CN204515031U - Large Oil immersion transformer is empty, load test complex - Google Patents

Large Oil immersion transformer is empty, load test complex Download PDF

Info

Publication number
CN204515031U
CN204515031U CN201520066587.6U CN201520066587U CN204515031U CN 204515031 U CN204515031 U CN 204515031U CN 201520066587 U CN201520066587 U CN 201520066587U CN 204515031 U CN204515031 U CN 204515031U
Authority
CN
China
Prior art keywords
transformer
load
load test
voltage
large oil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520066587.6U
Other languages
Chinese (zh)
Inventor
王伟
付刚
郑含博
王立楠
李予全
李晓纲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Henan Electric Power Co Ltd
Henan Enpai High Tech Group Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Henan Electric Power Co Ltd
Henan Enpai High Tech Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Henan Electric Power Co Ltd, Henan Enpai High Tech Group Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201520066587.6U priority Critical patent/CN204515031U/en
Application granted granted Critical
Publication of CN204515031U publication Critical patent/CN204515031U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Measurement Of Resistance Or Impedance (AREA)

Abstract

Large Oil immersion transformer is empty, load test complex, and Large Oil immersion transformer is empty, load test complex is divided into experiment power supply part and measuring system; Experiment power supply part comprises the induction voltage regulator, intermediate transformer, oil immersed type intensive compensation Capacitor banks and the experiment control system that are connected successively by circuit; Measuring system comprises precision measurement current transformer, voltage transformer (VT) and power analyzer.Zero load and load loss measurement test can be carried out to 110kV and 220kV electric pressure transformer field, no-load transformer current measurement, transformer noload losses measurement, no-load transformer harmonic measure can be completed, Transformer Short Circuit Impedance measures and transformer load loss is measured.

Description

Large Oil immersion transformer is empty, load test complex
Technical field
The utility model relates to high voltage electric equipment experimental technique field, particularly relates to the rig-site utilization device of the zero load of 110kV and 220kV electric pressure oil-filled transformer and load test.
Background technology
No-load transformer and load test are the important tests projects of oil-immersed power transformer.No-load test generally applies the sine wave of rated voltage, rated frequency from the winding that voltage is lower, other windings are opened a way, measuring transformer loss and exciting current with this understanding.Whether existing defects can be checked on transformer magnetic circuit by no-load test.Load test generally applies the alternating voltage of rated frequency at transformer high-voltage winding, make the electric current in this winding reach ratings, low-pressure side short circuit in winding, and other winding (if there is) are opened a way, the load loss of measuring transformer and short-circuit impedance.Load test can determine whether the operating index of transformer meets the requirement of standard, technical protocol, and meanwhile, load test is also for the temperature rise test of transformer lays the foundation.
But in actual field, because tested transformer capacity is larger, especially concerning large oil immersed power transformer, the capacity of required site test power supply is very large, therefore each test all needs huge testing equipment to drop into, not only floor area is large, and transport, carrying, wiring are all very inconvenient, also increase the error of test measurements and calculations simultaneously.Had research institution to carry out tentative research to the empty load test set of equipments of oil-filled transformer in recent years both at home and abroad, but due to testing equipment capacity not, the reason such as the not high and control system imperfection of measuring accuracy, have no and be extensively extended in actual production.
Utility model content
The purpose of this utility model is to provide a kind of Large Oil immersion transformer sky, load test complex, can carry out sky, load loss measures test to 110kV and 220kV electric pressure Power Transformer in Field.
The technical solution of the utility model is:
Large Oil immersion transformer is empty, load test complex, and Large Oil immersion transformer is empty, load test complex is divided into experiment power supply part and measuring system; Experiment power supply part comprises the induction voltage regulator, intermediate transformer, oil immersed type intensive compensation Capacitor banks and the experiment control system that are connected successively by circuit; Measuring system comprises precision measurement current transformer, voltage transformer (VT) and power analyzer.
The utility model adopts oil immersed type intensive compensation Capacitor banks to carry out inductive reactive power compensation, reduce the capacity of experiment power supply, make Large Oil immersion transformer field carry out sky load measure and become possibility, control system of the present utility model adopts programmable logic controller (PLC) to coordinate the form of host computer, to realize all control for testing equipments such as induction voltage regulator, intermediate transformer and precision measurement mutual inductors, meet in-site measurement requirement.
Advantage of the present utility model:
First, zero load and load loss measurement test can be carried out to 110kV and 220kV electric pressure transformer field, no-load transformer current measurement, transformer noload losses measurement, no-load transformer harmonic measure can be completed, Transformer Short Circuit Impedance measures and transformer load loss is measured, and there is sky, the automatic computing function of load loss measurement test findings;
Second, adopt high-precision power analyser LMG 500, realize voltage and current and measure group delay <3ns(sampling rate 3M/s between input), very high measurement level is ensure that under low power factor, basic accuracy reaches: ± 0.01%+ the range of the reading (0.02%), and phase angle error is <1 μ radian when 50Hz;
3rd, there is automatic calculating, controlling functions that compensation condenser group drops into combinations of voltages and combined capacity, significantly reduce the requirement to site test power supply capacity;
4th, experiment control system adopts programmable logic controller (PLC) to coordinate the form of host computer, and man-machine interface is friendly, simple to operation;
5th, it is convenient that equipment installs transformation, and test method is flexible and changeable.
Accompanying drawing explanation
Fig. 1 is electrical design figure of the present utility model;
Fig. 2 is the single-phase wiring diagram of no-load test of the present utility model;
Fig. 3 is no-load test equivalent schematic diagram of the present utility model;
Fig. 4 is the single-phase wiring of load test of the present utility model;
Fig. 5 is load test equivalent schematic diagram of the present utility model;
Fig. 6 is the primary circuit schematic diagram in Fig. 1.
Embodiment
As a shown in Figure 6, Large Oil immersion transformer sky of the present utility model, load test complex and method.Wherein, Large Oil immersion transformer sky, load test complex are divided into experiment power supply part and measuring system.Experiment power supply part comprises induction voltage regulator 2, intermediate transformer 3, oil immersed type intensive compensation Capacitor banks 4 and experiment control system; Measuring system comprises precision measurement current transformer, voltage transformer (VT) and power analyzer.Measuring system of the present utility model is Large Oil immersion transformer idling load-loss measuring equipment.
As shown in Figure 6, dotted portion is primary circuit of the present utility model schematic diagram, be made up of switch cubicle 1, induction voltage regulator 2, intermediate transformer 3, compensation condenser group 4, precision measurement mutual inductor 5 five part, whole loop is provided with the break-make of A.C. contactor for Long-distance Control major loop in the input side switch cubicle of induction voltage regulator 2.
As shown in Figure 1, the utility model secondary control system adopts programmable logic controller (PLC) to coordinate host computer to realize, and controller comprises input point and output point.As shown in Figure 1, input point from P00 to P23 totally 36, output point from P40 to P57 totally 24, the counting mode of its title is 16 systems.Input point is the contact of peripheral control unit, apply the power supply of appropriate voltage between contact and common port after, corresponding pilot lamp on controller can light, corresponding contact in its program also can action, its whole 36 contacts are equally divided into 2 groups, often organize all contacts and share a common port and COM, power supply uses direct current 24V.Input point is generally used for the state instruction of A.C. contactor, limit switch and button etc., and the content in Fig. 1 in the dotted line frame of right side is all outside at switch cubicle.Output point is the normal opened contact that controller inside programming controls, and as shown in Figure 1, it is divided into 7 groups, and often organize number of connections from 1 to 4 not etc., often in group, all contacts share a COM.
As shown in Figure 1; other secondary control systems comprise: precision measurement current and potential transformer secondary gear regulable control and instruction; compensation condenser group voltage and capacity grouping gear regulate instruction; intermediate transformer exports gear regulable control and instruction; induction voltage regulator buck (frequency converter) controls and the spacing instruction of height; the protection of induction voltage regulator input overcurrent relay, incoming power voltage and induction voltage regulator input current are measured.The opertaing device such as controller and electric components is assembled in switch board, and the connection of the control cable of system all uses the general aviation plug of different core number to carry out (in Fig. 1 1# ~ 8#), can prevent the incorrect link of cable.
The single-phase wiring of no-load test of the present utility model and equivalent schematic diagram are as shown in Figure 2,3.By no-load test, can the open circuit loss of measuring transformer with no-load current number percent , can ask for: the no-load voltage ratio of transformer simultaneously , transformer excitation parameter , with .No-load test can be carried out in any side of transformer, but in order to safety and instrument choosing convenience, usually carrying out in low-pressure side, i.e. low-pressure side making alive, opens a way in high-pressure side.Should be noted that during wiring: because of no-load current very little, in order to reduce the measuring error of electric current, reometer should be connected on transformer coil side.
During no-load test, regulate impressed voltage for ratings , read voltage table reading , ; Reometer reading ; Power meter reading .As can be seen from unloaded equivalent electrical circuit, ignoring under relatively little unloaded direct current resistance loss and insulation dielectric loss condition, the open circuit loss of transformer equals core loss , namely ; Ignoring relatively little leakage impedance pressure drop under condition, zero-load impedance is excitation impedance.
Therefore, can obtain according to unloaded measurement result:
(1)
(2)
(3)
(4)
(5)
(6)
For three-phase transformer, should according to testing the three phase power, line voltage and the line current that record, after obtaining the numerical value of every phase respectively, then use formula (1) ~ (6) to carry out the excitation parameter of calculating transformer, transformer voltage ratio also needs to calculate by phase voltage.
The single-phase wiring of load test of the present utility model and equivalent schematic diagram are as shown in Figure 4,5.The load loss of transformer can be asked for by load test and short-circuit impedance (the i.e. short-circuit voltage percentage value ratio of transformer ), the short-circuit parameter of transformer can be obtained simultaneously with .Load test also can be carried out in any side of transformer, but in order to safety and instrument choosing convenience, usually carries out in high-pressure side, i.e. high-pressure side making alive, low-pressure side short circuit.Because the short-circuit impedance of transformer is very little, in order to avoid excessive short-circuit current damages winding, impressed voltage must be very low.In order to reduce the measuring error of voltage, the potential winding of voltage table and power meter during wiring, should be noted to be connected in parallel on transformer coil side.Due to very low, in iron core, main flux is very little, therefore exciting current and core loss can be ignored, and the field excitation branch line namely in equivalent electrical circuit is equivalent to open circuit, thus equivalent electrical circuit when obtaining load test short circuit.
During load test, slowly raise impressed voltage, until namely short-circuit current reaches ratings , read voltage table reading immediately , reometer reading with power meter reading , then cut off the electricity supply.Record be called load loss, be also called short circuit loss, it equals the copper loss on first and second winding resistance, namely ; The primary side voltage recorded be called short-circuit voltage, be also called impedance voltage, it equals the pressure drop that rated current produces on short-circuit impedance, namely , then short-circuit voltage percentage value ratio is
(7)
Can calculate short-circuit parameter according to measurement result is
(8)
(9)
(10)
For large oil immersed power transformer, during load test, the capacity of required site test power supply is very large, therefore the utility model adopts oil immersed type intensive compensation Capacitor banks to carry out inductive reactive power compensation, reduce the capacity of experiment power supply, make Large Oil immersion transformer field carry out load measure and become possibility, the utility model load test capacitor compensation protocol step is as follows:
1, the short-circuit impedance of test specimen is determined and test rated current ;
2, according to the percentage of test rated current determine the voltage that will apply and electric current , namely , ;
3, basis value select gear, the gear of PT, the condenser voltage gear of intermediate transformer, according to value select the gear of CT;
4, surge capacity=power supply capacity/1.1(the utility model scheme is selected to consider the Capacity Margin of 10%), then surge capacity percentage=selection surge capacity/pressure regulator rated capacity ;
5, pressure regulator output current=pressure regulator rated current × surge capacity percentage;
6, intermediate transformer output current=pressure regulator output current/intermediate transformer no-load voltage ratio;
7, capacitor need compensate electric current= the electric current that – intermediate transformer exports;
8, select capacitor compensation capacity= rated voltage under the capacitor gear that × capacitor needs the electric current × step 3 compensated to select.
Above-mentioned parameters as: , deng, all can record with equipment or obtain from prior art.
In sum, the utility model structure is simple, microcomputer automatic controls, interface is simple to operation, breach traditional transformer idling and carry site test placing restrictions on power supply capacity, make the large oil immersed transformer field of 110kV and 220kV carry out the measurement of idling load-loss and become possibility, fill up the blank that domestic on-the-spot idling load-loss is measured, effectively ensure the reliable and secure operation of power transformer.

Claims (1)

1. Large Oil immersion transformer sky, load test complex, is characterized in that: Large Oil immersion transformer is empty, load test complex is divided into experiment power supply part and measuring system; Experiment power supply part comprises the induction voltage regulator, intermediate transformer, oil immersed type intensive compensation Capacitor banks and the experiment control system that are connected successively by circuit; Measuring system comprises precision measurement current transformer, voltage transformer (VT) and power analyzer.
CN201520066587.6U 2015-01-30 2015-01-30 Large Oil immersion transformer is empty, load test complex Active CN204515031U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520066587.6U CN204515031U (en) 2015-01-30 2015-01-30 Large Oil immersion transformer is empty, load test complex

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520066587.6U CN204515031U (en) 2015-01-30 2015-01-30 Large Oil immersion transformer is empty, load test complex

Publications (1)

Publication Number Publication Date
CN204515031U true CN204515031U (en) 2015-07-29

Family

ID=53712990

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520066587.6U Active CN204515031U (en) 2015-01-30 2015-01-30 Large Oil immersion transformer is empty, load test complex

Country Status (1)

Country Link
CN (1) CN204515031U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105044479A (en) * 2015-01-30 2015-11-11 国网河南省电力公司电力科学研究院 Apparatus for large-scale oil-immersed transformer no-load and on-load comprehensive tests and method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105044479A (en) * 2015-01-30 2015-11-11 国网河南省电力公司电力科学研究院 Apparatus for large-scale oil-immersed transformer no-load and on-load comprehensive tests and method

Similar Documents

Publication Publication Date Title
CN105044479A (en) Apparatus for large-scale oil-immersed transformer no-load and on-load comprehensive tests and method
CN102360857B (en) Integrated network distributing transformer with error compensating mutual inductor
CN201319064Y (en) Test circuit for field accuracy detection of high-voltage current transformer
CN103884933B (en) A kind of high-power transformer temperature-raising experimental method
CN203217005U (en) Converter transformer no-load test schematic wiring diagram
CN116106659B (en) Distribution transformer energy efficiency high-precision test system and application
CN103336188A (en) Current boosting apparatus suitable for GIS equipment
Oleksyuk et al. Magnetically controlled shunt reactors as sources of current and voltage harmonics
CN106249192B (en) Metering equipment field operation detecting system
Yan et al. Research on measurement technology of transformer no-load loss based on Internet of Things
CN111044828A (en) Three-phase transformer winding parameter online monitoring method based on positive and negative sequence equations
CN202330691U (en) Field calibrating equipment for voltage transformer
CN202041606U (en) Frequency tripling transformer load test device
CN204515031U (en) Large Oil immersion transformer is empty, load test complex
CN104808022A (en) Temperature rise test connection method for three-side combined operation of three-phase three-winding transformer
CN107861012A (en) A kind of through-flow device of high-power transformer
CN109637792B (en) Test transformer
CN102269786B (en) Load testing device for triple-frequency transformer
CN109375047B (en) System and method for testing double-end asynchronous polarity of high-voltage transmission line
CN104635083A (en) Field load testing device for power transformer
CN104678218A (en) Estimation method of optimal compensation capacitance of cable current rise test system
CN204359884U (en) A kind of Power Transformer in Field load testing apparatus
CN204613387U (en) For the electric supply installation that current transformer detects
CN103487705A (en) Quality control method for excitation characteristics of C-type iron core voltage transformer
CN102298109A (en) Determination method for circuit model for alternating-current voltage withstand test on power cable

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant