CN204386619U - A kind of bend loss reinforcement trolley - Google Patents

A kind of bend loss reinforcement trolley Download PDF

Info

Publication number
CN204386619U
CN204386619U CN201520025686.XU CN201520025686U CN204386619U CN 204386619 U CN204386619 U CN 204386619U CN 201520025686 U CN201520025686 U CN 201520025686U CN 204386619 U CN204386619 U CN 204386619U
Authority
CN
China
Prior art keywords
bend loss
door frame
reinforcement
chassis door
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520025686.XU
Other languages
Chinese (zh)
Inventor
孙昌忠
汪文亮
詹剑霞
刘勇
马少甫
李晓萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Three Gorges Construction Engineering Co Ltd
Original Assignee
China Gezhouba Group Co Ltd
China Gezhouba Group Three Gorges Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Co Ltd, China Gezhouba Group Three Gorges Construction Engineering Co Ltd filed Critical China Gezhouba Group Co Ltd
Priority to CN201520025686.XU priority Critical patent/CN204386619U/en
Application granted granted Critical
Publication of CN204386619U publication Critical patent/CN204386619U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model relates to a kind of bend loss reinforcement trolley, it comprises chassis door frame, the operating platform of adjustable angle is arranged respectively at chassis door frame both sides and top, operating platform is distributed with many reinforcing bar sample framves, there are walking mechanism and track bottom chassis door frame, bottom described chassis door frame, are provided with support locking.The utility model achieves quick at bend loss, accurate, safe installation reinforcing bar, improves efficiency of construction, ensure that construction quality.Trolley structure is simply convenient to dismounting and is turned hole, is conducive to multiple cavern with section bend loss reinforcement installation.

Description

A kind of bend loss reinforcement trolley
Technical field
The utility model relates to a kind of reinforcement trolley, especially a kind of bend loss reinforcement trolley.
Background technology
Underground chamber bend loss lining concrete construction in current hydropower industry, traditional form of construction work is that the mode setting up bent-frame bracing gang form is constructed, and the method is long in time limit, have a big risk.For accelerating construction progress, ensure construction safety, bend loss concrete construction proposes brand-new method, bend loss lining steel formwork jumbo.For shortening the reinforcing bar binding duration, ensureing bend loss reinforcement installation job safety, matching with bend loss lining steel formwork jumbo, need design and provide a kind of device being convenient to bend loss reinforcing bar Fast Installation.
Summary of the invention
Technical problem to be solved in the utility model is to provide technical problem to be solved in the utility model and is to provide a kind of bend loss reinforcement trolley, can be quick at bend loss, accurate and safe complete reinforcing bar binding work, accelerate construction speed, ensure that construction safety.
A kind of bend loss reinforcement trolley, it comprises chassis door frame, and the operating platform of adjustable angle is arranged respectively at chassis door frame both sides and top, operating platform is distributed with many reinforcing bar sample framves, there are walking mechanism and track bottom chassis door frame, bottom described chassis door frame, are provided with support locking.
There is reinforcing bar conveyer slideway above-mentioned chassis door frame front end.
Above-mentioned track is less than 30cm at bearing height.
Aforesaid operations platform adjustable angle.
Steel mesh reinforcement distance 8-12cm outside above-mentioned reinforcing bar sample frame end portion distance lining concrete.
The utility model has following beneficial effect:
A kind of bend loss reinforcement trolley that the utility model provides, is moved in orbit in the axial direction by trailer system connecting reinforcement chassis, ensures that chassis all can use in whole bend loss hole; Chassis top and both sides are provided with the operating platform of adjustable angle, ensure that platform can adapt to each operating mode operation in bend loss; On reinforcement trolley, vertical hole axis direction is furnished with reinforcing bar sample frame, to control reinforcement installation precision in whole bend loss; Thus achieve quick at bend loss, accurate, safe installation reinforcing bar, improve efficiency of construction, ensure that construction quality.Trolley structure is simply convenient to dismounting and is turned hole, is conducive to multiple cavern with section bend loss reinforcement installation.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the utility model is described in further detail.
Fig. 1 is that bend loss of the present utility model first section of reinforcement installation reinforcement trolley runs schematic diagram.
Fig. 2 is reinforcement trolley elevation of the present utility model.
Fig. 3 is reinforcement trolley top view of the present utility model.
Fig. 4 is reinforcement trolley lateral view of the present utility model.
Fig. 5 is that the utility model runs schematic diagram.
Detailed description of the invention
Below in conjunction with accompanying drawing, embodiment of the present utility model is described further.
See Fig. 2-4, a kind of bend loss reinforcement trolley, comprises chassis door frame 1, and the operating platform 4 of adjustable angle is arranged respectively at chassis door frame 1 both sides and top, operating platform 4 is distributed with many reinforcing bar sample framves 5.Walking mechanism 2 and track 3 is had bottom chassis door frame 1.
Described chassis door frame 1 adopts section steel manufacture, and based on bolt connection, to be welded to connect be auxiliary, can meet the requirement of integral hoisting in hole, is convenient to be transferred to adjacent cavern and uses.
Described operating platform 4 adjustable angle, adapts to reinforcement trolley and under bend loss different angles operating mode, operating platform 4 can be adjusted to level all the time, convenient construction personnel operation at an upper portion thereof, ensure operating personnel's safety.
Described operating platform 4 is welded with reinforcing bar sample frame 5, for controlling reinforcement installation location, reinforcing bar sample frame 5 end is preferably apart from steel mesh reinforcement distance 8-12cm outside lining concrete.One is facilitate reinforcement installation and control reinforcement installation precision, and two is avoid reinforcing bar sample frame 5 and steel mesh reinforcement mutually to disturb, and is convenient to reinforcement trolley and walks at bend loss.During bend loss reinforcing bar in-site installation, only need first section to carry out measurement and positioning with total powerstation to reinforcing bar sample frame 5, after first section of reinforcement installation completes, during residue section reinforcement installation, only need carry out measurement and positioning to reinforcement trolley center, no longer to reinforcing bar sample frame 5 duplicate measurements location, accelerate reinforcement installation progress.
Preferred steel structure support in the scope that described track 3 is less than 30cm at bearing height, horizontal plane angle is less than 15 degree, steel work adopts anchor pole to fix in bedrock surface, adopts this kind of form of structure to be cost-saving input, to accelerate track construction progress; Preferred continuous concrete track structure in the scope that track 3 horizontal plane angle is greater than 15 degree, adopts this kind of form of structure to be ensure reinforcement trolley security of operation.
Be provided with support locking 8 bottom described chassis door frame 1, adopt support locking 8 hold out against track and lock behind reinforcement trolley location, fixing reinforcement trolley is not shifted, and ensures reinforcement trolley security of operation.
There is reinforcing bar conveyer slideway 7 described chassis door frame 1 front end, and reinforcing bar to be installed bottom chassis door frame 1, utilizes the means such as cucurbit or rope to be transported to the operating platform 4 at chassis door frame 1 top along slide rail 7 traction, accelerates reinforcement installation progress by convenient construction personnel.
One utilizes above-mentioned bend loss reinforcement trolley to carry out reinforcement installation method, as shown in Figure 1 and Figure 5, comprises the following steps:
One, at trailer systems 9 such as upper horizontal section 12 backplane hoist engines, directive wheel 10 is laid near bend loss 14 position in upper horizontal section 12 top, lays track 3 at bend loss 14 base plate bedrock surface.Described track 3 can select steel work or concrete structure, and in this example, preferred concrete structure and steel work combine, and top adopts steel work close to flat section, and bottom curved segment adopts concrete structure.
Two, trailer system 9 is by wire rope 9 and directive wheel 8 connecting reinforcement chassis door frame 1, is slided to bottom bend loss 14 for 3 times by reinforcement trolley along track.Bend loss reinforcement installation, is divided into some sections of constructions according to the width of reinforcement trolley, and from bend loss bottom, upwards segmentation is installed successively.
Three, support locking 8 held out against track 3 and lock, fixing reinforcement trolley is not shifted.
Four, reinforcing bar to be installed is transported to chassis door frame 1 bottom by working tunnel 13, can adopt hand haulage or simple and easy chassis transporting apparatus transports, and in this example, preferred simple and easy chassis transport can accelerating construction progress, does not go out in figure.Adjustment operating platform 4 is to horizontal job state, by cucurbit or rope, reinforcing bar is drawn to the top operating platform 4 of chassis door frame 1 along chassis door frame 1 front end slide rail 7, constructor does with reference to installing assembling reinforcement with reinforcing bar sample frame 5, and steel mesh reinforcement 15 is fixed by the anchor pole 6 of bedrock surface excavation supporting.
Five, unclamp the support locking 8 bottom chassis door frame 1, upwards draw reinforcement trolley to next section.
Six, repeat above-mentioned three ~ five steps, complete reinforcement installation colligation work piecemeal.
Realize the safety of bend loss reinforcing bar, Fast Installation colligation according to the method described above.

Claims (5)

1. a bend loss reinforcement trolley, it comprises chassis door frame (1), it is characterized in that: the operating platform (4) of adjustable angle is arranged respectively at chassis door frame both sides and top, operating platform is distributed with many reinforcing bar sample framves (5), there are walking mechanism (2) and track (3) bottom chassis door frame, bottom described chassis door frame, are provided with support locking (8).
2. bend loss reinforcement trolley according to claim 1, is characterized in that: there is reinforcing bar conveyer slideway (7) described chassis door frame front end.
3. bend loss reinforcement trolley according to claim 1 and 2, is characterized in that: described track is less than 30cm at bearing height.
4. bend loss reinforcement trolley according to claim 1 and 2, is characterized in that: described operating platform adjustable angle.
5. bend loss reinforcement trolley according to claim 1 and 2, is characterized in that: steel mesh reinforcement distance 8-12cm outside described reinforcing bar sample frame end portion distance lining concrete.
CN201520025686.XU 2015-01-15 2015-01-15 A kind of bend loss reinforcement trolley Expired - Fee Related CN204386619U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520025686.XU CN204386619U (en) 2015-01-15 2015-01-15 A kind of bend loss reinforcement trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520025686.XU CN204386619U (en) 2015-01-15 2015-01-15 A kind of bend loss reinforcement trolley

Publications (1)

Publication Number Publication Date
CN204386619U true CN204386619U (en) 2015-06-10

Family

ID=53359350

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520025686.XU Expired - Fee Related CN204386619U (en) 2015-01-15 2015-01-15 A kind of bend loss reinforcement trolley

Country Status (1)

Country Link
CN (1) CN204386619U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111267064A (en) * 2020-04-20 2020-06-12 中国水利水电第四工程局有限公司 Large-inclination hydroelectric penstock assembling and welding trolley

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111267064A (en) * 2020-04-20 2020-06-12 中国水利水电第四工程局有限公司 Large-inclination hydroelectric penstock assembling and welding trolley

Similar Documents

Publication Publication Date Title
CN104727833A (en) Method of conducting steel bar installation on bend section through bend-section steel bar trolley
CN202148909U (en) Operation vehicle for mounting tunnel arch trusses
CN100538011C (en) Railway large-bore tunnel overhead contact built-in sliding chute construction method
CN106150511A (en) Shield driving formula sky pushes through ground fissure bored tunnel construction method
CN102287209A (en) Tunnel arch center installation operation vehicle
CN208010370U (en) A kind of novel tunnel tunneling boring arch installation trolley
CN104032967B (en) Prefabricated assembled frame structure component construction method for hanging
CN109441459A (en) A kind of earth pressure balanced shield separate launching side excavating construction method
CN108343783B (en) The installation method and hanging apparatus of high-altitude large-diameter pipeline under complex environment
CN107255188A (en) A kind of lifting pipeline method suitable at pipe gallery intersection node
CN202148920U (en) Conveying mechanism for tunnel construction
CN210566648U (en) Installation device for directional sliding of large pipeline in limited space
CN201874583U (en) Initiating device for shield machine
CN204386619U (en) A kind of bend loss reinforcement trolley
CN103787203B (en) For installing the bracing frame of precast beam jack
CN106837376B (en) Bind module turnover device for subway tunnel section of jurisdiction
CN203959689U (en) A kind of large-type sinterer depositing dust pipeline is installed and is adjusted with operation car
CN104895336A (en) Method for installing steel beam of stiff hybrid structure in place
CN213705734U (en) Boats and ships pipe installation auxiliary device that makes a command
CN110053936A (en) A kind of pipeline transporter and applied pipeline transportation method
CN103486330B (en) Either inside high-altitude pipeline mounting construction method
CN102704952B (en) Self-propelled tunnel grouting trolley
CN106437047B (en) A kind of equipment transported for factory building roof plate with installing
CN201309817Y (en) Hydraulic lifting mounting carrier vehicle
WO2019019742A1 (en) Rapid railway auxiliary beam transporting and erecting trailer

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160901

Address after: 443000 Dongshan Avenue, Hubei, Yichang, No. 11

Patentee after: CHINA GEZHOUBA GROUP THREE GORGES CONSTRUCTION ENGINEERING Co.,Ltd.

Address before: 443002 Hubei province Yichang City Road No. 1

Patentee before: CHINA GEZHOUBA GROUP Co.,Ltd.

Patentee before: CHINA GEZHOUBA GROUP THREE GORGES CONSTRUCTION ENGINEERING Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150610

Termination date: 20220115