface of projection and the outside surface of inspection section 1.The both ends that projection 6 stretches out the part of inspection section 1 outside surface stretch out formation first flange 7 and the second flange 8, are greater than the width of strip groove 4 from the width of the first flange 7 to the second flange 8.The bottom of pre-buried bar 2 is fixedly connected with embedded board 3, and on embedded board 3 interval be provided with many exhausting holes, make contact area when pre-buried between embedded board and roadbed larger, pre-buried more solid of embedded board, relative movement can not be there is in roadbed, make testing result more accurate.
In use, first embedded board 3 is filled in roadbed, after highway has been built, inspection section 1 is nested with on pre-buried bar 2, keep projection 6 to stretch out the state of inspection section 1 outside surface, and allow the first flange 7 of projection 6 and the second flange 8 aim at 0 ° of position of scale mark.After highway uses a period of time, again this device is observed, the situation of change of the scale aimed at by the first flange 7 and second flange 8 of projection 6, the sedimentation situation of accurate reflection highway subgrade.
Obviously, described embodiment is only a part of embodiment of the present utility model, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all should belong to the scope of the utility model protection.

Claims (3)

1. a highway subgrade settlement observer, comprise inspection section (1) and pre-buried bar (2), described pre-buried bar (2) bottom is fixedly connected with embedded board (3), this pre-buried bar (2) is sheathed in inspection section (1), this inspection section (1) two bottom sides is provided with base (5), it is characterized in that: described inspection section (1) sidewall runs through and is provided with a strip groove (4), inspection section (1) is provided with scale mark, described scale mark is positioned at strip groove (4) outside, described pre-buried bar (2) top side wall is connected with a projection (6), this projection (6) is stretched out by (4) in described strip groove, the two ends of projection (6) stretch out formation first flange (7) and the second flange (8).
2. highway subgrade settlement observer according to claim 1, is characterized in that: described base (5) lower surface is set to rough surface.
3. highway subgrade settlement observer according to claim 1, is characterized in that: (3) are arranged at intervals with through hole to described embedded board.
CN201520446094.5U 2015-06-26 2015-06-26 Highway subgrade settlement observer Expired - Fee Related CN204666135U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520446094.5U CN204666135U (en) 2015-06-26 2015-06-26 Highway subgrade settlement observer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520446094.5U CN204666135U (en) 2015-06-26 2015-06-26 Highway subgrade settlement observer

Publications (1)

Publication Number Publication Date
CN204666135U true CN204666135U (en) 2015-09-23

Family

ID=54136511

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520446094.5U Expired - Fee Related CN204666135U (en) 2015-06-26 2015-06-26 Highway subgrade settlement observer

Country Status (1)

Country Link
CN (1) CN204666135U (en)

Similar Documents

Publication Publication Date Title
CN103616493B (en) A kind of three-dimensional artificial rainfall reservoir landslide physical experiments equipment
CN203561633U (en) Three-dimensional artificial rainfall reservoir type physical slide model test equipment
CN202433017U (en) Wireless monitoring early-warning system for subgrade settlement of high-speed railway
CN109543149B (en) Safe parking sight distance calculation method for asphalt pavement in rainy days
ATE461419T1 (en) METHOD FOR MEASURING THE THREE-DIMENSIONAL PROFILE OF A SOIL AND DEVICE FOR IMPLEMENTING THE METHOD
CN105527165A (en) Test method and test device for asphalt pavement crack load response relative displacement
CN204666135U (en) Highway subgrade settlement observer
CN103852062B (en) The measurement of the level foot pin of use can be overturned
CN205636837U (en) Highway foundation ditch settlement observation device
CN205580449U (en) Side slope detection ruler of highway subgrade construction
CN204405494U (en) The determinator of porous pavements limit water discharge
CN205295897U (en) Hand propelled bituminous paving rut detector
Uddin Pavement Performance Measures Using Android-Based Smart Phone Application
CN204496646U (en) Freeway tunnel entrance detection prior-warning device icy on road
CN205775703U (en) A kind of drainage pavement pore plugging prior-warning device
CN213090752U (en) Highway bridge subsides detection device
CN208505294U (en) Slope rule for highway engineering
CN207528218U (en) A kind of high-speed railway subgrade settles detection platform
Luo Pavement hydroplaning risk evaluation with inertial measurement unit (IMU) and 1mm 3D texture data
CN204329953U (en) A kind of multi-function settlement plate of highway subgrade settlement observer
CN112525036A (en) Detection device for bridge cracks
CN205138470U (en) Wear monitoring devices who road surface that highway arouses subsides under tunnel
CN205012197U (en) Imitative brick with high water permeability ability
CN209144698U (en) A kind of weather type protrusion graticule
CN210690079U (en) Chessboard type low-temperature environment automobile brake performance detection road

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170324

Address after: Hangzhou City, Zhejiang province 310000 Jianggan District Peng town red cape Road No. 759 Building 2, 1101, 1102, 1103.

Patentee after: Hangzhou Hydropower Construction Co., Ltd.

Address before: 324014 Zhejiang Province, Quzhou City Kecheng District Hang Town Road No. 179 building four Aerospace

Patentee before: ZHEJIANG HEYI CONSTRUCTION CO., LTD.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150923