CN203320545U CN2013203529728U CN201320352972U CN203320545U CN 203320545 U CN203320545 U CN 203320545U CN 2013203529728 U CN2013203529728 U CN 2013203529728U CN 201320352972 U CN201320352972 U CN 201320352972U CN 203320545 U CN203320545 U CN 203320545U
Authority
CN
China
Prior art keywords
steel
tower crane
fixed base
platform
base tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2013203529728U
Other languages
Chinese (zh)
Inventor
黄楠
郑荣跃
黄吉永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo University
Original Assignee
Ningbo University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo University filed Critical Ningbo University
Priority to CN2013203529728U priority Critical patent/CN203320545U/en
Application granted granted Critical
Publication of CN203320545U publication Critical patent/CN203320545U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a support platform which comprises a supporting structure and used for supporting a fixed type tower crane. The support platform is characterized in that the supporting structure is formed in a way that four section steel columns are buried in the ground; the support platform is a steel platform; the top parts of the section steel columns are fixedly connected with the steel platform; at least one horizontal reinforcement steel beam is arranged between each two adjacent section steel columns. The support platform has the advantages that during the construction process, the bottoms of the section steel columns are inserted into ground and fixed, and the top parts of the section steel columns are fixedly connected with the steel platform, the base structure of the fixed type tower crane can be obtained, so that the construction process is simple, and the construction efficiency is effectively improved with low cost. Moreover, the section steel columns are removed and transported outside in a mechanical way, so that the dismounting process is very convenient and environment-friendly; and the dismounted device can be recyclable and used again, so that the resource is greatly saved.

Description

A kind of foundation structure of fixed base tower crane
Technical field
The utility model relates to the foundation structure in a kind of building, especially a kind of foundation structure of fixed base tower crane.
Background technology
Crane is on-the-spot main lifting, plane haulage device of construction work, especially fixed base tower crane, it is little that its foundation structure takies construction plant, flexible arrangement, easy for installation, and tower body can without depending on, other supporters are independent carry out work at certain altitude, tower body adheres to the advantages such as scaffolding height is large after building, so application is quite extensive.
The general pile foundation structure that adopts in fixed base tower crane basis, need to be arranged in the building basement foundation ditch or outside foundation ditch according to construction.
In the time of in fixed base tower crane is arranged in basement foundation ditch, the general concrete drilling bored concrete pile that adopts is as foundation pile, structure commonly used is: the concrete drilling bored concrete pile top is equal with the bottom of basement bottom board, at the bottom of concrete bearing platform a little more than the basement roof face, the foundation bolt of crane derrick tower body is embedded on concrete bearing platform in advance, between the stake top of concrete bearing platform and concrete drilling bored concrete pile, by steel pile, be connected, the upper end of steel pile is stretched in concrete bearing platform, and lower end is inserted in concrete drilling bored concrete pile and carried out anchoring; Concrete bearing platform reaches after design strength the tower body of erection crane again; With the process of excavation of foundation pit, the steel support structure of vertical and horizontal direction is set to strengthen the integral rigidity of steel pile between steel pile.
In the time of outside fixed base tower crane is arranged in basement foundation ditch, general preformed pile or the cast-in-place concrete pile of adopting done basis, structure commonly used is: at the bottom of the stake top embeds concrete bearing platform, the absolute altitude of concrete bearing platform end face is suitable with natural ground, the foundation bolt of crane derrick tower body is embedded on concrete bearing platform in advance, and concrete bearing platform reaches after design strength the tower body of erection crane again.
Mainly there is following shortcoming in fixed base tower crane pile foundation structure practices well:
1, need construction and installation concrete drilling bored concrete pile or preformed pile, also need to carry out the structure such as concreting cushion cap and the step such as steel pile, working procedure more complicated are installed in concrete drilling bored concrete pile;
2, need to consume the resources such as a large amount of steel, concrete, engineering cost has high input, and the construction period is long;
3, the foundation structure of such fixed base tower crane is Bullet structure, once engineering finishes this basis, just goes out of use, and can't reuse, and causes the profligacy of resource.
Summary of the invention
Technical problem to be solved in the utility model is to provide that a kind of operation is simple, construction fast, engineering cost is lower and can reuse remove after the foundation structure of fixed base tower crane of surplus resources.
The utility model solves the problems of the technologies described above adopted technical scheme: a kind of foundation structure of fixed base tower crane, comprise braced structures and for supporting the support platform of placing fixed base tower crane, described braced structures is comprised of four steel columns of imbedding in the soil body, described support platform is the steel platform, the top of described steel column is fixedly connected with described steel platform, between adjacent two described steel columns, has been horizontally disposed with at least one horizontal reinforcing girder steel.
Described horizontal reinforcing girder steel is for vertically equally distributed more than two, be provided with the intersection reinforcing steel beam between adjacent two described horizontal reinforcing girder steels on vertical direction, described intersection reinforcing steel beam comprises two cant beams arranged in a crossed manner, and the end of described cant beam is fixedly connected with described steel column.Support between steel column is more firm.
Described steel platform comprises square steel framework and two supporting beams between four drift angles of described square steel framework arranged in a crossed manner, on described supporting beam, is provided with for fixedly laying the mounting base of described fixed base tower crane.Greatly saved the use amount of steel.
The top of described steel column is fixedly connected with the bottom of described square steel framework by bolt.Only need to twist and go bolt detachable, construct very convenient.
The described soil body is provided with for supporting the concrete cushion of basement bottom board, and described steel column, through described concrete cushion, is provided with the flexible isolating pad between described steel column and described concrete cushion.The flexible isolating pad has separated concrete cushion and has contacted with the direct of steel column, convenient and strength-saving while pulling out steel column.
Compared with prior art, the utility model has the advantage of: in work progress, need directly by the bottom of steel column, insert in the soil body and fix, the top of steel column is fixedly connected with the steel platform, can form the foundation structure of fixed base tower crane, therefore work progress is simple, and can effectively improve efficiency of construction, reduce construction cost simultaneously.Steel column only needs to pull out and transport outward by machinery, so unloading process is very convenient and environmental protection, and the device after dismounting is recyclable and utilization again, has greatly saved resource.
The accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is part-structure top view of the present utility model.
The specific embodiment
Below in conjunction with accompanying drawing, embodiment is described in further detail the utility model.
Embodiment mono-: a kind of foundation structure of fixed base tower crane, comprise braced structures and for supporting the steel platform 1 of placing fixed base tower crane 6, braced structures is comprised of four steel columns 2 of imbedding in the soil body, steel platform 1 comprises square steel framework 11 and two supporting beams 12 between four drift angles of square steel framework 11 arranged in a crossed manner, be provided with the mounting base 121 for fixedly laying fixed base tower crane on supporting beam 12, the top of steel column 2 is fixedly connected with the bottom of square steel framework 11 by bolt, be horizontally disposed with a horizontal reinforcing girder steel 21 between adjacent two steel columns 2.
Embodiment bis-: remainder is identical with embodiment mono-, its difference is in the soil body to be provided with basement and the concrete cushion 3 for supporting basement bottom board, steel column 2 is through concrete cushion 3, be provided with flexible isolating pad 4 between steel column 2 and concrete cushion 3, vertically equally distributed three horizontal reinforcing girder steels 21 have been horizontally disposed with between adjacent two steel columns 2, be provided with the intersection reinforcing steel beam between adjacent two horizontal reinforcing girder steels 21 on vertical direction, the reinforcing steel beam that intersects comprises two cant beams 5 arranged in a crossed manner, the end of cant beam 5 is fixedly connected with steel column 2.

Claims (5)

1. the foundation structure of a fixed base tower crane, comprise braced structures and for supporting the support platform of placing fixed base tower crane, it is characterized in that described braced structures is comprised of four steel columns of imbedding in the soil body, described support platform is the steel platform, the top of described steel column is fixedly connected with described steel platform, between adjacent two described steel columns, has been horizontally disposed with at least one horizontal reinforcing girder steel.
2. the foundation structure of a kind of fixed base tower crane according to claim 1, it is characterized in that described horizontal reinforcing girder steel is for vertically equally distributed more than two, be provided with the intersection reinforcing steel beam between adjacent two described horizontal reinforcing girder steels on vertical direction, described intersection reinforcing steel beam comprises two cant beams arranged in a crossed manner, and the end of described cant beam is fixedly connected with described steel column.
3. the foundation structure of a kind of fixed base tower crane according to claim 2, it is characterized in that described steel platform comprises square steel framework and two supporting beams between four drift angles of described square steel framework arranged in a crossed manner, is provided with on described supporting beam for fixedly laying the mounting base of described fixed base tower crane.
4. the foundation structure of a kind of fixed base tower crane according to claim 3, is characterized in that the top of described steel column is fixedly connected with the bottom of described square steel framework by bolt.
5. the foundation structure of a kind of fixed base tower crane according to claim 1, it is characterized in that the described soil body is provided with for supporting the concrete cushion of basement bottom board, described steel column, through described concrete cushion, is provided with the flexible isolating pad between described steel column and described concrete cushion.
CN2013203529728U 2013-06-18 2013-06-18 Base structure of fixed type tower crane Expired - Fee Related CN203320545U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013203529728U CN203320545U (en) 2013-06-18 2013-06-18 Base structure of fixed type tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013203529728U CN203320545U (en) 2013-06-18 2013-06-18 Base structure of fixed type tower crane

Publications (1)

Publication Number Publication Date
CN203320545U true CN203320545U (en) 2013-12-04

Family

ID=49659911

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013203529728U Expired - Fee Related CN203320545U (en) 2013-06-18 2013-06-18 Base structure of fixed type tower crane

Country Status (1)

Country Link
CN (1) CN203320545U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110747884A (en) * 2019-10-12 2020-02-04 上海建工二建集团有限公司 Tower crane foundation of internal climbing tower crane and installation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110747884A (en) * 2019-10-12 2020-02-04 上海建工二建集团有限公司 Tower crane foundation of internal climbing tower crane and installation method thereof

Similar Documents

Publication Publication Date Title
CN102127974B (en) Design and construction method of additional cellar under existing building
CN103437567B (en) Method for supporting existing building underground added storey through original pile foundations
CN104453274B (en) Utilize supporting and protection structure and underpinning structure to support existing building underground and increase layer method
CN105972313B (en) One kind is across base pit engineering conduit wiring suspension method and overhung construction
CN102561384A (en) Steel hoop truss type elevated pile cap tower crane foundation construction method and structure
CN201901879U (en) Nonstandard foundation used for fixing tower crane
CN204899204U (en) Mouthful structure concrete structure's of department a template system fetches earth among reverse construction method
CN104532856A (en) Fabricated lattice unit for foundation pit supporting and installation method
CN205806684U (en) A kind of across base pit engineering conduit wiring suspension structure
CN105421477A (en) Construction method for tower crane foundation
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN104878786B (en) Tiltedly orthogonal is for group's Pile-soil-structure Interaction experimental model
CN205024712U (en) Combined tower crane foundation
CN202144598U (en) Sunk type underground structure
CN206769047U (en) A kind of steel lattice column and bored concrete pile attachment structure
CN203320545U (en) Base structure of fixed type tower crane
CN204266216U (en) Bamboo beam anchoring and supporting structure of side slope
CN204199296U (en) Foundation pit supporting structure based on old underground outdoor wall structure
CN202416339U (en) Fixed base for tower crane
CN102535496A (en) Expanded pier structure and forming method thereof
CN201722700U (en) Infrastructure of tower crane
CN204435389U (en) A kind of assembled lattice unit for pattern foundation pit supporting structure
CN206562613U (en) A kind of mini pile suspension roof support structure
CN103215965A (en) Laminate type high-rise platform pile tower crane foundation and construction method
CN205188982U (en) Removable system of strutting of rectangle work well

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131204

Termination date: 20160618