CN204597354U - Detachable 10 kilovolts of concrete bridge line force-saivng frames - Google Patents

Detachable 10 kilovolts of concrete bridge line force-saivng frames Download PDF

Info

Publication number
CN204597354U
CN204597354U CN201520246439.2U CN201520246439U CN204597354U CN 204597354 U CN204597354 U CN 204597354U CN 201520246439 U CN201520246439 U CN 201520246439U CN 204597354 U CN204597354 U CN 204597354U
Authority
CN
China
Prior art keywords
anchor ear
kilovolts
brace
saivng
detachable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520246439.2U
Other languages
Chinese (zh)
Inventor
杨金成
韩斌
闫学实
张琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Xinjiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Xinjiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Xinjiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201520246439.2U priority Critical patent/CN204597354U/en
Application granted granted Critical
Publication of CN204597354U publication Critical patent/CN204597354U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The application relates to a kind of detachable 10 kilovolts of concrete bridge line force-saivng frames, comprise the upper and lower anchor ear of parallel arrangement, described upper anchor ear both sides level is laid with symmetrical drag link, described lower anchor ear side is equiped with symmetrical brace, being fixedly linked with drag link outer end in the middle part of described brace, being evenly laid with the tie point for being connected with wires-erecting pulley along brace interval.Owing to implementing technique scheme, the application is convenient to carry out Poling Construction to diameter at the wire of 185mm-240mm.Can greatly reduce workman's working strength, reduce muscle power and export, reduce construction risk, improve efficiency of construction.

Description

Detachable 10 kilovolts of concrete bridge line force-saivng frames
Technical field
The application relates to a kind of detachable 10 kilovolts of concrete bridge line force-saivng frames.
Background technology
Tradition 10 kilovolts of straight line concrete bridge lines, after formerly installing and fixing cross-arm, are fixed on cross-arm by wires-erecting pulley by linesman.Then use pull rope to be pulled to below cross-arm by wire, then by workman tiltedly lean out health adopt pure muscle power pickaback mode wire lifted with hands walk around cross-arm one end and put in wires-erecting pulley groove.Because circuit transmission capacity constantly increases, diameter of wire has had 90mm to be progressively promoted to 240mm, and difficulty of construction increases greatly, continue to adopt traditional stringing mode greatly to consume workman's muscle power, easily damage is caused to workman's health, there is security risk, reduce operating efficiency.
Summary of the invention
The object of the application is to propose a kind of detachable 10 kilovolts of concrete bridge line force-saivng frames of being convenient to carry out at the wire of 185mm-240mm diameter Poling Construction.
The object of the application is achieved in that detachable 10 kilovolts of concrete bridge line force-saivng frames, comprise the upper and lower anchor ear of parallel arrangement, described upper anchor ear both sides level is laid with symmetrical drag link, described lower anchor ear side is equiped with symmetrical brace, being fixedly linked with drag link outer end in the middle part of described brace, being evenly laid with the tie point for being connected with wires-erecting pulley along brace interval.
Owing to implementing technique scheme, the application is convenient to carry out Poling Construction to diameter at the wire of 185mm-240mm.Can greatly reduce workman's working strength, reduce muscle power and export, reduce construction risk, improve efficiency of construction.
Accompanying drawing illustrates: the concrete structure of the application is provided by following drawings and Examples:
Fig. 1 is detachable 10 kilovolts of concrete bridge line force-saivng frame structural representations.
Legend: 1, wires-erecting pulley, 2, brace, 3, wind-force tachymeter, 4, drag link, 5, upper anchor ear, 6, lower anchor ear, 7, rope ladder.
Embodiment:
The application by the restriction of following embodiment, can not determine concrete execution mode according to the technical scheme of the application and actual conditions.
Embodiment: as shown in Figure 1, detachable 10 kilovolts of concrete bridge line force-saivng frames comprise the upper and lower anchor ear 5,6 of parallel arrangement, described upper anchor ear 5 both sides level is laid with symmetrical drag link 4, described lower anchor ear 6 side is equiped with symmetrical brace 2, being fixedly linked with drag link 4 outer end in the middle part of described brace 2, being evenly laid with the tie point for being connected with wires-erecting pulley 1 along brace 2 interval.
Described drag link 4 is equiped with the holder for fixing wind-force tachymeter 3.
Live with the same position of lower anchor ear 6 and be connected in described two brace 2 lower ends.
Described lower anchor ear 6 is connected with the rope ladder 7 for climbing.
During use, first the application is fixed on above the cross-arm position of electric pole by upper and lower anchor ear 5,6, then wires-erecting pulley 1 is hung on brace 2, then cross-arm and coaster are installed 1 and fix.Then pull rope is used respectively by the wires-erecting pulley groove that is lowered into by wire again after above some groups of wire pull-ups to cross-arm on cross-arm.
First cross-arm is fixed compared to conventional method, wire directly cannot be pulled to above cross-arm by pull rope, by manpower wire must be lifted with hands and walk around cross-arm-end and just can put in pulley stile, the application is first fixed on above cross-arm position, can easily by above lifting wire to cross-arm, workman slightly adjusts and wire can be transferred in the wires-erecting pulley groove on cross-arm.
Above technical characteristic constitutes the most preferred embodiment of the application, and it has stronger adaptability and best implementation result, can increase and decrease inessential technical characteristic according to actual needs, meet the needs of different situations.

Claims (4)

1. detachable 10 kilovolts of concrete bridge line force-saivng frames, it is characterized in that: the upper and lower anchor ear comprising parallel arrangement, described upper anchor ear both sides level is laid with symmetrical drag link, described lower anchor ear side is equiped with symmetrical brace, being fixedly linked with drag link outer end in the middle part of described brace, being evenly laid with the tie point for being connected with wires-erecting pulley along brace interval.
2. detachable 10 kilovolts of concrete bridge line force-saivng frames as claimed in claim 1, is characterized in that: described drag link is equiped with the holder for fixing wind-force tachymeter.
3. detachable 10 kilovolts of concrete bridge line force-saivng frames as claimed in claim 1, is characterized in that: live with the same position of lower anchor ear and be connected in described two brace lower ends.
4. detachable 10 kilovolts of concrete bridge line force-saivng frames as claimed in claim 1, is characterized in that: described lower anchor ear is connected with the rope ladder for climbing.
CN201520246439.2U 2015-04-22 2015-04-22 Detachable 10 kilovolts of concrete bridge line force-saivng frames Expired - Fee Related CN204597354U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520246439.2U CN204597354U (en) 2015-04-22 2015-04-22 Detachable 10 kilovolts of concrete bridge line force-saivng frames

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520246439.2U CN204597354U (en) 2015-04-22 2015-04-22 Detachable 10 kilovolts of concrete bridge line force-saivng frames

Publications (1)

Publication Number Publication Date
CN204597354U true CN204597354U (en) 2015-08-26

Family

ID=53933468

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520246439.2U Expired - Fee Related CN204597354U (en) 2015-04-22 2015-04-22 Detachable 10 kilovolts of concrete bridge line force-saivng frames

Country Status (1)

Country Link
CN (1) CN204597354U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104779555A (en) * 2015-04-22 2015-07-15 国家电网公司 Detachable effort-saving stand for 10 KV concrete pole wiring

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104779555A (en) * 2015-04-22 2015-07-15 国家电网公司 Detachable effort-saving stand for 10 KV concrete pole wiring

Similar Documents

Publication Publication Date Title
CN203645249U (en) Hook-net-plane-type charged crossing device
CN101582572B (en) Method of extra-high voltage tension stringing
CN205178393U (en) Super high tension transmission line equipotential live working device
CN203352049U (en) Overhead line pulling-up assisting device
CN204597354U (en) Detachable 10 kilovolts of concrete bridge line force-saivng frames
CN106356763A (en) Method for entering equal potential of compact type electric transmission line and used folding ladder
CN103779809B (en) The two oidiospore wire pitch operational method of charged adjustment
CN200987049Y (en) Insulation rope ladder for live-wire process operation of earthing wire and optical fiber composite type aerial extension
CN104779555A (en) Detachable effort-saving stand for 10 KV concrete pole wiring
CN102611057A (en) Crossing mesh
CN207813473U (en) A kind of hard ladder applied to ultra-high-tension power transmission line maintenance
CN203754114U (en) Automatic retracting device for twice-carrying cable of heading machine
CN204538618U (en) A kind of cable clip making cable movement on steel strand wire
CN206442059U (en) A kind of insulated gin
CN204118374U (en) The earth lead point protection device in succession of earth connection
CN204012462U (en) A kind of for setting up the suspender of wire
CN203905791U (en) Insulating ladder
CN203774728U (en) Pre-twisted damping wire
CN208516850U (en) A kind of cement rod-type power transmission line overhead ground wire auxiliary device
CN106115504A (en) A kind of suspender
CN202970094U (en) Guyed tower applied to transmission line project
CN202190023U (en) Wire bracing device for overhead wire
CN204577991U (en) Ropes aid
CN206735691U (en) A kind of handling apparatus for deep basal pit installation reinforcing bar
CN205882554U (en) Work platform on power line pole

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150826