CN204059418U - Deeply covered layer seepage prevention of dam founda wall construction - Google Patents

Deeply covered layer seepage prevention of dam founda wall construction Download PDF

Info

Publication number
CN204059418U
CN204059418U CN201420370814.XU CN201420370814U CN204059418U CN 204059418 U CN204059418 U CN 204059418U CN 201420370814 U CN201420370814 U CN 201420370814U CN 204059418 U CN204059418 U CN 204059418U
Authority
CN
China
Prior art keywords
concrete
wall
right bank
slotted eye
basement rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420370814.XU
Other languages
Chinese (zh)
Inventor
姜苏阳
郭其峰
王耀军
李泽民
邢建营
李远程
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Engineering Consulting Co Ltd
Original Assignee
Yellow River Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Engineering Consulting Co Ltd filed Critical Yellow River Engineering Consulting Co Ltd
Priority to CN201420370814.XU priority Critical patent/CN204059418U/en
Application granted granted Critical
Publication of CN204059418U publication Critical patent/CN204059418U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of deeply covered layer seepage prevention of dam founda wall construction, comprise the concrete slotted eye impervious wall be arranged between left and right bank on riverbed basement rock, in insertion riverbed, the bottom basement rock of concrete slotted eye impervious wall; Linking is fixed on the top of concrete slotted eye impervious wall concrete cast-in-situ wall; Concrete cast-in-situ wall is fixedly connected with left and right bank basement rock respectively by cast-in-situ concrete High-toe wall its underpart with the left and right two ends of concrete slotted eye impervious wall, and its top is fixedly connected with left and right bank concrete junction plate; Left and right bank concrete junction plate is fixedly connected with left and right bank basement rock respectively with by left and right bank toe board.The utility model advantage is the local penetration destruction solved because concrete slotted eye impervious wall construction mass defect causes.

Description

Deeply covered layer seepage prevention of dam founda wall construction
Technical field
The utility model relates to seepage prevention of dam founda wall construction, especially relates to deeply covered layer seepage prevention of dam founda wall construction.
Background technology
Build the Concrete Face Rockfill Dam on deeply covered layer, its Riverbed seepage control measure is by squeezing into covering layer by concrete slotted eye impervious wall and inserting in basement rock, block the current in the dam foundation, concrete slotted eye impervious wall upper end is closely connected by junction plate with the toe board of face dam, form seepage prevention for deep covering system, prevent the current under high water head effect from permeating with this.The end be connected with left and right bank basement rock due to the slotted eye impervious wall in covering layer and the bad control of upper end construction quality, cause concrete slotted eye impervious wall often easily to produce local quality defect.
Summary of the invention
The utility model object is to provide a kind of deeply covered layer seepage prevention of dam founda wall construction.
For achieving the above object, the utility model takes following technical proposals:
Deeply covered layer seepage prevention of dam founda wall construction described in the utility model, comprises the concrete slotted eye impervious wall be arranged between left and right bank on riverbed basement rock, and the bottom of described concrete slotted eye impervious wall is inserted in described riverbed basement rock; Linking is fixed on the top of described concrete slotted eye impervious wall concrete cast-in-situ wall; Described concrete cast-in-situ wall is fixedly connected with left and right bank basement rock respectively by cast-in-situ concrete High-toe wall its underpart with the left and right two ends of concrete slotted eye impervious wall, and its top is fixedly connected with described left and right bank concrete junction plate; Described left and right bank concrete junction plate is fixedly connected with left and right bank basement rock respectively with by left and right bank toe board.
The utility model advantage is the concrete cast-in-situ wall being fixedly engaged on described concrete slotted eye impervious wall top, thus solves the local penetration destruction because concrete slotted eye impervious wall construction mass defect causes.Concrete cast-in-situ wall is fixedly connected with described left and right bank concrete junction plate respectively by cast-in-situ concrete High-toe wall with the left and right two ends of concrete slotted eye impervious wall, not only improve being connected of concrete slotted eye impervious wall top and toe board, adaptive deformation displacement capacity is strong, good seepage-proof property, also make together with junction plate is cast in concrete cast-in-situ wall with concrete slotted eye impervious wall more securely simultaneously, make dam body more abundant at the deformation displacement of construction period, the distortion of such retaining phase junction plate can reduce a lot.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
As shown in Figure 1, deeply covered layer seepage prevention of dam founda wall construction described in the utility model, comprises the concrete slotted eye impervious wall 1 be arranged between left and right bank on riverbed basement rock 5, and the bottom of described concrete slotted eye impervious wall 1 is inserted in described riverbed basement rock 5; The top of described concrete slotted eye impervious wall 1 is fixed and is connected that to have be highly the concrete cast-in-situ wall 3 of a meter; Described concrete cast-in-situ wall 3 is fixedly connected with left and right bank basement rock 5 respectively by cast-in-situ concrete High-toe wall 2.1,2.2 its underpart with the left and right two ends of concrete slotted eye impervious wall 1, and its top is fixedly connected with described left and right bank concrete junction plate 4.1,4.2; Described left and right bank concrete junction plate 4.1,4.2 is fixedly connected with left and right bank basement rock respectively with by left and right bank toe board.

Claims (1)

1. a deeply covered layer seepage prevention of dam founda wall construction, comprises the concrete slotted eye impervious wall be arranged between left and right bank on riverbed basement rock, and the bottom of described concrete slotted eye impervious wall is inserted in described riverbed basement rock; It is characterized in that: linking is fixed on the top of described concrete slotted eye impervious wall concrete cast-in-situ wall; Described concrete cast-in-situ wall is fixedly connected with left and right bank basement rock respectively by cast-in-situ concrete High-toe wall its underpart with the left and right two ends of concrete slotted eye impervious wall, and its top is fixedly connected with described left and right bank concrete junction plate; Described left and right bank concrete junction plate is fixedly connected with left and right bank basement rock respectively with by left and right bank toe board.
CN201420370814.XU 2014-07-07 2014-07-07 Deeply covered layer seepage prevention of dam founda wall construction Expired - Lifetime CN204059418U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420370814.XU CN204059418U (en) 2014-07-07 2014-07-07 Deeply covered layer seepage prevention of dam founda wall construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420370814.XU CN204059418U (en) 2014-07-07 2014-07-07 Deeply covered layer seepage prevention of dam founda wall construction

Publications (1)

Publication Number Publication Date
CN204059418U true CN204059418U (en) 2014-12-31

Family

ID=52200962

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420370814.XU Expired - Lifetime CN204059418U (en) 2014-07-07 2014-07-07 Deeply covered layer seepage prevention of dam founda wall construction

Country Status (1)

Country Link
CN (1) CN204059418U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013263A (en) * 2016-07-16 2016-10-12 黄河勘测规划设计有限公司 Impermeable method of clay core wall dam foundation of deep river valley with deep sand gravel layer
CN110939108A (en) * 2019-12-27 2020-03-31 中水北方勘测设计研究有限责任公司 Structure for preventing concrete face dam high-toe wall from being damaged
CN111058469A (en) * 2019-11-29 2020-04-24 中国水利水电科学研究院 Impervious wall structure and ecological seepage-control solid bed system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013263A (en) * 2016-07-16 2016-10-12 黄河勘测规划设计有限公司 Impermeable method of clay core wall dam foundation of deep river valley with deep sand gravel layer
CN106013263B (en) * 2016-07-16 2018-04-20 黄河勘测规划设计有限公司 Clay core wall dam Foundation Anti-seepage method with deep sand gravel layer entrenched valley
CN111058469A (en) * 2019-11-29 2020-04-24 中国水利水电科学研究院 Impervious wall structure and ecological seepage-control solid bed system
CN110939108A (en) * 2019-12-27 2020-03-31 中水北方勘测设计研究有限责任公司 Structure for preventing concrete face dam high-toe wall from being damaged

Similar Documents

Publication Publication Date Title
CN204023501U (en) A kind of reinforcement Anti-seeping technology structure for earth and rockfill dam
CN204059418U (en) Deeply covered layer seepage prevention of dam founda wall construction
CN207452895U (en) A kind of high slope anchored pile supporting
CN104480958A (en) Bridge prefabricated bearing platform and bridge construction method
CN202954377U (en) Cover-plate dam foundation triangle-region curtain structure
CN204370370U (en) A kind of liftable ground sills
CN104278671B (en) Insert stiffness Soil-cement soldier pile and the construction method thereof of inverted cup shaped steel bucket
CN103938584B (en) The connection construction method of covering layer top panel toe plate, junction plate, impervious wall
CN203583514U (en) Pre-buried structure of ultra-deep foundation bolt
CN203113359U (en) Earth rock cofferdam structure
CN201865118U (en) Grouting spiral anchor base
CN204199325U (en) Support column passes through underground structure bottom plate structure
CN104652467A (en) Construction method for reserved hole of equipment foundation bolt
CN203546706U (en) Electroosmosis composite vacuum preloading system for reinforcing soft soil foundation
CN203795387U (en) Connecting structure of covering layer top panel dam-toe plate, connecting plate and diaphragm wall
CN207295706U (en) A kind of Pile feeder suitable for engineering method pile-type steel
CN206448270U (en) A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement
CN204279891U (en) The middle wing wall structure of a kind of pair of depressed place parallel connection
CN204475355U (en) Plugging structure
CN204645056U (en) A kind of combined type double-row pile foundation pit support structure
CN204266254U (en) Reinforcing bar seal ring
CN204326091U (en) Building lot
CN204753544U (en) Laid dry stone composite construction escape canal
CN204662374U (en) A kind of box-type suction foundation siphon gallery water intaking structure
CN205152997U (en) Drainage subtracts superficial structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 450003 Jinshui Road 109, Zhengzhou City, Henan Province

Patentee after: Yellow River Survey Planning and Design Research Institute Co., Ltd.

Address before: 450003 Jinshui Road 109, Zhengzhou City, Henan Province

Patentee before: Yellow River Engineering Consulting Co., Ltd.