CN203546736U - Green protection of high and steep stony filled side slope - Google Patents

Green protection of high and steep stony filled side slope Download PDF

Info

Publication number
CN203546736U
CN203546736U CN201320585177.3U CN201320585177U CN203546736U CN 203546736 U CN203546736 U CN 203546736U CN 201320585177 U CN201320585177 U CN 201320585177U CN 203546736 U CN203546736 U CN 203546736U
Authority
CN
China
Prior art keywords
side slope
ecology bag
slope
bags
steep
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320585177.3U
Other languages
Chinese (zh)
Inventor
刘府生
周青爽
尹士清
赵新益
顾湘生
邢中晓
周宏元
陈共贤
张协崇
谭远发
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201320585177.3U priority Critical patent/CN203546736U/en
Application granted granted Critical
Publication of CN203546736U publication Critical patent/CN203546736U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a protection of a high and steep filled stony side slope. The protection of the high and steep filled stony side slope comprises various ecological bags stacked on the side slope and connected by connecting buckles. The ecological bags are connected with a geogrid pre-embedded in the side slope. The ecological bags of the green protection of the high and steep stone fill side slope are stacked on the stable side slope from the bottom to the top, and the stacked layers are staggered from each other. The connecting buckles are horizontally mounted between two bags so as to form the strong connection and a stable triangular inside-lock structure between the upper and lower layers of ecological bags, and in the meantime, the parts of the ecological bags touched with the side slope are connected with the geogrid in the side slope through connecting buckles, and the ecological bags are firmly attached with the side slope by the aid of the tamping of the worker or a small device, and accordingly the ecological bags stacked layer by layer and the filled stony stable side slope form the comprehensive and stable ecological side slope together.

Description

A kind of high steep stone matter embankment slope green protection
Technical field
The utility model relates to a kind of steep stone matter of height embankment slope green protection that is applied in the industries such as highway, railway, municipal administration, airport, water conservancy, mine.
Background technology
In hills area, mountain area carries out design of civil, when construction; in embankment location, slope, in order to reduce, take up an area and earth and rock works; save engineering cost; conventionally can adopt a kind of packaging type abrupt slope reinforcement technology; ratio of slope is generally 1:1.25~1:0.3; the slope protection measures that the embankment stone matter high gradient slope that at present ratio of slope is 1:1.0~1:1.25 can adopt is: soil moved in to improve the original grass planting or completely spread soil moved in to improve the original grass planting protection in the empty window of mortar flag stone in hollow brick, and ratio of slope there is no reliable Green Protection technology in the stone matter embankment high gradient slope of 1:1.0 suddenly.
The filler of embankment stone matter high gradient slope is the coarse-grained soils such as sand gravel, rubble, slabstone, piece stone, filler good water permeability, because soil moved in to improve the original can only be with manually making real domatic, soil moved in to improve the original compactness and poor with domatic combination effect, for preventing that soil moved in to improve the original from collapsing along domatic slipping and guaranteeing the stable of slope protection measures, soil moved in to improve the original thickness is generally not more than 10cm; Employing is laid hollow brick grass planting after first laying the soil moved in to improve the original that is not more than 10cm, there is certain afforestation effect, but less soil moved in to improve the original thickness causes the slope table layer soil body water conservation time short, in the wild under unmanned curing condition, soil moved in to improve the original can not provide vegetation growth required enough and long-term moisture and nutriment, vegetation generally survives very low, and afforestation effect is poor.
Completely spread mortar flag stone stronger to the compliance of slope gradient, also can guarantee the stable of embankment stone matter high gradient slope, but have the deficiencies such as not environmental protection,, poor visual effect inharmonious with periphery natural environment.
Therefore, need improve prior art.
Summary of the invention
The purpose of this utility model is exactly the deficiency that will solve above-mentioned background technology, provides a kind of constitutionally stable integral type high steep stone matter embankment slope green protection.
The technical solution of the utility model is: a kind of high steep stone matter embankment slope green protection, it is characterized in that: it comprises that a plurality of heaps are located at the ecology bag in side slope, between described a plurality of ecology bag, by junction button, connect, ecology bag is connected with the geo-grid in being embedded in side slope by junction button.
In such scheme:
Described ecology bag by different level fissure of displacement pendulum is built.
Described junction button is horizontally set between ecology bag, and described junction button upper end is connected with an ecology bag, and junction button lower end is connected with two ecology bags.
Described junction button comprises junction plate, and described junction plate offers a plurality of drain holes, and the upper and lower end face of described junction plate is equipped with a plurality of nails repeatedly.
Ecology bag of the present utility model is at stable side slope pile from bottom to top, and fissure of displacement pendulum is built layer by layer, between two sacks of junction button horizontal positioned, makes to form lock construction in a strong connection and stable triangle between upper and lower layer ecology bag; Simultaneously, ecology bag and side slope contact portion connect together by the geo-grid in junction button and side slope, adopt the external force of artificial or mini-plant to ram bat, make ecology bag and side slope closely connected, guarantee that the ecology bag of layering pile forms the Ecological Slope of comprehensive stability together with embankment stone matter stable side slope.
On ecology bag after the moulding of layering pile, adopt and sow grass seeds by duster, directly to plant or the method such as pack mixed seeding is carried out greening side slope plantation, vegetation seed selects to take into account the plant variety that grass, filling, the bow structure of landscape effect are closed, and guarantees greening side slope effect.
The beneficial effects of the utility model are:
1, the green ecological side slope protection technology of geo-grid associating junction button has solved the green channel construction difficulty of high steep embankment stone matter side slope, has good social benefit;
2, in ecology bag, dress is planted the immature soil for the vegetation growth of stone matter high gradient slope provides soil environment, moisture and the nutriment of adequate thickness, has improved artificial vegetation's survival rate and the diversity of landscape planting effect and plant, has good ecological benefits;
3, compare with adopting mortar flag stone protection, not only there is good afforestation effect, environmental protection, nature, the feature such as coordinate, friendly with surrounding environment, and according to the difference of slope gradient, mortar flag stone thickness, can save construction investment approximately 15%~40%, social benefit, ecological benefits and economic benefit are good.
Accompanying drawing explanation
Fig. 1 is the utility model section structure schematic diagram;
Fig. 2 is ecology bag and side slope connection diagram in the utility model;
Fig. 3 is ecology bag pile front schematic view in the utility model.
The specific embodiment
Below in conjunction with accompanying drawing, the utility model is described in further detail with concrete case study on implementation.
A kind of high steep stone matter embankment slope green protection as shown in FIG., it comprises that a plurality of heaps are located at the ecology bag 2 in side slope 1, between a plurality of ecology bags 2, by junction button 3, connects, ecology bag 2 is connected with the geo-grid 4 in being embedded in side slope 1 by junction button 3.
In the present embodiment:
A plurality of ecology bags 2 by different level fissure of displacement pendulum are built, junction button 3 is horizontally set between adjacent ecology bag 2, junction button 3 upper ends are connected with an ecology bag, junction button 3 lower ends are connected with two ecology bags, and this can make to form lock construction in a strong connection and stable triangle between upper and lower layer ecology bag.
Junction button 3 comprises junction plate, and junction plate offers a plurality of drain holes, and the upper and lower end face of junction plate is equipped with a plurality of nails repeatedly, and when ecology bag pile, nail enters into ecology bag 2 and geo-grid 4 repeatedly.
Ecology bag in the present embodiment is at stable side slope pile from bottom to top, and fissure of displacement pendulum is built layer by layer, between two sacks of junction button horizontal positioned, makes to form lock construction in a strong connection and stable triangle between upper and lower layer ecology bag; Simultaneously, ecology bag and side slope contact portion connect together by the geo-grid in junction button and side slope, adopt the external force of artificial or mini-plant to ram bat, make ecology bag and side slope closely connected, guarantee that the ecology bag of layering pile forms the Ecological Slope of comprehensive stability together with embankment stone matter stable side slope.On ecology bag after the moulding of layering pile, adopt and sow grass seeds by duster, directly to plant or the method such as pack mixed seeding is carried out greening side slope plantation, vegetation seed selects to take into account the plant variety that grass, filling, the bow structure of landscape effect are closed, and guarantees greening side slope effect.
It is raw material by polypropylene (PP) or polyester fiber (PET) that ecology bag in the present embodiment must adopt, there is uvioresistant, anti-aging, nontoxic, not combustion-supporting, breach does not extend, the two-sided flatiron needle punched non-woven fabrics of non-degradable, the performance such as permeable processes, be no less than 30 years the application life of ecology bag.
The main material parameter of ecology bag is as follows:
Mass area ratio: 100~150g/m 2
Vertical transverse tensile strength: >=4.5~7.5KN/m
In length and breadth to fracture elongation: 40~80%
In length and breadth to tearing resistance: >=0.14~0.21KN
CBR bursting strength: >=0.8~1.4KN
Vertical transmission coefficient: (1.0~9.9) * 10 -1~10 -3cm/s
Effective aperture O95:0.07~0.2mm
Uvioresistant: the UV of 500 hours irradiates residual strength >=90%
In ecology bag, plant the immature soil mixing that mainly fetches earth on the spot at the construction field (site), earth material must be applicable to plant growth, plant in immature soil mixing process and should add the admixtures such as water-loss reducer, fertilizer, medium coarse sand, to strengthen water permeability and the water retaining capacity of the soil body, preventing that the soil body from hardening affects plant growth, and provides enough nutrients for vegetation growth; Plant in the immature soil and mix for general every cubic metre: 30~40% sand, the water-loss reducer of 50g left and right and mushroom or other fertilizer of 13~20kg.
Loading and compactness that ecology bag requires are even, and ecology bag is filled rear size and is generally:
Length (cm)=ecology bag length-(12~15);
Width (cm)=ecology bag width * 0.7.
Ecology bag adopts binding strap or portable sewing machine suture to seal, and sealing is wanted firmly, in order to avoid sack, in the operation processes such as carrying, piling, occurs ecology bag, gets loose, and plants immature soil leakage and spills etc.Suture and binding strap are made by high strength, anti-ultraviolet material.
When ecology bag is constructed at pile: first toe along stone matter reinforced slope by ecology bag from bottom to top layering pile, fissure of displacement pendulum build, and by each ecology bag being connected, fixing by junction button and geo-grid.
The greening of side slope mainly adopts and sows grass seeds by duster, directly plants or pack the methods such as mixed seeding, vegetation seed selects to resist cold, drought-enduring, impoverishment tolerant, well developed root system, be easy to survive, adaptable indigenous plant is main, takes into account the plant variety that grass, filling, the bow structure of landscape effect are closed simultaneously.
In the utility model: ecology bag outer pile avoided the direct irradiation of field ultraviolet ray to layering reinforced geo-grid, played protection geo-grid, delayed the aging of geo-grid and strength retrogression's speed, the effect that extends geo-grid and embankment side slope application life; Packedly be mixed with planting the immature soil and can avoiding rainwater to domatic directly washing away and soil erosion of fertilizer and water-loss reducer, thickness 30~50cm, can provide for the long term growth of vegetation necessary nutriment and moisture simultaneously, and good vegetation covers aging, the flourishing root system of plant delayed conversely ecology bag the soil body is also played to reinforcement effect, make whole green edge slope preventive works enter a benign development process, reach the object of the permanent stable and ecological afforestation of side slope.

Claims (4)

1. one kind high steep stone matter embankment slope green protection, is characterized in that: it comprises that a plurality of heaps are located at the ecology bag in side slope, between described a plurality of ecology bags, by junction button, connects, and ecology bag is connected with the geo-grid in being embedded in side slope by junction button.
2. a kind of high steep stone matter embankment slope green protection according to claim 1, is characterized in that: described ecology bag by different level fissure of displacement pendulum is built.
3. a kind of high steep stone matter embankment slope green protection according to claim 2, is characterized in that: described junction button is horizontally set between ecology bag, and described junction button upper end is connected with an ecology bag, and junction button lower end is connected with two ecology bags.
4. a kind of high steep stone matter embankment slope green protection according to claim 3, is characterized in that: described junction button comprises junction plate, and described junction plate offers a plurality of drain holes, and the upper and lower end face of described junction plate is equipped with a plurality of nails repeatedly.
CN201320585177.3U 2013-09-22 2013-09-22 Green protection of high and steep stony filled side slope Expired - Lifetime CN203546736U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320585177.3U CN203546736U (en) 2013-09-22 2013-09-22 Green protection of high and steep stony filled side slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320585177.3U CN203546736U (en) 2013-09-22 2013-09-22 Green protection of high and steep stony filled side slope

Publications (1)

Publication Number Publication Date
CN203546736U true CN203546736U (en) 2014-04-16

Family

ID=50464872

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320585177.3U Expired - Lifetime CN203546736U (en) 2013-09-22 2013-09-22 Green protection of high and steep stony filled side slope

Country Status (1)

Country Link
CN (1) CN203546736U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652358A (en) * 2015-01-04 2015-05-27 杭州木易景观工程有限公司 Ecological slope protection system
CN104798664A (en) * 2015-05-07 2015-07-29 四川大学 Control system for high-steep hill vegetation recovery water
CN107794887A (en) * 2017-12-16 2018-03-13 兰州理工大学 A kind of mud-rock flow beneficial to ecological management is blocked structure and construction method
CN109537567A (en) * 2019-01-23 2019-03-29 西施生态科技股份有限公司 Accumulation gangue answers the construction method and constructing structure of green engineering

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652358A (en) * 2015-01-04 2015-05-27 杭州木易景观工程有限公司 Ecological slope protection system
CN104798664A (en) * 2015-05-07 2015-07-29 四川大学 Control system for high-steep hill vegetation recovery water
CN107794887A (en) * 2017-12-16 2018-03-13 兰州理工大学 A kind of mud-rock flow beneficial to ecological management is blocked structure and construction method
CN109537567A (en) * 2019-01-23 2019-03-29 西施生态科技股份有限公司 Accumulation gangue answers the construction method and constructing structure of green engineering

Similar Documents

Publication Publication Date Title
CN102652480B (en) Vegetation recovery method for acid metal mine solid waste stock dump
CN205475263U (en) High steep slope planting structure of open -air metallic ore
CN204023586U (en) A kind of ecological revetment system
CN107893422B (en) A kind of reinforcement type ecological slope protection structure and its construction method
CN203546736U (en) Green protection of high and steep stony filled side slope
CN206599772U (en) A kind of cover type biological checkboard
CN105839649A (en) Ecological restoration method for metal mine waste storage yard
CN205012180U (en) Environmental anti - packet mode geogrid adds muscle tail ore sand road bed
CN102359113A (en) Integrally-cast cement pervious concrete ecological protection slope and construction method thereof
CN107396807A (en) A kind of implantation methods of arid biogeographic zone transplanting big tree
CN108708350B (en) Ecological slope protection structure and construction method thereof
CN201746828U (en) Geogrid enclosed type reinforced road embankment
CN104963312A (en) Ecological tubular bag revetment soil wall and filling method thereof
CN203530993U (en) Steel-bar mesh planting hole
CN102919010A (en) TEPS (Total Ecology Protection System) for vegetation and construction method of TEPS
CN102972125A (en) Plant cushion for filling plant growing mediums and application thereof
CN110839368A (en) Plant growth bag device for slope ecological restoration, protective structure and construction method
CN102953353B (en) Microbial river embankment reinforcement ecological slope protection technology
CN105970978A (en) Slope ecological restoration system and method
CN111485565A (en) Integrated reinforcing method for green ecological side slope
CN204875669U (en) Ecological pipe bag bank protection cob wall
CN104164854A (en) Method for ecologically re-greening hardened slope
CN202658611U (en) Plant slope protection material
CN109505302A (en) A kind of high precipitous rock slope vegetation type ecological bag fixer
CN203602980U (en) Flake rubble stack reinforced soil composite embankment structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140416

CX01 Expiry of patent term