CN204531464U - Connecting structure of formed concrete beam and newly-added concrete beam - Google Patents

Connecting structure of formed concrete beam and newly-added concrete beam Download PDF

Info

Publication number
CN204531464U
CN204531464U CN201520203631.3U CN201520203631U CN204531464U CN 204531464 U CN204531464 U CN 204531464U CN 201520203631 U CN201520203631 U CN 201520203631U CN 204531464 U CN204531464 U CN 204531464U
Authority
CN
China
Prior art keywords
concrete beam
newly
concrete
increased
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520203631.3U
Other languages
Chinese (zh)
Inventor
陈小东
金健
李社凤
王志鹏
杨曼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201520203631.3U priority Critical patent/CN204531464U/en
Application granted granted Critical
Publication of CN204531464U publication Critical patent/CN204531464U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a connection structure of concrete beam has taken shape and newly-increased concrete beam, including the concrete beam that has taken shape and newly-increased concrete beam, be provided with reinforcing bar A in the concrete beam that has taken shape, implant reinforcing bar B in the newly-increased concrete beam back, reinforcing bar B passes through the bolt fastening in the concrete beam that has taken shape, makes and increases concrete beam and an overall structure of concrete beam formation that has taken shape, reinforcing bar B in the newly-increased concrete beam plants and passes through the bolt fastening behind the concrete beam that has taken shape. The utility model can ensure that the anchoring degree of the stress steel bar of the newly added beam meets the standard requirement, can be better connected with the beam structure, and simultaneously, the construction of the newly added beam is simpler and more convenient, thereby being beneficial to the engineering construction progress and ensuring the construction quality; meanwhile, the damage to the original beam structure concrete and the reinforcing steel bars can be avoided as much as possible, the stability of the beam structure concrete and the reinforcing steel bars is ensured, and the beam structure concrete and reinforcing steel bar composite material has a wide application prospect.

Description

The syndeton of a kind of beam of forming concrete and newly-increased concrete beam
Technical field
The utility model belongs to Hydraulic and Hydro-Power Engineering technical field, particularly relates to the syndeton of a kind of beam of forming concrete and newly-increased concrete beam.
Background technology
In hydraulic structure; usually appearing on the beam concrete structure that has been shaped needs newly-increased slab and girder as the expansion of structure; now; the reinforcing bar of newly-increased concrete structure needs to stretch in the beam concrete be shaped, prior art due to the cross dimensions of beam own less, structural strength, rigidity are also lower; as other newly-increased girder constructions need be connected; then reinforcing bar anchoring in beam of newly-increased beam is comparatively difficult, and anchorage length can not meet code requirement, makes its connecting portion steadiness poor.Simultaneously because beam upper part concrete peeled off by needs, the Stability Analysis of Structures of beam own is also had a certain impact.
Utility model content
For solving the problem, the utility model provides the syndeton of a kind of beam of forming concrete and newly-increased concrete beam.Thus make the anchoring degree of newly-increased beam stress reinforcing bar meet code requirement, better can be connected with girder construction, reduce the destruction to original girder construction, ensure that it is stablized.
The utility model is achieved by following technical solution.
The syndeton of a kind of beam of forming concrete and newly-increased concrete beam, comprise forming concrete beam and newly-increased concrete beam, reinforcing bar A is provided with in the described beam of forming concrete, post-installing rebar B in described newly-increased mixed earth beam, described reinforcing bar B is bolted in forming concrete beam, makes increasing concrete beam and forming concrete beam form an overall structure.
Reinforcing bar B in described newly-increased concrete beam plants and is bolted through after forming concrete beam.
Described reinforcing bar A is connected in length and breadth and is arranged in forming concrete beam.
The beneficial effects of the utility model are:
Compared with prior art, the utility model can make the anchoring degree of newly-increased beam stress reinforcing bar meet code requirement, can better be connected with girder construction, ensures the stressed according calculation model of binding site; Make the construction newly increasing beam more simple, convenient simultaneously, be conducive to engineering construction progress, ensure construction quality.Implant reinforcing bar and arrange that boring is implanted according to newly-increased girder construction principal rod, anchoring is forced through screw bolt reinforcing, and reinforcing mode is reliable, and method is simple; The destruction to former girder construction concrete and reinforcing bar can be avoided simultaneously as far as possible, ensure that it is stablized, have broad application prospects.
Accompanying drawing explanation
Fig. 1 is the syndeton schematic diagram of the utility model forming concrete beam and newly-increased concrete beam;
Fig. 2 is the section structure schematic diagram of forming concrete beam in the utility model.
In figure: 1-is forming concrete beam, 2-reinforcing bar A, 3-increases concrete beam newly, 4-reinforcing bar B, 5-bolt.
Detailed description of the invention
The technical solution of the utility model is further described below in conjunction with accompanying drawing, but described in claimed scope is not limited to.
As shown in Figure 1 and Figure 2, the syndeton of a kind of beam of forming concrete described in the utility model and newly-increased concrete beam, comprise forming concrete beam 1 and newly-increased concrete beam 3, reinforcing bar A2 is provided with in the described beam of forming concrete 1, post-installing rebar B4 in described newly-increased mixed earth beam 3, described reinforcing bar B4 is fixed in forming concrete beam 1 by bolt 5, makes increasing concrete beam 3 and forming concrete beam 1 form an overall structure.Adopt the technical program, making the anchoring degree of newly-increased concrete beam 3 steel bar stress meet code requirement, can better be connected with becoming ellbeam 1 structure, ensure the stressed according calculation model of binding site; Reduce the destruction to original girder construction as possible, ensure that it is stablized.Make the construction newly increasing concrete beam 3 more simple, convenient simultaneously, be conducive to engineering construction progress, ensure construction quality.
Reinforcing bar B4 in described newly-increased concrete beam 3 is planted and is fixed by bolt 5 through after forming concrete beam 1.
Reinforcing bar A2 in the described beam of forming concrete 1 is connected in length and breadth and is arranged in forming concrete beam 1.As shown in Figure 2, reinforcing bar A2 comprises the steel hoop that section is rectangle, and is connected with longitudinal reinforcement on four angles of steel hoop.
The described beam of forming concrete 1 arranges employing dabbing with the connecting surface of newly-increased concrete beam 3.
As shown in Figure 1, the utility model, when implementing, mainly carries out in accordance with the following steps:
The first step, in the boring of the position of newly-increased concrete beam 3 structure of forming concrete beam 1, boring is arranged and is determined according to the layout of main stress reinforcing bar;
Second step, reinforcing bar B4 implants forming concrete beam 1 side need be processed into the pattern that can be connected with bolt 5;
3rd step, is implanted into reinforcing bar B4 in the hole that the first step is bored;
4th step, to be fixed on reinforcing bar B4 on forming concrete beam 1 with bolt 5 after above-mentioned steps completes.

Claims (3)

1. the syndeton of forming concrete beam and newly-increased concrete beam, it is characterized in that: comprise forming concrete beam (1) and newly-increased concrete beam (3), reinforcing bar A (2) is provided with in the described beam of forming concrete (1), the described newly-increased mixed interior post-installing rebar B (4) of earth beam (3), described reinforcing bar B (4) is fixed in forming concrete beam (1) by bolt (5), makes increasing concrete beam (3) and forming concrete beam (1) form an overall structure.
2. the syndeton of a kind of beam of forming concrete according to claim 1 and newly-increased concrete beam, is characterized in that: the reinforcing bar B (4) in described newly-increased concrete beam (3) plants through forming concrete beam (1) is fixing by bolt (5) afterwards.
3. the syndeton of a kind of beam of forming concrete according to claim 1 and newly-increased concrete beam, is characterized in that: described reinforcing bar A (2) is connected in length and breadth and is arranged in forming concrete beam (1).
CN201520203631.3U 2015-04-07 2015-04-07 Connecting structure of formed concrete beam and newly-added concrete beam Active CN204531464U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520203631.3U CN204531464U (en) 2015-04-07 2015-04-07 Connecting structure of formed concrete beam and newly-added concrete beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520203631.3U CN204531464U (en) 2015-04-07 2015-04-07 Connecting structure of formed concrete beam and newly-added concrete beam

Publications (1)

Publication Number Publication Date
CN204531464U true CN204531464U (en) 2015-08-05

Family

ID=53745492

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520203631.3U Active CN204531464U (en) 2015-04-07 2015-04-07 Connecting structure of formed concrete beam and newly-added concrete beam

Country Status (1)

Country Link
CN (1) CN204531464U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105525765A (en) * 2016-01-26 2016-04-27 四川航天建筑工程有限公司 Laminated concrete member and construction structure and construction method thereof
CN109469349A (en) * 2018-11-19 2019-03-15 中国矿业大学 A kind of floor strengthening reconstruction method for adding reinforced concrete secondary beam

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105525765A (en) * 2016-01-26 2016-04-27 四川航天建筑工程有限公司 Laminated concrete member and construction structure and construction method thereof
CN109469349A (en) * 2018-11-19 2019-03-15 中国矿业大学 A kind of floor strengthening reconstruction method for adding reinforced concrete secondary beam

Similar Documents

Publication Publication Date Title
CN106988483B (en) A kind of assembled steel reinforced Concrete U Vierendeel girder and its connection steelframe
CN107143034A (en) A kind of assembly concrete frame structure beam column rigid connection node
CN203547773U (en) Channel combined support structure suitable for slowly inclined stratified rock mass
CN106567499B (en) Assembled steel reinforced concrete joining column structure and its implementation method
CN210177522U (en) Ecological slope protection structure of prefabricated assembled anchor rope lattice beam
CN105239726B (en) The prefabricated combined special-shaped power consumption post of steel reinforced concrete
CN102477781A (en) Integrally assembled steel-concrete superposed component and manufacturing method thereof
CN103993753A (en) Angle hoop tie reinforcement system of traditional stone masonry house and construction technology
CN108532796A (en) Assembly concrete shear wall and face inner beam rigid connection node and construction method
CN110359452A (en) A kind of nodal-connection components, frame pre-stress cable bolting structure and construction method
CN204531464U (en) Connecting structure of formed concrete beam and newly-added concrete beam
CN104972550B (en) The polygonal mould and preparation method of a kind of in-situ precast concrete-pile
CN206157913U (en) Assembled square steel tube concrete post and girder steel connected node
CN209260897U (en) Assembly concrete beam column sleeve combination connecting node
CN102031876A (en) Method for newly adding upright column for building
CN207436278U (en) A kind of assembly concrete-filled steel tube column-girder steel punching node
CN103741883B (en) Prefabricated reinforced concrete column template and preparation method thereof
CN108756038A (en) Assembly concrete shear wall and floor support plate rigid connection node and construction method
CN103866866A (en) Ultra-high layer core tube and outer framework beam post-cast joint
CN103590600B (en) A kind of prefabricated post mould and application process thereof
CN204386611U (en) A kind of tunnel sprayed mortar non-dismantling formwork
CN205153212U (en) Steel pipe concrete shear force wall and building
CN212129882U (en) Prefabricated construction outrigger drawknot structure
CN106988321A (en) A kind of miscellaneous fill foundation ditch bamboo reinforcement support system and its construction method
CN207079809U (en) A kind of assembled steel reinforced Concrete U Vierendeel girder and making mould and connection steelframe

Legal Events

Date Code Title Description
C14 Grant of patent or utility model