CN203865928U - Special hoisting device for substation structure - Google Patents

Special hoisting device for substation structure Download PDF

Info

Publication number
CN203865928U
CN203865928U CN201420148962.7U CN201420148962U CN203865928U CN 203865928 U CN203865928 U CN 203865928U CN 201420148962 U CN201420148962 U CN 201420148962U CN 203865928 U CN203865928 U CN 203865928U
Authority
CN
China
Prior art keywords
transformer substation
substation framework
base
fixing plate
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420148962.7U
Other languages
Chinese (zh)
Inventor
苏丛辉
师威
刘立强
赵之洞
刘伟良
张磐
苏伟泽
袁继森
周兆辉
宋晓军
尹翠华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Power Supply Branch Guo Wang Hebei Electric Power Corp Zhao County
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Original Assignee
Power Supply Branch Guo Wang Hebei Electric Power Corp Zhao County
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Power Supply Branch Guo Wang Hebei Electric Power Corp Zhao County, State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd filed Critical Power Supply Branch Guo Wang Hebei Electric Power Corp Zhao County
Priority to CN201420148962.7U priority Critical patent/CN203865928U/en
Application granted granted Critical
Publication of CN203865928U publication Critical patent/CN203865928U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a special hoisting device for a substation structure. The special hoisting device comprises a base which is arranged on a transverse beam of the substation structure, a support is fixedly welded to the upper end face of the base, and a pulley is installed at the top end of the support. The base comprises an upper fixing plate and a lower fixing plate, wherein the upper fixing plate is located above the transverse beam of the substation structure, the lower fixing plate is located below the transverse beam of the substation structure, and the opposite ends, stretching out of the transverse beam of the substation structure, of the upper fixing plate and the lower fixing plate are connected through a connecting device. The support comprises a hollow base tube and a steel insertion tube, wherein the hollow base tube is fixedly welded to the upper fixing plate, and the steel insertion tube is inserted in a cavity of the base tube. The pulley is arranged at the top end of the steel insertion tube. The special hoisting device is simple in structure, convenient to carry, easy to assemble and suitable for hoisting and installing equipment on the substation structure. When the special hoisting device is used in an operation process, labor intensity is relieved, working efficiency is improved, an operation procedure is optimized, and safety production is further guaranteed.

Description

Transformer substation framework Special lifting device
Technical field
The utility model relates to a kind of auxiliary device for electrical domain, refers in particular to a kind of hanging apparatus that is applicable to substation.
Background technology
When exchange device (as disconnector, insulator, discharging rod etc.) is installed more by substation, because these equipment are all mounted on framework, generally need to adopt crane or pole to lift.Because crane is bulky, while using in charging equipment district, the swing of its crane arm and lifting are subject to site space position and the restriction of charging equipment around, and operation is very inconvenient, and has serious potential safety hazard; Pole is because its length is relatively long, and in substation, intensive, the adjacent charged spacing distance of battery limits equipment installation is near, can not meet the safety distance that pole is used; If, there is again the problems such as rising height is inadequate, deadweight is large, transportation is inconvenient in use fork truck; If rely on merely manpower lifting, not only operating personnel's labour intensity is large, inefficiency, and the personnel that easily cause injure and device damage.Therefore need a kind of equipment lifting appliance that transformer substation framework is installed and used that adapts to.
In Chinese patent CN102064485A, a kind of substation upper air installing device is disclosed, it comprises horizontal base, horizontal base top is provided with bearing seat, on bearing seat, by flange, be combined with column, horizontal hanging arm is equipped with on the top of column, is fixed with electric block on horizontal hanging arm.It realizes the lifting of equipment by electric block is installed; On base, running in bearings can turn round with column arm within the scope of 360 degree, has improved the alerting ability in hoisting process.This hanging apparatus is applicable to substation's aloft work, reduces operating personnel's labour intensity, increases work efficiency, easy to use, but its structure is more complicated, and equipment cost is also higher.
In Chinese patent CN203278042U, a kind of substation equipment lifting appliance is disclosed, comprise a seat pipe, on the periphery of seat pipe, be fixed with anchor ear, the upper port of seat pipe insert one with a quarter bend tube for inside pipe wall free-running fit, the horizontal segment of quarter bend tube arranges one for lifting by crane with pulley, vertical section of quarter bend tube arranges an annulus limit dais equating with seat pipe external diameter, bearing is installed on limit dais, by rotating quarter bend tube, adjust the sensing of quarter bend tube horizontal segment, thus the equipment of lifting different azimuth.This lifting appliance is easy to carry, transports and installs, and the substation that is applicable to narrow space is used.But this device is to be fixed on the strut bar that framework is installed by anchor ear, the equipment of slinging from strut bar close to, damage easily bumps; And for the equipment that need to be arranged on framework medium position, because of its strut bar away from framework two ends, with this hanging apparatus, equipment can not be hung and gets desired location.
Utility model content
The utility model technical issues that need to address be to provide a kind of simple in structure, cost is lower, be applicable to the hanging apparatus of transformer substation framework.
For solving the problems of the technologies described above, technical solution adopted in the utility model is as follows:
Transformer substation framework Special lifting device, comprises the base being fitted on transformer substation framework crossbeam, and the upper surface of base is fixedly welded with support, and the top of support is provided with pulley; Described base comprises the bottom plate that is positioned at the upper mounted plate of transformer substation framework crossbeam top and is positioned at transformer substation framework crossbeam below, and upper mounted plate is connected by connecting device with the opposite end that bottom plate stretches out transformer substation framework crossbeam; Described support comprises the hollow seat pipe on fixing welding upper mounted plate and the grafting steel pipe of pegging graft in present pipe cavity; Described pulley is arranged on the top of grafting steel pipe.
Further improvement of the utility model is: described seat pipe is arranged on the upper mounted plate end of stretching out transformer substation framework crossbeam outside.
Further improvement of the utility model is: the top of described grafting steel pipe is welded with the hold-down arm perpendicular to grafting steel pipe, and the end of hold-down arm offers the hanging hole that hangs pulley.
Further improvement of the utility model is: described connecting device comprises bolt and the nut matching with bolt; The quantity of described nut is two, and the outside of upper mounted plate and bottom plate respectively arranges a nut.
Further improvement of the utility model is: described connecting device is at least two, is oppositely arranged on the two ends of base.
Owing to having adopted technique scheme, the technological advance that the utility model is obtained is as follows:
This apparatus structure of the utility model is simple, and cost is low, is easy to carry, and is easy to assembling, is applicable to, on transformer substation framework, lifting appliance is installed.
Base of the present utility model is the separated setting of upper mounted plate, bottom plate, by screw bolt and nut, coordinate upper mounted plate is connected with bottom plate, easy installation and removal, on transformer substation framework operating personnel not need undercarriage be dismantled and assembled movable base, this hanging apparatus is fixed on to the optional position of transformer substation framework crossbeam, conveniently equipment is directly hung and gets desired location.Because this hanging apparatus is fixed on transformer substation framework crossbeam, from the strut bar at transformer substation framework two ends away from, and seat pipe is arranged on the upper mounted plate end of stretching out transformer substation framework crossbeam outside, is difficult for bumping while hanging taking equipment, effectively prevents device damage.
Base of the present utility model adopts at least two connecting devices, makes its firm stable and is fixed on transformer substation framework.
Support of the present utility model adopts split-type design, effectively reduces the length of single steel pipe, is convenient for carrying, transports and install; Grafting steel pipe inserts in hollow seat pipe, not only guarantees the firm connection of the two but also can realize within the scope of grafting steel pipe 360 degree and freely turning round, and makes pulley adjust arbitrarily direction with grafting steel pipe, hangs the equipment of getting different azimuth; The top of grafting steel pipe arranges hold-down arm and hanging hole, the convenient pulley that connects.
Accompanying drawing explanation
Fig. 1: structural representation of the present utility model;
Fig. 2: birds-eye view of the present utility model;
Fig. 3: use view of the present utility model.
Wherein: 1, pulley, 2, grafting steel pipe, 3, seat pipe, 4, connecting device, 5, upper mounted plate, 6, bottom plate, 7, connecting device, 8, nut, 9, transformer substation framework crossbeam, 10, strut bar.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the utility model is done further to describe in detail:
Transformer substation framework Special lifting device, as shown in Figure 1, comprises base 4, support and pulley 1, floor installation on transformer substation framework crossbeam, welding support on base, the top dead sheave of support.
Described base 4 comprises upper mounted plate 5, bottom plate 6 and connecting device 7, and described connecting device comprises mutually equipped screw bolt and nut.Described support comprises hollow seat pipe 3 and grafting steel pipe 2, and seat pipe 3 lower ends are welded on the end that upper mounted plate 5 stretches out transformer substation framework crossbeam outside, the upper end of seat pipe and the socket of grafting steel pipe.The external diameter of grafting steel pipe is identical with the internal diameter of seat pipe 3, peg graft in present pipe 3 in the lower end of grafting steel pipe 2, the upper end of grafting steel pipe is welded with the hold-down arm perpendicular to grafting steel pipe, and the outer end of hold-down arm offers hanging hole, the hook of pulley 1 through hanging hole rear-mounted in hold-down arm outer end.
During use, upper mounted plate 5 is placed in to the top of transformer substation framework crossbeam 9, the below that bottom plate 6 is placed in transformer substation framework crossbeam 9, after being connected with the opposite end that bolt stretches out transformer substation framework crossbeam by upper mounted plate and bottom plate, fastening nut 8 is fixed, as shown in Figure 3.In the present embodiment, the quantity of bolt is 4, is separately positioned on four jiaos of inner sides of base, as shown in Figure 2.
When the equipment on transformer substation framework is installed, operating personnel climbs and arrives on transformer substation framework from strut bar 10, first hanging apparatus is arranged on to the correct position of transformer substation framework crossbeam, again the grafting steel pipe that pulley has been installed is inserted in seat pipe, rotate grafting steel pipe adjustment pulley and point to suitable direction, under frame, personnel coordinate personnel on frame to hang equipment such as getting disconnector, insulator by rope.If weight of equipment is larger, also can be used in conjunction with the fixing leading sheave in ground, reach time saving and energy saving effect.After installing place's equipment, base can be pulled down to another position, place that moves to same transformer substation framework, continue operation.
This apparatus structure is simple, is easy to carry and assembles, and is applicable to operation on transformer substation framework and uses, and uses this device to improve work efficiency, has optimized work flow, makes safety in production obtain further guarantee.

Claims (5)

1. transformer substation framework Special lifting device, is characterized in that: comprise the base (4) being fitted on transformer substation framework crossbeam (9), the upper surface of base is fixedly welded with support, and the top of support is provided with pulley (1); Described base (4) comprises the bottom plate (6) that is positioned at the upper mounted plate (5) of transformer substation framework crossbeam top and is positioned at transformer substation framework crossbeam below, and upper mounted plate is connected by connecting device (7) with the opposite end that bottom plate stretches out transformer substation framework crossbeam; The grafting steel pipe (2) that described support comprises the hollow seat pipe (3) being fixedly welded on upper mounted plate and pegs graft in present pipe (3) cavity; Described pulley (1) is arranged on the top of grafting steel pipe.
2. transformer substation framework Special lifting device according to claim 1, is characterized in that: described seat pipe (3) is arranged on the upper mounted plate end of stretching out transformer substation framework crossbeam outside.
3. transformer substation framework Special lifting device according to claim 1, is characterized in that: the top of described grafting steel pipe (2) is welded with the hold-down arm perpendicular to grafting steel pipe, and the end of hold-down arm offers the hanging hole that hangs pulley.
4. according to the transformer substation framework Special lifting device described in claims 1 to 3 any one, it is characterized in that: the nut (8) that described connecting device (7) comprises bolt and matches with bolt; The quantity of described nut is two, and the outside of upper mounted plate and bottom plate respectively arranges a nut.
5. transformer substation framework Special lifting device according to claim 4, is characterized in that: described connecting device (7) is at least two, is oppositely arranged on the two ends of base (4).
CN201420148962.7U 2014-03-31 2014-03-31 Special hoisting device for substation structure Expired - Fee Related CN203865928U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420148962.7U CN203865928U (en) 2014-03-31 2014-03-31 Special hoisting device for substation structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420148962.7U CN203865928U (en) 2014-03-31 2014-03-31 Special hoisting device for substation structure

Publications (1)

Publication Number Publication Date
CN203865928U true CN203865928U (en) 2014-10-08

Family

ID=51646907

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420148962.7U Expired - Fee Related CN203865928U (en) 2014-03-31 2014-03-31 Special hoisting device for substation structure

Country Status (1)

Country Link
CN (1) CN203865928U (en)

Similar Documents

Publication Publication Date Title
CN201381166Y (en) Hanging-point adjustable transverse hanging beam
CN203977422U (en) Building pile foundation holing with slurry wall protection sediment treating apparatus
CN204118585U (en) A kind of installation cross-arm auxiliary support apparatus
CN202544468U (en) Drawbar-type electrical steel tubular rod
CN203846858U (en) Sucking disc fixed type fence ground stake
CN203998746U (en) Portable suspension installation
CN201215876Y (en) Assistant hanging rack for mounting top rack of electric pole
CN204864614U (en) Telescopic safety belt hook support
CN205132955U (en) Hoist and mount operation of electric power industry low latitude is with hoist and mount frame
CN203754331U (en) Hoisting device applied to telegraph pole top end
CN203865928U (en) Special hoisting device for substation structure
CN103318745A (en) Lightweight special-purposed spreader and mounting method thereof
CN204675726U (en) Purlin lifting auxiliary device
CN207553654U (en) A kind of vertical supporting device of assembled architecture
CN204252614U (en) High voltage iron tower inner support Telescopic contracted-pole
CN104925687A (en) Electric lifting device and working method thereof
CN207375669U (en) The electronic lifting bracket of cable tunnel inner column formula cable
CN207122174U (en) A kind of composite material electric pole
CN202441098U (en) Ladder and pull rope type steel tube tower
CN105060154A (en) Suspension installation machine of suspended load type transformer
CN204714417U (en) A kind of power ramp device
CN206144154U (en) Novel template frame for external wall construction
CN217535247U (en) Detachable removal is violently hung
CN203065072U (en) Outdoor substation equipment hoisting device
CN203895816U (en) Hoisting tool for disconnecting switch

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141008