- CN204532717U CN204532717U CN201520177830.1U CN201520177830U CN204532717U CN 204532717 U CN204532717 U CN 204532717U CN 201520177830 U CN201520177830 U CN 201520177830U CN 204532717 U CN204532717 U CN 204532717U
- Authority
- CN
- China
- Prior art keywords
- board
- water guide
- foundation
- foundation ring
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/728—Onshore wind turbines
Landscapes
- Wind Motors (AREA)
Abstract
一种风力发电机组基础环外壁与混凝土缝隙防水装置,包括混凝土地基、防水装置及基础环,防水装置包括固定板、导水板A、导水板B、挡水板、填料及密封材料,混凝土基础顶部设有挡水板且挡水板与混凝土基础之间设有密封材料,挡水板与混凝土基础通过螺栓固定,挡水板位于基础环外壁与混凝土缝隙的外沿,基础环外部套有两个半圆形的固定板,两个固定板通过固定扣固定,通过填充在导水板和挡水板之间的柔性不规则填料阻挡所有的被风携带的雨雪。
Description
技术领域:
本实用新型涉及节能环保设备与设施,具体涉及一种风力发电机组基础环外壁与混凝土缝隙防水装置。
背景技术:
目前,大功率风力发电机组塔筒与风机基础的连接多采用基础环的方式,基础环与钢筋混凝土浇筑成为一体,由于风力发电机组运行过程中,塔筒始终处于振动状态,灌注在基础环外壁与混凝土的密封胶不断被撕裂,失去防水功能,导致雨水进入到混凝土基础中。由于设计的缺陷,塔筒的振动导致基础环与混凝土产生摩擦,缝隙不断扩大并向下扩散,基础环表面的防腐涂料被破坏,失去防腐功能,进入到缝隙中的雨水严重侵蚀基础环及混凝土中的钢筋,对风力发电场的安全生产带来严重的影响,为了解决上述技术问题,特提出一种新的技术方案。
实用新型内容:
本实用新型的目的是为了克服上述现有技术存在的不足,而提供一种风力发电机组基础环外壁与混凝土缝隙防水装置,该装置采用疏和挡的原理,彻底克服了常规的用密封剂封堵的不足。在导水板与挡水板及混凝土基础表面预留足够的空间,避免塔筒振动造成导水板与挡水板及混凝土刚性的接触,破坏防水装置,降低防水效果。在导水板和挡水板之间填充柔性不规则填料,阻止雨水不被风力吹进基础环与混凝土缝隙内。本装置工程造价低,安装方便,可重复拆卸及安装,一次施工永久使用,无需维护,易于大规模推广应用。
本实用新型采用的技术方案为:一种风力发电机组基础环外壁与混凝土缝隙防水装置,包括混凝土地基、防水装置及基础环,防水装置包括固定板、导水板A、导水板B、挡水板、填料及密封材料,混凝土基础顶部设有挡水板且挡水板与混凝土基础之间设有密封材料,挡水板与混凝土基础通过螺栓固定,挡水板位于基础环外壁与混凝土缝隙的外沿,基础环外部套有两个半圆形的固定板,两个固定板通过固定扣固定,固定板与基础环外侧壁之间设有密封材料,固定板与导水板A由角铁卷成且固定板与导水板A之间所成的角度为β,β的角度不少于90度,导水板A与导水板B之间通过焊接固定,导水板A及导水板B与挡水板之间设有填料。
本实用新型的有益效果是:在使用的过程中,当出现雨雪天时,雨水从基础环外壁流下,经导水板流到混凝土基础表面,由于挡水板的作用,雨水被挡在挡水板外,由于在导水板和挡水板之间填充了柔性不规则填料,阻挡所有被风吹进的雨雪,雨雪不会通过导水板A与挡水板的空隙进入到基础环外壁与混凝土的缝隙中。通过以上工作原理可以达到以下效果:1、通过导水板和挡水板可以将所有不受风力影响的雨雪阻挡在挡水板以外。
2、通过填充在导水板和挡水板之间的柔性不规则填料阻挡所有的被风携带的雨雪。
附图说明:
图1是本实用新型结构示意图。
图2是本实用新型局部放大图。
图3是本实用新型固定板俯视图。
具体实施方式:
参照各图,一种风力发电机组基础环外壁与混凝土缝隙防水装置,包括混凝土地基3、防水装置2及基础环1,防水装置2包括固定板5、导水板A9、导水板B10、挡水板7、填料4及密封材料6,混凝土基础3顶部设有挡水板7且挡水板7与混凝土基础3之间设有密封材料4,挡水板7与混凝土基础3通过螺栓固定,挡水板7位于基础环1与混凝土3缝隙的外沿,基础环1外部套有两个半圆形的固定板5,两个固定板5通过固定扣8固定,固定板5与基础环1外侧壁之间设有密封材料6,固定板5与导水板A9由角铁卷成且固定板5与导水板A9之间所成的角度为β,β的角度不少于90度,导水板A9与导水板B10之间通过焊接固定,导水板A9及导水板B10与挡水板7之间设有填料4。在使用的过程中,当出现雨雪时,雨水从基础环1外壁流下,经导水板流到混凝土基础3表面,由于挡水板7的作用,雨水被挡至挡水板7外,由于在导水板和挡水板7之间填充了柔性不规则填料4,阻挡所有被风吹进的雨雪,不会通过导水板A9与挡水板7之间的空隙进入到基础环1与混凝土的缝隙中。通过以上工作原理可以达到以下效果:1、通过导水板和挡水板7可以将所有不受风力影响的雨水阻挡在挡水板7以外。2、通过填充在导水板和挡水板7之间的柔性不规则填料4阻挡所有的被风携带的雨雪。
Claims (1)
1. 一种风力发电机组基础环外壁与混凝土缝隙防水装置,包括混凝土地基(3)、防水装置(2)及基础环(1),其特征在于:防水装置(2)包括固定板(5)、导水板A(9)、导水板B(10)、挡水板(7)、填料(4)及密封材料(6),混凝土基础(3)顶部设有挡水板(7)且挡水板(7)与混凝土基础(3)之间设有密封材料(6),挡水板(7)与混凝土基础(3)通过螺栓固定,挡水板(7)位于基础环外壁(1)与混凝土基础(3)缝隙的外沿,基础环(1)外部套有两个半圆形的固定板(5),两个固定板(5)通过固定扣(8)固定,固定板(5)与基础环(1)外侧壁之间设有密封材料(6),固定板(5)与导水板A(9)由角铁卷成且固定板(5)与导水板A(9)之间所成的角度为β,β的角度不少于90度,导水板A(9)与导水板B(10)之间通过焊接固定,导水板A(9)及导水板B(10)与挡水板(7)之间设有填料(4)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520177830.1U CN204532717U (zh) | 2015-03-27 | 2015-03-27 | 风力发电机组基础环外壁与混凝土缝隙防水装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520177830.1U CN204532717U (zh) | 2015-03-27 | 2015-03-27 | 风力发电机组基础环外壁与混凝土缝隙防水装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204532717U true CN204532717U (zh) | 2015-08-05 |
Family
ID=53746727
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520177830.1U Expired - Fee Related CN204532717U (zh) | 2015-03-27 | 2015-03-27 | 风力发电机组基础环外壁与混凝土缝隙防水装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204532717U (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111779636A (zh) * | 2020-07-13 | 2020-10-16 | 中国能源建设集团湖南火电建设有限公司 | 一种提高风力发电机组基础防水性能的方法 |
-
2015
- 2015-03-27 CN CN201520177830.1U patent/CN204532717U/zh not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111779636A (zh) * | 2020-07-13 | 2020-10-16 | 中国能源建设集团湖南火电建设有限公司 | 一种提高风力发电机组基础防水性能的方法 |
CN111779636B (zh) * | 2020-07-13 | 2023-05-02 | 中国能源建设集团湖南火电建设有限公司 | 一种提高风力发电机组基础防水性能的方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204216820U (zh) | 水上浮筒光伏发电*** | |
CN204532717U (zh) | 风力发电机组基础环外壁与混凝土缝隙防水装置 | |
CN201771688U (zh) | 一种风力发电塔架地脚螺栓保护套 | |
CN110735388A (zh) | 设置在桥墩上的防护装置及其施工方法 | |
CN204056207U (zh) | 一种船舶压载水排放装置 | |
CN106438164A (zh) | 斜击式水利发电装置及安装方法 | |
CN201857800U (zh) | 高效防风抑尘墙 | |
CN102518146A (zh) | 围堰与承台的连接方式 | |
CN205205849U (zh) | 可更换式预应力锚栓风机基础 | |
CN207229305U (zh) | 一种带有防水复合结构的风力发电基础 | |
CN204046490U (zh) | 光伏发电装置的安装结构 | |
CN105971394A (zh) | 一种装配式光伏围挡及其生产工艺 | |
CN206752427U (zh) | 一种水电站地面厂房尾水出口结构及其水电站 | |
CN104790353A (zh) | 一种中小型拦河闸闸墩施工方法 | |
CN201581144U (zh) | 铝电解直流供电***整变阀侧母线防水装置 | |
CN204003249U (zh) | 一种适用于低水头发电的万向轴水力驱动装置 | |
CN206736714U (zh) | 一种具有防堵功能的桥梁 | |
CN202323971U (zh) | 围堰与承台的连接方式 | |
CN202830904U (zh) | 一种船闸伸缩缝 | |
CN101787686B (zh) | 建设海上风力发电场的方法 | |
CN208633992U (zh) | 一种塔筒基础环防水裙 | |
CN205678279U (zh) | 一种水池满水试验池壁洞口封堵装置 | |
CN201598606U (zh) | L型变形缝止水带 | |
CN204398123U (zh) | 预制混凝土塔筒转换段模具 | |
CN104195949B (zh) | 一种用于封堵护栏挂板底部缝隙的挡板及其使用方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20190516 Address after: 163000 Dongfeng New Village, Saertu District, Daqing City, Heilongjiang Province, through the east side of Eighth Street Guangyuan Cuiting New Garden D2-8 # business clothing Patentee after: Daqing Guangwei Construction and Installation Co.,Ltd. Address before: 163000 D-02-4-402, Aolong District, Longfeng District, Daqing City, Heilongjiang Province Patentee before: Yu Lin |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150805 |